CHAPTER 1 INTRODUCTION 1.1 Research Background Delay is a common occurrence in construction industry. 1 This is essentially because of the nature of construction works. Particularly, construction projects take a long period of time to complete. The construction operations involve many parties2 and workmen of various trades. The construction contracts contain many clauses and documents. If the construction works are not properly managed, delays may occur. There are many causes that may cause delays to construction works. The delays may basically be classified into two main categories; one, excusable delays and the other, non-excusable delays.3 Excusable delays are those that are caused by the employer4 or his agents5 and by some neutral events that are beyond the control 1 Abd. Majid, M.Z. and McCaffer, R., “Factors of Non-excusable Delays that Influence Contractors’ Performance”. Journal of Management in Engineering. ASCE, May/June (1998) 42-49. 2 Employers, consultants, main contractors, subcontractors, suppliers, etc. 3 Kenneth C. Gibs, Gordon Hunt. California Construction Law. Aspen Publishers. New York. (2000) 4 Employer’s requirements for variations 2 of the parties.6 For delays that come within this category, the contractor is normally entitled to extension of time.7 Non-excusable delays are those that are caused by the contractor’s own faults or non-performance. 8 Naturally, the contractor is not entitled to extension of time; and instead, the contractor is liable to the employer in the form of liquidated damages.9 Relating to excusable delays, the causes may be further classified into two sub-categories: one, cause by the employer or his agents/consultants and, the other, cause by neutral events that are outside the contractor’s control and they are unforeseeable.10 Examples of excusable delays of the first category are variation orders,11 delay in giving possession of site,12 delay by consultants in issuing instructions,13 etc. Examples of employer’s caused delays of the second sub-category are unusually severe weather condition,14 strike,15 unavailability of materials,16 etc. Excusable delays basically entitled the contractor to an extension of time.17 As in the case of Ellis Don v The Parking Authority of Toronto,18 the contractor was granted 17½ weeks extension of time due to winter season which had delayed the concreting works. Non-excusable delays are those that are due to the contractor’s lack of performance or simply or breach of contract. There are multiple causes under contractor’s caused delays. Some obvious examples of contractor’s caused delays are 5 Delay in issue instructions or drawings, etc Force majeure, statutory authorities, outbreak of war or hostilities 7 Clause 23.0 PAM (2006), Clause 24.0 CIDB (2000), Clause 43.0 PWD 203A (2010) 8 Timothy R. Hughes. A Layperson’s Guide to Delay Claims. Masonry Magazine. Hughes & Associates. (2003). 9 Clause 22.1 PAM (2006), Clause 26.2 CIDB (2000), Clause 40.1 PWD 203A (2010) 10 Cushman, R. F., Myers, J. J. Construction Law Handbook. New York. Aspen Law & Business. (1999) 11 Clause 24.1(l) CIDB 2000, Clause 23.8(g) PAM 2006, Clause 43.1(e) PWD 2010 12 Clause 24.1(i) CIDB 2000, Clause 23.8 (f) PAM 2006, Clause 43.1(h) PWD 2010, 13 Clause 24.1(e) CIDB 2000, Clause 23.8(e) PAM 2006, Clause 43.1(f) PWD 2010 14 Clause 24.1(b) CIDB 2000, Clause 23.8(b) PAM 2006, Clause 43.1(b) PWD 2010 15 Clause 24.1(c) CIDB 2000, Clause 23.8(d) PAM 2006 16 Clause 23.8(k) PAM 2006 17 Clause 24.0 CIDB (2000), Clause 23.0 PAM (2006), Clause 43.0 PWD 203A (2010) 18 (1978) 28 BLR 98 6 3 defective works, subcontractors’ related caused delays,19 poor communication, financial related delays and improper planning.20 This category of delay does not entitle the contractor to get extension time. Usually, the contractor is liable to pay the employer liquidated damages.21 Since delay is a normal occurrence, particularly when it is within the excusable delay category, time for completion may become at large and the employer may not be able to deduct the liquidated damages.22 It is submitted that all standard forms of contract contain express provisions relating to granting contractors extension of time caused by excusable delays.23 Generally these provisions give power to the contract administrator24 to grant the extension of time, set out the conditions and procedure for the application. One of the normal conditions required of contractors to fulfil for the purposes of granting the extension of time is that the contractor must have used his best endeavours to reduce or prevent delay. For example, in clause 23.6 of the PAM 2006 standard form of contract, states that: “The contractor shall constantly use his best endeavour to prevent or reduce delay in the progress of the works, and to do all that may reasonably be required to the satisfaction of the Architect to prevent and reduce delay or further delay in the completion of the Works beyond the completion date”. 19 Westminster CC v. Jarvis & Sons [1970] 7 BLR 64 Afshari, H., et. al. Identification of Causes of Non-Excusable Delays of Construction Projects. 2010 International Conference on E-Business, Management and Economics. Vol. 3. Hong Kong. (2011) 21 Clause 22.1 PAM (2006), Clause 26.2 CIDB (2000), Clause 40.1 PWD 203A (2010) 22 Rapid Building Group Ltd v Ealing Family Housing Association Ltd [1984] 29 BLR 5 23 Clause 23.0 PAM (2006), Clause 24.0 CIDB (2000), Clause 43.0 PWD 203A (2010) 24 A neutral term that refers to S.O. in PWD and CIDB, Architect in PAM and Engineer in IEM 20 4 Another example is as in clause 25.3.4 of the Joint Contract Tribunal (JCT) standard form of contract 199825 provides that: “the Contractor shall use constantly his best endeavours to prevent delay in the progress of the Works…’ Based on the provisions above, one of the requirements in granting the contractor with an extension of time is that the contractor must use his best endeavour to avoid the delay of the works. However, there are other standard forms, for examples, the PWD 201026 and CIDB 200027 that use the term ‘taken all reasonable steps’ instead of ‘best endeavours.’ It is submitted that, the courts have interpreted these two terms, both of them having no material distinctions.28 Clause 43.1 in PWD 203A Standard Form of Contract (Rev 2010)29 states that: “…Provided always that the Contractor has taken all reasonable steps to avoid or reduce such delay and shall do all that may reasonably be required to the satisfaction of the S.O. to proceed with the Works”. CIDB Standard Form of Contract 2000 in its Delay and Extension of Time Clause, Clause 24.1 mentions that: 25 JCT Standard Form of Contract. (1998) Clause 43.1 27 Clause 24.1 28 Slaughter and May. Best endeavours v. reasonable endeavours, what do they mean? Does either mean anything? London. (2007) 29 Public Works Department. PWD 203A Standard Forms of Contract. (2010) 26 5 “Provided that the Contractor has carried out the Works or any section of the Works with due diligence and has taken all reasonable steps to avoid or reduce such delays,” According to Chappell (2011) the term best endeavours used in the JCT 98 standard forms imposes on contractors two express duties: one, to take remedial actions to prevent the occurrence of delay and, two, also a duty to mitigate the loss incurred from the potential delay.30 1.2 Problem Statement Contractors have an obligation to carry out their works regularly and diligently in order to make sure that they meet the agreed completion date. Accordingly, when delay occurs or when delay is likely to occur, this duty to carry work regularly and diligently may include a duty to take any positive action which can reduce the consequences of delay and of potential delays in future. It is submitted that such an interpretation may also be made with respect the term “best endeavours” and “taken all reasonable steps” in relation to the duty to prevent and reduce delay. Hence, it is important for contractor to understand what is meant by both terms so that they can act appropriately in order to avoid the delay and put the loss at a minimum level. In addition, the fulfilment of this duty is important for the purpose of applying for extension of time. The contractor is under a legal and moral obligation to prove that he has taken mitigation steps against the overall damages.31 30 Chappell, D. Building Contract Claims. Wiley-Blackwell. UK. (2011) Simon, M.S. Construction Contracts and Claims. McGraw-Hill Book Company. United States. (1979) 31 6 It is submitted that the courts have not been consistent in construing the term best endeavours. In the case of Midland Land Reclamation Ltd v. Warren Energy Ltd,32 the court held that the term best endeavour did not mean the next best thing to an absolute obligation or guarantee. According to this interpretation, the contractor has a heavy duty to discharge because according to the judge, it was an absolute obligation and second best was simply insufficient. In another case, Terrell v Mabie Todd and Co.33, the judge in this case had construed the term best endeavours as just requiring the contractor to do what was commercially practicable and what is considered as reasonable in that circumstances. It is submitted that this standard of duty is less burdensome than that under Midland Land Reclamation case. Furthermore, according to Slaughter and May (2007) there was no exact and certain meaning to the terms “best endeavour” and “taken all reasonable steps”.34 This leads to a conflict relating to the correct construction of the term “best endeavours” used in the standard form of contract. Keating considers the contractor’s duty to do his best endeavours to prevent delay is an important proviso for the granting of extension of time. He states in his book ‘Keating on Building Contracts’ (2003): “The proviso is an important qualification to the right to an extension of time. Thus, for example, in some cases it might be the contractor’s duty to reprogramme the works either to prevent or reduce delay. How far the contractor must take other steps depends upon the circumstances of each case, but it is thought 32 [1997] [1952] 69 RPC 234 34 Slaughter and May. Best endeavours v. reasonable endeavours, what do they mean? Does either mean anything? London. (2007) 33 7 that the proviso does not contemplate the expenditure of substantial sums of money.35” Relating to the extent of the contractor’s duty to prevent delay under the best endeavours proviso, Keating suggests that, the contractor may re-programme his works. However, the actions must not involve the incurring of substantial amount of money. Despite the above statement, it is submitted that there is no clear guidelines or established benchmark to what extent a contractor is needed to act in order to put the delay risk at the minimum level. Due to this uncertainty, the contractors are facing difficulties in deciding when it is necessary to carry out such mitigation action, to what extent and also at what cost. Even in the contractor’s opinion, they had taken some reasonable steps to avoid the delay, they are still not being granted with the extension of time from the employer36. 1.3 Objective of Research Based on the above problem statement, the objective of this research is essentially to identify the requirements in performing the duty of best endeavours for the purpose of compliance with the proviso for the granting extension of time. 35 Mokhtar Azizi Mohd Din. The Extent of The Contractors Effort to Mitigate Delay. PMINZ Conference. Auckland. (2011) 36 Keane, P.J., Caletka, A.F. Delay Analysis in Construction Contracts. Blackwell Publishing Ltd. United Kingdom. (2008) 8 1.4 Scope of Research The scope of this research is confined to the both Malaysian and international main standard forms of contract. The Malaysian main standard form of contract here refers to PWD 2010, PAM 2006, and CIDB 2000 while for international main standard form of contract is refer to JCT 1998. Relating to the case law analysis, the cases are mainly those that are reported in the law reports provided by the Lexis Malaysia online data base. The cases retrieved were only from common law jurisdiction or Commonwealth countries. 1.5 Significance of Research The books on construction law and construction contracts seem to give little emphasis on this topic. The contract administrators in Malaysia too do not seem to put great emphasis on this duty of best endeavours when considering contractors’ applications for extension of time. Although there no reported cases regarding the issue of mitigating delay in the local construction industry, it is hoped that this research will give some guidelines and overview to employers, contractors and contract administrators in the local construction industry on the issue of mitigation duty. 9 1.6 Research Methodology In order to achieve the objective of this research and successfully complete it in the stipulated time, there is a need to a proper plan for its implementation. Basically, this research is carried out in four main stages, they are: initial study stage, data collection stage, data analysis stage and completion stage. All of these stages will be explained further. 1.6.1 Initial Study Initial study is important as at this stage the issue or the problem is identified. This stage requires extensive readings from various sources of literature materials in order to get a clear view on the topic chosen. This stage also involves discussion with lecturers to get more ideas relating to the topic and feasible issues of the subject matter. After all the issue and objective as well as the scope are identified, the next stage is the collection of data. 1.6.2 Data Collection The data or information required for this research are mainly relating to the clauses in the standard forms, commentaries about those clauses. The sources for those commentaries are in the various articles, seminar papers, books and journals. The other main information require for the research is of course the relevant case law collected from the law journals available from the Lexis Malaysia online database. The data collection stage is in fact being carried continuously beginning from the initial stage. All data related to the research topic is valuable even though it is not being cited in the research writing. 10 The commentaries on the clauses are considered as the secondary data. The primary data are the relevant clauses and the case law. The relevant landmark and important cases are important for the purpose of achieving the objective of the research. The relevant cases are retrieve from Lexis Malaysia online database the University’s Library, (Perpustakaan Sultanah Zanariah) subscribes. 1.6.3 Data Analysis This is the final stage of the whole research process where researcher needs to compare and discuss all the law cases in order to achieve the objective. Data analysis is very crucial because this part requires fine analytical and critical thinking. It appraises the researcher’s mental and intellectual ability to analyse and synthesise the legal principles, the contract provisions and legal arguments collected. 1.6.4 Conclusion and Recommendation After the analysis and review of all the cases, this is the stage that the researcher will make the conclusion and summary what is basically the purpose of this. This stage will summarise the research findings. I will set out in summary what actions amount to and what action do not amount to best endeavours. The researcher will also make suggestion as to the possible future research topic in relation to this area of research. There will also an explanation on the problems, weaknesses and limitations in carrying out this research. 11 1.7 Research Flow Process Initial Study Statement of Problem Scope of Study Objective Literature Review Data Collection Documentation Review Case Review Data Analysis Report Writing CHAPTER 2 EXTENSION OF TIME 2.1 Introduction A contractor’s obligation under a construction contract is, generally, to carry out and complete the construction works either before or on the agreed date of completion.37 However, due to the unique features of construction works, there are many influencing factors that may affect the progress of the works and thereby cause delay in the completion. The causes of delays in construction works can be classified into excusable and non-excusable delays. Generally excusable delays are those that are caused by the employer or his consultants and some neutral events beyond the control of the parties.38 In other words, the contractor is not liable to the employer for those delays. The contractor is normally granted with extension of time.39 In addition, in relation to employer’s 37 Clause 1.0 PAM (2006), Clause 7.0 CIDB (2000), Clause 2.0 PWD 203A (2010) M.Z. Abd Majid and Ronald McCaffer. Factors of Non-Excusable Delays that Influence Contractor’s Performance. Journal of Management in Engineering. May/June. (1998). 