Standard Title: LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Group Technology Unique Identifier: 34-953 Part 3 - LV Area of Applicability: Distribution Engineering Documentation Type: Standard Revision: 0 Total Pages: 71 Next Review Date: March 2017 Controlled Disclosure Disclosure Classification: Compiled by Approved by (SCOWT SC Chairperson) Bruce McLaren Riaz Asmal IARC Custodian LV MV/LV SC Chairperson Date: 15/03/2012 Date: 16/03/2012 Functional Responsibility (Dx) Authorized by Vinod Singh Prince Moyo Power Plant Technologies Manager Power Delivery Engineering GM (Acting) Date: 22/03/2012 Date: 27/03/2012 ESKOM COPYRIGHT PROTECTED B Morrison / March 2012 / Rev 0 Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 2 of 71 Content Page Foreword ............................................................................................................................................... 3 1. Scope ........................................................................................................................................... 4 2. Normative references ................................................................................................................... 6 3. Definitions and abbreviations ....................................................................................................... 7 3.1. Definitions......................................................................................................................... 7 3.2. Abbreviations ................................................................................................................... 8 4. Contextual application of the LV standard ................................................................................... 8 4.1. Reticulation methods ........................................................................................................ 8 4.2. Layout design options ...................................................................................................... 16 4.3. Standard Requirements ................................................................................................... 16 4.4. Clearances ....................................................................................................................... 23 4.5. Telkom conditions for sharing of services ........................................................................ 25 4.6. Protection ......................................................................................................................... 26 4.7. Transformers and surge arresters ................................................................................... 29 4.8. Earthing installation and tests .......................................................................................... 30 4.9. Poles and stays ................................................................................................................ 30 4.10. Service connections ......................................................................................................... 31 4.11. Customer installations ...................................................................................................... 31 4.12. Customer metering ........................................................................................................... 32 4.13. Bills of materials (BOM) ................................................................................................... 32 4.14. Power Office ..................................................................................................................... 32 4.15. Marking and labeling ........................................................................................................ 32 5. Tests and commissioning................................................................................................. 33 5.1. Electrical tests .................................................................................................................. 33 Annex A – Impact Assessment ............................................................................................................. 34 Annex B - Conductor properties ........................................................................................................... 38 Annex C - Design spans for bare and insulated neutral ABC systems ................................................ 41 Annex D - Design spans for ACSR bare wire systems ........................................................................ 45 Annex E - Design spans for AAAC bare wire systems ......................................................................... 48 Annex F - Urban reticulation ................................................................................................................. 51 Annex G - Minimum separation between parallel LV and HV lines ...................................................... 52 Annex H - List of drawings .................................................................................................................... 55 Annex I - Connector installation practices on low voltage ABC networks ............................................ 60 Annex J - ABC connectors ................................................................................................................... 67 Annex K - National contract for Low Voltage Aerial Bundled Conductor with Insulated neutral Conductor ................................................................................................................................. 68 ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 3 of 71 Foreword Not applicable. Revision history This revision cancels and replaces revision no 5 of document no. DISASAAM2. Date Rev. Compiled By March 2012 0 B McLaren Clause Remarks Document reviewed and re packed. Clause no. Scope changed to exclude pole service box requirements which are to be included in the services standard Part 8. Relevant drawings will depict pole service box placement. Connectors to the LV lines remain in this standard. Check sheets have been removed due to duplication with other standards. Minimum separation between parallel LV and MV lines now included as an Annex (informative). Document number changed to DST 34-953. Feb 2006 5 Document reformatted according to a new template. Document approved Dec 2005 4 Expanded to include single-phase and dual-phase and generally modified for clarity SABS changed to SANS SCS Changed to DIS References updated Options indicated in fig.4 DT-SAT replaced by R-SAT Clause 2.4.1: LV ABC updated to cater for both insulated neutral ABC and bare neutral ABC Clause 2.4.1.2: LV ABC fittings updated for insulated neutral Clause 2.4.1.4: Marking of the insulated neutral highlighted Clause 2.4.1.9 is updated and fig.6 is included Clause 2.4.1.10: Shearing of IPC torque shearing nuts added Clause 2.4.11 added Clause2.4.15: Conductor size updated Clauses 2.5.4, 2.7.6, 2.8.1and 2.8.3 updated Clause 2.16: DT project replaced by Power Office and CAD replaced by MicroS BMS codification removed and standard amendment 1 is incorporated April 1997 3 References to service connections standard Part 8 section 1 added ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Compiled By Unique Identifier: 34-953 Revision: 0 Page: 4 of 71 Date Rev. Clause Remarks Feb 1996 2 A general improvement to the clarity, content and layout of rev.1. The minimum ground clearance of 2,5 m for service connections, stipulated in rev.1, has been reduced to 2,2 m in rev.2. June 1995 1 “Original issue – DISASAAM2 Acceptance This document has been seen and accepted by: Name Designation P Moyo Power Delivery Engineering GM (Acting) V Singh Power Plant Technologies Manager R Asmal MV/LV SC Chairperson This standard shall apply throughout Eskom Holdings Limited, its divisions, subsidiaries and entities wherein Eskom has a controlling interest. Development team This revision was reviewed by; Bruce McLaren Rigard Sander Keywords Low voltage, Aerial bundled conductor, Overhead, single phase, dual phase, three phase. Bibliography The following documents, in addition to those in clause 2, were a source of reference in compiling this standard. They do not constitute provisions of this standard but are referenced for further information. NRS 018, Fittings and connectors for LV overhead powerlines using ABC cable. NRS 018-1:1995, Fittings and connectors for LV overhead powerlines using ABC cable — Part 1: Strain and suspension fittings for self-supporting ABC. NRS 018-2:1995, Fittings and connectors for LV overhead powerlines using ABC cable — Part 2: Strain and suspension fittings for insulated supporting core ABC. NRS 018-4:1995, Fittings and connectors for LV overhead powerlines using ABC cable — Part 4: Strain fittings for service cables. (No draft available). NRS 027:1994, Distribution transformer — Completely self-protecting type. NRS 034-1:1992, Guidelines for the provision of electrical distribution networks in residential areas — Part 1: Planning and design of distribution systems : with amendment 1, Financial analysis. 1. Scope ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 5 of 71 The Distribution Standard is a multi-part document whose total structure is defined in Part 0. This part of the Distribution Standard consists of the following sections under the general title: Low voltage reticulation: Section 1: Low-voltage overhead reticulation. Section 2: Low-voltage underground reticulation. Section 3: Low-voltage protection philosophy. Section 4: Low-voltage protection philosophy for low consumption areas. The intention behind the production of the standard is that all Eskom LV overhead distribution systems will be built using standard designs as specified in the standard. The standardized materials are specified in SCSPVAAT6, IARC, Part 9: Buyers Guide. This section of the Distribution Standard has been prepared to establish specifications for and promote the use of standardized designs, structures and materials for low-voltage (LV) overhead distribution systems. It covers the construction of bare wire and insulated conductor overhead LV reticulation systems using either wood or concrete poles. These systems are normally fed from MV/LV transformers and are used to supply individual customers at LV. The topology includes three overhead low-voltage reticulation methods, namely single-phase (2 wire), dual-phase (3 wire), and three-phase (4 wire). These methods provide the reticulation designer with the best known options to achieve cost effective reticulation for most electrification areas in South Africa. The three topologies use similar materials and construction techniques. Where appropriate, bare and insulated systems can be used in combinations of the three topologies to achieve cost effective reticulation. Transformers feeding the LV overhead lines are generally pole-mounted (first choice for electrification and smaller transformers) but ground-mounted units can also be used, where circumstances and size dictate. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 6 of 71 This standard will be required to change continually as Eskom strives for continual improvements to its standards. Users of this standard are thus required to establish the appropriate applications, however, these should comply with the standard requirements set out in this document. Designers should be cognizant of continuous improvement and standard changes to allow for designs to be frozen at the desired point in a project to prevent the continual change from interfering with the project and its associated costs. The relevant T&Q change control forum enables the local area to cope with continual change to standards while progressing with projects. 2. Normative references The following standards contain provisions that, through reference in the text, constitute provisions of this standard. At the time of publication, the editions indicated were valid. All standards are subject to revision, and parties to agreements based on this standard are encouraged to investigate the possibility of applying the most recent editions of the standards listed below. Information on currently valid national and international standards may be obtained from the South African Bureau of Standards. Information on valid Eskom standards and software tools is available from Industrial Association Resource Centre. TSI report no. RES/IR/99/00043, “Safety of dwellings under transmission lines” SANS 10142-1:2009, ED 1.07, The wiring of premises Part 1 :Low voltage installations SANS 780:2009, ED 4, Distribution transformers. SANS 10292:2001, Ed1.01, Earthing of low-voltage (LV) distribution systems. SANS 10198 -14:1996, Ed 2, The selection, handling and installation of electric power cables of rating not exceeding 33 kV Part 14: Installation of aerial bundled conductor (ABC) cables. SANS 10280:2010, Ed 1.01, Overhead power lines for conditions prevailing in South Africa. NRS 043:2005 ED 2, Code of practice for the joint use of structures for power and telecommunication lines. NRS 018-2:1995 Ed 1, Fittings and connectors for low voltage overhead power lines using aerial bundled conductors – Part 1: Strain and suspension fittings for insulated neutral supporting conductors. DTC 0106, Specification for concrete poles (reinforced, partially pre-stressed and pre-stressed types). ESKASAAN0:Rev.1, Standard for the labelling of high voltage equipment. DST 34-1439 SCSAGAAF5:Rev.1, Distribution standard — Part 3: Low-voltage reticulation — Section 3: Lowvoltage protection philosophy. SCSAGAAH8:Rev.0, Distribution standard — Part 3: Low-voltage reticulation — Section 4: Lowvoltage protection philosophy for low consumption areas. SCSAGAAI2:Rev.0, Design notes for single- and dual-phase reticulation. DST 34 – 1985 REV 0, Distribution standard — Part 2: Earthing: Section 1: — MV and LV reticulation earthing. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 7 of 71 DST34-1270– Distribution Standard - Part 4: Medium Voltage Reticulation: Section 2 – 22 kV Overhead Reticulation for conductors up to Hare/Oak SCSASAAS3:Rev.2, Distribution standard — Part 8 Low voltage services: Section 1 - Electrification. S DST34-4, Distribution standard — Part 9: Buyer’s guide. DSP34-1803, Aerial bundled conductor with un-insulated (bare) neutral. DSP34-1647, Specification for wood poles, cross-arms and spacer blocks. DSP34-343, Specification for oil-immersed power transformers to 500 KVA and 33 kV. SCSSCAAL4:Rev.2, Fittings for bare neutral aerial bundled conductor. SCSSCAAO1:Rev.1, Specification for conventional stay planting, percussion stay and rock anchor installations and compaction testing DSP34-342 – Specification for phase to phase (11, 22 & 33 kV) connected transformers with centre tapped low voltage winding. Occupational Health and Safety ACT, Act 85 of 1993. TRR/E/96/ELI68, Large single phase motors (TRI Report). Tools • Retic Master / CART • Power Office (NACS) 3. Definitions and abbreviations 3.1. Definitions The definitions and abbreviations listed below apply to this document. Balanced system: A dual- or three-phase system where all phase conductors are carrying a similar load. The neutral return conductor carries little or no current LV dual-phase: A 50 Hz a.c. supply at 230 V r.m.s. phase-to-neutral. 