CE 142 Principles of Transportation Engineering EARTHWORKS LESSON 5 Transportation construction projects almost always involve a certain amount of earthwork. In many cases, one of the objectives in the geometric design of the facility will be to minimize the cost of earthwork. The present chapter covers techniques for estimating earthwork quantities and costs, and for planning haul strategies so as to minimize these costs. These techniques are presented both as an example of how construction costs are estimated and for the insight they offer into how problems of horizontal and vertical location may be approached. EARTHWORK CROSS SECTIONS Earthwork quantities are normally expressed as volumes; in metric units, they are given in cubic meters (cubic yards in traditional units). For “linear” facilities such as, highways or railways, these volumes are usually calculated by estimating the areas of earthwork on cross sections taken at intervals along the facility and multiplying the average of adjacent cross-sectional areas by the distance between them. Fig 1. Earthwork cross section for a roadway. Figure 1 illustrates an earthwork cross section for a roadway. The cross section shows both the existing ground and the constructed section, and is drawn as seen by an observer facing in the direction of increasing stations. The top of the earthwork, as actually constructed, is the subgrade elevation at the bottom of the pavement; in drawing the earthwork cross section, however, the usual practice is to represent the top of the constructed section as a horizontal line at profile grade elevation. A standard correction is later applied to cross-sectional areas to account for the thickness of the pavement and the cross-slopes of the normal crown section. Vertical distances are measured from the profile grade elevation, and horizontal distances are measured left and right from the centerline. EARTHWORK VOLUMES Earthwork volumes are normally calculated by the average end area method In this method, the two end areas as determined from the earthwork cross section are averaged and multiplied by the distance between them. In other words, the earthwork volume is approximated by where A1 and A2 are the end areas and L is the distance between them. This method is entirely accurate only if the two end areas are equal. If one end area is zero the earthwork volume is a pyramid, and the proper formula for its volume is Thus, as the area of one end of the earthwork volume approaches zero, the error in the volume calculated by the average end area method approaches 50 percent. A more accurate formula, known as the prismoidal formula, is available. This is where Vp is the volume as given by the prismoidal formula and Am is the area of plane surface midway between cross sections with areas A1 and A2. The prismoidal formula is sometimes used in computerized calculations but use of the average end are method is more common because only approximate volumes are required for purposes of estimation. The usual practice is to use the average end area method except in cases in which the area of one end of the earthwork is actually 240. In that case the volume is calculated by using the pyramid formula. Such pyramid sections are often involved in transitions between cut & fill. The usual surveying practice to take a cross section at the points at which the transition occurs on each edge of the roadway and at the point it occurs at the centerline. Such a practice results in two pyramid volumes, one in cut and the other in fill, as illustrated by Figure 4. Fig 4. Earthwork calculations in transition from fill to cut. MASS DIAGRAMS Calculation of optimum haul strategies and earthwork costs is done by means of a mass diagram. The mass diagram is a graph of cumulative volume of earthwork versus distance in stations from the beginning of the job, in which cut is considered to be positive and fill negative. Consequently, a rising mass diagram indicates an excess of cut over fill in a particular section and a falling mass diagram indicates an excess of fill over cut. Use of the graph of cumulative earthwork makes it easy to identify sections for which the volume of cut equals that of fil, since any horizontal line spanning a loop of the diagram, as illustrated in Figure 5, will identify such a section. Fig 4. Properties of mass diagrams. Such lines are called balance lines, since the amounts of cut and fill within the loop they span are said to balance each other. Of course, what is actually being equated is the masses of cut and fill material, so that either the cut or fill volume must be corrected for shrinkage or swell before the diagram is plotted. Mass diagrams are plotted from tables known as summary sheets. These tables list the cut and fill volumes for each section and the cumulative volumes of earthwork that are to be plotted as the mass diagram ordinates at each station. The table shows an example of a summary sheet. The optimum haul strategy is determined on the basis of the properties of the mass diagram and the prices of various earthwork items for which contractors are paid. The exact definition of these pay items may vary from agency to agency and is normally determined by the standard specifications of the owner of the project. Common pay items include excavation, borrow, overhaul, and occasionally, waste. COSTS OF COMMON PAY ITEMS The cost of excavation normally includes the cost of removing the material from its existing state, hauling it up to some specified distance referred to as the free haul distance, and placing it in a properly compacted fill. In most cases, the cost of excavation will also include the cost of removing excess cut material. The cost of excavation will be quoted in dollars per cubic meter. The cost of overhaul is the cost of hauling material beyond the free haul distance. It is quoted in dollars per stationmeter. Costs of Common Pay Items … continuation • The cost of borrow, also quoted in dollars per cubic meter, is the cost of any material that has to be obtained off the job site in order to make a fill. The cost of borrowed material is usually several times that of material excavated locally. • In the event that disposal of excess cut material is not included in the item for excavation, there will be a separate pay item for waste, also quoted in dollars per cubic meter. Earthwork quantities for transportation projects are usually estimated by drawing vertical cross sections and estimating the volumes between them. Cross-sectional areas may be measured by planimeters, calculated by computer using a coordinate method, or calculated by hand. Earthwork volumes are normally calculated by the average end area method. Optimum haul strategies and earthwork costs are calculated by means of a mass diagram. Haul strategies are determined by fitting the optimal balance lines to the diagram. Excavation costs are calculated by summing the cut column of the summary sheet used to make up the mass diagram. Costs of overhaul, borrow, and waste (where applicable) are determined from the mass diagram.