39 Clause 23.0 PAM (2006), Clause 24.0 CIDB (2000), Clause 43.0 PWD 203A (2010) 38 13 caused delays, the contractor may also be compensated for any direct loss and expense,40 but not in relation to excusable delays caused by neutral events. Non-excusable delays are those delays that are caused by the contractor’s own faults. They are essentially the contractor’s breaches of contract. The contractor is not granted with extension of time. Moreover, the contractor will be liable for the delay in the form of liquidated and ascertained damages.41 Hence, this chapter specifically focuses on extension of time granted due to the occurrence of compensable excusable delay events. The discussion is substantially based on the express extension of time provisions contained in the standard forms. The discussion also includes the reasons for extension of time clause, requirement for granting extension of time, duties of contract administrator, time for granting extensions and finally is summary for the whole chapter. 2.2 Purpose of Extension of Time Provision Hudson’s Building and Engineering Contracts, 11th Edition, p 624 (2010) explains the rationale for such clauses: “It has been seen that, for the purpose of treating the contract as repudiated, in the rare cases where time is of the essence, the contract time for completion may cease to be applicable for a variety of reasons, including the ordering of extras or other interference or prevention by 40 41 Clause 24.0 PAM (2006), Clause 31.0 CIDB (2000), Clause 44.0 PWD 203A (2010) Section 75 of the Contract Act 1950; Clause 22.1 PAM (2006), Clause 26.2 CIDB (2000), Clause 40.1 PWD 203A (2010) 14 the employer. In the case of damages, it is equally obvious that where the reason is some act of the employer or his architect or engineer preventing completion by the due date, it cannot be the intention of the parties that liquidated or other damages should be calculated from that date even if the act, such as ordering extras, is not a breach of contract. Liquidated damages stipulated for at a rate for each day or week of delay in completing the works must begin to run from some definite date. It follows, therefore, that if the date in the contract has for some such reason ceased to be the proper date for the completion of the works, and no contractual provision exists for the substitution of a new date, there is such a case no date from which liquidated damages can run and the right to liquidated damages will have gone. This, rather than solicitude for the contractor, is the reason for the provision usually known as the extension of time clause.” By and large every standard form of construction contract provides a clause on extension of time.42 It is an important provision in the sense that it can continuously maintain time as of the essence of the contract when the progress of the work is hindered by factors under excusable delays. Without the power to extend the time for completion, the time for completion becomes at large, the contractor is only required to carry out and complete the work within reasonable time. The effect is that the employer is not entitled for liquidated damages.43 It is submitted that the extension of time clause is chiefly for the employer’s benefit and not so much for the contractor.44 It is now settled law that if the employer causes the delay, wholly or partly he is not entitled recover liquidated damages.45 Denning L.J. in the House of Lords had 42 Clause 24.0 PAM (2006), Clause 31.0 CIDB (2000), Clause 44.0 PWD 203A (2010) Rapid Building Group Ltd v Ealing Family Housing Association [1985] 29 BLR 5 44 Oon Chee Kheng. Extension of Time and Liquidated Damages in Construction Contracts. Seminar on Construction Contracts and Arbitration. Institution of Engineers, Malaysia. Perak. (2003). 45 Peak Construction (Liverpool) Pty Ltd v. McKinney Foundation Ltd [1970] 1 BLR 111 43 15 in the case of Amalgamated Building Contractors Ltd v. Waltham Holy Cross UDC,46 said: “I would also observe that on principle there is a distinction between cases where the cause of delay is due to some act or default of the building owner, such as not giving possession of the site in due time, or ordering extras, or something of that kind. When such things happen the contract time may well cease to bind the contractors, because the building owner cannot insist on a condition if it is his own fault that the condition has not been fulfilled.”47 Later, in the case of Peak Construction (Liverpool) Pty Ltd v. McKinney Foundation Ltd,48 Salmon L.J. futher said “The liquidated damages clause contemplates a failure to complete on time due to the fault of the contractor. It is inserted by the employer for his own protection; for it enables him to recover a fixed sum as compensation for delay … If the failure to complete on time is due to the fault of both the employer and the contractor, in my view, the clause does not bite. … I consider that unless the contract expresses a contrary intention, the employer … is left to his ordinary remedy … No doubt if the extension of time clause provided for a postponement of the completion date on account of delay caused by some breach or fault of on the part of the employer, the position would be different. This would mean that the parties had intended that the employer could recover liquidated damages notwithstanding that he was partly to blame for the failure to achieve the 46 [1952] 2 All ER 452 Ibid., at p. 455 48 Supra, n. 46 47 16 completion date, and the contractor would be liable to pay liquidated damages for delay as from the extended date. …”49 In this case the plaintiff was the main contractor and the defendant was the nominated subcontractor for piling. The project was a housing project owned by Liverpool Corporation. After the completion of the project in 1964 and the contractors had left the site, defects were discovered in one of the building’s perimeter piles. The owner delayed in engaging the expert to examine and prepare the report. The main contractors reported to the parties in late May 1965. The following day Peak wrote to the corporation asking for an instruction to carry out the work recommended by the expert. Peak heard nothing and so wrote to the corporation in late June. It was not until 30 July 1965 that the expert’s recommendations were approved by the corporation. The remedial work was commenced by Peak on 12 August 1965 and completed in early November 1965 – some 58 weeks after the works had been suspended. As a result of the delay, the corporation sought Liquidated Damages from Peak. Peak, in turn, sought Liquidated Damages for that entire period from McKinney Foundation. The issues was whether Peak was entitled to Liquidated Damages. The Court of Appeal held that main contarctor was not entitled to recover liquidated damages from subcontractor as the corporation was not entitled to recover those liquidated damages from Peak. The Court of Appeal found that at least part of the 58-week delay had been caused by the corporation itself, and the extension of time clause in the main contract did not enable the corporation to extend time for its own delays. Further, no attempt had been made by the corporation to extend time. Accordingly, there was no date from which liquidated damages under the head contract could commence. 49 [1970] 1 BLR 111 at p.121 17 The principle enunciated in Peak Construction case is known as the prevention principle. It simply demonstrates that an employer is not entitled to rely on a liquidated damages clause where the reason for late completion is an act of hindrance or prevention by the employer, at least in the absence of a suitable extension of time clause. The application of this prevention principle may be found in the an Australian case of Gaymark Investments Pty Limited v. Walter Construction Group Limited,50 Due to prevention acts by Gaymark, the employer, the contractor (Walter) was delayed in completing the work. According to the standard form of contract, the contractor was not either able to be granted with extension of time or even to set a new completion date. Hence, the court held that time had become at large and the contractor was obliged to perform and complete the works within a reasonable time. 2.3 Extension of Time Provision The essence of the extension of time clause is to confer to the contract administrator power to grant extension of time to the contractor. This is because the contract administrator basically has no inherent power to extend time for completion without express provision to that effect.51 In the case of Rapid Building Group Ltd v Ealing Family House Association,52 it was held that without such an express term the architect was not able to grant extension of time to the contractor. In this case the court held that the architect had no power to grant the contractor extension of time for delays caused by employer’s late in giving site possession because the extension of time clause in the contract did not include such cause in its relevant events. 50 [1999] NTSC 143 Lim Chong Fong, The Malaysian PWD form of Construction Contract, Sweet and Maxwell Asia, Kuala Lumpur, 2004, at page 92 52 Supra, n.43 51 18 Another aspect of the clause is that there is always a list of relevant events that entitle the contract administrator to grant extension of time.53 It simply shows that the power of the contractor administrator to grant extension of time is limited to delays caused by those events and no other.54 Usually the relevant events are causes of delays bring about by the employer or his agents and neutral events beyond the control of the parties. Examples of relevant events cause by employer include delay in giving instructions,55 delay in supplying information,56 delay in nominating nominated subcontractors,57 etc. Examples of neutral events are exceptionally inclement weather condition,58strike by workers,59 etc. The standard forms normally have long list of relevant events principally, it is submitted, to maintain the employer’s entitlement to liquidated damages.60 The extension of time clauses also specifies the procedure for making the application. One important procedure is that the contractor must serve the contract administrator two notices. First notice is intention to claim the extension of time.61 This notice is described as condition precedent for the granting of the extension of time. The court has interpreted it literally and held that the notice is mandatory.62 Specifically, PAM 2006 provides:63 53 Clause 23.0 PAM (2006), Clause 24.0 CIDB (2000), Clause 43.0 PWD 203A (2010) Rapid Building Group Ltd v Ealing Family Housing Association [1985] 29 BLR 5 55 Clause 24.1(e) CIDB 2000, Clause 23.8(e) PAM 2006, Clause 43.1(f) PWD 2010 56 Clause 24.1(e) CIDB 2000, Clause 23.8(e) PAM 2006, Clause 43.1(d) PWD 2010 57 Clause 24.1(e) CIDB 2000, Clause 23.8(e) PAM 2006, Clause 43.1(j) PWD 2010 58 Clause 24.1(b) CIDB 2000, Clause 23.8(b) PAM 2006, Clause 43.1(b) PWD 2010 59 Clause 24.1(c) CIDB 2000, Clause 23.8(d) PAM 2006 60 The detail of the relevant events is discussed in section 2.4 below 61 Clause 23.1 PAM (2006), Clause 24.2 CIDB (2000), Clause 43.1 PWD 203A (2010) 62 Smith, H. Notice Requirements in Construction Contracts – A Southeast Asia Perspective. (2012); Oon Chee Kheng. Standard Construction Contracts in Malaysia: Issues and Challenges. Innovations in Construction Contracts. Malacca. Pp 8-9. (2002) 63 Clause 23.1 (a) PAM Standard Form of Contract 2006, Clause 43.1 PWD Standard Form of Contract 2010, Clause 24.2 (a) CIDB Standard Form of Contract 2010. 54 19 “the Contractor shall give written notice to the Architect his intention to claim for such extension of time…”64 Based on a plain meaning in interpreting the clause, it seems that the notice is a condition precedent before a contractor can be entitled with the time extension. However, there are many literature stated that failure to comply with this notice requirements does not make the contractor not qualified for the extension of time.65 One of the cases that illustrated this opinion is the case of Maidenhead Electrical Services v. Johnson Controls.66 The contract provision stated that any claim for an extension of time must be made within 10 days from the event which the claim arises. The court held that the contractor’s failure to comply with the provisions did not bring the claim as an invalid document. Similarly in another case of London Borough of Merton v Stanley Hugh Leach,67 the court held that a written notice was not consider as a condition precedent in granting an extension of time whereby it was under duty of an independent architect. Therefore, it is suggested that if the employer intends to make this notice a condition precedent for claiming time extension, there must a clear term to that effect and non-compliance with this notice leads to waiver of contractor’s right in getting the extension of time.68 The second notice is served after the end of the delay event. The notices should supply the contract administrator the delay event, the estimated period of 64 PAM Standard Form of Contract. Clause 23.1 (a). (2006) Smith, H. Notice Requirements in Construction Contracts – A Southeast Asia Perspective. (2012); Oon Chee Kheng. Standard Construction Contracts in Malaysia: Issues and Challenges. Innovations in Construction Contracts. Malacca. Pp 8-9. (2002) 66 [1996] 67 [1985] 32 BLR 51 68 Knowles Commercial Services. Delays, Extensions of Time and Liquidated Damages. (n.d) 65 20 delay and other relevant information and documents to enable him to assess the extension of time the contractor should be granted with. CIDB (2000) Standard Form of Contract requires contractor to provide any appropriate contract references as supporting document in applying extension of time.69 This reference can be a construction programme in the form of a bar chart or network programme showing the critical path of the project. There are two types of information can be obtained from this programme, namely duration of work and sequence of the works. A good work programme will provide information on actual start dates, durations, and also completion date. By referring to this, the contract administrator can evaluate the planned works with the as-built works and at least it can help him in assessing the extension application. There are requirements provided in establishing an extension of time as in the case of Balfour Beatty Construction Ltd v The London Borough of Lambeth70: i) The original programme and substantiation to show its validity and reliability as a contractual starting point, or ii) Revised programmes on the occurrence of the event which can give convincing relationship of cause and effect71. The contractor’s failure to provide an effective programme may put himself at a risk on proof of entitlement to the time extension72. 69 Clause 24.2 (a) [2002] BLR 288 71 Price D. Delay and Disruption Claims under FIDIC Contracts-Procedural Issues, Evidence and Assessment. Hill International. (n.d) 72 Eggleston, B. Liquidated Damages and Extensions of Time. Blackwell Publishing. United Kingdom. Pp 248-249. (2009) 70 21 Thereafter the administrator may grant the contractor the extension of time by issuing the certificate of extension of time.73 This power to grant extension of time is extended beyond the date of certificate of non-completion if the relevant event occurs after the issuance of the certificate.74 The contract administrator may also review the extension of time granted after the practical completion that may result that the total extension of time may be reduced or increased.75 One particular condition that the contractor must also include in his application of extension is the proviso that he must have taken actions to prevent or reduce delay. In clause 23.6 of PAM 2006, it is stated that: “The Contractor shall constantly use his best endeavours to prevent or reduce delay in the progress of the Works and to do all that may reasonably be required to the satisfaction of the Architect ....” Clause 43.1 PWD 2010 specifies: “…Provided always that the Contractor has taken all reasonable steps to avoid or reduce such delay and shall do all that may reasonably be required to the satisfaction of the S.O. to proceed with the Works”. Clause 24.1 of CIDB provides: “Provided that the Contractor has carried out the Works or any section of the Works with due diligence and has taken all reasonable steps to avoid or reduce such delays.” 