460 V r.m.s. phase-to-phase (180° vector phase displacement). Note the difference to two-phase supply LV single-phase: A 50 Hz a.c. supply at 230 V r.m.s. phase-to-neutral. The neutral carries the full load current LV three-phase: A 50 Hz a.c. supply at 230 V r.m.s. phase-to-neutral; 400 V r.m.s. phase-to-phase (120° vector phase displacement). MV phase-to-phase: Any two phases of a three-phase MV supply. An unbalanced three-phase MV supply. (This is not a recommended method but it is obtained as a result of using two phases of a three-phase system. It appears here to ensure that it is not confused with dual-phase). ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 8 of 71 MV single-phase: A 50 Hz a.c. supply at derived typically from a fully earthed 33 kV system, 19.05 kV r.m.s. phase-to-neutral. The neutral which originates from the source transformer, carries the residual load current. MV three-phase: A 50 Hz a.c. supply at 12,7 kV r.m.s. phase-to-neutral; 22 kV r.m.s. phase-to-phase (120° vector phase displacement). Single wire earth return: A 50 Hz a.c. supply typically at 19 kV r.m.s. phase-to-earth, where the return current is through the general body of the earth. Unbalanced system: A dual- or three-phase system where the phase conductors do not carry a similar load. The neutral return conductor carries a significant current 3.2. Abbreviations ABC: Aerial bundled conductors SWER: Single wire earth return LV: Low voltage 4. Contextual application of the LV standard 4.1. Reticulation methods 4.1.1. Introduction The practice of three-phase MV and LV reticulation is sometimes not the most cost effective method of electrification. The use of MV philosophies like SWER, single-phase and phase-to-phase systems combined with LV philosophies like single-phase and dual-phase systems are often more appropriate, especially when dealing with small, dispersed loads. This is mainly due to the fact that three-phase conductors may have a power transfer capability greater than that required by the load and the transformer ratings resulting in the conductors not being fully utilized. The main cost advantages of the above methods are a) SWER and two-phase MV systems could require shorter poles and/or can provide longer span lengths than three-phase designs when using the same height poles, b) SWER and two-phase MV systems require less pole-dressing equipment, c) single-phase and dual-phase transformers are less costly than three-phase units, and d) single- and dual-phase LV ABC can be spanned up to 30 % further than three-phase ABC. e) reduced maintenance and life cycle costs There are some possible disadvantages of these methods and these are ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 9 of 71 a) traditional three-phase LV supplies are not available but a three-phase supply can be created using power electronics. Refer to TRI report TRR/AE/96/ELI68 “Large Single Phase Motors”, b) if there is sufficient motivation to upgrade an area to three-phase supply the customers would experience outages on these networks to enable the upgrade, and c) unbalance could limit transfer capabilities however this is not expected to have an undesirable effect on electrification projects. The three-phase, dual-phase and single-phase LV reticulation methods are described in figures 1, 2 and 3. 4.1.2. Three phase system 3 phase MV RED 400V W H IT E BLU E NEU T RAL N +E L N E DOM ES TIC S UPP LY P OINT Note separate neutral & earth in custom ers dw elling 22 kV/400V (230V ∠ 0°, 230V ∠ 120°, 230V ∠ 240°). Vector group: Dyn11/Yzn11 Figure 1 — Three-phase LV system ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION 4.1.3. Unique Identifier: 34-953 Revision: 0 Page: 10 of 71 Dual phase system 3 phase or ph-ph MV or SWER PHASE 1 + 230V - 230V PHASE 2 NEUTRAL N+E L N Note separate neutral & earth in customers dwelling E DOMESTIC SUPPLY POINT 22 kV/460V ( 230V ∠ 180°, 230V ∠ 0° ). Figure 2 — Dual-phase LV system 4.1.4. Single-phase system 3 phase or ph-ph MV or SWER 230V PHASE NEUTRAL N+E L N E DOMESTIC SUPPLY POINT Note separate neutral & earth in customers dwelling 22 kV/400V ( 230V ∠ 0°) ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 11 of 71 Figure 3 — Single-phase LV system Table 1 — Combinations of MV and LV for various methodologies 1 2 3 4 LV methodology MV options Transformer options LV cable options Three-phase Three-phase 50 kVA , 100 kVA & 200kVA Three-phase ABC or bare wire two-wire, four-wire three-wire or 16 kVA single-phase 32 kVA & 64 kVA dualphase Dual-phase Single-phase 32 kVA & 64 kVA dualphase for SWER or ph-ph ABC or bare wire OR SWER Three-phase, Ph-Ph Three-phase or 16 kVA single-phase ABC or bare wire ph-ph 4.1.5. three-wire and two-wire two-wire Mixing of technology options The above topologies provide for the various options available for mixing methods on a particular project or reticulation system. It is important to mix the methods in a manner that ensures the best overall electrification solution, for example, due to the marginal difference in cost between two-wire and three-wire 35 mm² ABC it would not make sense to mix the two if significant cost benefit was not evident. On the other hand an electrically sound design using a mix of four-wire and two-wire ABC would generally show significant cost savings. Also note that the combination of bare wire and ABC systems in a particular transformer zone is allowed. These issues shall be discussed with and agreed to by the Regional T&Q. 4.1.6. Planning factors Planners and designers should take a medium to long term view when deciding on technology options. This long term view should be influenced by historical patterns, human settlement dynamics, system master plans and key MV feeder routes. This doesn’t imply all systems should be 3 phase, however with judicious thinking, the most appropriate technology should be applied and the “percentage game plan” should be used to influence planning thinking. From electrification review projects, the fundamental aspects that influence MV/LV designs long term success are correct scoping and appropriate customer loading criteria. If phase-to-phase or SWER MV and dual-phase or single-phase LV provide the right technology fit and a customer requests a three-phase supply point, designers should consider various options before changing to three-phase technology, including, does the customer actually need three-phase supply? In most cases a three-phase supply point is not necessary for the application required. In almost all cases it is much more cost effective to supply a single-phase point and install a load that will run on the single-phase supply. For example, single-phase motors up to 7,5 kW are readily available (e.g. GEC motors). Loads that can be serviced by motors of about 3 kW include a) pumps, b) commercial and industrial coolers and freezers, ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION c) mortuary rooms, d) 4-post car hoists, and e) miscellaneous garage equipment. Unique Identifier: 34-953 Revision: 0 Page: 12 of 71 For motor loads greater than 7,5 kW, written pole and other single-phase motor types are available. Note that modifications or adjustments to the customer equipment may be required. 4.1.6.1 Load balancing On both three-phase and dual-phase LV systems, balancing two-phases per node (pole-top box) for customer connections will result in the minimum number of nodes to achieve load balancing. This is difficult in practice due to the customer layouts, particularly on rural networks. The Eskom standard pole-top box (node) is only equipped for connection to a single-phase supply for this reason. On projects where the balancing of two phases per node is needed two options exist, depending on the circumstances. Option (1): Layouts where most nodes will only have enough customer connections for a singlephase connection. a) Use a single, standard pole-top box that has a single-phase connection for most nodes. b) Use two single pole-top boxes for those nodes that can be balanced on two phases, as appropriate. Option (2): Layouts where most nodes can be balanced by using two phases. Specify the pole-top box for two-phase connections. The specification allows for this option. The diagrams in figure 4 illustrate the differences between balancing with one or two phases per node: ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 13 of 71 OPTION 1 ph1 ph1 ph1 ph2 ph1 ph2 ph2 ph2 ph3 ph3 ph3 ph3 ph3 ph3 ph3 ph3 ph2 ph2 ph2 ph2 ph1 ph1 Balanced three-phase LV phase connection — One phase per node OPTION 2 ph1 ph1 Ph2 Ph2 Ph2 Ph2 ph3 ph3 Ph3 Ph3 Ph1 Ph1 Balanced three-phase LV phase connection — Two phases per node OPTION 1 ph1 ph1 ph1 ph1 ph2 ph2 ph2 ph2 ph2 ph2 ph2 ph2 ph1 ph1 ph1 ph1 Balanced dual-phase LV phase connection — One phase per node OPTION 2 ph1 ph2 ph1 ph2 ph1 ph2 ph1 ph2 ph1 ph1 ph2 ph2 ph1 ph2 ph1 ph2 Balanced dual-phase LV phase connection — Two phases per node Figure 4 — Load balancing ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. ph1 ph1 Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 14 of 71 The following vector diagrams indicate the different types of networks: Balanced three-phase LV network with neutral voltage drop = 0 Three-phase network with only one phase loaded, equivalent to a single-phase system or a two-phase LV system with only one phase loaded Balanced dual-phase LV network with neutral voltage drop = 0 (180° between the phases) NOTE — In all practical situations unbalance will exist giving rise to neutral current. The prime objective is to design for minimal unbalance. Balancing of a dual-phase system is easier than a three-phase system as only two phases are under consideration. Figure 5 — Vector diagrams ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION 4.1.6.2 Unique Identifier: 34-953 Revision: 0 Page: 15 of 71 Voltage drop The power transfer capability ratios of the three-phase, dual phase and the single-phase methods are as follows: Three-phase Dual-phase Single-phase 6 4 1 This means that the balanced three-phase method is 6 times more efficient in transmitting power than the single-phase method and the dual-phase method is four times more efficient in transmitting power than the single-phase method. Use of approved load flow design software e.g. “Reticmaster” will verify the optimum methodology for any electrification design. 4.1.6.3 Upgrade paths Eskom has introduced a philosophy into electrification design that requires the networks to be appropriate for the customer base. This means that a certain amount of information is needed about the customers in order to design appropriate networks after considering the load for the first 5 years, then 10 years and 20 years. Planning guidelines in support of the philosophy are obtainable from the Planning functions in the Operating Divisions. Full advantage needs to be taken of delaying capital expenditure whilst considering the customer needs. The philosophy thus needs to be supported by an Upgrade Guideline, the main points of which are indicated in table 2: Table 2 — Upgrade paths 1 Existing network Three-phase MV feeding three-phase LV 2 Reason for upgrade 1 LV voltage drop too high 2 Transformer overload 3 Combination of above Three-phase MV feeding single-phase LV 1 LV voltage drop too high 2 Transformer overload 3 Combination of above Phase-to-phase feeding single-phase LV 1 LV voltage drop too high 2 Transformer overload 3 Combination of above or SWER Phase-to-phase or SWER feeding dual-phase LV 1 LV voltage drop too high 2 Transformer overload 3 Combination of above 3 Upgrade options 1.1 Add extra conductor or increase conductor size 1.2 Reduce LV line length by extending MV and adding transformers 2.1 Increase transformer size or create two transformer areas from one as above 2.2 Suitable combination of above 1.1 Bare wire-Convert to three-phase or dual-phase by changing transformer and adding extra conductor 1.2 ABC-Convert to dual-phase by changing transformer and adding one more ABC conductor 2.1 Change transformer 2.2 Suitable combination of above 1.1 Bare wire-Convert to dual-phase by changing transformer and adding extra conductor 1.2 ABC-Convert to dual-phase by changing transformer and adding one more ABC conductor 2.1 Change transformer 2.2 Suitable combination of above 1.1 Double circuit dual-phase 1.2 Reduce LV line length by extending MV and adding transformers 2.1 Increase transformer size or create two transformer areas from one as above 2.2 Suitable combination of above It is generally not necessary to upgrade phase-phase MV and SWER to three-phase. This situation may arise in the event of a special load being required. This situation needs to be treated on its merits. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 16 of 71 The requirements of the Occupational Health and Safety Act, Act 85 of 1993 (OHS Act) and all subsequent amendments and regulations shall be observed. Factors of safety shall be as stated in the OHS Act except where exemption has been obtained. 4.2. Layout design options Radial LV systems are generally the most economical with conductor sections selected after optimization utilizing approved design software. There are a number of customer layouts that shall be considered when doing an electrification design. These can be classified into two main layouts: 4.2.1. Structured or grid layout Two acceptable LV reticulation designs for a structured/grid layout are as follows depending on the circumstances: a) between the stands in a block, (mid block) with spurs to poles for street lights where necessary; and b) along the street frontage of the stands. 4.2.2. Unstructured (informal) or Scattered layouts The most appropriate reticulation design for this type of layout shall be used. LV layouts will be dependent on optimum transformer installation positions, accessibility and density of areas. 4.3. Standard Requirements 4.3.1. Overhead topologies The two standard overhead systems to be used by Eskom are: a) Aerial bundled conductor (ABC) with un-insulated (bare) neutral and aerial bundled conductor (ABC) with insulated neutral b) ACSR and AAAC bare conductors. ABC has generally accepted as the preferred option due to its apparent simplicity of construction, minimal components and its inherent long-term reliability. Recent findings indicate that ABC installations require specific skills and components applied in the correct manner. A disturbing trend of the lack of adherence to specific ABC stringing and connection techniques will result in these poorly constructed installations providing long term operational problems with inherent flaws that will require difficult fault finding procedures to be implemented. This will impact negatively on safety, performance resulting in high life cycle costs. Furthermore, LV feeder problems may indicate symptoms similar to those of transformer overloads, which further exacerbates the aforementioned cycle. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 17 of 71 Factors which support LV ABC installations and related initial capital/project cost benefits are, inter alia; • Lower clearance requirements • Lower stringing costs • Relatively longer preventative maintenance inspection intervals. The following myths regarding the safe use of ABC which have developed over time and need to be exposed. ABC is a fully insulated system - Bare neutral ABC will become live if broken when connected to load. Due to the above inherent relaxations, has the potential to become significantly dangerous, particularly when; • Incorrect jointing/connecting/repairing techniques are used. • Fuses are bridged/by passed. • Incorrect stringing and tensioning techniques are used. Protection requirements for ABC can be less stringent that for bare wire systems - Due to its makeup, bare neutral ABC is unlikely to cause protection to operate in the event of a broken phase/neutral conductor. This can result in live exposed conductor on the ground. In view of this, Designers, Specifiers, Installers, Operators and Maintainers need to understand their role, responsibility and accountability in the relevant role of implementing, operating and maintaining this technology. Bare wire installations, have the reciprocal factors which impact on initial costs and maintenance components, however the following issues are considered to be important when considering the use of bare wire LV. • Specific conductor configuration requirement. The neutral shall be the lower/st conductor at all times. • Prospective fault currents and tripping times require faster operation times. • Specific stay requirements - conductor tension dependant. Notwithstanding the above, bare wire systems are simple and easy to operate and maintain as most of the fundamental components and techniques are used for MV lines. Eskom has used both insulated neutral ABC systems and bare neutral ABC systems extensively in the past. Presently bare neutral systems are used for inland (i.e. non corrosive) and insulated neutral systems for coastal (i.e. corrosive) areas. The low-voltage ABC shall conform to SCSSCAAD5. a) Insulated neutral ABC In coastal areas, existing bare neutral ABC systems shall be extended using insulated neutral ABC. The connector used for connection of the insulated neutral ABC to the bare neutral ABC is shown on D-DT-3039, (Part 9). Note that the connector is coloured white/cream to distinguish it from other connectors. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 18 of 71 The preferred conductor sizes are: • 3 × 70 mm² phase conductors + 50 mm² neutral: three-phase (4 -wire). • 2 × 70 mm² phase conductors + 50 mm² neutral: dual phase (2 -wire). • 3 × 35 mm² phase conductors + 35 mm² neutral : three-phase (4-wire). • 2 × 35 mm² phase conductors + 35 mm² neutral : dual-phase (3-wire). • 1 × 35 mm² phase conductors + 35 mm² neutral : single-phase (2-wire). b) Bare neutral ABC: The preferred conductor sizes are: • 3 × 70 mm² phase conductors + 50 mm² neutral (Bare): three-phase (4-wire). • 2 × 70 mm² phase conductors + 50 mm² neutral (Bare): dual phase (2 -wire). • 3 × 35 mm² phase conductors + 35 mm² neutral (Bare): three-phase (4-wire). • 2 × 35 mm² phase conductors + 35 mm² neutral (Bare): dual-phase (3-wire). • 1 × 35 mm² phase conductors + 35 mm² neutral (Bare): single-phase (2-wire). LV ABC fittings for bare neutral shall conform to SCSSCAAL4 and for insulated neutral suspension and strain fittings to NRS 018-2. LV ABC may allow for auxiliary supplies to street lights, traffic signals and other outlets. Where specified, auxiliary supplies of this nature are generally taken directly from a phase core. An additional supply core does enable more control of the apparatus connected to it, for example, control of groups of streetlights from a set point on the reticulation. The use of the additional auxiliary supply core is not a specified Eskom standard when using ABC and shall be the exception and not the rule. Phase cores are identified by indented or embossed numbers 1,2 or 3. a) The bare neutral requires no identification as it is bare. b) The insulated neutral shall be marked “N” and/or embossed coloured stripe c) Single-phase ABC shall have the phase core marked ‘1’. d) Dual-phase ABC shall have the phase cores marked ‘1’ and ‘2’. e) Three-phase ABC shall have the phase cores marked ‘1’, ‘2’ and ‘3’. Table 3 — ABC core allocation for different reticulation methods 1 2 3 4 ABC Marking Nominal Nominal phase-tophase phase-neutral voltage Three-phase 1 = White voltage 400 V 230 V N/A 230 V 460 V +230 V 2 = Blue 3 = Red Single-phase 1 = White or Blue or Red Dual-phase 1= +VE 2= -VE -230 V ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION 1 2 ABC Marking Unique Identifier: 34-953 Revision: 0 Page: 19 of 71 3 Nominal Nominal phase-tophase phase-neutral voltage Upgrading singlephase to dual-phase (both conductors have phase cores marked 1) 4 Original conductor + ve. nd Mark 2 phase conductor, at each pole, 2-ve using an aluminium label stuck end to end around the core. 460V voltage +230V -230V 2-Ve NOTE — It is possible that LV ABC systems may have to be upgraded in the future to compensate for unacceptable low voltage levels due to increased loads. Even though each situation needs to be treated separately some upgrade recommendations, applicable to ABC, are presented in Table 2. In this unlikely event of upgrading single-phase lines to dual-phase lines, use an aluminium label as described above to identify the cores. The service connections shall be distributed between the two or three phases as determined by the electrical planning function. The most effective method of LV distribution is usually several radial feeders from each transformer. Design span and sag tables for LV ABC are given in Annex C. Clearances applicable to shared Telkom Structures are found in NRS 043. Examples are given on drawings D-DT-0348 and D-DT-0349. The maximum span that can be tolerated by Telkom shall be established from Telkom in the area. Accommodation of Telkom maximum spans can be achieved by doing the following: a) MV poles at design span length with a LV pole between to accommodate LV and Telkom conductors; and b) MV or LV poles at the Telkom span length, for example, 60 m. Additional costs to accommodate Telkom shall be in accordance with the Eskom/Telkom agreement, specified in NRS 043. 4.3.1.1 Positioning and installation of insulation piercing connectors (IPC’s) and cable ties Annex I provides detailed information relating to the installation of insulation piercing connectors. Notwithstanding, The neutral IPC’s should be positioned closest to the pole and then the phase IPC’s shall follow. Where a pole-top box and streetlight is fitted on the same pole, the streetlight IPC’s (neutral and line) shall be put up last i.e. furthest from the pole The same spacing distance as in 1 & 2 above shall be valid for streetlight IPC’s. Streetlights are generally maintained from a bucket-truck and therefore distance from the pole is not a problem. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 20 of 71 The service distribution box and streetlight fitting cables (and thus IPC’s) shall be distributed, as far as reasonably practicable, evenly on both sides of intermediate and strain poles. This is to assist ease of maintenance, as it is done from a ladder. At terminal poles all service distribution box and streetlight fitting cables will be connected to the ABC on the tension side of the strain clamp. All IPC’s shall be positioned in such a manner that the tightening bolt is in a vertical position, with the torque-shear nut on top. This ensures that the grease, enhancing water-tightness, does not run out. As far as is practically possible the ABC bare neutral conductor should be positioned in such a way that it does not lie adjacent to the mouth of the phase IPC. 4.3.1.2 Shearing of IPC torque shear nuts • Personnel working on ABC networks shall be equipped with a 13-mm tube spanner with Tbar or a 6-sided (hexagon) socket, to be used with a ratchet. • NOTE - The performance of the tube spanner or socket is not affected by the temperature of the IPC and appears to consistently shear the torque shear nut as required. • During installation of IPC’s it shall be ensured that the IPC is held securely in order to prevent it from twisting. • A standard 24-sided socket or 13mm spanner shall not be used. • Sheared IPC torque shear nuts must be removed from the IPC and the Clerk of Works are to perform a visual inspection to check that all torque shear nuts are removed. 4.3.1.3 Jointing of ABC neutral after failures(D DT 0300) The following full tension jointing methods shall be used: • compression joint as per Eskom drawing D-DT-0302. • automatic line splice that is suitable for the ABC neutral conductor diameter (D DT 3228). On all bare neutral ABC systems the neutral shall be insulated from the strain clamp to the transformer connection with a UV protected covering. Refer to D-DT-3127. All ABC tails or ends shall be sealed using end caps. The ABC shall be installed in accordance with SANS 0198 part 14. Only 70 mm ABC aluminium conductors shall be used to connect between the transformer and the low-voltage fuse units. Where larger power transfer is required appropriately rated ABC shall be used. ABC to ABC (refer to D-DT-0314) a) Non-tension phase connections on ABC shall be made using a 95/35 - 95/35 IPC in accordance with D-DT-3039 (Part 9) b) Non-tension neutral connections on bare neutral ABC shall be made using either: 1) a minimum of one H crimp in accordance with D-DT-3019 (Part 9) per connection; or 2) two PG clamps in accordance with D-DT-3058 (Part 9) per connection; or ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION c) Unique Identifier: 34-953 Revision: 0 Page: 21 of 71 Non-tension neutral connections on insulated neutral ABC shall be made using two 95/35 95/35 IPC in accordance with D-DT-3039 (Part 9) ABC to pole top distribution box (refer D-DT- 3039 and 3058) d) The ABC shall be connected to the pole-top distribution box using either: 1) 35 - 95/6-25 IPC (refer to D-DT-3039 (Part 9)) for phase connections; 2) two PG clamps in accordance with D-DT-3058 (Part 9) per neutral connection. 3) Minimum of one H-crimp (refer to D-DT-3019 (Part 9) for bare neutral ABC connections; NOTE — The H-crimp and PG clamp is suitable for aluminium to copper connections only if, with the H-crimp/clamp vertically positioned, the copper conductor is below the aluminium conductor. The crimp is performed with a tool capable of exerting at least 10 tons and an ‘0’ die. 4) 2 x 35-95 (PG)/6-25 (IPC’s) (refer to D-DT-3039 (Part 9)) for bare neutral ABC connections; or 5) 2 x 35 - 95/6-25 IPC’s (refer to D-DT-3039 (Part 9)) for insulated neutral ABC connections. e) All workers performing crimp connections shall be certified as competent to do so by the project construction manager. f) When upgrading ABC systems and when it is necessary to optimize customer connections on the ABC run, it is better to leave the existing pole-top distribution boxes where they are and install new ones at more desirable positions. This is to ensure that the ABC remains sealed against moisture ingress. g) The pole top box shall be installed 300 mm below the neutral /earth conductor. h) Once an IPC connector has been applied to an ABC phase conductor (or any insulated conductor) it shall not be removed. The ABC insulation cannot be repaired by the use of grease and tapes and the ABC conductor and connector are best left as a system. Cut away phase conductors shall have their ends sealed. If the connection is in the wrong place leave it where it is and make a new connection at the desired point. 4.3.2. Bare LV conductors As with ABC systems, bare wire systems may be used for all the reticulation methods, i.e. threephase, single-phase, dual-phase and their practical combinations. The bare wire system has the following benefits; it is a) easy to rebalance; b) simple to apply and has good reliability; and c) easy to fault-find and maintain. From an initial cost perspective it is suited to rural, low-density application with site conditions that allow for long spans. It is also appropriate when an easy upgrade path is desired for the area. a) a stricter earth to neutral clearance requirement (5,5 m) for bare wire systems; ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 22 of 71 b) more stringent safety requirements for bare wire systems; and c) bare wire systems are less forgiving to poor initial installation practice than ABC. d) bare wire is more vulnerable to vandalism (wire throwing), however, based on past experience the occurrence is relatively seldom. The specific requirements for LV bare wire systems are as follows: a) the conductors shall be arranged in a vertical configuration with the neutral conductor always being closest to the ground i.e. the lowest conductor; b) where dedicated street lighting circuits exist which result in the neutral conductor not being the lowest, suspended earthing devices must be installed; c) Connections 1) Bare wire to bare wire connections may be made with the bolted PG (type) clamps or other acceptable crimping techniques i.e. the 4-point indent system or H-crimps. The H-crimp and PG clamp is suitable for aluminium to copper connections only if, with the H-crimp/clamp vertically positioned, the copper conductor is below the aluminium conductor. The crimp is performed with a tool capable of exerting at least 10 tons and an ‘0’ die. 2) Bare wire to insulated conductor connections. i. Bare wire (normally ACSR or AAAC) to ABC. o A suitably sized PG/IPC connector may be used. (Refer to D-DT-3039, Part 9). ii) Bare wire to insulated service box lead ii. 35-95 / 6-25(IPC). (Refer to D-DT-3039, Part 9) o Minimum of one H-crimp (refer to D-DT-3019 (Part 9) o PG clamps in accordance with D-DT-3058 (Part 9) per connection. Except for the H-crimp a single connector is used for the phase and two connectors for the neutral connections. The H-crimp and PG clamp is suitable for aluminium to copper connections only if, with the H-crimp/clamp vertically positioned, the copper conductor is below the aluminium conductor. The crimp is performed with a tool capable of exerting at least 10 tons and an ‘0’ die. d) All bolted clamps used for connections shall have non-oxide grease applied. e) The pole top box shall be installed 300 mm below the neutral /earth conductor. f) The pole top box leads shall be stapled to the pole using double pin clips (Concentric clips) (refer to D-DT-3111, Part 9). The opening of the pole top service box shall be installed in-line to the line direction (D- DT0921). g) The structure drawing (D DT 0920) shows an eye-nut attached to the neutral hardware. This is to facilitate the service connection at a higher attachment point and to obviate the need for additional pigtail bolts. h) All nuts that are associated with insulator supports shall have nut retention paint applied. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 23 of 71 i) All galvanized metal work that is cut on site shall have anti-corrosion treatment applied immediately i.e. cold galvanizing. This method to be approved prior to execution by the local Technology and Quality department. j) The phase and neutral conductor position on the poles shall be as follows for the single-, dual- and three-phase methods. Three-phase White Blue Red Neutral Single-phase Phase (W,B,R) Neutral Nil Nil Dual-phase Phase +ve Phase -ve Neutral Nil NB: Upgrading involves moving conductors to be inline with the above, or redoing the connections to suit. Pre-energization tests to ensure correct connections are mandatory. k) l) Upgrading 1) Where conditions allow, poles shall be installed at maximum spacing (100 m to 115 m) or the project engineer shall decide on maximum spacing using R-SAT. Phase separators shall be installed for spacing greater than 80m. The spacing shall allow for future intermediate installations thus the initial spacing shall be in multiples to allow for final spacing exceeding 40m. 2) When upgrades occur, additional hardware is installed, conductors are run out, service boxes are reset and loads are balanced. 3) With the latest technology developments, more emphasis shall be placed on dualphase LV networks and dual-phase transformers, with upgradeable backbones and lateral feeders placed as close to the load as possible so as to facilitate the use of 4mm² concentric service cable. Standard conductors 1) ACSR : Squirrel, Fox, Mink, Hare. 2) AAAC : Acacia, Pine, 35, Oak. m) Only aluminium conductors shall be connected to low-voltage fuse units. 4.4. Clearances The SANS 10280 published during 2010 has different clearance requirements to those published in the OHS Act. The following table has been taken from SANS 10280. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 24 of 71 Table 4 — Clearance (at maximum sag or swing as applicable) 1 2 3 Highest system r.m.s. voltage System nominal r.m.s. voltage kV kV <1 7,2 12 24 36 48 72 100 145 245 300 362 420 b 800 d.c. c 533 kV 4 Safety Safety clearance clearance phase-to- phase-toearth phase 5 6 7 8 9 Minimum vertical clearances Minimum clearances any direction m Roads in townships, and proclaimed roads, railways To telecommunication lines and between power lines Ground clearance 10 Minimum vertical and horizontal clearances m To buildings, poles, structures not part of power lines and vegetation m Tower-top clearances at maximum insulator swing and minimum clearances at extreme wind conductor blowout m m – 6,6 11 22 33 44 66 88 132 220 – 0,15 0,20 0,32 0,43 0,54 0,77 1,00 1,45 2,1 – 0,2 0,3 0,4 0,5 0,61 0,89 1,14 1,68 2,7 4,9 5,5 5,5 5,5 5,5 5,5 5,7 5,9 6,3 7,0 a 6,1 6,2 6,3 6,4 6,5 6,6 6,9 7,1 7,5 8,2 0,6 0,7 0,8 0,9 1,0 1,1 1,4 1,6 2,0 2,7 3,0 3,0 3,0 3,0 3,0 3,0 3,2 3,4 3,8 4,5 0,1 0,1 0,1 0,1 0,1 0,15 0,20 0,24 0,35 0,6 275 330 400 765 2,5 2,9 3,2 5,5 3,6 4,3 4,8 8,9 7,4 7,8 8,1 8,6 9,0 9,3 11,6 3,1 3,5 3,8 6,1 4,9 5,3 5,6 8,5 0,7 0,86 1,0 1,9 – 3,7 – 10,4 8,6 9,8 a 4,3 a m a 6,1 NOTE The assumption on which the values are based, is given in C.2. a For insulated power lines complying to SANS 1418-1 and SANS 1418-2 (Aerial bundled conductor systems) or SANS 1507-6 (concentric cable) no minimum safety clearances are required here. The same will apply to technologies for which compulsory SANS safety standards may be developed. Sag and ground clearances shall be calculated using the conductor operating temperature and this can be assumed to be 50 °C, unless the operating te mperature is more than this value. A minimum conductor temperature of 50 °C shall be u sed to determine clearances under conductor swing conditions. The swing angle shall be that corresponding to 500 Pa of wind pressure. These separation distances shall apply under all operating and environmental conditions. ABC with a bare neutral is classified as a fully insulated system, notwithstanding designers are to be cognizant of risks associated with broken neutrals regardless of the technology, where dangerous voltages will occur on exposed fallen neutral conductors as well as all customer installations where a neutral conductor breaks. On method to mitigate against this risk, is to connect all LV feeder neutrals in the same transformer zone, by means of neutral line interconnectors. While not normally practicable, unless neutrals are connected to conductive poles which are part of a meshed neutral systems, the conductive path including footing resistance of conductive poles needs to be such as to prevent dangerous touch potentials. Whenever a part of an insulated conductor is bare at the structure (e.g. a bare terminal) then the bare conductor separation distances shall apply. Bare conductor clearances above water shall comply with the requirements set out in SANS 10280. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION 4.5. Unique Identifier: 34-953 Revision: 0 Page: 25 of 71 Telkom conditions for sharing of services The requirements for the joint use and sharing of structures are set out in NRS 043 which surpasses this document in terms of hierarchical placement and should always be the main reference in all thing relating to shared structures. Relevant excerpts of the specification and set out below. 4.5.1. Clearances (minimum) for shared services The minimum attachment spacing between Eskom and Telkom services are listed in table 5. Table 5 — Attachment spacing 1 2 3 Bare Insulated Bare Insulated 2m 0,9 m 1,2 m 0,9 m MV 4 LV The minimum attachment clearance between an insulated power conductor and a Telkom conductor on the same structure 0,9 m. The separation distance between a power conductor and a separated Telkom line will be 3m.. There are no restrictions on the Eskom conductor type as specified in this document. Separation distances at attachment points are between the telecommunication cable and the lowest attachment point of the power conductor or the lowest attachment point of the service distribution box. Table 6 lists the minimum Telkom clearances. Table 6 — Ground clearance of telecommunication cables 1 2 Location of route Minimum ground clearance 1) Across non-electrified railways 6,10 2) Across any national road 6,50 3) Across abnormal provincial roads 7,50 4) Across other provincial roads 6,10* 5) Across other public roads 6,10 6) Across streets, roads other than (2), (3), or (4) above, or across privately owned railway tracks in or near towns 5,50 7) Across private roads or railway tracks not in or near towns 4,90 8) Along streets (including midblock), roads or privately owned railway lines in or near towns. 3,70 9) Along country roads or railway lines, or over veld or private lands other than (10). 3,00 10) Over cultivated farm lands and across points of entry into cultivated lands. 4,90 * This may be reduced to 5,5 m subject to negotiation with provincial authorities. Telkom and Eskom service conductors may be hung from the same attachment points on the 4 m/5 m poles only if no electrical connection points exist on the pole top in question. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION 4.5.2. Unique Identifier: 34-953 Revision: 0 Page: 26 of 71 Conditions The clearances in tables 4, 5 and 6 are mandatory and no deviation shall be permitted without the written agreement of Telkom and the power supply authority. Earth connection of conductive poles resistance to earth shall be such that the pole does not become live during an earth fault. No further earthing is required on poles bonded to an LV neutral. Telkom employees are required to go through a basic training as specified in the Eskom training course before they can do work on power line structures. Stay anchors shall be supplied by each authority where they deem it necessary. All plans for residential areas electrification shall be submitted to Telkom in the prescribed manner .In view of the time factor involved in the submission and approval of plans it is strongly recommended that the proposed layout be clearly shown on acceptable plans and discussed with Telkom Regional representatives in the earliest stage of the project. Telkom will provide Eskom with a request for any shared circuits. Eskom should only agree to sharing of circuits if Telkom’s contribution to the shared circuits is greater than any additional Eskom expenditure to accommodate Telkom. 4.6. Protection All protection issues set out in this standard should be applied in conjunction with LV protection philosophy for low consumption areas, SCSAGAAH8. CSP transformers are being phased out. Where these occur designers are to take cognizance of and apply protection requirements applicable to SANS 780 transformers. The requirements for protection of the low-voltage system are as follows: The rating of the protective device applied at the transformer LV shall be chosen in order that the lowest possible phase-to-neutral fault level on an LV distributor will operate the device. In order to ensure this: a) LV ABC distributors protected by CSP type circuit-breakers shall have a minimum phase-toneutral fault level of 2 × the full load rating of the transformer; b) LV ABC distributors protected by fuses shall have a minimum phase-to-neutral fault level of 1.6 × the fuse rating i.e. the conventional fusing current of the fuse. Where this cannot be achieved suitable fuses shall be applied down the line. On bare wire LV systems the protective device applied at the transformer LV or any point down line shall ensure that the lowest possible phase-to-neutral fault level within its zone of protection will result in a protection operating time of less than 100 s. CSP type transformers have an internal oil immersed circuit-breaker that protects the transformer against overloading. The circuit-breaker can also provide adequate protection of LV ABC distributors if the full load rating of the transformer that it protects is less than 70 % of the full load rating of the conductor. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 27 of 71 Where 100 kVA or 200 kVA CSP transformers supply 35 mm² ABC and 70 mm² ABC this requirement is not always met, however the circuit-breaker will protect the ABC provided the LV distributor does not exceed the length specified in table 7: ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 28 of 71 Table 7 — Maximum protected lengths of ABC 1 2 3 CSP Transformer Maximum recommended length of 35 mm² ABC Minimum recommended 2 length of 70 mm ABC 100 kVA 250 m See 2.7.3 200 kVA Will not protect ABC 170 m Transformers without internal oil immersed circuit-breakers shall be equipped with external fuses using the following guidelines: a) 16 kVA single-phase 1 × 80 A HRC fuse. b) 32 kVA dual-phase 2 × 80 A HRC fuses. c) 50 kVA three-phase 3 × 80 A fuses d) 100 kVA three-phase 3 × 160 A HRC fuses e) 200 kVA three-phase 2 × 3 × 160 A HRC fuses The fuses will also provide adequate protection for the LV distributor if the fuse rating is less than the full load rating of the conductor used for the LV distribution. Where 100 kVA or 200 kVA transformers with 160 A fuses supply 35 mm² ABC, this requirement is not met, however the fuse will protect the ABC provided the LV distributor does not exceed the length specified in table 8: Table 8 — Maximum protected lengths of ABC Transformer Maximum recommended length of 35 mm² ABC 100 kVA 280 m 200 kVA 290 m Due to the introduction of split metering and with the view of future smart metering applications, the pole service box requirements are covered in distribution standard part 8 services. Notwithstanding, to ensure continuity, both standards shall ensure compatibility in terms of grading and protection requirements. In view of this as an interim measure, until such time as the relevant protection standards are revised, the following are to be accepted. Service cables of the concentric type originate from a pole-top box that is equipped with a 50 A MCB. This will grade reasonably with the transformer protection and the customer’s installation. Overload protection of the service cable is provided by the load limiting function of the energy control unit (ECU), however short circuit protection shall be provided by the protection device in the pole service box, with the proviso, this protective device will operate before the damage to the concentric cable in the event of overloading.. Further details regarding the low-voltage protection philosophy are given in SCSAGAAF5 and SCSAGAAH8. Previously issued ED’s were equipped with a single-pole isolator. Current ED’s do not have any protective devices and rely on the protective device in the pole top box for isolation. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION 4.7. Transformers and surge arresters 4.7.1. Transformers Unique Identifier: 34-953 Revision: 0 Page: 29 of 71 Transformers shall comply with the following: a) Three phase and single phase transformers shall comply with SCSSCAAH4. Dual phase transformers shall comply with DISSCAAK7. b) The preferred sizes for transformers are 16 kVA (single-phase), 32 and 64 kVA (dual-phase), 50, 100 and 200 kVA (three-phase). The actual size will depend on the ADMD predicted for the supply area and load platform. The time/overload capacity of the transformer shall be considered to ensure cost effective design and the full overload capability of the transformer shall be used in estimating the number of customers / transformers for a specific ADMD. c) All transformers shall be earthed in accordance with drawing D-DT-0627 in SCSASAAL9. d) The transformer LV connection shall be made in accordance with drawing D-DT-0308 for CSP units or drawing D-DT-0309 for the SANS 780 type. The LV earth may be positioned at the transformer (preferred) or one span away on at least two feeders. The choice will depend on the prevailing circumstances; however the MV and LV earths shall be at least 5 m apart. 4.7.2. LV neutral surge arrester An LV surge arrester shall be placed between the LV neutral bushing and the transformer tank to protect the transformer during transient fault conditions. The connection shall be in accordance with D-DT-0308 for CSP transformers and D-DT-0356 for SANS 780 transformers. 