PERMIT TO WORK SYSTEM Prepared By: Tufail Ahmed Reviewed By: Aijaz Ahmed Approved By : Ali Raza Kazmi 1. OBJECTIVE The objective of this work instruction is to ensure that work performed within the project premises is conducted in safe, coordinated and consistent manner without harm to people, property, environment, and local community. 2. SCOPE Permit to work (PTW) system will be applicable to all associated AMCORP Projects which are parts in EMAAR and associated Pilling Projects, 3. GUIDELINE TO THE PERMIT TO WORK SYSTEM Permits are required for all kinds’ jobs related to construction and commissioning The contractor must ensure the appropriate work permit procedures, consider standard of training and skill of the employee, equipment and tools are used in good condition and suitable for the job also safety equipment should be in good condition. 4. RESPONSIBILITIES 4.1 PERMIT ISSUER Promac will responsible to issue permit in operational, restricted and sensitive areas in concern Activities, Promac Site Engineer is considered as a permit issuing authority in EMAAR VIEWS operational areas. They may be lead responsible for operation. In this case, PROMAC issue permit to the AMCORP. ________________________________________________________________________________________________________________________________ THIS DOCUMENT IS THE INTELLECTUAL PROPERTY OF AMCORP ANY UNAUTHORIZED USE, INCLUDING MODIFICATION AND REPRODUCTION OF THE CONTENT IS STRICTLY PROHIBITED. PAGE: 1 OF 4 PERMIT TO WORK SYSTEM AMCORP will responsible to issue permit in non-live ground areas in concern pilling activities, AMCORP site manager is considered as a permit issuing authority. In this case, AMCORP issue permit to the Sub-Contractor. The issuer is responsible for 4.2 Ensure that all appropriate control measures are put in place prior to allowing a permit. Ensure a work site visit has been carried out PERMIT RECEIVER / JOB PERFORMER Sub-Contractor should assigned competent person for this permit receiving task. The receiver is responsible for Permit receiver/ job performer will fill permit format and highlight hazards and mention safety precaution in format and write complete description of activity. Supervising the work prescribed in the PTW to ensure it is conducted in the most efficient and safe manner. Notifying the Issuer of work progress and completion, and ensuring that the site is returned to a safe and operational state. Taking adequate care to preserve the permit in good condition 4.3 Providing/arranging all necessary resources related with performing the work, including standby-man for confined space entry. Site Supervisor/Engineer Site Supervisor/Engineer will responsible to supervise activity according to PTW by applied proactive approach. The EHS Officer is responsible for: 4.4 Ensure all appropriate safety measures are taken before start the work Workplace inspection before start activity Ensure TBT Conducted at site regularly Strictly follow or implement PPEs requirement at workplace, Etc HSEQ DEPARTMENT The department is responsible for, Provide information instruction Training Supervision to easily implement PTW procedure at Sites ________________________________________________________________________________________________________________________________ THIS DOCUMENT IS THE INTELLECTUAL PROPERTY OF AMCORP ANY UNAUTHORIZED USE, INCLUDING MODIFICATION AND REPRODUCTION OF THE CONTENT IS STRICTLY PROHIBITED. PAGE: 2 OF 4 PERMIT TO WORK SYSTEM 5. Periodic/random auditing of PTW system at site to ensure that this procedure is followed correctly. Participating in joint annual auditing of PTW files. TYPES OF PERMITS General / Cold Work Permit Excavation Permit Hot Work Permit Electrical Permit Confined Space Permit Work at Height Permit Heavy Lifting Permit 5.1 General / Cold Work Permit Any work that does not produce any actual or potential source of ignition such as opening of machinery, painting jobs, piping but not limited too. 5.2 Excavation Permit Excavation work permit is required before any digging work begin, which depth are 1.2Meter (4 Feets) or more. Following points must be considered before excavation work. Appropriate approval from relevant authorities has been take prior to any digging activity Identify underground utilities before start any excavation Each moving equipment is in good condition, area barricading provided and safety signs posted Appropriate PPE’s to be used at site while excavation job. 5.3 HOT WORK PERMIT Any work where there is a potential of flame or spark such as welding, burning/cutting, grinding, drilling, use of equipment’s in facilities etc. These types of activity required hot work permit. ________________________________________________________________________________________________________________________________ THIS DOCUMENT IS THE INTELLECTUAL PROPERTY OF AMCORP ANY UNAUTHORIZED USE, INCLUDING MODIFICATION AND REPRODUCTION OF THE CONTENT IS STRICTLY PROHIBITED. PAGE: 3 OF 4 PERMIT TO WORK SYSTEM 5.4 ELECTRICAL PERMIT Any work that involves working on electrically energized system, such as, inspection, maintenance, looping, termination Etc. Electrical work permit approval is required whenever energy source is electricity. 5.5 CONFINED SPACE PERMIT This is a storage tank, process vessel, ditch/trench deeper more than 4ft or any other enclosure, with limited access, not designed or intended for human occupancy except for purpose of performing work, in which there may be an oxygen-deficient atmosphere. 5.6 WORK AT HEIGHT PERMIT Work at height permit is required where working at a height of more than 2meter (6 Feet). Full body safety harness with double lanyard and shock absorber is must for these kind of activities 5.7 HEAVY LIFTING PERMIT Heavy lifting permit required where heavy lifting more than 50Ton will be commenced. Following safety parameters should be considered while lifting at any weight Crane shall be placed on the firm ground. Outriggers shall be properly opened. Clearance of Overhead power lines while lifting Area should be cleared and barricaded Wind speed factor should be considered 6. WORK PERMIT VALIDITY, EXTENSION, SUSPENSION Permit will be suspended after emergency situations, unsafe condition or weather conditions, Permit issuing authority has rights to suspend the permit upon declaration of above said situations or any breach of safety measures. General / cold work permits valid for 10 Days. However other permits including confined space, Hot Work etc. valid for only each activity at site. Extension of permits will possible with the permission of AMCORP HSE Representative & PM such as long term excavation to make trenches etc. It will also extent for 10 days. Written permission required on permit ________________________________________________________________________________________________________________________________ THIS DOCUMENT IS THE INTELLECTUAL PROPERTY OF AMCORP ANY UNAUTHORIZED USE, INCLUDING MODIFICATION AND REPRODUCTION OF THE CONTENT IS STRICTLY PROHIBITED. PAGE: 4 OF 4