73 Clause 23.4 of PAM 2006 Clause 23.9 PAM 2006 75 Clause 23.10 PAM 2006 74 22 2.4 Relevant Events Clause for extension of time in standard forms of contract provide long list of relevant events that entitled contractor to get extension of time from the employer in order to complete the works. Basically, an extension of time will be granted if the delay occurred on the employer’s default which is categorized as compensable excusable delays76. Besides getting time extension, the contractor also will be entitled with recovery of any increasing of costs incurred due to the default 77. There are several events under this type of delay and each will be discussed further next. 2.4.1 Force Majeure It is common to have force majeure as one of the listed events which entitled the contractor for an extension of time.78 In order to have understanding what is meant by force majeure, most writers or researchers interpret it as any unforeseen act of God. However, not all events that make performance impossible are considered as force majeure and plus, in construction contract it is normal to have event that must inclusive “man-made” factors. Robinson et. al. (1996) henceforth classified force majeure into two areas which are act of God and ‘vis major’79. Act of God is referred to a natural causes event which could not be foreseen and does not involved human intervention such as earthquake, extraordinary flood or death. Whilst a vis major are circumstances which may or may not inclusive human factor but including an act of God. For the 76 Thomas, J. Kelleher and G. Scott Walters. Smith, Currie & Hancock’s Common Sense Construction Law. John Wiley & Sons. United States of America. Pp 281 – 283. (2009). 77 Thomas, J. Kelleher and G. Scott Walters. Smith, Currie & Hancock’s Common Sense Construction Law. John Wiley & Sons. United States of America. Pp 281 – 283. (2009). 78 Pertubuhan Arkitek Malaysia. PAM Standard Form of Contract. (2006) 79 Robinson, N.M. et.al. Construction Law in Singapore and Malaysia. 2nd Edition. Singapore. (1996) 23 example is war, strikes, terrorism, actions of governing authorities and Act of Parliament. Based on the explanation above, force majeure is considered as any action which uncontrollable and unavoidable by both parties that makes a performance to be impossible.80 The contractor does not have any liability on the effect occurs from the force majeure events and hence he is entitle for extension of time. 2.4.2 Failure to Provide Access Access to the site is very important in order to allow the contractor to commence his works on time. The employer has implied obligation to provide an adequate access to the contractor. This is very important since it allows the transportation and delivery of materials, plant, labours and equipment to reach the site. Besides provide ease to get access, the route also must be suitable for the type of vehicle required and available at the appropriate time81. The employer is also being responsible if the access to the site required local permissions as in the case of Penvidic Contracting Co Ltd v International Nickel Co. of Canada Ltd.82. The plaintiff was a contractor in the contract for laying of track and top ballasting on a railroad. He had been delayed because of failure by other contractor to properly grade and sub-ballast the right of way. Somehow, the defendant failed to obtain necessary permissions to cross various hydro lines and highways. Hence, the defendant was under breach of contract and entitled the plaintiff for damages. 80 Denise L. Nestel. Force Majeure Clause: The Basics. Executive Magazine. (2006) Daniel Atkinson. Access to Site. Atkinson Law. (2000) 82 [1975] 53 DLR 748 81 24 Under PAM 2006, breach due to failure in provide access to works giving the contractor time extension under the Clause 23.8 (u). 2.4.3 Late Possession of Site Delay or failure in giving possession of site makes the employer breach for implied duties. As Megarry J. said in London Borough of Hounslow v Twickenham Garden Developments83 Ltd: “The contract necessarily requires the building owner to give the contractor such possession, occupation and use as is necessary to enable him to perform the contract…” In the case of The Rapid Building Group Ltd v Ealing Family Housing Association Ltd84, the defendant who was the employer was clearly in breach of Clause 21 of the contract for failure in giving possession of site. There were some squatters occupying the north-east corner of the land. The defendant had conducted eviction action, but it was only succeed after 19 days effort before enable the contractors to take whole possession of the site. In interpreting the whole site possession terms, Whittal Builders v Chester-leStreet District Council85 case explains the phrase for possession of the whole site does not include the action for giving possession in piecemeal or portion of the site. If the employer does so, he is in breach of contract and entitles the contractor for damages. 83 [1970] 7 BLR 81 [1984] 1 Con LR 1 85 [1987] 40 BLR 82 84 25 All those cases shows that failure to give possession is a fundamental breach from the side of the employer, but recently the architect’s power seems getting wider and enable him to postpone the giving of possession. Latest Standard Forms of Contract provide provision for contractor’s entitlement to get extension of time in the event of delay in giving site possession.86 2.4.4 Excessive Change Orders Change in the context of construction contract means that any aspect of contractor’s performance which is different with what had been agreed in original contract87. Once employer had identified the area of changes, his agent on behalf of him, need to issue change orders so that the contractor can comply with it. Under variation clause in standard form of contract, the employer is permitted to give change orders against the project’s design either in terms of quantity or specification. There are many aspects of change orders made by the employer. For example, change in project’s scope, change in design, and substitution of materials. Poor planning and management may be the main reason of employer’s change order. However, excessive change orders can damage the sequence and planning of the project88. It does not only add the labour and material cost, but also affect a job’s productivity89 which contributes to delay. Leonard C. A. had conducted a study on The Effects of Change Orders on Productivity and he concluded that the accumulation of change orders results many 86 Clause 43.1 (h) PWD 203A 2010, Clause 23.8 (f) PAM 2006, Clause 24.1 (i) CIDB 2000. Michael T. Callahan. Construction Change Order Claims. Aspen Publishers. United States of America. Pp 3-10. (2005) 88 Michael T. Callahan. Construction Change Order Claims. Aspen Publishers. United States of America. Pp 471-472. (2005) 89 William Ibbs and Caroline Vaughan. Change and the Loss of Productivity in Construction: A Field Guide. (2012) 87 26 causes of loss of productivity such as stop-and-go operations, out-of-sequence work, loss of productive rhythm, unbalancing of successive operations and lack of management and engineering support90. The board in Ingalls Shipbuilding Division, Litton System91 case allowed the cumulative impact claim where three contracts had affected by several thousand change orders and also additional 58% of the contract price and 70% increase in project duration. Another case which proves that excessive change orders may contribute to delay is the case of Bell BCI Co. v. United States.92 The contractor was responsible to construct a five-story laboratory for the National Institutes of Health (NIH). During the construction works, the NIH decided to add another additional floor to the existing design which produced thousand change orders. Due to this modification, the contractor incurred extra $2 million and the whole project was delayed for 4 years. All cases mentioned above shows that excessive change orders issued from employer can result in delay for few years and big additional expenses. Hence, the employer must be careful in giving orders on changes to ensure that the contractor able to execute it without consuming extra time. 2.4.5 Delay in Issuing Drawings and Instructions Certainty in issuing drawings can resolve many disputes within construction industry. This is due to problems arise because of the uncertain information given and late in giving instructions which at the end give additional works to contractor and affect the sequence of works as well. 90 91 92 Charles A. Leonard. The Effects of Change Orders on Productivity. Concordia University. (1988) [1978] ASBCA No. 17579 [2008] 81 Fed Cl 617 27 Referred to the case of Roberts v Bury Improvement Commissioners93, it stressed on the importance of plans and drawings for contractors to commence their works on site and all of those documents need to be supplied within the reasonable time. Similarly in Wells v army & Navy Co-operative Society94, it was said that: “The plaintiffs (the contractors) must within reasonable limits be allowed to decide for themselves at what time they are to be supplied with detail”. In another case, J and J Fee Ltd. v. The Express Lift Company Ltd95, Bowsher J. held that the main contractor is under implied term to supply correct information on the works within reasonable times to enable the sub-contractors to fulfil its obligations under the sub-contract. 2.5 Requirement for Granting Extension of Time When submitting the application for extension of time, contractors need to follow the procedures that have been set out in the construction contracts and also several other conditions to ensure that the application will be granted. 2.6 Burden of Proof The contractor is responsible to proof that he is entitled to the extension of time. He must show proof that the employer causes the delay or it is caused by a neutral event. The contractor must be able to produce the relevant records of events. The decision to grant the extension will be based fully on the quality of the records. 93 [1870] LR 5 CP 310 [1902] 86 LT 764 95 [1993] 34 Con LR 147 94 28 If the contractors experienced delay because of variation orders or excessive orders, the contractor can produce the wages sheet for labours, extra usage for plant and equipment. Or if the contractor has record on loss of productivity, this can help him in successfully get the time extension. Besides that, the minutes of the monthly progress meeting can be a valid supporting documents since they record the actual progress on site besides any problems encountered by every parties involved in the project.96 2.7 Duties of Contract Administrator A contract administrator (CA) is required to act impartially and reasonably when dealing with application for extension of time. This is very important so that the contractor will not be harmed by the power of the CA. This obligation is expressly stated in the standard form of contract as follows: i) PWD 2010 Form of Contract mentioned that the S.O must make a fair reasonable extension of time;97 ii) CIDB 2000 Form of Contract requires the Superintending Officer to grant such extension of time after making fair, reasonable and necessary opinion;98 and iii) PAM 2006 Form of Contract gives power to Architect to make fair and reasonable decision in granting extension of time.99 96 Eggleston, B. Liquidated Damages and Extensions of Time. Blackwell Publishing. United Kingdom. Pp 248-249. (2009) 97 PWD 203A Standard Form of Contract. (2010). 98 CIDB Standard Form of Contract. (2000). 99 PAM Standard Form of Contract. (2006). 29 The general rule in determining a fair and reasonable decision to grant an extension of time is that there should be a thorough analysis and a proper application of the provisions of the contract. This rule was stated in John Barker Construction v London Portman Hotel Ltd.100 It cannot be denied that the architect was concern with the cost and time overrun on the contract, but the architect failed in making a fair and rational judgment. The court held that even if the architect was acting in good faith or not in ultra vires, the determination in giving extension of time was not a fair decision and hence made the certificate invalid. As a certifier, a CA is not only bound to act based on his own passive role, but also must take the employer’s right into consideration since he is also acting as an agent for the employer. This is well explained in the case of Holland Hannan & Cubitts (Northern) Ltd v Welsh Health Technical Services Organisation.101. The architect in this case had failed to issue a variation order and an extension of time to the contractor for the design defects in window supplied by a nominated subcontractor. The architect believed that the problem only involved the main contractor and the subcontractor; hence he opposed issue either variation order or extension of time. Newey J in giving his judgment stated that: “However, I find it impossible to believe that architects in charge of a great building project, which has been brought to a stop by an unexpected difficulty, are entitled to adopt a passive attitude, as PTP did in this case. PTP’s failures were ones of omission rather than of commission, but I think that they nonetheless amounted to a breach of contract. The same conclusion as I have reached in regard to the issue of a variation instruction applies, I think, to the grant to Cubitts of an extension of time…” 100 101 [1996] 12 Const. L.J. 277 [1981] 18 BLR 80 30 If an extension of time certificate is not valid, there will be no initial date to run liquidated damages from and hence, the employer can sue for every general damages that he can prove. The invalid certificate can falls either in any one of follows: a) Not given on time, b) Not in a right form, c) It is given by a wrong person, d) It does not have certifier’s name, e) The decisions taken is not carrying out properly, f) Unfair issuance of certificate, g) Contractual machinery not applied.102 2.8 Time for Granting Extensions In discussing the issue of timing for granting extension of time, the general rule is that, it must be not too late so that: i) The liquidated damages provision will still be effective, and ii) The contractor has sufficient time to re-programme his works. In order to get better understanding of this rule, the case of Miller v London County Council103 is the best example to look at. The contract provided an extension of time clause that allowed the engineer to give it via retrospectively as follows: 102 103 Brian Eggleston. Liquidated Damages and Extensions of Time. Blackwell Publishing. United Kingdom. Pp 219-227. (2009) [1934] 151 LT 425 31 “It shall be lawful for the Engineer, if he thinks fit, to grant from time to time, at any time or times, by writing under his hand such extension of time for completion of the work and that either prospectively or retrospectively and to assign such other time or times for completion as to him may seem reasonable”. The original completion date was on 15 November 1931 while the contractor successful completed all the works on 25 July 1932. The Engineer issued the Certificate of Extension of Time on 17 November and the extension period was until 7 February 1932. Even though the express provisions allowed the Engineer to back-dated the time for extension, but the court held that it did not give him the power to fix a new completion date after all works have been completed. Due to negligent of the Engineer not to exercise his power in a reasonable time, hence the contractor did not have a sufficient time to re-programme his works in order to achieve the new completion date and this made the employer lost the benefits of the clause to recover liquidated damages from the contractor. Different decision was held in the case of Amalgamated Building Contractors Ltd v Waltham Holy Cross UDC.104 The contractors experienced difficulties in getting available materials and labours and hence failed to complete the works on the original agreed date, 7 February 1949. The contractors fully completed all works on 28 August 1950. On 19 January 1949, the contractors applied for 12 months extension and the architect only replied by giving letters on 20 December 1950, stated that the extension of time was from 7 February 1949 until 23 May 1949. The employer henceforth claimed for liquidated damages at £50 per week for period of 23 May 1949 until 28 August 1950. 104 [1952] 2 All ER 452 32 The contractors opposed the liquidated damages claimed and relied on Clause 18 which stated that: “The architect shall make a fair and reasonable extension of time for completion of the works”. Whereby, the contractors understand this provision as duties for architect to give them a date which they can aim in the future, not a date which had passed and claimed that the extension certificate was invalid. Lord Denning and other members of the Court of Appeal in giving judgment on this case did not agree with what had been understood by the contractors. The judges interpreted the retrospective power of the architect as giving him authority to give a certificate of extension even after the works had already been completed and the date had been passed. As a result, the contractors were liable to pay liquidated damages of £50 a week from 23 May 1949 to 28 August 1950. Both results show contrary interpretation on timing for granting extension. In order to resolve this problem, it is better if the standard form can have proper and clear wording so that the parties become clear on this matter. In Malaysia, CIDB Standard Form of Contract is the only contract form provided on this provision105. 