4.7.3. LV connections and jumpers Pre insulated lugs (DDT 3116) shall be used to connect the jumpers to the transformer bushings. Where a large number of jumpers are required to be connected to the transformer bushing but is restricted due to the available bushing thread, either transformer lugs (DDT3126) or extension connectors can be used. Transformer jumpers between the transformer phase bushings and the fuse unit shall be made of 70 mm2 ABC. Neutral conductors are to be brought up from the LV circuit and made off on the neutral bushing using the above connectors or a bi metallic lug. Copper tinned lugs (D DT 3102) shall be used to connect the copper earth wire to the neutral bushing to avoid bi-metallic corrosion. LV fuse unit The LV fuse units shall be positioned in a way that facilitates ease of operation from ground level using a link stick with the appropriate attachments. The units shall be placed below the LV conductor and the position shall also allow for future LV units to be installed where upgrading of the network is anticipated. The transformer structure drawing D-DT-0309 indicates proposed fuse unit positions for up to 4 units. Typically, two LV feeders can be fed from one fuse unit. LV jumpering The LV jumpering shall be bunched together and neatly routed from the transformer bushings to the LV fuse units. The ABC shall not be bent in an arc with a radius of less than 200mm so that the entry ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 30 of 71 point is not under stress. Sharp bends shall be avoided. In the case of a bare neutral conductor the neutral shall be covered with LDPE tubing, in accordance with D-DT-3127, from the neutral bushing to the LV fuse unit. The jumpering shall be routed in such a way that it will not chafe against sharp objects. Cable ties can also be used to keep the jumpering in position: stainless steel strapping is not recommended. A separate set of jumpers is required for each fuse unit. The neutral conductor shall bypass the fuse unit and shall not be broken. LV feeder take off The LV feeder shall be located at a position that maintains ground clearance from the transformer and MV network. To ensure a safe working clearance the fuse unit must be installed a radial distance of 1.1m from the bottom of the transformer tank. 4.8. Earthing installation and tests Installation earthing and earth tests shall be carried out in accordance with SANS 10292, and SCSASAAL9, with particular reference to D-DT-0627 in SCSASAAL9. 4.9. Poles and stays Poles may be either wood or concrete. The preference of the local engineering area shall be established. Concrete and wooden poles of the same height are not inter-changeable without considering the stresses they can withstand. Poles shall be selected in accordance with SCSSCAAO1. a) b) Safety factors 1) Wood pole structures shall be designed with a safety factor of 2,7 in the case of suspension structures and 4,5 in the case of strain structures. 2) Concrete poles are to be designed in accordance with clause 14 of the OHS Act. Specifications of pole lengths 1) Wood poles shall comply with SCSSCAAD7. Standard wood pole lengths are 5 m, 7 m, 9m, 10 m, 11 m, 12 m and 13 m. 2) Concrete poles shall be manufactured in accordance with DTC 0106. The standard concrete pole lengths are 4 m, 7 m, 9 m, 10 m and 11 m. The design drawings of standard concrete poles used are given in Annex J. c) It can be cost effective for LV, MV, street lighting and telephone services to share poles. This shall be undertaken whenever practical and appropriate. If MV and LV share the same structure then a taller pole shall be used with the LV connections at the same height above the ground as for LV alone. Refer to D-DT-0335 and D-DT-0336 of SCSASAAP2. d) Where conductive poles e.g. steel, are used, all conductive parts shall be bonded to the LV neutral. Concrete poles are considered semi conductive and do not need to be bonded to the LV neutral: e) The planting depths of concrete and wood poles are specified in table 9; ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 31 of 71 Table 9 — Planting depths of equivalent concrete and wood poles 1 2 3 4 Concrete poles 5 6 Wooden poles 55 MPa Length Strength Planting depth m kN mm Length Pole top m Planting depth mm mm 4 1 800 5 80 1 000 7 4 1 300 7 120 1 300 9 6 1 500 9 140 1 500 10 8 1 800 10 160 1 800 10 (Trf.) 8 1 800 11(Trf.) 180 1 800 11 8 1 800 11 160 1 800 12 200 2 000 13 200 2 200 NOTE — These are recommended pole sizes. If other sizes are used Distribution Technology shall be consulted. f) Planting poles g) 1) Pole holes shall be dug in such a way that the longest side of the hole dug for the pole is parallel to the feeder line, the hole shall be dug so that the width is as narrow as possible whilst allowing the pole to be planted to the correct depth. 2) The designer shall determine and include measures to mitigate against the impact of both overturning and subsidence where poor soil conditions are encountered (stay plates, lintels, cement to soil mixture). 3) After a pole has been planted to the required depth, the soil that is to be filled into the hole shall be slightly damp. If the soil is held in the hand and squeezed, it shall stay as it was squeezed after opening the hand: that will indicate an optimum moisture content to ensure good soil compaction. Compaction Compaction shall be in accordance with SCSSCAAO1. h) Stays may be of the conventional type in accordance with D-DT-0341 or of the percussion type. An example using the “mule stay” is shown on D-DT-0350 sheet 2. Stay rod installation is shown on D-DT-0350 sheet 1. i) For bare wire systems the designer is to ensure that correctly rated stays are used in accordance with the conductor type. This implies that 95kN stays are to be deployed for conductor sizes greater than 50mm2. 4.10. Service connections The service connections shall conform to the requirements of DISASAAS3. 4.11. Customer installations The customer installations shall conform to the requirements of DISASAAS3. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION 4.12. Unique Identifier: 34-953 Revision: 0 Page: 32 of 71 Customer metering The customer metering shall conform to the requirements of DISASAAS3. Structure drawings for bare wire and ABC overhead reticulation systems and a list thereof, can be found in annex H. A separate structure drawing for each reticulation method (single-phase, dual-phase, three-phase), for bare wire and ABC and for wood and concrete poles is provided. NOTE — Bare wire lines are constructed on wood poles only. 4.13. Bills of materials (BOM) A bill of materials in list form is not provided, however all the materials required are described on each drawing and are referenced to SCSPVAAT6. 4.14. Power Office Power Office will be available from IARC, Simmerpan or the Local Operating Divisions This tool will be used to provide a complete Bill of Resources for all structure types and conductor combinations used on a particular project. It will interface with MicroStation systems and the Eskom Project Management to provide the necessary Bills of Resources. 4.15. Marking and labeling 4.15.1. Statutory requirements All controlling apparatus shall be permanently marked or labelled so as to identify the system or part of the system or the electrical machinery that it controls. Where such control apparatus is accessible from the front and back, these markings shall be on both the front and the back. NOTE — Dymotape, masking tape, etc., are not permanent labels and may not be used under any circumstances. The Local Operating Division labelling requirements are to be established and used for reticulation in that area. 4.15.2. Labelling requirements All labels shall be permanently and indelibly inscribed and of a size that can be read from ground level and shall be in accordance with ESKASAAN0. All labels shall have black letters on a yellow background. The label size shall be in accordance with the labelling requirements. The material used shall be durable and resistant to ultraviolet and pollution. Recommended materials are: Iscor Chromodek 0,6 mm (Ref. PO4008 yellow) or aluminium alloy 25 painted with PVF2 yellow. All lettering/numbering shall be a minimum of 50 mm high. It is recommended that Scotch vinyl decals (Ref. GSP220) be used. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 33 of 71 The label shall be positioned in such a way that it is: a) readable from ground level from the direction that is most logical from an operational perspective. b) not accessible to the public. Labelling of transformer/s zones a) each feeder b) LV fuses or circuit-breakers along the line: pole-top boxes. 5. Tests and commissioning To ensure the safe and reliable operation of a reticulation system the visual inspections and electrical tests shall be done before and after permanent energizing. Sample inspection and test sheets are given in annexes F for use by the project resources. The OHS ACT shall be the minimum requirement for testing and inspection. 5.1. 5.1.1. Electrical tests Insulation resistance tests Disconnect the LV feeders at the transformer. With all pole-top box MCBs switched off use a 1 kV insulation tester and test between each phase and earth as well as between phases. Care shall be taken to discharge the ABC before disconnecting the insulation tester leads. Record readings on a test result sheet (annex H). Expected results are 1 MΩ or higher between phases and 1 MΩ or higher between phase and neutral. If the results are below 1 MΩ, corrective action shall be taken. 5.1.2. Earth resistance tests These tests shall be done in accordance with SCSASAAL9. These tests shall be done after the insulation test. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 34 of 71 Annex A – Impact Assessment (Normative) Impact assessment form to be completed for all documents. A1 Guidelines o All comments must be completed. o Motivate why items are N/A (not applicable) o Indicate actions to be taken, persons or organisations responsible for actions and deadline for action. o Change control committees to discuss the impact assessment, and if necessary give feedback to the compiler of any omissions or errors. A2 Critical points A2.1 Importance of this document. E.g. is implementation required due to safety deficiencies, statutory requirements, technology changes, document revisions, improved service quality, improved service performance, optimised costs. Comment: A2.2 If the document to be released impacts on statutory or legal compliance - this need to be very clearly stated and so highlighted. Comment: A2.3 Impact on stock holding and depletion of existing stock prior to switch over. Comment: A2.4 When will new stock be available? Comment: A2.5 Has the interchangeability of the product or item been verified - i.e. when it fails is a straight swop possible with a competitor's product? Comment: A2.6 Identify and provide details of other critical (items required for the successful implementation of this document) points to be considered in the implementation of this document. Comment: A2.7 Provide details of any comments made by the Regions regarding the implementation of this document. Comment: (N/A during commenting phase) ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 35 of 71 Annex A (continued) A3 Implementation timeframe A3.1 Time period for implementation of requirements. Comment: A3.2 Deadline for changeover to new item and personnel to be informed of DX wide changeover. Comment: A4 Buyers Guide and Power Office A4.1 Does the Buyers Guide or Buyers List need updating? Comment: A4.2 What Buyer’s Guides or items have been created? Comment: A4.3 List all assembly drawing changes that have been revised in conjunction with this document. Comment: A4.4 If the implementation of this document requires assessment by CAP, provide details under 5 A4.5 Which Power Office packages have been created, modified or removed? Comment: A5 CAP / LAP Pre-Qualification Process related impacts A5.1 Is an ad-hoc re-evaluation of all currently accepted suppliers required as a result of implementation of this document? Comment: A5.2 If NO, provide motivation for issuing this specification before Acceptance Cycle Expiry date. Comment: A5.3 Are ALL suppliers (currently accepted per LAP), aware of the nature of changes contained in this document? Comment: ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 36 of 71 Annex A (continued) A5.4 Is implementation of the provisions of this document required during the current supplier qualification period? Comment: A5.5 If Yes to 5.4, what date has been set for all currently accepted suppliers to comply fully? Comment: A5.6 If Yes to 5.4, have all currently accepted suppliers been sent a prior formal notification informing them of Eskom’s expectations, including the implementation date deadline? Comment: A5.7 Can the changes made, potentially impact material/equipment? upon the purchase price of the Comment: A5.8 Material group(s) affected by specification: (Refer to Pre-Qualification invitation schedule for list of material groups) Comment: A6 Training or communication A6.1 Is training required? Comment: (If NO then 6.2 – 6.6 will be N/A) A6.2 State the level of training required to implement this document. (E.g. awareness training, practical / on job, module, etc.) Comment: A6.3 State designations of personnel that will require training. Comment: A6.4 Is the training material available? Identify person responsible for the development of training material. Comment: A6.5 If applicable, provide details of training that will take place. (E.G. sponsor, costs, trainer, schedule of training, course material availability, training in erection / use of new equipment, maintenance training, etc). Comment: ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 37 of 71 Annex A (continued) A6.6 Was Technical Training Section consulted w.r.t module development process? Comment: A6.7 State communications channels to be used to inform target audience. Comment: A7 Special tools, equipment, software A7.1 What special tools, equipment, software, etc will need to be purchased by the Region to effectively implement? Comment: A7.2 Are there stock numbers available for the new equipment? Comment: A7.3 What will be the costs of these special tools, equipment, software? A8 Finances A8.1 What total costs would the Regions be required to incur in implementing this document? Identify all cost activities associated with implementation, e.g. labour, training, tooling, stock, obsolescence Comment: ………………………………………………………………………………………………………………………. ………………………………………………………………………………………………………………………. ………………………………………………………………………………………………………………………. Impact assessment completed by: Name: _________________________________________________________________ Designation: _____________________________________________________________ ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 38 of 71 Annex B - Conductor properties Aerial Bundled Conductor (Refer SCSSCAAD5) ACSR AAAC ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: Draft 0.1 Page: 39 of 71 Annex B (Continued) Conductor properties — LV ABC (cater for insulated) 1 2 3 4 5 6 7 8 9 Thickness of dielectric Conductor mm (Note 1) Type of conductor of core Phase (aluminum) Supporting & neutral (aluminum alloy) Conductor size mm2 Number of wires Resistance at 20 °C Diameter of conductor Breaking force Ω / km max. mm N Min Max Min Average Min Max 35 70 7 19 0,868 0,443 6,6 9,3 7,5 10,2 4500 8900 1,3 1,5 1,1 1,3 1,5 1,7 35 7 0,986 6,6 7,5 10300 N/A N/A N/A 50 7 0,720 7,7 8,4 14200 N/A N/A N/A NOTE 1 — Columns 8 and 9 show the preferred radials as these are believed to be the most cost effective. Due to the manufacturing technology differences which may exist products with up to the following radial thicknesses will not be rejected provided that they are within the concentricity requirements described below: Table of maximum dielectric thicknesses and concentricity Core (mm2) Average (mm) Maximum (mm) Minimum (,,) 35 1,6 1,8 1,5 70 1,8 2,0 1,5 ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: Draft 0.1 Page: 40 of 71 Annex B (Continued) Conductor properties — ACSR & AAAC 1 2 3 Conductor Stranding Copper Code Name and wire dia. Equiv. Area Overall Dia. Total Area Mass mm2 mm mm2 6,35 6,33 mm 4 5 6 7 8 Mechanical properties 9 Coeff. 