Operation Control Procedure for Monitoring and Controlling of
Spillages and Leakages of All Type of Oil, Coolant, And Water
Section: OCP002
Sheet 1 of 2
Version 1.0
AIM:
This document will explain the procedure to control the effects of control spillages and
leakages of all types of oil, water, and coolant.
SCOPE: This work instruction is applicable to all departments.
RESPONSIBILITY: Departmental HOD.
Leakages of all types of oil, water, and coolant
INSTRUCTIONS:
1.
Ensure the effective preventive maintenance of pipelines, Drainage, and Taps.
2. If the leakage of oil informs about leakage to the maintenance supervisor.
3. Check gravity of leak physically.
4. If the gravity of the leak found more, immediately close the valve and inform the charge
of maintenance immediately.
5.
If necessary, stop processing.
6. Start work after arresting leakage completely.
7.
Collect leaked oils in containers and clean the area.
8. Avoid parking in the leakage area.
Prepared By
Renuka K
Signature
Date
Approved By
Shashank Srivaths
Signature
01-06-2021
Date
01-06-2021
Operation Control Procedure for Monitoring and Controlling of
Spillages and Leakages of All Type of Oil, Coolant, And Water
Section: OCP002
Sheet 2 of 2
Version 1.0
9. Do not allow employees to pass on through leaked areas to avoid slippage.
10. If leakage from the waterline, carry out a survey to identify water leakages from
Pipelines.
11. Take corrective measures considering survey reports and arrest leakages.
12. If small quantity leakage occurs arrest, it immediately.
13. If the gravity of the leak found more, immediately close the valve and inform to
maintenance in charge.
14. If necessary, stop processing.
15. Start work after arresting leakage completely.
***END OF THE DOCUMENT***