105 CIDB Standard Form of Contract. Clause 24.7 (2000) 33 2.9 Conclusion Extension of time is the extended time granted to contractors in any circumstances which beyond of their control. Standard form of contracts normally provide a provision on this matter since construction is an industry with many uncertainties and expose to many external risk which can delay the completion. In order to make sure that the contractors can get the extension of time, they must be able to proof that the event lead to delay in performing the works and hence entitled them for the extra period. They can use any contract particulars or their own records as the supporting documents for their application. The contract administrator who acts as a certifier and as an agent as well, has big responsibility in either to allow or reject the contractor’s application. He needs to make impartial decision and grant a fair and reasonable time extension to the contractors. Besides, he also has duty to make sure that the time for granting the extension is not too late so that the contractors has sufficient and adequate period to re-programme their works so they able to complete all the works according to the new completion date as granted by the contract administrator. CHAPTER 3 BEST ENDEAVOURS 3.1 Introduction Best endeavours terms are widely used in various contracts and it goes the same in construction contract. Thus, it is not unique to find this phrase in standard forms of construction contract, particularly in the extension of time clauses. The word ‘shall’ in the provisions indicate that the contractor’s duty to use best endeavours is a condition precedent. It also means that the contractor must perform this duty before he can be granted with an extension of time and also as a relief from being imposed with liquidated and ascertained damages. Hence, this clause is provided to remind the contractor to put his best effort in preventing delay or put the delay losses as minimum as possible. Referring to The Official Journal of the Law Society of Hong Kong (2004), best endeavours and best efforts terms are used interchangeably in the court. This is also supported by the case of Corporate Development International Ltd v The 35 Hartstone Group plc,106 where the court held that ‘best efforts’ undertaking amounted to a ‘best endeavours’ obligation. Best endeavours have been used as an indicator for contractor’s standard of duty in preventing the occurrence of delay. Besides best endeavours, there are several other terms also being used to show the standard of duty, which are: i) Reasonable endeavours, ii) Reasonable care and skill, iii) Absolute duty. It is submitted that the contractor’s duty to use his best endeavours to prevent delay is similar to duty to mitigate losses under the general law of contract. Mitigation is a duty of an innocent party when claiming damages against the party in breach. In order to make sure he is entitled for the damages, he must prove that he has carried out mitigation measures to reduce the consequences of that breach event. Otherwise, his entitlement towards the damages may be reduced or totally loss. Based on the brief introduction on best endeavours, thus this chapter will provides an overview of what is meant by best endeavours, the contractual provisions and also other types of standard of duty applicable in mitigating delay in order for the contractor to be granted with an extension of time. 106 QBD November 1992 36 3.2 Principles of Mitigation If a party does not carry out his obligations to the standard required as stated in the contract, the party is in breach of contract. Section 74 Contract Act 1950 sets out the guidelines for compensation entitled to the innocent party for loss or damage caused by breach of contract107. Any loss suffered by the innocent party is compensable with condition that it is not too remote. Thus, the basis of law for recoverable damages is contained in the judgment of Alderson B. in the case of Hadley v. Baxendale108, where it is limited to: i) Damage which naturally arose in the usual course of things from the breach; and ii) Damage which in the contemplation of both parties, at the time they entered into the contract, is likely to be occur if they are in breach.109 The measure of damages does not include losses caused by the failure of innocent parties to take reasonable steps to mitigate the loss. Mitigation can be defined as to make less rigorous or penal110. There are three rules relating to mitigation for breach of contract. They are: i) Damages that can be avoided by taking reasonable steps - The injured party is not entitled to damages that could be avoided by taking reasonable steps, if he fails to carry out them. 107 Contract Act 1950 (Act 136). International Law Book Services. Selangor. (2008) [1854] 9 Exch. 341 109 Section 74(1) Contract Act 1950. 110 The Free Dictionary by Farlex. Retrieved from http://legal-dictionary.thefreedictionary.com. August. (2012). 108 37 ii) Damages that cannot be recovered by unreasonable steps - If the injured party takes any unreasonable steps in order to mitigate the losses, and he succeeds, he is not entitled for that loss incurred. iii) Damages that can be recovered by reasonable steps - If the injured party taking any reasonable steps to mitigate the losses, he is entitled for the expenses incurred during the mitigation actions. - Even if the mitigation action fails to reduce the loss or in the opposite, it just increases the loss, he is entitled for the damages.111 These principles had been applied in the case of Kabatasan Timber Extraction Co. v. Chong Fah Shing112. In this case, the Federal Court held that it was the duty of the respondent to take reasonable steps to mitigate the damages caused by the appellant when he failed to deliver logs to the mill but left them some 500 feet away. The court held that there was ‘no need for the respondent to have gone to the expense and trouble of buying logs from elsewhere when the logs were lying a few hundred feet away and all that was required was additional expense for hauling them up to the sawmill’. The respondent had instead purchased timber from other sources to make good the shortage. The damages awarded to the respondent for failing to mitigate were reduced accordingly. In the case of Dunkirk Colliery Co. v. Lever113, James LJ emphasised that this principle does not impose on the plaintiff an obligation to take any step which a reasonable and prudent men would not ordinarily take in the particular circumstances.114 111 See British Westinghouse v. Underground Electric Railway [1912] A.C. 673 [1969] 2 MLJ 6. 113 [1878] 9 Ch. D. 20 114 Thomas Lundmark. Common Law Tort & Contract. LIT Verlag Munster. London. (1998) 112 38 “The person who has broken the contract is not to be exposed to additional cost by reason of the plaintiffs having done what they ought to have done as reasonable men, and the plaintiffs not being under any obligation to do anything otherwise than in the ordinary course of business.” 3.3 Definition of Best Endeavours Best endeavours is a standard of duty115 in order to mitigate loss occurred from delay caused by the employer or neutral event. Standard forms of contract provide this requirement as one of the express provisions which make it a condition precedent before an extension of time can be granted to the contractor.116 Even without this express provision, section 74 of Contract Act 1950 and under common law as well, the contractor, by implication is under the duty to reduce or prevent the delay: “In estimating the loss or damage arising from a breach of contract, the means which existed of remedying the inconvenience caused by the non-performance of the contract must be taken into account”.117 In order to get brief idea of what endeavour is, it seems useful to have a look at the definition given by The Free Dictionary by Farlex. It defines ‘endeavour’ as: 115 116 117 Aleka Mandaraka-Sheppard. Modern Admiralty Law 2nd Edition. Routledge-Cavendish. New York. (2007). Clause 25.3.4 JCT (1998), Clause 23.1 CIDB (2000), Clause 23.8 PAM (2006), Clause 43.1 PWD (2010) Explanation, Section 74 Contract Act 1950 (Act 136). (2008) 39 i) A purposeful or industrious undertaking (especially one that requires effort or boldness); ii) Earnest and conscientious activity intended to do or accomplish something; iii) Give the best shot; or iv) The supreme effort one can make118. Hence, from those definitions, even without the ‘best’ phrase, it is clear that the meaning of ‘endeavour’ is stronger and dominant than the simple comparison of a ‘good try’. From the view of case law, it can be understood from the decision in Pips (Leisure Productions) Limited v. Walton119 that: “Best endeavours are something less than efforts which go beyond the bounds of reason but are considerably more than casual and intermittent activities. They must at least be the doing of all that reasonable persons could do in the circumstances.” 3.4 Standard of Duty to Reduce Delay The standard forms require the contractor to take steps to reduce the effects of delays, to mitigate the delay, but the extent of the obligation differs. It appears that, it is submitted; failure to comply with the obligation may reduce or even extinguish the contractor’s entitlement to extension of time. Thus this section will discuss the 118 The Free Dictionary by Farlex. Retrieved from http://legal-dictionary.thefreedictionary.com. August. (2012). 119 [1982] P&CR 450 40 extent of obligation in mitigating the delay and each of them will relate with the requirement of best endeavours. 3.4.1 Best Endeavours and Absolute Duty An absolute requirement is the highest obligation in order to achieve a particular outcome. Absolute obligations impose a heavy burden to the contractor as he is liable to do all that is required by contract, by what method it is120. This may come with the wording of ‘shall’ or ‘procure’ in the standard form of contract. In a UK recent case Sweet (UK) Ltd. v. Michael Wight Homes Ltd121, the quantity surveyor (QS) was obliged by its appointment to ‘prepare contract documentation and arrange for such documents to be executed by the parties thereto’. The contractor became insolvent before providing the performance bond in favour of the employer. The court rejected the employer’s argument that the QS was under an absolute obligation to procure the bond from the contractor. The QS was subject to the implied test of reasonable skill and care and had satisfied its duty in these circumstances. The lesson from this case is if a party wants to imply an absolute obligation on another party to achieve something, a clear wording to that effect should be used122. However, according to Charles Boundy (2010), obligation to use best endeavours is not a proper substitution for an absolute obligation123. 120 This is Arnheim & Co. Solicitors. Contractual Drafting. Retrieved from http://www.arnheimsolicitors.co.uk. (2012) 121 [2012] EW Misc 3 (CC) 122 Suzanne Reeves. 2012 Construction Case Law Summary (January-June). Wedlake Bell. London. 2012. 123 Charles Boundy. Business Contract Handbook. Gower Publishing Company. USA. (2010). 41 supported by the case of Midland Land Reclamation Ltd. v. Warren Energy Ltd.124, where the court held that best endeavours obligation was not the next best thing to an absolute obligation or guarantee. While in Terrell v Mabbie Todd and Co.125, it was held that a best endeavours obligation only required a party to do what was commercially practicable and what it could reasonably do in the circumstances.126 As referred to the case of Victor Stanley Hawkins v. Pender Bros Pty Queensland127, the term best endeavours should be construed objectively. The test is relied on the compliance of prudence and reasonableness elements. 3.4.2 Best Endeavours and Reasonable Endeavours The court had for long time tried to draw a line between best endeavours and reasonable endeavours phrases as there is no affirmative legal definition on them. Mustill J. in the case of Overseas Buyers v. Granadex128 said that: “Perhaps the words best endeavours in a … contract mean something different from doing all that can reasonably be expected - although I cannot think what the difference might be”. A recent guidance regarding this issue can be obtained from the decision of Mr Julian Flaux QC sitting as a judge in the case of Rhodia International Holdings Ltd. v. Huntsman International LLC,129 where he made it clear that those best and reasonable endeavours placed the contractor at two different levels of obligations: 124 [1997] [1952] 69 RPC 234 126 Vivian Ramsey and Thomas Telford. Construction Law Handbook. Thomas Telford. London. (2007). 127 [1994] 10 BCL 111 128 [1980] 2 Lloyd’s Rep 608 129 [2007] EWHC 292 125 42 “There may be a number of reasonable courses which could be taken in a given situation to achieve a particular aim. An obligation to use reasonable endeavours to achieve the aim probably only requires a party to take one reasonable course, not all of them, whereas an obligation to use best endeavours probably requires a party to take all the reasonable courses he can.” The recent guidance regarding this issue can be obtained from the case of Rhodia International Holdings Ltd. v. Huntsman International LLC130. Mr J Flaux QC made it clear the border line between best and reasonable endeavours by placed them at different levels of obligation upon the obliged party. Best endeavours is the most onerous obligation need to be fulfilled by the party, while reasonable endeavours is less stringent compared to best endeavours. In order to describe in details the difference between best and reasonable endeavours, he further said that: “There may be a number of reasonable courses which could be taken in a given situation to achieve a particular aim. An obligation to use reasonable endeavours to achieve the aim probably only requires a party to take one reasonable course, not all of them, whereas an obligation to use best endeavours probably requires a party to take all the reasonable courses he can.” David Chappel thought that reasonable endeavours placed less stringent standard of duty upon the contractor than best endeavours.131 This opinion is similar to a court decision in the case of UBH (Mechanical Services) Limited v. Standard Life Assurance Co.132 where it was held that the reasonable endeavours was appreciably less than best endeavours. 130 [2007] EWHC 292 David Chappell, Michael Dunn and Michael Cowlin. Building Law Encyclopaedia. John Wiley and Sons. UK. (2009) 132 [1990] BCLC 895 131 43 It is understandable that if a party is under reasonable endeavours obligation, he may carry out at least one course of action until it is exhausted but if the same party is under best endeavours obligation, he must performs all reasonable actions until they are exhausted. In the case of Jolley v Carmel Ltd.133 the court held that best and reasonable endeavours are placed at opposite ends of a spectrum of obligations, while all reasonable endeavours may be placed somewhere in the middle of those two endeavours.134 Hence, it can be concluded that reasonable endeavours offer less burden of obligation than best endeavours and this can be measured from the duty in performing number of steps in achieving the outcome. 3.4.3 Best Endeavours and Mitigation Extension of time is a type of remedy provided for the contractor in the event of delay caused by employer’s breach or neutral event.135 Here, the contract administrator is under a duty to consider the contractor’s duty to mitigate the delay when granting the extension of time. According to Robinson (2004), there are two situations when discussing duty to mitigate, they are: 133 i) Shall take reasonable steps to minimise its loss, and ii) Shall not take unreasonable steps that increase its loss.136 [2000] 2 EGLR 154 Slaughter and May. Best endeavours v. reasonable endeavours, what do they mean? Does either mean anything? London. (2007) 135 Clause 25.3.4 JCT (1998), Clause 24.1 CIDB (2000), Clause 23.8 PAM (2006), Clause 43.1 PWD (2010) 136 Allens Arthur Robinson. Delay and Disruption Protocol. Construction Breakfast Seminar. The Society of Construction Law. (2004). 