10 11 Electrical properties Breaking Load Final Modulus of linear expansion D.C. res. Rating @ 20°C @ 75°C kg/km kg GPa 10-6 / °C Ω/km A 24,71 139,7 1893 133,76 13,68 2,707 78 24,48 85,2 818 80,4 19,31 1,3677 110 Table A1 - ACSR (Aluminium Conductor Steel Reinforced) - Extra Strong Magpie 3/4/2,118 6,65 Table A2 - ACSR (Aluminium Conductor Steel Reinforced Squirrel 6/1/2,11 12,9 Fox 6/1/2,79 22,58 8,37 42,8 149 1340 80,4 19,31 0,7822 155 Mink 6/1/3,66 38,71 10,98 73,65 257 2230 80,4 19,31 0,4546 215 Hare 6/1/4,72 64,52 14,16 122,48 427 3670 80,4 19,31 0,2733 290 6,24 23,79 65 682 61 23 1,39 110 Table A3 - AAAC (Aluminium Conductor Aluminium Alloy reinforced) Acacia 7/2,08 13 35 7/2,77 22 8,31 42,18 115 1210 61 23 0,785 155 Pine 7/3,61 38 10,83 71,65 196 2060 61 23 0,462 215 Oak 7/4,65 63 13,95 118,9 325 3400 61 23 0,279 290 Table A4 - Galvanized Steel Wire ¼ 1/4,00 – 4 12,57 102 1410 193 11,52 14,67 27 3/3,35 3/3,35 – 7,35 26,44 215 2910 191 11,52 7,4 41 ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: Draft 0.1 Page: 41 of 71 Annex C - Design spans for bare and insulated neutral ABC systems THREE PHASE DESIGN SPANS FOR LV ABC 35 mm² CONDUCTOR Pole Pole top Length dia ( mm ) Nominal Weight Wood Pole Structures Suspension Wood Pole Strain Structures Max span length Max span length Max span length-1*3 Phase ( m ) Span ( m ) Span ( m ) 1 *3 Phase ( m ) Max span length-2*3 Phase ( m ) 2 *3 Phase ( m ) Dev. 30' Dev. 60' Dev. 90' Dev. 30' Dev. 60' Dev. 90' 7 0.12 90 210 78 39 210 210 210 210 140 55 7 0.14 90 210 118 59 210 210 210 210 210 210 7 0.16 90 210 168 84 210 210 210 210 210 210 7 0.18 90 210 231 116 210 210 210 210 210 210 9 0.12 100 210 71 36 210 210 210 185 75 * 9 0.14 100 210 108 54 210 210 210 210 210 205 9 0.16 100 210 154 77 210 210 210 210 210 210 9 0.18 100 210 211 105 210 210 210 210 210 210 210 10 0.12 110 210 67 33 210 210 200 140 35 * 10 0.14 110 210 100 50 210 210 210 210 210 130 10 0.16 110 210 143 72 210 210 210 210 210 210 10 0.18 110 210 196 98 210 210 210 210 210 210 10 0.2 110 210 261 130 210 210 210 210 210 210 11 0.12 120 210 62 31 210 215 125 105 * * 11 0.14 120 210 94 47 210 210 210 210 155 65 11 0.16 120 210 134 67 210 210 210 210 210 210 11 0.18 120 210 183 92 210 210 210 210 210 210 11 0.2 120 210 242 121 210 210 210 210 210 210 ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 42 of 71 Annex C (Continued) THREE PHASE DESIGN SPANS FOR LV ABC 70 mm² CONDUCTOR Nominal Weight Wood Pole Structures Pole Pole top Length dia ( mm ) Span ( m ) Span ( m ) 1 * 3 Phase ( m ) Max span length Suspension Wood Pole Strain Structures Max span length Max span length-1*3 Phase ( m ) Max span length-2*3 Phase ( m ) 2 * 3 Phase ( m ) Dev. 30' Dev. 60' Dev. 90' Dev. 30' Dev. 60' Dev. 90' 7 7 7 7 0.12 0.14 0.16 0.18 85 85 85 85 120 120 120 120 63 95 136 187 32 48 68 94 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120 115 120 120 120 45 120 120 120 9 9 9 9 0.12 0.14 0.16 0.18 100 100 100 100 120 120 120 120 58 87 124 171 29 44 62 85 120 120 120 120 120 120 120 120 120 120 120 120 150 120 120 120 60 120 120 120 * 120 120 120 10 10 10 10 10 0.12 0.14 0.16 0.18 0.2 110 110 110 110 110 120 120 120 120 120 54 81 116 159 211 27 41 58 79 105 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120 115 120 120 120 120 25 120 120 120 120 * 105 120 120 120 11 11 11 11 11 0.12 0.14 0.16 0.18 0.2 120 120 120 120 120 120 120 120 120 120 50 76 108 148 196 25 38 54 74 98 120 120 120 120 120 120 120 120 120 120 120 120 120 120 120 85 120 120 120 120 * 120 120 120 120 * 50 120 120 120 ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 43 of 71 Annex C (Continued) DUAL PHASE DESIGN SPANS FOR LV ABC 35 mm² CONDUCTOR Wind Wood Pole Suspension Structures Pole Pole top Length dia ( mm ) Nominal Weight Max span length Max span length Wood Pole Strain Structures Max span length-1*Dual Phase ( m ) Max span length-2*Dual Phase ( m ) Span ( m ) Span ( m ) 1 *Dual Phase ( m ) 2 * Dual Phase ( m ) Dev. 30' Dev. 60' Dev. 90' Dev. 30' 5 0.08 30 280 58 29 225 220 215 110 5 0.1 30 280 105 52 7 0.12 110 280 103 51 280 280 280 280 7 0.14 110 280 155 78 280 280 280 280 7 0.16 110 280 222 111 280 280 280 280 7 0.18 110 280 305 153 280 280 280 280 9 0.12 125 280 94 47 280 280 280 240 9 0.14 125 280 142 71 280 280 280 280 9 0.16 125 280 203 102 280 280 280 280 9 0.18 125 280 279 139 280 280 280 280 10 0.12 140 280 88 44 280 280 260 185 10 0.14 140 280 133 66 280 280 280 280 10 0.16 140 280 189 95 280 280 280 280 10 0.18 140 280 259 130 280 280 280 280 10 0.2 140 280 344 172 280 280 280 280 11 0.12 150 280 82 41 280 280 165 135 11 0.14 150 280 124 62 280 280 280 280 11 0.16 150 280 177 88 280 280 280 280 11 0.18 150 280 242 121 280 280 280 280 11 0.2 150 280 320 160 280 280 280 280 237 Dev. 60' 105 232 Dev. 90' 100 227 190 280 280 280 70 280 280 280 100 280 280 280 * 270 280 280 45 280 280 280 280 * 170 280 280 280 * 205 280 280 280 * 85 280 280 280 ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 44 of 71 Annex C (Continued) SINGLE PHASE DESIGN SPANS FOR LV ABC 35 mm² CONDUCTOR Pole Pole top Length dia ( mm ) Nominal Weight Span ( m ) Span ( m ) Wood Pole Structures Suspension Max span length Max span length Wood Pole Strain Structures Max span length-1*1 Phase ( m ) Max span length-2*1 Phase ( m ) 1 *1 Phase ( m ) 2 * 1 Phase ( m ) Dev. 30' Dev. 60' Dev. 90' Dev. 30' Dev. 60' Dev. 90' 5 0.08 50 440 74 37 289 282 276 141 135 128 5 0.1 50 440 135 67 305 298 292 7 0.12 125 440 123 62 440 440 440 395 230 85 7 0.14 125 440 186 93 440 440 440 440 440 440 7 0.16 125 440 266 133 440 440 440 440 440 440 7 0.18 125 440 366 183 440 440 440 440 440 440 9 0.12 140 440 113 57 440 440 440 290 125 * 9 0.14 140 440 170 85 440 440 440 440 440 325 9 0.16 140 440 243 122 440 440 440 440 440 440 9 0.18 140 440 334 167 440 440 440 440 440 440 10 0.12 150 440 105 53 440 440 315 220 55 * 10 0.14 150 440 159 79 440 440 440 440 345 205 10 0.16 150 440 227 113 440 440 440 440 440 440 10 0.18 150 440 311 155 440 440 440 440 440 440 10 0.2 150 440 412 206 440 440 440 440 440 440 11 0.12 160 440 98 49 440 340 200 165 * * 11 0.14 160 440 148 74 440 440 440 410 245 100 11 0.16 160 440 212 106 440 440 440 440 440 440 11 0.18 160 440 289 145 440 440 440 440 440 440 11 0.2 160 440 384 192 440 440 440 440 440 440 ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 45 of 71 Annex D - Design spans for ACSR bare wire systems LOW VOLTAGE DESIGN SPANS - SQUIRREL CONDUCTOR 1 Conductor Description Angle 2 Weight Span 3 Nominal Span 8m 9m 10 m 4 Wind Span - Wood Poles 11 m 140m m 7m 160m m 180m m 140m m 9m 160m m 180m m 200m m 140m m 10m 160m m 180m m 200m m 140m m 11m 160m m 180m m 200m m SINGLE PHASE BARE WIRE LV SQUIRREL DUAL WIRE PHASE 0 30 60 90 290 290 290 290 65 65 65 65 105 105 105 105 135 135 135 135 180 180 180 180 265 290 290 290 380 290 290 290 520 290 290 290 240 290 290 290 345 290 290 290 475 290 290 290 630 290 290 290 225 290 290 290 325 290 290 290 445 290 290 290 590 290 290 290 210 290 290 290 300 290 290 290 410 290 290 290 545 290 290 290 0 30 60 90 290 290 290 290 40 40 40 40 100 100 100 100 125 125 125 125 170 170 170 170 180 290 290 290 260 290 290 290 355 290 290 290 165 290 290 290 235 290 290 290 320 290 290 290 430 290 290 290 155 290 290 170 220 290 290 290 300 290 290 290 400 290 290 290 140 290 290 * 200 290 290 290 275 290 290 290 370 290 290 290 0 30 60 90 290 290 290 290 * * * * 85 85 85 85 110 110 110 110 155 155 155 155 140 290 290 290 200 290 290 290 275 290 290 290 125 290 290 15 180 290 290 290 245 290 290 290 330 290 290 290 115 290 200 * 165 290 290 290 230 290 290 290 305 290 290 290 105 290 20 * 155 290 290 200 210 290 290 290 280 290 290 290 BARE LV SQUIRREL THREE PHASE BARE WIRE LV SQUIRREL NOTES: 1) 2) The selected span length is determined by the limiting factors and is the least of the spans given in columns 2, 3 and 4. Span lengths for the Strain Structure's were calculated assuming that the stays are positioned on the bisector of the conductors 3) *- exceed design limit ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 46 of 71 Annex D (Continued) 1 Conductor Description Angle 2 Weight Span 3 Nominal Span 8m 9m 10 m LOW VOLTAGE DESIGN SPANS - FOX CONDUCTOR 4 Wind Span - Wood Poles 11 m 140m m 7m 160m m 180m m 140m m 9m 160m m 180m m 200m m 140m m 10m 160m m 180m m 200m m 140m m 11m 160m m 180m m 200m m SINGLE PHASE BARE WIRE LV FOX DUAL WIRE PHASE 0 30 60 90 290 290 290 290 60 60 60 60 105 105 105 105 140 140 140 140 175 175 175 175 200 290 290 290 285 290 290 290 395 290 290 290 180 290 290 290 260 290 290 290 360 290 290 290 475 290 290 290 170 290 290 210 245 290 290 290 335 290 290 290 445 290 290 290 155 290 290 * 225 290 290 290 310 290 290 290 410 290 290 290 0 30 60 90 290 290 290 290 35 35 35 35 95 95 95 95 125 125 125 125 165 165 165 165 135 290 290 125 195 290 290 290 270 290 290 290 125 290 260 * 175 290 290 290 245 290 290 290 325 290 290 290 115 290 100 * 165 290 290 290 225 290 290 290 300 290 290 290 105 290 * * 150 290 290 30 210 290 290 290 280 290 290 290 0 30 60 90 290 290 290 290 * * * * 75 75 75 75 110 110 110 110 155 155 155 155 105 290 190 * 150 290 290 290 205 290 290 290 95 290 * * 135 290 290 120 185 290 290 290 245 290 290 290 90 290 * * 125 290 290 * 175 290 290 290 230 290 290 290 80 185 * * 115 290 105 * 160 290 290 265 210 290 290 290 BARE LV FOX THREE PHASE BARE WIRE LV FOX NOTES: 1) 2) 3) The selected span length is determined by the limiting factors and is the least of the spans given in columns 2, 3 and 4. Span lengths for the Strain Structure's were calculated assuming that the stays are positioned on the bisector of the conductors. *- exceed design limit ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 47 of 71 Annex D (Continued) LOW VOLTAGE DESIGN SPANS - MINK CONDUCTOR 1 Conductor Description Angle 2 Weight Span 3 Nominal Span 8m 9m 10 m 4 Wind Span - Wood Poles 11 m 140m m 7m 160m m 180m m 140m m 9m 160m m 180m m 200m m 140m m 10m 160m m 180m m 200m m 140m m 11m 160m m 180m m 200m m SINGLE PHASE BARE WIRE LV MINK DUAL WIRE PHASE 0 30 60 90 290 290 290 290 55 55 55 55 105 105 105 105 135 135 135 135 170 170 170 170 150 290 290 20 220 290 290 290 300 290 290 290 140 290 210 * 200 290 290 290 275 290 290 290 365 290 290 290 130 290 35 * 185 290 290 280 255 290 290 290 340 290 290 290 120 290 * * 170 290 290 * 235 290 290 290 310 290 290 290 0 30 60 90 290 290 290 290 35 35 35 35 90 90 90 90 120 120 120 120 160 160 160 160 105 290 * * 150 290 290 200 205 290 290 290 95 290 * * 135 290 290 * 185 290 290 290 245 290 290 290 85 230 * * 125 290 140 * 175 290 290 290 230 290 290 290 80 80 * * 115 290 * * 160 290 290 * 210 290 290 290 0 30 60 90 290 290 290 290 * * * * 75 85 85 85 110 110 110 110 150 150 150 150 80 290 * * 115 290 290 * 155 290 290 290 70 115 * * 100 290 * * 140 290 290 85 190 290 290 290 65 20 * * 95 290 * * 130 290 290 * 175 290 290 290 60 * * * 90 235 * * 120 290 75 * 160 290 290 155 BARE LV MINK THREE PHASE BARE WIRE LV MINK NOTES: 1) 2) 3) The selected span length is determined by the limiting factors and is the least of the spans given in columns 2, 3 and 4. Span lengths for the Strain Structure's were calculated assuming that the stays are positioned on the bisector of the conductor *- exceed design limit ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 48 of 71 Annex E - Design spans for AAAC bare wire systems 1 Conductor Description Angle 2 Weight Span LOW VOLTAGE DESIGN SPANS - ACACIA CONDUCTOR 3 Nominal Span 8 m 9 m 10 m 11 m 4 Wind Span - Wood Poles 7m 9m 10m 11m 140mm 160mm 180mm 140mm 160m 180mm 200mm 140mm 160mm 180mm 200mm 140mm 160mm 180mm 200mm m SINGLE PHASE BARE WIRE LV ACACIA 0 30 60 90 290 290 290 290 65 65 65 65 100 100 100 100 130 130 130 130 180 180 180 180 270 290 290 290 385 290 290 290 530 290 290 290 245 290 290 290 350 290 290 290 480 290 290 290 640 290 290 290 230 290 290 290 330 290 290 290 450 290 290 290 600 290 290 290 210 290 290 290 305 290 290 290 415 290 290 290 550 290 290 290 0 30 60 90 290 290 290 290 35 35 35 35 100 100 100 100 115 115 115 115 165 165 165 165 185 290 290 290 260 290 290 290 360 290 290 290 165 290 290 290 240 290 290 290 329 290 290 290 435 290 290 290 155 290 290 290 225 290 290 290 305 290 290 290 405 290 290 290 145 290 290 290 205 290 290 290 280 290 290 290 375 290 290 290 0 30 60 90 290 290 290 290 * * * * 80 80 80 80 100 100 100 100 150 150 150 150 140 290 290 290 200 290 290 290 275 290 290 290 125 290 290 290 180 290 290 290 250 290 290 290 335 290 290 290 120 290 290 230 170 290 290 290 235 290 290 290 310 290 290 290 110 290 290 25 155 290 290 200 215 290 290 290 285 290 290 290 DUAL PHASE BARE WIRE LV ACACIA THREE PHASE BARE WIRE LV ACACIA NOTES: 1) 2) 3) The selected span length is determined by the limiting factors and is the least of the spans given in columns 2, 3 and 4. Span lengths for the Strain Structure's were calculated assuming that the stays are positioned on the bisector of the conductors. *- exceed design limit ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 49 of 71 Annex E (Continued) 1 2 Conductor Description Angle Weigh Span 3 LOW VOLTAGE DESIGN SPANS - PINE CONDUCTOR 4 Nominal Span 8 m 9 m 10 m 11 m Wind Span - Wood Poles 7m 9m 10m 11m 140mm 160mm 180mm 140mm 160m 180mm 200mm 140mm 160mm 180mm 200mm 140mm 160mm 180mm 200mm m SINGLE PHASE BARE WIRE LV PINE 0 30 60 90 290 290 290 290 55 55 55 55 110 110 110 110 140 140 140 140 175 175 175 175 155 290 290 290 220 290 290 290 305 290 290 290 140 290 290 290 200 290 290 290 275 290 290 290 370 290 290 290 130 290 290 290 190 290 290 290 260 290 290 290 345 290 290 290 120 290 290 290 175 290 290 290 240 290 290 290 315 290 290 290 0 30 60 90 290 290 290 290 35 35 35 35 95 95 95 95 125 125 125 125 165 165 165 165 105 290 290 290 150 290 290 290 205 290 290 290 95 290 290 290 135 290 290 290 185 290 290 290 250 290 290 290 90 290 290 290 125 290 290 290 175 290 290 290 235 290 290 290 80 290 290 75 115 290 290 290 160 290 290 290 215 290 290 290 0 30 60 90 290 290 290 290 * * * * 75 75 75 75 115 115 115 115 155 155 155 155 80 290 290 290 115 290 290 290 160 290 290 290 70 290 290 135 105 290 290 290 145 290 290 290 190 290 290 290 65 290 290 * 95 290 290 290 135 290 290 290 180 290 290 290 60 290 125 * 90 290 290 290 120 290 290 290 165 290 290 290 DUAL PHASE BARE WIRE LV PINE THREE PHASE BARE WIRE LV PINE NOTES: 1) 2) 3) The selected span length is determined by the limiting factors and is the least of the spans given in columns 2, 3 and 4. Span lengths for the Strain Structure's were calculated assuming that the stays are positioned on the bisector of the conductors. *- exceed design limit ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 50 of 71 Annex E (Continued) 1 2 Conductor Description Angle Weigh Span LOW VOLTAGE DESIGN SPANS - 35 CONDUCTOR 3 4 Nominal Span 8 m 9 m 10 m 11 m Wind Span - Wood Poles 7m 9m 10m 11m 140mm 160mm 180mm 140mm 160m 180mm 200mm 140mm 160mm 180mm 200mm 140mm 160mm 180mm 200mm m SINGLE PHASE BARE WIRE LV 35 CONDUCTOR 0 30 60 90 290 290 290 290 60 60 60 60 110 110 