134 44 The first situation may show the steps taken by contractor against the delay event. It may come in the form of acceleration of work, re-scheduling of work programme, or even by requiring working overtime. In order to determine whether the contractor is entitled to recover the losses incurred by these actions, it is referred to the basic principles of damages.137 The general principle is that every party is under a legal and moral obligation not to build up the damages after there has been a default by the other party; instead the injured party is required to take reasonable steps to try to keep potential damages as low as reasonably possible.138 Thus, as long as the contractor’s actions to mitigate delay are reasonable, he can recover the losses involved. In the second situation, it means that duty to mitigate does not extend the party to carry out any change in scope than the original scope, or spend more money to reduce the effect of the delay event.139 In the other situation, there may be some limited actions that are stipulated in the contract that shall be taken by the contractor; the contractor’s non-performance of those actions may taken as failure in taking mitigation action. . This can be seen from the case of Motherwell Bridge Construction Limited v. Micafil Vakuumtecchnik,140 where the condition of contract had stated that if unexpected delays and difficulties occurred, Motherwell was required to provide additional personnel at no extra cost at the request of Micafil to meet the completion date. However, Motherwell had carried out acceleration and has incurred some costs along the activities. Thus, the contractor’s claim for the extra cost was dismissed. Similar to the principle of best endeavours, as long as the contractor has taken any reasonable steps to prevent the delay or put the losses to as minimum as possible, 137 Michael S. Simon. Construction Contracts and Claims. McGraw-Hill Book Company. United States. pp 240-241. (1979) 138 See Maraldo Asphalt Paving Inc. v. Harry D. Osgood Co. Inc. [1974] 220 N.W. 2d 50 139 Allens Arthur Robinson. Delay and Disruption Protocol. Construction Breakfast Seminar. The Society of Construction Law. (2004). 140 [2002] TCC 81 CONLR 44 45 hence he has rights to claim what had been loss. This had been specified in the case of Terrell v Mabie Todd & Co. Ltd.141 whereby the judge held that best endeavours obligation only required a party to do what could reasonably be done in the circumstances. “Best endeavours are something less than efforts which go beyond the bound of reason, but are considerably more than casual and intermittent activities. There must be at least be the doing of all that reasonable persons reasonably could do in the circumstances.” Thus, from the discussion, it can be concluded that mitigation refers to any action taken to prevent the delay but it must be carried out within a standard of duty known as reasonableness whilst best endeavours refers to the level of requirement in performing mitigation action. So, in short, best endeavours is one of the subset of standard of duty to fulfil mitigation obligation and the combination of these two terms subjected the contractor to execute all reasonable steps which a prudent and reasonable person may take in a such circumstances. 3.5 Contractual Provisions It is submitted that even in the absence of express provisions in the standard form of contract, the contractor is still under an implied duty to mitigate his loss. The fact that the construction contract include express clauses in order for contractor to reduce delay, make that duty as an important one and in fact is a condition precedent before an extension of time can be granted. 141 [1952] 69 RPC 234 46 For example, in clause 23.6 of the PAM 2006 standard form of contract, states that: “The contractor shall constantly use his best endeavour to prevent or reduce delay in the progress of the works, and to do all that may reasonably be required to the satisfaction of the Architect to prevent and reduce delay or further delay in the completion of the Works beyond the completion date”. Another provision is as in clause 25.3.4 of the Joint Contract Tribunal (JCT) standard form of contract 1998142 provides that: “the Contractor shall use constantly his best endeavours to prevent delay in the progress of the Works…’ Another terms being used to describe best endeavours for other standard forms as found in PWD 203A Standard Form of Contract (Rev 2010)143, Clause 43.1 mentions that: “…Provided always that the Contractor has taken all reasonable steps to avoid or reduce such delay and shall do all that may reasonably be required to the satisfaction of the S.O. to proceed with the Works”. While in Clause 24.1 in CIDB Standard Form of Contract 2000, Clause 24.1 states that: 142 143 JCT Standard Form of Contract. (1998) Public Works Department. PWD 203A Standard Forms of Contract. (2010) 47 “Provided that the Contractor has carried out the Works or any section of the Works with due diligence and has taken all reasonable steps to avoid or reduce such delays,” Regardless of what terms being used in the standard forms of contract, all of them have the same intention to instruct the contractor, in order to be granted with an extension of time, they must prove that they have used their best effort in mitigating the delay or put the delay losses as minimum as possible. 3.6 Summary As a conclusion, best endeavours can be easily understandable by equating it with the word reasonableness whereby it is one of the benchmark to measure the standard of duty. Besides best endeavours, there are various standard of duty available, for example absolute obligation which holds the highest and greatest burden on the contractor’s shoulder. Other than that is reasonable endeavours obligation which is less stringent than best endeavours. In order to mitigate the delay, the contractor must comply with the standard of duty required by the standard form of contract. CHAPTER 4 ANALYSIS OF CASES FOR BEST ENDEAVOURS 4.1 Introduction The main focus of this chapter is the analysis and reviews those cases relating to the issues of best endeavours. The selected cases are English cases and not limited to construction contract only since best endeavours are not a crucial issue in construction contract. There are cases relating to sale and purchase of property and sale and purchase of shares where all of them contained best endeavours clauses. Based on the nine cases reviewed and analysed, the findings can be summarized as follows: 4.1.1 Planning Permission Case 1 : IBM UK Ltd v Rockware Glass [1980] FSR 335 This case related to duties to obtain planning permission and whether action not to appeal is considered as breach of best endeavours. The obligations on best endeavours are: 49 i) Not to expend large sums of money, ii) The responsibility is under the party who has interest on that matter. Case 2 : Obagi v Stanborough (Developments) Ltd [1993] EGCS 205 This case related to duties in obtaining planning permission from local authority. The issue was again whether action not to appeal was considered as breach of best endeavours. The obligation on best endeavours is: i) Carry out all reasonable steps available. Case 3 : Yewbelle and Knightsbridge Green Ltd. v. London Green Developments [2006] EWHC 3166 This case related to duties in obtaining planning permission for a land development. The issue was whether a party is considered as having taken all reasonable endeavours once all efforts had been performed but still did not succeed. The obligation on best endeavours is: i) 4.1.2 Required to perform all reasonable steps even it ends up with a failure. Sale and Purchase of Shares Case 1 : Rackham & Anor. v. Peek Foods Ltd & Ors. [1990] BCLC 895 This case related to sale and purchase agreement of shares in a company. The issue was whether the decision to not proceed with the business transaction caused 50 that party to breach the best endeavours duty, indirectly breaching the agreement. The obligation on best endeavours is: i) Does not require the party to sacrifice his own interests and put his position at risk. Case 2 : Rhodia International Holdings Ltd v Huntsman International LLC [2007] EWHC 292 This case related to a sale and purchase agreement of a chemical manufacturing company. The issue was whether failure to carry out a particular action required in the contract was considered as failure to carry out reasonable endeavours. The obligation on best endeavours is: i) 4.1.3 Carry out the particular steps as specified in the contract form. Defective Works Case 1 : Terrell v. Mabie Todd [1952] WN 434 This case related to a license agreement to manufacture and sell fountain pens. The issue here is whether non-compliance with plaintiff’s instruction was considered the defendant in breach of best endeavours. The obligations on best endeavours are: i) The defendant should comply with plaintiff’s instruction, ii) The defendant must not cause losses to plaintiff. 51 Case 2 : Midland Land Reclamation Ltd, Leicestershire CC v. Warren Energy Ltd [1995] ORB No 254 This case related to responsibility in handling the generation of electricity using methane gas. The issue was whether the defendant had failed use its best endeavours in preventing the loss. The obligation on best endeavours is: i) Not to spend large amount of money. Case 3 : Sandhu v Sidhu [2010] EWCA Civ 531 This case related delivering of share certificates as instructed by the court. The issue was whether the defendant had use his best endeavours to comply the order. The obligation on best endeavours is: i) Must perform the action as early as possible. Case 4 : Walter Lilly & Co Ltd v. Mackay & Anor. Company [2012] EWHC 1773 This case related to the excessive delay and extension of time issued by the architect. The issue was what amounted to best endeavours under the contract. The obligations on best endeavours are: i) Giving notice regarding the delay event or likely to be delayed, ii) Estimate the time extension period. 52 4.2 Analysis of Relevant Cases - Planning Permission 4.2.1 IBM UK Ltd v Rockware Glass [1980] FSR 335 Rockware agreed to sell IBM some land for development, and the sale was conditional upon planning permission being obtained, with a further proviso that IBM ‘will make an application for planning permission and use its best endeavours to obtain the same’. The local authority refused to grant the planning permission. IBM did not appeal against that decision to the Secretary of State. The issue was whether, by not appealing, IBM had failed to use its best endeavours to obtain planning permission. Under the Planning Act, an unsuccessful applicant may make an appeal but the seller did not make the appeal. It was accepted that making an appeal to the Secretary of State would cost a significant amount of money. The issue that arose here was whether IBM had failed to perform its best endeavours in obtaining the planning permission when it did not appeal to the Secretary of State. The court held that, taking into account the facts of the case and the amount of money involved, it was not likely that the parties would have considered a refusal of planning permission at a local level to be the end of the matter, but that they must have had in mind the prospect of an appeal to the Secretary of State. The test of ‘best endeavours’ which was approved was that the purchasers of land were bound to take all those steps in their power which were capable of producing the desired results, namely the obtaining of planning permission, being steps which a prudent, determined and reasonable owner, acting in his own interests and desiring to achieve that result, would take. 53 The court further said: “ It was expressly stated that the criterion was not that of someone who was under a contractual obligation, but someone who was considering his own interests.” A sale and purchase agreement of a land usually can only be purchased after the purchaser has obtained the planning permission. It was in the purchaser’s interest to make sure that the planning permission obtained allowed the purchaser to develop the land according to his plans. Therefore, in this case, the contract had provided that the developer needed to use his ‘best endeavours’ in getting the planning permission. Failure at the first stage of application should drive them to make an appeal since that was considered as an action which another comparative person would take. When considering best endeavours, it was not about complying with the contractual requirement, but the compliance was subject to the interest of the parties. Whilst it seemed clear that a contractor or subcontractor may be required to expend some money to meet the obligation to ‘use constantly his best endeavours’ to prevent delay, the intention was not to expend large sums, particularly where the delay has been caused by the engineer or the architect. However, the liability to take that action which was appealed against the decision did not entitle the developer to spend large sums of money. This was not the principles in fulfilling ‘best endeavours’ obligations. Hence, the developers were not subjected to make an appeal against the local authority’s decision even though they were the interested parties in the subject matter of the sale if the effort to do that required them to spend substantial sums of money. 54 From this case, not making the appeal to the Secretary of State for failure in getting planning permission from the local authority is considered as not a breach of the ‘best endeavours’ obligation. 4.2.2 Obagi v Stanborough (Developments) Ltd [1993] EGCS 205 The plaintiff claimed that, pursuant to a contract entered into by him with the defendants on 8 March 1984, the defendants were obliged to apply to Windborne District Council, the local planning authority, as soon as reasonably practicable for planning permission for the erection at least 125 residential units and to use their best endeavours to obtain such permission within a period of five years from 8 March 1984. No permission of any kind for the development of the site was obtained within the five year period. Further, the plaintiff claimed that the defendants failed, in breach of their obligations under clause 12 of the contract, to use their best endeavours to obtain such planning permission and that had they used their best endeavours such planning permission could have been obtained or, at the very least, there was a reasonable chance that such permission could have been obtained. If the requisite planning permission had been obtained within the five year period the contract entitled the plaintiff to acquire one half of the site for £200,000 plus half of all planning fees and charges incurred by the defendant in obtaining the requisite planning permission. Accordingly the plaintiffs seek damages for the defendants’ breach. The defendants argued that they were not obliged to apply for, much less obliged to use their best endeavours to obtain the planning permission. But even if 55 they were, they were under no obligation to appeal any refusal by the local planning authority. It was a fact that the defendants did indeed apply for the permission and that, the application was refused. The application was made in late February 1988 and was refused by the local planning authority on 9 May 1988. The defendant said that at no stage during the five year period was there ever any reasonable prospect of the site receiving planning permission whether from the local planning authority or on appeal to the Secretary of State. It therefore resisted the plaintiff's claim. They also disputed the plaintiff's approach to the assessment of damages. There were two issues arose here. First, did the clause oblige the defendants to use their best endeavours to obtain within five years the planning permission? Second, did the clause oblige the vendor to appeal any refusal of the local planning authority to grant such permission? It was a fact that the defendants took no further action on the process for local plan apart from sending to the District Council in June 1984 a copy of feasibility study of the site and sending to the Council on 8 February 1985 a letter of representation on the consultative draft plan. Besides, the defendants refused to give any assistance to the plaintiff, or to those who represented him, in their attempts, given the defendants’ unwillingness to get further involvement, to challenge the density levels for the site set out in the deposit plan. The judge stated that the use of best endeavours by the defendants to obtain the requisite planning permission included involving itself in the local plan process by objecting to the deposit plan policies for the site and by seeking at the inquiry to argue for a greater density and by taking steps to interest officers in, and persuade them of the merits of the subsequent planning application. By failing to do these things the defendants were in breach of their obligation to use their best endeavours. 56 The judge with assistance from the similar case in IBM United Kingdom Ltd v. Rockware Glass Ltd said that : “In my judgment, the obligation to use best endeavours to obtain the requisite planning permission required the defendant to take all such reasonable steps to obtain the requisite planning permission which a prudent and determined man, acting in his own interest and anxious to obtain such planning permission, would have taken.” This is another case related to planning permission besides IBM UK Ltd v Rockware Glass.144 The present case showed that defendant had taken his reasonable action in order to obtain the planning permission for the proposed project by submitting the report of feasibility study and letter of representative on draft plan within the time frame of 5 years. After around one month from the submission date, the local planning authority rejected the application. By sending those documents to the authority, it showed defendant’s endeavours in getting the planning approval. However, this was not adequate to described what best endeavours meant in the contract. The defendants still had other alternative ways to obtain the planning approval since the time duration left was still long. This is the point where this present case is different from IBM’s case. Defendant in this case can make an appeal against the decision by involving in the local plan process as required by the local authority, besides expressing his objection against the plan policies for the site and try to convince the authority regarding his 125 units plan. All of this effort would not affect defendants’ position or financial interest or commercial interest. Contrast this with what happened in 144 [1980] FSR 335 57 IBM’s case whereby the defendant needed to spend substantial amount of money in order to appeal the decision. Hence, what can be concluded here is that the responsible party need to put all effort in obtaining the planning permission as stated in the contract, to use best endeavours. Obligations for performing best endeavours can come in various actions and ways, depending on the situation as long as all the steps required do not put the party into a disadvantage position. 4.2.3 Yewbelle and Knightsbridge Green Ltd. v. London Green Developments [2006] EWHC 3166 Knightsbridge Green Ltd entered into an agreement for the sale of a property in South London for £13.75 million to London Green Developments Limited (LGD). Under the agreement, LGD was not obliged to complete the purchase until an agreement under Section 106 of the Town and Country Planning Act 1990 for planning permission had been entered into with the planning authority, London Borough of Merton. The sale agreement provided that Knightsbridge was obliged to use all reasonable endeavours to secure a completed Section 106 agreement substantially in the form of the draft attached to the sale agreement. Soon after the sale agreement was entered into the requirements of the planning authority changed in relation to the Section 106 agreement. To compound the situation and crucial to this case, it turned out that a small parcel of land, known as the third party land, at the south-east corner of the property which was needed for its proposed development did not belong to Knightsbridge but was in fact owned by an entirely independent company. This impacted on the obtaining of the requisite Section 106 agreement. 58 Subsequently, Knightsbridge transferred the property to Yewbelle Ltd subject to the sale agreement with LGD. In February 2006, Yewbelle/Knightsbridge’s solicitor informed LGD’s solicitor that it would not be possible to obtain the Section 106 agreement in the form attached to the sale agreement and asked if the sale could be completed without the Section 106 agreement being in place. If it could not be, the solicitor stated that Yewbelle would have no option but to treat the sale agreement as at an end. Subsequently, Yewbelle’s solicitor told LGD’s solicitor that since LGD had stated it did not wish to complete the purchase without the Section 106 agreement, the sale agreement should be treated as at an end because the Section 106 agreement could not be obtained. In June 2006, LGD came to an agreement with the owner of the third party land in relation to the Section 106 agreement. Importantly, however, LGD did not inform Yewbelle that it was aiming to do this, nor was Yewbelle told that it had done it until sometime later during the course of the subsequent proceedings. Proceedings were issued in June with LGD seeking to require Yewbelle to complete the sale of the property, even though there was no Section 106 agreement. Yewbelle argued that by then the sale agreement had already come to an end. The issue here is there any implied term under the contract that allows the seller to rescind the contract whereby the buyer not having an option to proceed with the transaction if the seller had use his all reasonable endeavours in obtaining planning permission but seems it end with a failure? Besides, to what extent the seller is required to put effort regarding ‘all reasonable endeavours’ terms? The judges in the Court of Appeal judge agreed that the seller did not need to sacrifice its own interest but only had to use all reasonable endeavours until it had exhausted all the possibilities. Impliedly, it meant that the contract will 59 automatically terminate because the seller failed to obtain the planning permission from the local authority. Yewbelle case shows that even ‘best endeavours’ term does not being used in the contract, where the present case substitute it with ‘all reasonable endeavours’, but the party was still obliged to carry out all reasonable steps which a prudent and determined person will take. Besides, both terms using the same principle whereby any effort in fulfil the obligation does not required the party to sacrifice his own interest as in Yewbelle’s case, it did not mean to go as far as buying the third party’s land so that he could get the planning permission. 4.3 Analysis of Relevant Cases – Sale and Purchase of Shares 4.3.1 Rackham & Anor. v. Peek Foods Ltd & Ors. [1990] BCLC 895 On 9 November 1973 the plaintiffs entered into an agreement to sell their shares in Roeday Ltd to the defendant (formerly known as Consolidated Commercial Co. Ltd. (Consolidated)) and Consolidated's merchant bankers, Edward Bates & Sons Ltd (Bates). The sale was conditional upon the approval of the shareholders of Consolidated, and Consolidated and Bates covenanted to use their best endeavours to procure the fulfilment of that condition. On 5th December 1973 the directors of Consolidated issued a circular to their shareholders recommending that they vote in favour of the acquisition of Roeday at an extraordinary general meeting convened for 28 December 1973. Bates supported the recommendation. On 17 December 1973 the government announced measures designed to restrain lending to property companies and to increase the tax on profits from property transactions. 60 On 19 December 1973 at a meeting between the plaintiffs, the managing director and few shareholders from Consolidated, a reduction in the purchase price was discussed and G was asked and he agreed to vote his shares irrevocably in favour of the Roeday acquisition. The extraordinary general meeting was postponed until 28 January 1974 and the Consolidated board issued press releases and a second circular stating that it could no longer recommend the Roeday acquisition. In the second circular the directors asked shareholders to return the blank proxies. At the extraordinary general meeting the Consolidated directors and Bates used their votes and the open proxies to ensure that the resolution for the approval of the Roeday acquisition was not put to the meeting. The plaintiffs brought an action claiming damages for the breach of the 'best endeavours' covenant by Consolidated and Bates, alleging that at the meeting on 19 December 1973 a reduction of the purchase price had been agreed and Consolidated’s Director had agreed to vote in favour of the Roeday acquisition. Both Consolidated and Bates are subjected to carry out ‘best endeavours’ to procure the fulfilment of condition in this sale and purchase agreement. Finally Consolidated’s Director drew their intention to not purchase Roeday from the plaintiff. The issue here is whether the action taken by Consolidated’s Director and their shareholders not to purchase Roeday considered as breach of ‘best endeavours’. The approval to acquire Roeday would have been passed at the extraordinary general meeting of the consolidated shareholders if Consolidated and Bates had recommended it. However, there was no breach of the 'best endeavours' covenant since that covenant did not oblige the directors of Consolidated or Bates to give bad advice. The directors of Consolidated and Bates no longer believed that the acquisition could benefit Consolidated because of the government measures to restrain lending to property companies, and accordingly they were under a duty to advise Consolidated shareholders against the acquisition and to use their powers to ensure that it was not approved. 61 Furthermore, in the case of Bates there was a possible conflict between its interests as a banker (under an obligation to supply finance for the acquisition) and its duty as an adviser, and in those circumstances, Bates was also not in breach of the 'best endeavours' covenant, as an independent merchant banker would have condemned the acquisition. Hence, the plaintiff’s application for the damages had been dismissed by the court. The plaintiff tried had referred to one previous case which was almost similar to the present. Northern Countries Securities Ltd v. Jackson & Steeple Ltd145 case was about a company which had entered into an unconditional contract to issue shares sough to evade obedience to a decree of specific performance by encouraging its shareholders to vote against the issue of the shares. It was held that the company was under a duty to comment the issue. While in the present case, the contract was conditional on the approval of the shareholders of Consolidated. The vendors at all times accepted the risk that the shareholders, properly advised that the contract was not in their best financial interests, would reject the contract. As stated in the contract, both Consolidated and Bates were obliged to use their best endeavours to get approval from all shareholders before they could purchase Roeday’s company. This meant that only if they really want to purchase the shares, so they were subjected to carry out their best endeavours. The general meeting held can be considered as one of the steps taken to show their endeavours to take over the shares. Unfortunately, the government announced on lending restriction and imposing increase tax on any property transaction. This brought them to lose interest in purchasing the shares anymore since it was no longer financially attractive. 145 [1974] 2 All ER 625, [1974] 1 WLR 1133 62 Hence, in another general meeting, the director of Consolidated issued circulars to the shareholders informing that the business transaction was not recommended. Even the director did not proceed with the transaction, but his action to stop the transaction was considered as in breach of the best endeavour covenant. From this case, it shows that for just a little action, it can be considered as taking best endeavours. The important main point here is that best endeavours must bring benefit to the party. The negative advice from the director to the shareholders not to vote in favour of the acquisition is not a breach of that duty. This is because, that action had protect the company from sacrificing their financial interests and indirectly give a better future to the organization. 4.3.2 Rhodia International Holdings Ltd v Huntsman International LLC [2007] EWHC 292 By a Sale and Purchase Agreement dated 27 February 2001 (‘the SPA’), Rhodia agreed with Huntsman to sell its chemical manufacturing business in Whitehaven to a recently incorporated subsidiary of Huntsman. One of the assets of the business was an energy supply contract with National Power (Co-Generation) Limited (‘Cogen’) under which Cogen supplied power and steam from an on-site Combined Heat and Power Facility (the ‘CHP’ Plant) to Rhodia’s business. The energy supply contract contained ‘take-or-pay’ provisions. Clause 15.1.2 of the SPA imposed obligations on both parties to use reasonable endeavours to obtain Cogen’s consent to the novation of the energy supply contract so that the Huntsman subsidiary would become the contracting place of Rhodia. It also required Huntsman to supply to Cogen all information reasonably requested by Cogen (including information about the financial position of the Huntsman Group) and, if Cogen reasonably required, to enter into a direct covenant 63 with Cogen to perform and observe the terms of the energy supply contract, in other words to guarantee its subsidiary obligations. Pending novation, Huntsman undertook to perform Rhodia’s obligations as agent under the energy supply contract (and did in fact do so between March 2001 and March 2004) and to pay all liabilities arising under, or in connection with, the energy supply contract as a result of the non-performance or negligent performance of its obligations. If the novation had still not been completed within six months, Huntsman was entitled to serve notice on Rhodia to exclude the energy supply contract from the sale of the business assets and terminate its obligations to Rhodia in relation to that contract. Under the terms of the energy supply contract, Rhodia could assign, novate or otherwise transfer any of its rights and obligations under that contract if it could satisfy Cogen that the proposed assignee was capable of fulfilling Rhodia’s obligations and duties under that contract. Huntsman was initially proactive and approached Cogen for its consent to the novation. Shortly afterwards, Cogen confirmed that, while it had no objection in principle to the proposed novation, since the company accounts for the Huntsman subsidiary were not available at that time (it being a special purpose vehicle recently incorporated to take over the chemicals business with no trading history or financial accounts), Cogen would require a parent company guarantee or similar security from Huntsman. Huntsman refused to provide any such security. When Huntsman provided Cogen with financial information in respect of its subsidiary, the accounts showed a significant inter-company debt, including a £14 million loan secured on the assets of the business. Cogen refused to consent to the novation until the Huntsman subsidiary substantially improved its financial results. 64 By this stage, Huntsman was considering closing the Whitehaven site and was looking at ways to minimize its liability under its principal/agency relationship with Rhodia with respect to the energy supply contract. Negotiations were not taken further by Huntsman and the novation was not completed. In March 2004, Huntsman formally withdrew its application to Cogen and gave notice to Rhodia that it no longer intended to perform its obligations under the energy supply contract. At that time, Rhodia had no operational presence at the Whitehaven site and so was not in a position to perform the obligations under the energy supply contract itself. A few days later, the CHP Plant was shut down and had not been in operation since. Later that year, Huntsman announced its intention to close the chemical manufacturing plant. The issue here is whether Huntsman had failed to carry out reasonable endeavours by failing to fulfil what had been stated in the contract term. Mr Julian Flaux QC concluded that the qualification of reasonable endeavour only required the performing party to take one reasonable course and not all of those courses available. It was considered that there may be a number of reasonable courses which could be taken in a given situation to achieve a particular aim. An obligation to use reasonable endeavours to achieve the aim probably only required a party to take one reasonable course, not all of them, whereas an obligation to use best endeavours probably required a party to take all the reasonable courses he could. The High Court decided that, by refusing to provide the guarantee reasonably required by Cogen or to explore with Cogen what form of security would be acceptable, Huntsman had failed to use its reasonable endeavours to obtain Cogen’s consent and so was not entitled to exercise the right to terminate its obligations under the SPA in respect of the energy supply contract. 