110 110 140 140 140 140 180 180 180 180 200 290 290 290 290 290 290 290 395 290 290 290 185 290 290 290 265 290 290 290 360 290 290 290 480 290 290 290 170 290 290 290 245 290 290 290 340 290 290 290 450 290 290 290 160 290 290 210 225 290 290 290 310 290 290 290 415 290 290 290 0 30 60 90 290 290 290 290 35 35 35 35 95 95 95 95 130 130 130 130 170 170 170 170 135 290 290 290 195 290 290 290 270 290 290 290 125 290 290 105 180 290 290 290 245 290 290 290 325 290 290 290 115 290 290 * 165 290 290 290 230 290 290 290 305 290 290 290 105 290 290 * 155 290 290 105 210 290 290 290 280 290 290 290 0 30 60 90 290 290 290 290 * * * * 80 80 80 80 115 115 115 115 160 160 160 160 105 290 290 35 150 290 290 290 205 290 290 290 95 290 150 * 135 290 290 290 185 290 290 290 250 290 290 290 90 290 30 * 125 290 290 200 175 290 290 290 230 290 290 290 80 290 * * 115 290 290 * 160 290 290 290 215 290 290 290 DUAL PHASE BARE WIRE LV 35 CONDUCTOR THREE PHASE BARE WIRE LV 35 CONDUCTOR NOTES: 1) 2) 3) The selected span length is determined by the limiting factors and is the least of the spans given in columns 2, 3 and 4. Span lengths for the Strain Structure's were calculated assuming that the stays are positioned on the bisector of the conductor *- exceed design limit ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 51 of 71 Annex F - Urban reticulation Typical mid block design ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 52 of 71 Annex G - Minimum separation between parallel LV and HV lines Earth fault current flowing in HV lines can induce a potentially hazardous voltage on LV lines that run parallel to the HV lines (refer to TSI report RES/IR/99/00043). HV lines are defined as lines with voltage greater than or equal to 44 kV. The earthing scheme employed on the HV network will have to be solid bonding to earth for there to be a problem (resistance earthing would limit the single-phase-toearth fault level to safe levels). It is necessary to ensure that the separation between the parallel HV and LV lines is sufficient to ensure that the voltage induced on the LV line is not hazardous. The voltage induced on the LV line is proportional to the length that the two lines run parallel to each other and to the fault current on the HV line. The greater the separation between the lines, the lower the induced voltage. The voltage induced on LV lines due to earth faults on MV lines was not considered in the TSI report, but it is unlikely to be hazardous because the NECRT in the earth return path of the MV system limits the MV earth fault current dramatically. Since the voltage induced on the LV system is proportional to the fault current on the MV system, the voltage induced on the LV system is limited. Problems may arise where MV and LV lines share structures for a significant distance. In order to determine whether the proposed LV line route will be safe, split the LV line into line segments. A line segment starts and ends at a point where the line changes direction or at the beginning or end of the line. Calculate the voltage induced on each line segment using the following procedure: 1. Determine the separation between the HV line and the proposed LV line segment in metres. If the LV line segment is at an angle to the HV line, use the average separation between the two lines given by: Average _ separation = max imum _ separation − min imum _ separation 2 Where: minimum separation is the minimum separation between the HV line and the LV line segment in metres and maximum separation is the maximum separation between the HV line and the LV line segment in metres. Note: Calculations based on an average separation calculated in this manner will not be 100% accurate but will serve to give a rough estimate of the induced voltage on the LV line segment. 2. Determine the effective length of the LV line segment in parallel with the HV line. This is given by: Effective _ length = LV _ line _ segment _ length × cos(α ) Where: LV-line-segment-length is the length of the LV line segment and α is the angle between the HV line and the LV line segment. α is defined as 0 º when the HV line and LV line segment are parallel to each other and the LV line segment is heading away from the transformer, 90 º when the HV line and LV line segment are perpendicular to each other and 180 º when the HV line and LV line segment are parallel to each other and the LV line segment is heading back towards the transformer. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 53 of 71 Annex G (Continued) 3. Determine the prospective single-phase-to-earth fault level of the HV system at the point at which the HV and LV lines begin their parallel run. This information should be obtained from the Planning department. The prospective single-phase-to-earth fault level is assumed constant for the segment of the HV line in question. 4. Determine the voltage induced on the LV line segment under HV fault conditions. This is given by: Induced voltage = k x single-phase-to-earth-fault-level x effective-length x reduction factor Where: k depends on the soil resistivity and effective separation and is read from the graph below (extracted from the TSI report), where p in the graph’s legend is the soil resistivity in ohm.metres. The reduction factor is read from the table below (based on information extracted from the TSI report): Shield wires None 2 x 7/3,35 steel 2 x 19/2,65 steel Reduction factor 1 0,9 0,8 Now that the induced voltage per LV line segment has been calculated, determine whether the line is safe. This is done by starting with a voltage of zero volts at the transformer and then adding the voltage induced on each segment of the LV line to the total voltage in turn, working from the segment connected to the transformer towards the end of the line. The voltage on segments that form an angle of greater than 90 º with the HV line (i.e. when the LV line has a component in the direction towards the transformer) will have a negative sign. The magnitude of the total voltage from the transformer to the end of any of the line segments shall not exceed 650 V (i.e. –650 V< total voltage < 650 V). This criterion can be summarised as follows: ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 54 of 71 Annex G (Continued) N ∑V n =1 n ≤ 650 VFor all integer N such that 0 < N ≤ the total number of line segments in the line Where: n is the line segment number Vn is the voltage induced on line segment n If the voltage induced on the LV line between the transformer and the end of any of the line segments is greater than 650 V then the proposed LV network will have to be redesigned to reduce the voltage (the 650 V criterion was extracted from the TSI report). This can be done by increasing the separation between the HV line and LV line and by reducing the number and length of LV line segments that run parallel to the HV line. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 55 of 71 Annex H - List of drawings The following drawings form part of this annex: List of three-phase ABC wood pole drawings No. Description Rev D-DT-1100 ABC Suspension Assembly 0-30 3 D-DT-1120 LABC Terminal Assembly 4 D-DT-1121 ABC Strain Assembly (0-60°) 5 D-DT-1122 ABC Strain Assembly (60-90°) 4 D-DT-1140 ABC T from Intermediate 4 D-DT-1141 ABC Intermediate Suspension Assembly 4 D-DT-1142 ABC T from Strain 4 D-DT-1143 ABC X Intermediate-Strain Assembly 4 List of three-phase bare wire wood pole drawings No. Description Rev D-DT-0920 Intermediate Assembly 4 D-DT-0921 In line strain Assembly 4 D-DT-0922 Angle Assembly 1-100° 4 D-DT-0924 Terminal Assembly 4 D-DT-0925 T-off from Intermediate 4 D-DT-0926 Intermediate-Intermediate Crossing 4 D-DT-0927 T-off from strain 4 D-DT-0928 Cable to BW connection 2 D-DT-0929 Service Box connection 4 D-DT-0932 ABC to BW connection 2 D-DT-0934 Intermediate-Strain Crossing 2 D-DT-0935 Strain-Strain Crossing 3 List of dual-phase ABC wood pole drawings No. D-DT-1145 D-DT-1146 D-DT-1147 D-DT-1148 D-DT-1149 D-DT-1150 D-DT-1151 D-DT-1152 Description ABC Suspension Assembly 0-30 LABC Terminal Assembly ABC Strain Assembly (0-60°) ABC Strain Assembly (60-90°) ABC T from Intermediate ABC Intermediate Suspension Assembly ABC T from Strain ABC X Intermediate-Strain Assembly Rev 0 0 0 0 0 0 0 0 ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 56 of 71 Annex H (Continued) List of dual-phase bare wire wood pole drawings No. Description D-DT-0940 D-DT-0941 D-DT-0942 D-DT-0944 D-DT-0945 D-DT-0946 D-DT-0947 D-DT-0948 D-DT-0949 D-DT-0950 D-DT-0951 D-DT-0952 Intermediate Assembly In line strain Assembly Angle Assembly 1-100° Terminal Assembly T-off from Intermediate Intermediate-Intermediate Crossing T-off from strain Cable to BW connection Service Box connection ABC to BW connection Intermediate-Strain Crossing Strain-Strain Crossing Rev 0 0 0 0 0 0 0 0 0 0 0 0 List of single-phase ABC wood pole drawings No. Description Rev D-DT-1153 ABC Suspension Assembly 0-30 0 D-DT-1154 ABC Terminal Assembly 0 D-DT-1155 ABC Strain Assembly (0-60°) 0 D-DT-1156 ABC Strain Assembly (60-90°) 0 D-DT-1157 ABC T from Intermediate 0 D-DT-1158 ABC Intermediate Suspension Assembly 0 D-DT-1159 ABC T from Strain 0 D-DT-1160 ABC X Intermediate-Strain Assembly 0 List of single-phase bare wire wood pole drawings No. Description Rev D-DT-0960 Intermediate Assembly 0 D-DT-0961 In line strain Assembly 0 D-DT-0962 Angle Assembly 1-100° 0 D-DT-0964 Terminal Assembly 0 D-DT-0965 T-off from Intermediate 0 D-DT-0966 Intermediate-Intermediate Crossing 0 D-DT-0967 T-off from strain 0 D-DT-0968 Cable to BW connection 0 D-DT-0969 Service Box connection 0 D-DT-0970 ABC to BW connection 0 D-DT-0971 Intermediate-Strain Crossing 0 D-DT-0972 Strain-Strain Crossing 0 ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 57 of 71 Annex H (Continued) List of three-phase ABC concrete pole drawings No. Description Rev D-DT-0100 ABC Suspension Assembly 0-30 3 D-DT-0120 ABC Terminal Assembly 4 D-DT-0121 ABC Strain Assembly (0-60°) 5 D-DT-0122 ABC Strain Assembly (60-90°) 4 D-DT-0140 ABC T from Intermediate 4 D-DT-0141 ABC Intermediate Suspension Assembly 4 D-DT-0142 ABC T from Strain 4 D-DT-0143 ABC X Intermediate-Strain Assembly 4 List of single-phase ABC concrete pole drawings No. Description Rev D-DT-0153 ABC Suspension Assembly 0-30 0 D-DT-0154 ABC Terminal Assembly 0 D-DT-0155 ABC Strain Assembly (0-60°) 0 D-DT-0156 ABC Strain Assembly (60-90°) 0 D-DT-0157 ABC T from Intermediate 0 D-DT-0158 ABC Intermediate Suspension Assembly 0 D-DT-0159 ABC T from Strain 0 D-DT-0160 ABC X Intermediate-Strain Assembly 0 List of dual-phase ABC concrete pole drawings No. Description Rev D-DT-0145 ABC Suspension Assembly 0-30 0 D-DT-0146 ABC Terminal Assembly 0 D-DT-0147 ABC Strain Assembly (0-60°) 0 D-DT-0148 ABC Strain Assembly (60-90°) 0 D-DT-0149 ABC T from Intermediate 0 D-DT-0150 ABC Intermediate Suspension Assembly 0 D-DT-0151 ABC T from Strain 0 D-DT-0152 ABC X Intermediate-Strain Assembly 0 ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 58 of 71 Annex H (Continued) List of auxiliary drawings No. Description Rev D-DT-0165 Concrete pole LV stay Assembly 5 D-DT-0166 Stay attaching methods for concrete poles 3 D-DT-0167 Strut Pole for 7m and 9m concrete poles 2 D-DT-0168 Flying stay for concrete poles 2 D-DT-0180 ABC System Service Box Assembly 5 D-DT-0183 Bare wire Service Box Assembly 3 D-DT-0300 ABC full Tension compression Joint 3 D-DT-0302 ABC Full Tension compression Joint - Joining a core 1 D-DT-0305 BN ABC Intermediate Suspension with S/Box - Assembly Detail 6 D-DT-0307 BN ABC -Intermediate Suspension without S/Box - Assembly Detail 2 D-DT-0309 SABS 780 Transformer and LV Fuseholder connections Sheet 1 0 D-DT-0309 SABS 780 Transformer and LV Fuseholder connections Sheet 2 0 D-DT-0309 SABS 780 Transformer and LV Fuseholder connections Sheet 3 0 D-DT-0309 SABS 780 Transformer and LV Fuseholder connections Sheet 4 0 D-DT-0314 LV Barewire Connection Methods 0 D-DT-0315 Stay Assembly details 0 D-DT-0330 Pole Foundation Arrangement 2 D-DT-0332 Pole Planting Depths-Wood and Concrete 2 D-DT-0335 MV and LV Pole Hole Legend 0 D-DT-0336 Woodpole Hole positions D-DT-0339 Concrete pole orientation layout 0 D-DT-0340 Surge Arrester connections 2 D-DT-0345 Schematic for 160kVA CSP Pole mounted transformer 1 D-DT-0348 Example for Shared Structure Clearances-MV, ABC and Telkom 3 D-DT-0349 Example for shared structure clearances ABC and Telkom 2 D-DT-0350 Sheet 1 Stay rod installation detail 2 D-DT-0350 Sheet 2 Mule stay Rod installation Detail 2 D-DT-0354 Streetlight Assembly 4 D-DT-0356 LV Surge Arrester Installations 2 D-DT-0357 Rock Anchor Installation 2 D-DT-0363 Fourway Pole top box connection detail - Sheet 1 2 D-DT-0363 Fourway Pole top box connection detail - Sheet 2 2 D-DT-0364 Terminal assembly for meter box customer from ABC 2 ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 59 of 71 Annex H (Continued) No. Description Rev D-DT-0365 Service connection from Con. Intermediate pole D-DT-0980 MV / LV Bare Wire Staying Methodology 0 D-DT-0981 LV Metering Unit - Sheet 1 0 D-DT-0981 LV Metering Unit - Sheet 2 0 D-DT-0981 LV Metering Unit - Sheet 3 0 D-DT-0981 LV Metering Unit - Sheet 4 0 D-DT-0982 Eye Nut Assembly 0 D-DT-0983 LV Barewire Binding Techniques 0 D-DT-1165 LV Stay Assembly for Woodpoles D-DT-1167 Strut for 7m and 9m Woodpoles 3 D-DT-1168 Flying Stay Arrangement for Wood Poles 3 ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 60 of 71 Annex I - Connector installation practices on low voltage ABC networks BACKGROUND This bulletin highlights problems that are being created on LV ABC systems as a result of current practices with regards to the following: 1. The use of cable ties and the positioning of the neutral conductor relative to the IPC’s at service lead take-off points; 2. The use of a plastic spanners for shearing of IPC torque shear nuts; and 3. Jointing of ABC neutral conductor after failures. Recommendations are made for future standard practices. 1. Positioning of cable ties, neutral conductor and IPC’s at service lead takeoffs • Problem Eskom drawings D-DT-0305 and D-DT-0306 show two different applications of ABC, IPC’s and cable ties. In general it appears that the trend in the field is to configure the IPC’s and cable ties according to D-DT-0306 i.e. to have cable ties positioned before, between and after the IPC’s. This arrangement results in the ABC conductors and the service distribution box cables being tightly bunched together. There is also no clear guideline with regards to the minimum spacing required between the IPC’s, the spacing affects the tightness of the bunched conductors. A number of ABC failure investigations have highlighted that this practice can lead to the following types of faults: • The ABC bare neutral conductor is pressed into the mouth of the phase conductor IPC which does not create an immediate fault as the IPC teeth are insulated. Instead it takes a number of months/years of vibration and movement for the ABC neutral conductor to wear through the IPC teeth insulation and cause a phase to neutral fault. See photograph 1. The ABC bare neutral conductor makes contact with only the outer teeth of the IPC resulting in an arcing fault that may not raise sufficient fault current to operate the upstream fuses however do enough damage to result in mechanical failure of the neutral conductor. See photograph 2. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 61 of 71 Annex I (Continued) Photo 1: ABC bare neutral conductor pressed into phase IPC mouth Photo 2: Damaged ABC bare neutral conductor adjacent to removed phase IPC ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 62 of 71 Annex I (Continued) • The cable tie strapping of the PVC insulated service distribution box cables to the ABC bare neutral conductor also results in chaffing of the PVC insulation at the cable tie positions to such an extent that phase to neutral faults are created. An arcing fault is created that may not raise sufficient fault current to operate the upstream fuses however do enough damage to result in mechanical failure of the neutral conductor. See photograph 3. Photo 3: Phase to neutral fault under cable ties resulting in neutral burn off • Recommendations It is recommended that the following guidelines be adopted: • IPC’s shall be spaced in the following manner: 1. The two neutral IPC’s are spaced > 100mm and ≤ 200mm apart. 2. The distance between phase IPC’s; and from any phase IPC to a neutral IPC are spaced > 200mm and ≤ 300mm. 3. The neutral IPC’s should be positioned closest to the pole and then the phase IPC’s shall follow. 4. Where a pole-top box and streetlight is fitted on the same pole, the streetlight IPC’s (neutral and line) shall be put up last i.e. furthest from the pole The same spacing distance as in 1 & 2 above shall be valid for streetlight IPC’s. NOTE - Streetlights are generally maintained from a bucket-truck and therefore distance from the pole is not a problem. • The service distribution box and streetlight fitting cables (and thus IPC’s) shall be distributed, as far as reasonably practicable, evenly on both sides of intermediate and strain poles. NOTE - This is to assist ease of maintenance, as it is done from a ladder. • At terminal poles all service distribution box and streetlight fitting cables will be connected to the ABC on the tension side of the strain clamp. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 63 of 71 Annex I (Continued) • All IPC’s shall be positioned in such a manner that the tightening bolt is in a vertical position, with the torque-shear nut on top. This ensures that the grease, enhancing water-tightness, does not run out. • As far as is practically possible the ABC bare neutral conductor should be positioned in such a way that it does not lie adjacent to the mouth of the phase IPC. • Cable Ties are applied in the following manner: 1. The service distribution box neutral cable shall not be cable tied to the ABC. 2. Phase service distribution box cables shall be cable tied, to that specific ABC phase conductor to which it is connected, only. These cable ties shall be positioned in the centre point between adjacent phase IPC’s. 3. No cable ties shall be allowed between the two neutral IPC’s. 4. Cable ties around all phases and neutral conductors of the ABC shall only be used after the last IPC; at a distance of ≥ 300mm away from the last IPC. 2. Shearing of IPC torque shear nuts • Problem The Eskom buyers guide drawing D-DT-3039 for IPC’s requires the supplier/manufacturer to provide a plastic hexagonal ring spanner within each package of 12 IPC’s. Field experience has shown that the ring spanner is incapable of shearing the torque shear nuts on the IPC’s if either the spanner or IPC become too hot from sunlight exposure. As a result of this there are a number of Electrification projects where the IPC torque shear nuts have not been sheared and are therefore incorrectly torqued. The use of a ring spanner also tends to twist the IPC during the shearing process often resulting in the IPC being badly applied onto the ABC conductor. A further problem is that it is not standard practice to physically remove the torque shear nut from the IPC once it has sheared. This makes it impossible for the Clerk of Works to check from the ground whether the IPC’s are correctly torqued. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 64 of 71 Annex I (Continued) • Recommendation The following actions are recommended: • Personnel working on ABC networks shall be equipped with a 13-mm tube spanner with Tbar or a 6-sided (hexagon) socket, to be used with a ratchet. See photographs 4 and 5. NOTE - The performance of the tube spanner or socket is not affected by the temperature of the IPC and appears to consistently shear the torque shear nut as required. • During installation of IPC’s it shall be ensured that the IPC is held securely in order to prevent it from twisting. • A standard 24-sided socket or 13mm spanner as shown in photograph 6 shall not be used. Photo 4: Tube spanner with T-bar used on IPC’s Photo 5: 6-sided socket. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 65 of 71 Annex I (Continued) Photo 6: Standard socket and 13mm spanner. • Sheared IPC torque shear nuts must be removed from the IPC and the Clerk of Works are to perform a visual inspection to check that all torque shear nuts are removed. 3. Jointing of ABC neutral after failures • Problem In order to maintain continuity of supply on ABC networks where the neutral conductor has failed, the field staff are resorting to the use of two IPC’s and a new section of bare neutral conductor to make the joint. See photograph 7. This practice is not according to the Eskom drawing D-DT-0302 and is totally unacceptable as it poses a safety risk to Eskom operational staff as well as the public and is a contravention of the Occupational Health and Safety Act. • Recommendation The following action is recommended: • Any joints made in this manner shall be replaced immediately with a midspan compression joint as per Eskom drawing D-DT-0302. • In areas where there are problems with obtaining the required compression tool it is recommended that an automatic line splice that is suitable for the ABC neutral conductor diameter is used. See photograph 8. Further information on this product can be obtained from Distribution Technology. Staff are to be trained and certified before using the product. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 66 of 71 Annex I (Continued) Photo 7: Broken ABC neutral conductor jointed with IPC’s Photo 8 : Automatic line splice suitable for neutral conductor of 35 to 70 mm2 ABC ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 67 of 71 Annex J - ABC connectors Arial Bundle Conductor networks have a number of connectors for which there is a requirement for standard tooling and accessories in the field. The tables below intend to cover all connectors for Low voltage arial bundle conductor systems and give the required information. Table 1: Connectors for overhead arial bundle conductor 1 Type 2 35-95 mm IPC Bimetallic clamp 2 Al/Cu 6-25 mm 2 35-95 mm IPC Bimetallic clamp 2 Al/Cu 35-95 mm Bare Neutral 35-95 2 mm Bimetallic clamp Al/Cu 6-25 2 mm IPC 2 35-95 mm IPC Bimetallic clamp Bare Neutral Al/Cu 2 35-95 mm 4-15 mm dia. PG clamp 2 35 mm Bimetallic lug 2 2 Buyer guide drawing # D-DT-3039 T-off to insulated Cu Torque Wrench D-DT-3039 T-off to insulated Al Torque Wrench D-DT-3039 Bare neutral T-off to insulated Cu Torque Wrench D-DT-3039 T-off to bare neutral Al Torque Wrench D-DT-3058 Bare neutral Al to Al connections Al bare neutral connection to Cu transformer terminal Torque Wrench D-DT-3024 35 mm lug D-DT-3116 35 mm Full Tension Joint 2 D-DT-3089 1 Type 2 Buyer guide drawing # D-DT-3024 2 50 mm Bimetallic lug 2 70 mm Full Tension Joint 2 70 mm lug 3 Application 4 Tool FFG Hydraulic Compression toolsBurndy Y35, Siemel C12, Alcon 12A Al insulated Terminal lug FFG Hydraulic Compression toolsBurndy Y35, Simel C12, Alcon 12A Mid Span joint FFG Hydraulic Compression toolsBurndy Y35, Siemel C12, Alcon 12A 3 4 Application Tool Al bare neutral connection to Cu transformer terminal D-DT-3089 Mid Span joint D-DT-3116 Al insulated Terminal lug FFG Hydraulic Compression toolsBurndy Y35, Simel C12, Alcon 12A FFG Hydraulic Compression toolsBurndy Y35, Simel C12, Alcon 12A FFG Hydraulic Compression toolsBurndy Y35, Simel C12, Alcon 12A 5 Accessories Jointing grease Hex Die A/F = 17.3 mm 4E173 Hex Die A/F = 17.3 mm 4E173 Hex Die A/F = 17.3 mm 4E173 5 Accessories Hex Die A/F = 17.3 mm 4E173 Hex Die A/F = 17.3 mm 4E173 Hex Die A/F = 17.3 mm 4E173 NOTE 1. PG Clamps are only to be used on Aluminium to Aluminium connections. Bimetallic connections shall not be made with PG clamps. 2. The bare neutral connection to the pole top box, which is a Copper to Aluminium connection, shall be made with two IPC 35-95B to 6-25 3. Duplicate connectors are required on the neutral conductor. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 68 of 71 Annex K - National contract for Low Voltage Aerial Bundled Conductor with Insulated neutral Conductor 1 Introduction A national contract has been established for Aerial Bundle Conductor (Insulated Neutral). The contract period is 01 October 2010 to 30 September 2015. The current LAP listing is also updated with technically acceptable products. Details regarding the contract and the specific items on contract are provided in this technical bulletin. The List of accepted Products can either be accessed by following the hyperlink in the IARC website designated as “Accepted Products” or by typing in the web browser’s address field: http://hyperwave.eskom.co.za/IARC_LAP 2 Technical Evaluation 2.1 Applicable specifications The contract enquiry was issued based on the following list of published Distribution specifications and drawings: Spec No. Rev DSP 34-1803 0 D-DT-3141 10 2.2 Title AERIAL BUNDLED CONDUCTORS WITH BARE OR INSULATED NEUTRAL SUPPORTING CONDUCTOR LOW VOLTAGE AERIAL BUNDLED CONDUCTOR Items evaluated The following table list the items evaluated for this Material Group. Some of these items might not be submitted by the supplier and will therefore not have an acceptance allocated to it. Buyer’s Guide Drawing Item SAP No Description 1 0215201 LV-ABC Ins Neutral 1x35 Ph + 54,6 Ins-N (2000m) D DT 3141 2 0215202 LV-ABC Ins Neutral 2x35 Ph + 54,6 Ins-N (2000m) D DT 3141 3 0215203 LV-ABC Ins Neutral 3x35 Ph + 54,6 Ins-N (1500m) D DT 3141 4 0215204 LV-ABC Ins Neutral 2x70 Ph + 54,6 Ins-N (1000m) D DT 3141 5 0215205 LV-ABC Ins Neutral 3x70 Ph + 54,6 Ins-N (1000m) D DT 3141 6 0215206 LV-ABC Ins Neutral 3x35 Ph + 1x25 Ph + 54,6 Ins-N (1000m) D DT 3141 7 0215207 LV-ABC Ins Neutral 3x70 Ph + 1x25 Ph + 54,6 Ins-N (1000m) D DT 3141 ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 69 of 71 Annex K (Continued) 3 Contract details The contract has been established as a National contract based upon enquiry number Corp-1469. 3.1 Supplier Contract Dates Contract No. Aberdare Cables (Pty) Ltd 01 October 2010 to 30 September 2015 Dx: 4600038543 Wuxi Jiangnan Cable co.Ltd 01 October 2010 to 30 September 2015 Dx: 4600038666 Contract communication All technical and commercial issues pertaining to the contracts listed below shall be raised with the following technical, quality and commercial specialists: Contract Data TECHNICAL QUALITY CONTRACT MANAGER 3.2 Name Vinod Singh Contact No (011) 629 5086 e-mail address vinod.singh @eskom.co.za Name Andrew Else Contact No (011) 629 5137 e-mail address Andrew.else@eskom.co.za Name Kebone Mogase Contact No (011) 800 3214 e-mail address MogaseKK@eskom.co.za Generic Contract Data Contract Scope The manufacture, testing and supply of the estimated quantities of LV ABC to Eskom’s Distribution division. Storage Not included. Transport & off-loading TBA Erection & Installation Not included. Commissioning Not included. Training Not included. ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 70 of 71 Annex K (Continued) 3.3 Contract Data The following tables summarises the contact data for each affected supplier. Contract Data Aberdare Cables (Pty) Ltd Contract No 4600038543 Contract Date 01 October 2010 Valid until 30 September 2015 Supplier Details Refer to clause 3 above Warrantee Periods Fifty two (52) weeks after Delivery of each Purchase Order Designed work life 25 years from the end of the warranty period of each purchase order Product lead times Delivery lead time is 4 weeks but the date on the purchase order will take precedence Special conditions Refer to the Goods Information on the contract documentation page 13. Tools and spares As per Distribution specification DSP_34-1803 Rev 0 Contract Data Wuxi Jiangnan Cable co.Ltd Contract No 4600038666 Contract Date 01 October 2010 Valid until 30 September 2015 Supplier Details Refer to clause 3 above Warrantee Periods Fifty two (52) weeks after Delivery of each Purchase Order Designed work life 25 years from the end of the warranty period of each purchase order Product lead times Delivery lead time is 5 to 8 weeks but the date on the purchase order will take precedence. Special conditions Refer to the Goods Information on the contract documentation page 13. Tools and spares As per Distribution specification DSP_34-1803 Rev 0 4 4.1 4.1.1 Supplier details SUPPLIER: Aberdare Cables (Pty) Ltd MANUFACTURER Aberdare Cables (Pty) Ltd Nominated Contact Persons: Contact Person: Tel No: Fax No: Cell No: e-mail: Frank Rook +27 11 396 8000 +27 11 396 8012 +27 82 895 4877 frooke@aberdare.co.za ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. Document Classification: Controlled Disclosure LOW-VOLTAGE RETICULATION SECTION 1: LOW-VOLTAGE OVERHEAD RETICULATION Unique Identifier: 34-953 Revision: 0 Page: 71 of 71 Annex K (Continued) 4.2 4.2.1 SUPPLIER: Wuxi Jiangnan Cable co.Ltd MANUFACTURER Wuxi Jiangnan Cable co.Ltd Nominated Contact Persons: Contact Person: Tel No: Fax No: Cell No: e-mail: 5 Tony Dong +27 11 493 1863 +27 11 493 3167 +27 83 4610588 tdong@global.co.za Product Acceptance The following tables list only the items and their associated products codes for which the supplier obtained technical and quality acceptance: 5.1 Aberdare Cables (Pty) Ltd Item SAP No Description 1 2 3 4 5 0215201 0215202 0215203 0215204 0215205 6 0215206 7 0215207 LV-ABC Ins Neutral 1x35 Ph + 54,6 Ins-N (2000m) LV-ABC Ins Neutral 2x35 Ph + 54,6 Ins-N (2000m) LV-ABC Ins Neutral 3x35 Ph + 54,6 Ins-N (1500m) LV-ABC Ins Neutral 2x70 Ph + 54,6 Ins-N (1000m) LV-ABC Ins Neutral 3x70 Ph + 54,6 Ins-N (1000m) LV-ABC Ins Neutral 3x35 Ph + 1x25 Ph + 54,6 Ins-N (1000m) LV-ABC Ins Neutral 3x70 Ph + 1x25 Ph + 54,6 Ins-N (1000m) 5.2 Product Code Wuxi Jiangnan Cable co.Ltd Item SAP No Description 1 2 3 4 5 0215201 0215202 0215203 0215204 0215205 6 0215206 7 0215207 LV-ABC Ins Neutral 1x35 Ph + 54,6 Ins-N (2000m) LV-ABC Ins Neutral 2x35 Ph + 54,6 Ins-N (2000m) LV-ABC Ins Neutral 3x35 Ph + 54,6 Ins-N (1500m) LV-ABC Ins Neutral 2x70 Ph + 54,6 Ins-N (1000m) LV-ABC Ins Neutral 3x70 Ph + 54,6 Ins-N (1000m) LV-ABC Ins Neutral 3x35 Ph + 1x25 Ph + 54,6 Ins-N (1000m) LV-ABC Ins Neutral 3x70 Ph + 1x25 Ph + 54,6 Ins-N (1000m) Product Code ESKOM COPYRIGHT PROTECTED When downloaded from the IARC WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.