65 The court then turned to consider what reasonable endeavours might entail. While the judge accepted that a reasonable endeavours obligation would not, in general, require a party to sacrifice its own commercial interests, the position was different where a party agreed (as Huntsman did here, to the provision of a direct covenant to Cogen) to take certain specific steps as part of the exercise of reasonable endeavours. In those circumstances, those steps would have to be taken, even if that could be said to involve the sacrificing of a party’s commercial interests. Indeed, the judge indicated that had it not been for the specific obligation for a direct covenant from Huntsman, he would probably have found that Huntsman had in fact used reasonable endeavours to procure the novation. From this case, it shows that ‘reasonable endeavours’ is less stringent than ‘best endeavours’. ‘Reasonable endeavours’ require the party to take at least one reasonable action but in ‘best endeavours’, the party needs to carry out all possible actions. However, in the event that ‘reasonable endeavours’ sets out any specific action to be taken by the party, that party is required to follow those steps as what a party in ‘best endeavours’ obliged to do. Even if the action will sacrifice the party’s commercial interest, he or she still bound to performed it. As what happen to Huntsman, he is in default since the contract had provided what steps should be taken by the contractual party for the novation. If this term is absence, Huntsman may be considered as had taken ‘reasonable endeavours’ after he provide Cogen with his financial information. 66 4.4 Analysis of Relevant Cases – Defective Works 4.4.1 Terrell v. Mabie Todd [1952] WN 434 The plaintiff (seller) entered into an agreement with the defendant (manufacturer) dated 3rd May 1948 whereby the plaintiff should grant the defendant a license to manufacture and sell fountain pens. They together agreed that the defendants should make their best endeavours to promote the sale of as many fountain pens made as reasonably possible in and should with all diligence place the said invention on the market and proceed to exploit it in accordance with the license scheduled to the agreement. The plaintiff alleged that the defendants had broken their obligations which that they had not used their best endeavours to promote the sale of either the fountain pens or the ink bottles as agreed and had failed to use all diligence to place the said inventions on the market or to exploit them. The defendants claimed that the contracts need to be read as a whole, required them to do only that which was commercially practicable, and this was interpreted to mean that the defendants were to sell the goods to the extent which was consistent with running the company efficiently and prudently and in the interests of the company and to no greater extent. The issue that arose in this case was the measure of best endeavours obligation by the defendants; to determine whether or not they were in breach of the best endeavours covenant. In delivering the decision, the judge referred to a few cases in defining the best endeavours term. In the case of Sheffield District Railway Co. v. Great Central 67 Railway Co.146, the court held that ‘best endeavours’ means what the words say, does not mean second-best endeavours. The defendants in fact were making a loss on their ink sales by not producing the ink according to the plaintiff’s design, but justified it as an advertisement. Referring to what the defendants had done, the court concluded that the defendants did not use their diligence and their best endeavours to promote the sale of either of the inventions. This case equates the best endeavours with due diligence action. The defendant shall take all reasonable steps in order to reach the objective of the agreement. Even though production of ink does not indicate the sales revenue but failure to follow plaintiff’s instruction automatically brings the defendant as breach of best endeavours. 4.4.2 Midland Land Reclamation Ltd and Leicestershire CC v. Warren Energy Ltd [1995] ORB No 254 Warren Quarry was a disused granite quarry which had been used since about 1981 for the disposal of waste by landfill and generated electricity from one of the gas produced through the disposal, methane gas. Formerly it was in the ownership of Leicestershire County Council (the Council). Since 26 July 1991 it had been in the ownership of Midland Land Reclamation Limited. By a written Deed of Assignment dated 8th April 1992 between the Council and Midland Land Reclamation Limited, the Council assigned absolutely to Midland Land Reclamation Limited with effect from the Completion Date (26th July 1991), all 146 [1911] 27 TLR 451 68 the benefit of its interest in the Warren Energy Agreement and Midland accepted absolutely all of the obligations of the Council to supply landfill gas for period of 15 years to the defendant and the defendant would purchase the gas which they would use to generate electricity for onward sale to the East Midlands Electricity Board. The parties included “best endeavours” clauses in the contract as follow: “4. COUNCIL’S OBLIGATIONS 4.11 The Council will use its best endeavours during the contract period to maintain, develop and operate at its own cost the gas extraction…” At one time, the gas which delivered to the generating engines was found to have been supplied at inadequate pressure and as a result less electricity had generated than might have been generated. The defendant claimed that the plaintiff did not take its best endeavours regarding to the problem. One step that the plaintiff could have taken was to install a system to overcome pressure losses which cost about £10,000 and this was the most expensive of the possible solutions. The issue arose in this case was whether the plaintiff was in breach of contract by failing to use its best endeavours required by the contract in improving the gas system and whether the plaintiff was subjected to spend money for that most expensive solution. In delivering the decision, the court also referred to some other cases in defining ‘best endeavours’. As in the case of Terrell v Mabie Todd & Co.147: 147 [1952] WN 434 69 “ ‘Best endeavours’ imposes a duty to do what can reasonably be done in the circumstances and the standard of reasonableness is that of a reasonable and prudent board of directors acting properly in the interests of their company.” The court rejected the submission made by the defendant that a ‘best endeavours’ obligation is the next best thing to an absolute obligation. The court held that the plaintiffs in this case had acted accordingly to the advice of competent consultants and hence it cannot be said that they had failed to use their best endeavours. Besides, the plaintiffs had installed a dewatering tanks costing £2,500 each. The court examined these actions as fulfilling the best endeavours obligation. Meanwhile for the installation of a system to overcome pressure losses which cost about £10,000, the court held that a party was not required to take action which would lead to its financial ruin or incur such expenditure. Hence, the court dismissed the counterclaim by the defendant and awarded the judgment to the plaintiffs. This is another case which strengthens the requirement of a party not to take steps which would give disadvantages in terms of financial or company’s interest as in IBM UK Ltd v Rockware Glass. Best endeavours obligation only requires the party to take action which is commercially practicable in both aspect of costs and degree of difficulty. Hence, regarding to the present case, the plaintiffs were not in breach to use best endeavours obligations even though they did not spend £10,000 to install the system because it was a big investment and the most expensive solution. Besides it was technically unsatisfactory. Furthermore, the plaintiffs had already taken other few steps which had put the loss into a minimum and referring to the court, this already considered as fulfilling the best endeavours obligation. 70 4.4.3 Sandhu v Sidhu [2010] EWCA Civ 531 This was an application for the striking out of an appeal, to a hearing on 27 November 2009, which had several applications named: application for permission to appeal, application to amend grounds of appeal, an application for security for costs of the appeal and an application to stay the appeal pending compliance with the order for security and, in the event of non-compliance of the Appellant’s Notice. By 4 February 2012, the respondent issued an application to strike the appeal out by reason of non-compliance with undertakings given in the order of 27 November 2009. The order made by the judge was to proceed on three undertakings by Mr Sidhu, the appellant. The first was that by 4.00 p.m. on 14 December 2009, he would deliver to the respondent’s solicitors, Messrs Masseys, to be held by them pending the determination of the appeal or further order an executed stock transfer form in respect of his 79,328 shares in the capital of a company called Orbit Resources Private Limited (Orbit). The second was to use his best endeavours to deliver the share certificates in respect of those shares to Masseys by 4.00 p.m. on 15 January 2009. The third was if he did not deliver the share certificates in respect of such shares to Masseys by that date and time, he was required to inform them by letter from his solicitors by 4.00 p.m. on 20 January of all steps by way of such best endeavours. As the first requirement, Mr Sidhu did deliver an executed stock transfer form by 14 December 2009. His solicitors did write on 20 January to explain what he had done because he had not succeeded in getting the share certificates into the hands of Masseys by 15 January. In the letter the solicitors said among other things was that: 71 "...we are instructed that our client has telephoned the Company to chase the issue of the duplicate share certificates. Once he gave his name he was asked to leave a message so that someone may return his call, but this has not occurred." On 11 February 2010 Orbit wrote a letter to Masseys, the respondent's solicitors, on the subject of duplicate share certificates, which referred implicitly to an email sent by Masseys in July 2009. The letter gave some details as to the documents and the procedure to be followed for the issue of duplicate share certificates and it said: "Once we receive the above papers we will issue duplicate share certificates in the name of Mr Sidhu." That letter, to whomsoever it was sent, did not get directly to Masseys. It did however come to the attention of Pitmans (representative for respondent), who on 15 February sent a copy to Masseys. In that letter they also said: "In the meantime we are instructed that Mr Sidhu is using his best endeavours to take the necessary steps to obtain the issue of duplicate share certificates relating to the shares." The issue to be determined here was whether Mr Sidhu had use his best endeavours to comply with his undertakings as regards to procuring the share certificates. The judge, after the hearing concluded that Mr Sidhu did not, on the evidence, use his best endeavours to comply with his undertaking as regards to 72 procuring the share certificates. The undertaking was given on 27 November 2009 while the order was sealed on 3 December, and it may be said that that was the date when the undertaking became effective. As against that, Mr Greenwood on behalf of the respondent was perfectly entitled to say that the undertaking was offered in a witness statement of 26 November, was given on the 27th and there was no doubt at that stage as to its terms. So Mr Sidhu should have got on with it immediately. The evidence as to what Mr Sidhu did was concrete but, all that he was said to have been done was to make a phone call to Orbit at some unspecified date before 8 January. It was reasonable to assume that this was not long before 8 January and that accordingly at least a whole month had gone by between the date when the undertaking was given and the date when he did for the first time, and indeed the only time, so far as his personal efforts are concerned, anything to comply with the undertaking. The judge, before delivering his decision, he cited the best endeavours principle used in previous cases. In IBM UK v Rockware Glass’s,148 the agreement being construed was an obligation to make an application for planning permission and to use its best endeavours to obtain the same. The judges in the Court of Appeal: Buckley LJ, Geoffrey Lane LJ, and Goff LJ, had to consider whether best endeavours had been used and Buckley LJ in particular formulated the test of best endeavours as being: “ In this context, what an owner of the property with which we are concerned in this case, who is anxious to obtain planning permission, would do to achieve that end. And later he said he was bound to take all those steps in his power which are capable of producing the desired results, namely the obtaining of planning permission, being steps which a prudent, determined and reasonable owner, acting in his own interests and desiring to achieve that result, would take.” 148 [1980] FSR 335 73 Besides, he also referred to another case of Rhodia International Holdings v Huntsman International149, the decision of Mr Julian Flaux QC where the question was an obligation to use reasonable endeavours, and he made the fairly self-evident comment that that was less demanding than an obligation to use best endeavours. Hence, the judge in this present case did not consider Mr. Sidhu’s actions amounted to best endeavours. Best endeavours involved not only what a party needed to do but also the time to do it. Mr Sidhu should have approached Orbit in the first week of December, even before the order was sealed and at any rate in the week after the order was sealed. Hence, the court held that Mr Sidhu did not comply with the undertaking because he did not use his best endeavours even he hardly used any endeavours but he did nothing and used no endeavours at all for at least a month. This case gives a new paradigm in interpreting what best endeavours are. If in the previous case of IBM UK Ltd v Rockware Glass stressed on the steps should be taken as a determined, prudent and reasonable person, this case highlighted on the importance of time in fulfilling the obligation of best endeavours. Basically, any action needs to be carried out within reasonable time unless the contract had stated specific dates for each action. What is define as reasonable time will depend on the type of transaction or duty undertaken. As in this case, Mr Sidhu was in default since he did not take any reasonable action to fulfil his best endeavours obligation for a month. 4.4.4 Walter Lilly & Co Ltd v. Mackay & Anor. Company [2012] EWHC 1773 The plaintiff, Walter Lilly & Company Limited (WLC) was a contractor for the proposed building project in London. DMW was a purpose designed vehicle for 149 [2007] EWHC 292 74 the acquisition of the land at Nos. 1, 2 and 3 Boltons Place and was formed by three people, Mr Mackay, Mr Daniel and Mr West. This was a sophisticated and big project since the employer DMW Developments Ltd had high expectation on it. However, little if any design had been completed prior to the involvement of WLC. There were substantial delays, much of which initially at least were not the responsibility of WLC, and as time went on DMW fell out seriously with its Architect. Separate contractors having been engaged to carry out the demolition work, four contractors, including WLC, were invited to tender for the main building works. WLC described itself as having particular and extensive experience of working on high-quality residential and new building projects. On 26 March 2004, WLC submitted its tender in the sum of £15,476,970.99 for construction of all three plots. It referred to there being limited information and how difficult it was to conclude an actual programme; although the stated completion period was 78 weeks, WLC's experience suggested 80 to 90 weeks, notwithstanding the enclosed programmes showing a 78 week period and some 23 work packages. The first major element of the works to be constructed was the piling and it was made clear to WLC that it was to be responsible for the design. This was confirmed at a project meeting on 4 May 2004. WLC negotiated with several piling contractors and on 28 June 2004 recommended that the piling package was awarded to Stent Foundations. By 10 September 2004, WLC reported that the contract was in delay by some four months. Some delay and disruption was caused by the presence on site of trees subject to tree preservation orders and over the following few months permission was secured for the felling of such trees. By early 2005, WLC had given notifications under Clause 25 of delays caused by tree removal problems, additional piling works and the late instruction of Keltbray, contractor for concrete works. Day by day, the submission of notice regarding time extension getting higher and the project was already experienced 75 delay from the original completion date. The project could only be completed after one year extended from the actual completion date. Since this project involved lots of delay and issuance of extension of time, the issue that the court had to decide was what amounted to ‘best endeavours’ as stated in clause 25.3.4 of the contract in order to prevent or at least minimize the delay and also the roles of Architect in granting an extension. The court held that, in defining the extension of time clause, it means: (a) The contractor should give notice if the works were being delayed or were likely to be delayed. This notice could relate therefore to actual delays being experienced or to future likely delays. (b) The notice should be accompanied or be followed as soon as practicable by particulars of expected effects and an estimate of the expected delay. (b) What was at least initially envisaged was that the architect would carry out a prospective exercise; this is because the Contractor can give notice when progress is likely to be delayed and the Architect has to assess what the likely delay will be. This makes sense so that the contractor and the architect could plan for the rest of the job. Of course, notice could be given when the works had actually been delayed but actual overall delay had not happened until after the original date for completion has passed. The clause did not describe the exercise of working out how much future delay would result from the relevant events in question. The architect would have to do the best that he or she could, this might well be assisted by programming exercises done by the contractor. 76 (d) Once the notice, particulars and estimate under Clauses 25.2.1 and 25.2.2 had been given, the architect was required to grant the appropriate extension of time. This is not an optional exercise: the word "shall" is clearly and intended to be mandatory. (e) No later than 12 weeks after Practical Completion, the Architect must carry out the final extension of time exercise, irrespective of whether notices and the particulars have been provided. This will necessarily be a retrospective exercise because Practical Completion will have passed and all the delays (whatever the causes) will have occurred. Again, the way in which this exercise is to be done is not defined. Referring to this case, the court had outlined steps that should be taken by the contractor in defining ‘best endeavours’ term as stated in the contract. For the initial step, the contractor should give the notice if in his opinion the works are being delayed or may be delayed. This notice needs to be attached together with the expected effect and also the estimated period of delay. It is better if the contractor can submit the notice before the delay becomes real because the contractor can have ample time to re-programme his works and put effort to finish it before the new completion date. As in the present case, some of the notices were given after the delay had happened, and when there are subsequent delays, the works still cannot be complete on time. Once notice had been given, the architect may assess it and grant the appropriate extension of time to the contractor. Architect’s judgment in this matter is really important because it determines whether the contractor can complete it on the given period of time or else he will be imposed with Liquidated and Ascertained Damages (LAD). As what happened in the present case, the architect granted less time extension compared to what had been applied by the contractor. By January 2006, 77 the contractor, Walter Lilly & Company Limited (WLC) reported that 27 weeks and three days extension of time was requested, however only four weeks had been awarded. Unreasonable granted of time extension can affect the whole progress of works, in addition this present project already had conflict at early stage on duration to complete whereby the contractor suggest it to be 80 to 90 weeks works compared to 78 works as in contract. Hence, from this case it can be concluded that best endeavours obligations includes the contractor’s compliance with extension of time clause, the determined procedure and also timing for giving notice. 4.5 Conclusion This chapter forms the most important part in achieving the research objective. The objective is to identify the requirements in performing the duty of best endeavours for the purpose of compliance with the proviso for the granting extension of time. There were altogether nine major cases that have been identified and presented in this chapter. Even though the selected cases are English cases and not within construction contract scope, however the principles in best endeavours were found to be applicable into Malaysian construction contract cases. The next chapter will conclude the discussion of those analysed cases and the relation with the addressed objective. CHAPTER 5 CONCLUSION AND RECOMMENDATIONS 5.1 Introduction The previous chapter had discussed and analysed the case law in relation to the obligation of parties that had been expressly imposed with a duty to use their best endeavours to achieve certain specific objectives. Hence, this final chapter will summarize the overall findings of the research according to the research objective. The research objective is to identify the requirement in performing the duty of best endeavours for the purpose of compliance with the proviso for the granting extension of time. In addition, this chapter will also discuss the problems that had occurred in the course of conducting this research. This chapter ends with some recommendations for future research which can be carried out by other researchers. 79 5.2 Relation with Extension of Time It should be noted that the majority of the cases analysed were not those that related to extension of time issue. Nevertheless it is submitted that, the general nature of the principles that arose from those cases make it possible for them to be considered as equally applicable to the contractors’ duty of best endeavours to prevent or reduce delay in an application for extension of time. Hence this section will particularly define the best endeavours obligation in terms of extension of time. Under construction contracts, it is an overriding requirement for contractors and the subcontractors to constantly use their best endeavours to avoid or minimise delay. In the course of discharging that requirement, they must adopt the appropriate approach. Generally, they should be able to recognise when delay would possibly occur and manage and respond quickly to the occasion so as to minimise disruption to the works. Below are the lists of requirements in performing the duty of best endeavours as retrieved from the examination of the cases law. It is suggested that they are equally applicable to construction contract, particularly in extension of time. i) The contractor should carry out all possible steps in order to prevent or put the losses at a minimum level. ii) Should the contractor need to expend money the expenses incurred must not be substantial. iii) The steps taken should not bring the contractor to sacrifice his own interest. 80 iv) The contractor should comply with all contractual procedures as stated and agreed at the time he entered the contract. v) The contractor should comply with any instructions from the contract administrator relating to reducing the delay. In relation to the above five main principles, below are some suggestions that contractors may take to minimise delay: i) Weather factor (e.g. : raining season) - The contractor can execute part of works that are not affected by the weather, for example, doing internal work such as plastering and painting, fixing internal doors and windows, tiling and others. ii) Delay in supply of materials - The contractor can remind/notify the suppliers to deliver the materials as what had been scheduled. - If this continues, the contractor can find alternative suppliers that can supply the equally standard quality materials. iii) Delay in giving instructions and getting approvals - The contractor must make confirmation regarding the oral instructions given by the contract administrator, if relevant. - This procedure to obtain verification regarding oral instructions is normally stated in the standard form of contract, and the contractor shall comply with the procedures. 81 - The contractor may reschedule his work programme according to the contract administrator’s requirement, if necessary150. iv) Delay by nominated subcontractors - The contractor may instruct the subcontractor to work regularly and diligently. - If this continues, the contractor may give notice of failure to perform works in a good manner. - The contractor can give another notice to the subcontractor and ask for their cooperation in performing the obligations. - Discuss with contract administrator regarding this problem and if necessary request to reappoint another sub-contractor (NSC).151 v) Delay in giving possession of or access to the site - The contractor can send a request letter to the employer, ask for possession of site.152 - Several notices submitted by contractor as request can be considered as best endeavours. 150 Andrew Noble. Contractors’ and sub-contractors’ constant best endeavours to prevent delay. Construction Law Journal. (1997) 151 Andrew Noble. Contractors’ and sub-contractors’ constant best endeavours to prevent delay. Construction Law Journal. (1997) 152 Rapid Building v Ealing Family House Association [1984] 29 BLR 5 82 vi) Variations - The contractor has rights to request for information related to the variation order given by the contract administrator.153 - If necessary, the contractor may rearrange his works programme and fit in those variation works within the work structure. - The contractor may reschedule his material deliveries since the works had been added or omitted by the variation orders.154 - In order to complete those variation works, the contractor may require making some reasonable expenses which later these expenses can be claimed under loss and expense to the employer.155 5.3 Problems Encountered during Research There are few constraints faced by the researcher in order to complete this research. They are: 153 Andrew Noble. Contractors’ and sub-contractors’ constant best endeavours to prevent delay. Construction Law Journal. (1997) 154 Andrew Noble. Contractors’ and sub-contractors’ constant best endeavours to prevent delay. Construction Law Journal. (1997) 155 Andrew Noble. Contractors’ and sub-contractors’ constant best endeavours to prevent delay. Construction Law Journal. (1997) 83 5.3.1 Duration of the Research The main problem encountered during the conduct of this research is the limited time frame. This research is carried out within a limited period of approximately five weeks. 5.3.2 Lack of Cases related to ‘Best Endeavours’ in Construction Contract While conducting this research, the researcher faced difficulties in finding law cases regarding to ‘best endeavours’ in respect of construction contract especially focusing on extension of time. As a result, the researcher widened the scope of cases selected to be review to all types of contract and make comparative analysis with construction industry practice. 5.4 Further Studies There are rooms for improvement regarding to this research topic. Based on this research, the following could be the possible areas for future research that may also be beneficial for the construction industry: 5.4.1 The Modification of ‘Best Endeavours’ Best endeavours term recently comes with other modification on it such as ‘reasonable endeavours’ and ‘all reasonable endeavours’. Future research in detail 84 regarding these two terms will be appreciate if our construction industry in the future may embedded these words in our standard form of contract. 5.4.2 Practicality of Best Endeavours This research is mainly focusing on best endeavours obligation in terms of extension of time. Construction contract is very wide. The principle of best endeavours may be suitable to be used in other aspect of construction contract. Hence, future researcher is suggested to carry out a study on best endeavour in other area of construction industry. 85 REFERENCES Abd. Majid, M.Za. and McCaffer, R., (1998). “Factors of Non-excusable Delays that Influence Contractors’ Performance”. Journal of Management in Engineering. ASCE, May/June. pp. 42-49. Afshari, H., et. al. (2011). Identification of Causes of Non-Excusable Delays of Construction Projects. 2010 International Conference on E-Business, Management and Economics. Vol. 3. Hong Kong. Aleka Mandaraka-Sheppard. (2007). Modern Admiralty Law 2nd Edition. Routledge-Cavendish. New York. Allens Arthur Robinson. (2004). Delay and Disruption Protocol. Construction Breakfast Seminar. The Society of Construction Law. Andrew Noble. (1997). Contractors’ and sub-contractors’ constant best endeavours to prevent delay. Construction Law Journal. Chappell, D. (2011). Building Contract Claims. Wiley-Blackwell. UK. Charles A. Leonard. (1988). The Effects of Change Orders on Productivity. Concordia University. Charles Boundy. (2010). Business Contract Handbook. Gower Publishing Company. USA. CIDB Standard Form of Contract for Building Works. (2000). Lembaga Pembangunan Industri Pembinaan Malaysia. 86 Contract Act 1950 (Act 136). (2008). International Law Book Services. Selangor. Cushman, R. F., Myers, J. J. (1999). Construction Law Handbook. New York. Aspen Law & Business. Daniel Atkinson. (2000). Access to Site. Atkinson Law. David Chappell, Michael Dunn and Michael Cowlin. (2009). Building Law Encyclopedia. John Wiley and Sons. UK. Denise L. Nestel. (2006). Force Majeure Clause: The Basics. Executive Magazine. Eggleston, B. (2009). Liquidated Damages and Extensions of Time. Blackwell Publishing. United Kingdom. Pp 248-249. JCT Standard Form of Contract. (1998) Keane, P.J., Caletka, A.F. (2008). Delay Analysis in Construction Contracts. Blackwell Publishing Ltd. United Kingdom. Kenneth C. Gibs, Gordon Hunt. (2000). California Construction Law. Aspen Publishers. New York. Knowles Commercial Services. (n.d). Delays, Extensions of Time and Liquidated Damages. Lim Chong Fong. (2004) The Malaysian PWD form of Construction Contract, Sweet and Maxwell Asia, Kuala Lumpur, p. 92. M.Z. Abd Majid and Ronald McCaffer. (1998). Factors of Non-Excusable Delays that Influence Contractor’s Performance. Engineering. May/June. Journal of Management in 87 Michael S. Simon. (1979). Construction Contracts and Claims. McGraw-Hill Book Company. United States. pp 240-241. Michael T. Callahan. (2005). Construction Change Order Claims. Aspen Publishers. United States of America. Pp 3-10. Mokhtar Azizi Mohd Din. (2011). The Extent of The Contractors Effort to Mitigate Delay. PMINZ Conference. Auckland. Oon Chee Kheng. (2003). Extension of Time and Liquidated Damages in Construction Contracts. Seminar on Construction Contracts and Arbitration. Institution of Engineers, Malaysia. Perak. PAM Standard Form of Contract. (2006). Pertubuhan Arkitek Malaysia. Price D. (n.d). Delay and Disruption Claims under FIDIC Contracts-Procedural Issues, Evidence and Assessment. Hill International. PWD 203A Standard Forms of Contract. (2010). Public Works Department. Robinson, N.M. et.al. (1996). Construction Law in Singapore and Malaysia. 2nd Edition. Singapore. Simon, M.S. (1979). Construction Contracts and Claims. McGraw-Hill Book Company. United States. Slaughter and May. (2007). Best endeavours v. reasonable endeavours, what do they mean? Does either mean anything? London. Smith, H. Notice Requirements in Construction Contracts – A Southest Asia Perspective. (2012); Oon Chee Kheng. Standard Construction Contracts in Malaysia: Issues and Challenges. Innovations in Construction Contracts. Malacca. Pp 8-9. (2002) 88 Suzanne Reeves. 2012 Construction Case Law Summary (January-June). Wedlake Bell. London. 2012. The Free Dictionary by Farlex. (2012). Retrieved from http://legal- dictionary.thefreedictionary.com. Thomas Lundmark. (1998). Common Law Tort & Contract. LIT Verlag Munster. London. Thomas, J. Kelleher and G. Scott Walters. (2009).. Smith, Currie & Hancock’s Common Sense Construction Law. John Wiley & Sons. United States of America. Pp 281 – 283. Timothy R. Hughes. (2003). A Layperson’s Guide to Delay Claims. Masonry Magazine. Hughes & Associates. Vivian Ramsey and Thomas Telford. (2007). Construction Law Handbook. Thomas Telford. London. William Ibbs and Caroline Vaughan. (2012). Change and the Loss of Productivity in Construction: A Field Guide. 89 BIBLIOGRAPHY Edwards Angell Palmer & Dodge. (2008). The Expanding Spectrum of ‘endeavours’ clauses. Retrieved from eapdlaw.com Entrusty Group (2006). Is The Contractor Still Entitled to Extension of Time When There is Concurrent Delay?. Master Builders. Marsden, J. and Scott, N. (2008). Much Effort, Much Prosperity? Best and Reasonable Endeavours Obligations and Relevants Commercial Differences. Memery Crystal. UK. Norhana Danial. (2007). Contractor’s Application for An Extension of Time. Master in CCM. Universiti Teknologi Malaysia. Rosenthal, A. & Fitzgerald. Do I have to Complete? Issues which arise when contracting parties change their mind about the sale/purchase of land. Falcon Chambers. Rush S. (2007). Are your best endeavours always reasonable?A recent case on ‘reasonable’ versus ‘best endeavours’. International Bar Association. Seltzer E.M & Gross A. M. (1956). Federal Government Construction Contracts: Liability for Delays Caused by the Government. Fordham Law Review.