Class Exercise: Liquidated Damages Facts: ONGC has entered into a contract with Saw Pipes for procuring casing pipes. Saw Pipes was not in a position to deliver the casing pipes on time. The steel material supplier to Saw Pipes was affected by Steel Mill strikes in Europe. Hence Saw Pipes could not provide the casing pipe on time to ONGC and requested extension of time of contract. Saw Pipes requested for an extension of 45 days time for execution of the order in view of the reasons beyond its control. By a letter, the time for delivery of the pipes was extended by ONGC with a specific statement that the amount equivalent to liquidated damages for delay in supply of pipes as per the contract would be recovered from the Saw Pipes. Saw Pipes was against the recovery of liquidated damages. Dispute reached the Supreme Court of India. Saw Pipes was trying to argue that unless the exact monetary loss could be determined, the damages cannot be claimed. ONGC contended that once a pre-determined liquidated damages clause is agreed upon, the exact monetary loss need not be proved. The relevant clause of contract is provided below: 11. Failure and Termination Clause/Liquidated Damages:Time and date of delivery shall be essence of the contract. If the contractor fails to deliver the stores, or any installment thereof within the period fixed for such delivery in the schedule or at any time repudiates the contract before the expiry of such period, the purchaser may, without prejudice to any other right or remedy, available to him to recover damages for breach of the contract:(a) Recovery from the contractor as agreed liquidated damages are not by way of penalty, a sum equivalent to 1% (one percent) of the contract price of the whole unit per week for such delay or part thereof (this is an agreed, genuine pre- estimate of damages duly agreed by the parties) which the contractor has failed to deliver within the period fixed for delivery in the schedule, where delivery thereof is accepted after expiry of the aforesaid period. It may be noted that such recovery of liquidated damages may be upto 10% of the contract price of whole unit of stores which the contractor has failed to deliver within the period fixed for delivery, or (e) It may further be noted that clause (a) provides for recovery of liquidated damages on the cost of contract price of delayed supplies (whole unit) at the rate of 1% of the contract price of the whole unit per week for such delay or part thereof upto a ceiling of 10% of the contract price of delayed supplies (whole unit). Liquidated damages for delay in supplies thus accrued will be recovered by the paying authorities of the purchaser specified in the supply order, from the bill for payment of the cost of material submitted by the contractor or his foreign principals in accordance with the terms of supply order or otherwise. (f) Notwithstanding anything stated above, equipment and materials will be deemed to have been delivered only when all its components, parts are also delivered. If certain components are not delivered in time the equipment and material will be considered as delayed until such time all the missing parts are also delivered.” Questions 1) What is damages and liquidated damages in a contract? 2) Can the damages be pre-determined in a contract? Is this possible in a government contract? Yes + Yes 3) Can ONGC claim the LD amount for delay in the supply of the casing pipe? Is Saw Pipes argument valid? No clarity of force majeure Not able to prove that saw mills were able to exhaust other alternatives Class Exercise: Force Majeure Adani Power and Tata Power wants to increase electricity charges of consumers, stating that they have additional financial burden due to a force majeure event. This is in relation with the Power Purchase Agreements entered into by Adani Power and Tata Power with power distributors. The sudden change in the coal price, especially coal in Indonesia, from where Tata Power and Adani Power are procuring coal is reason for the claim of the force majeure event Analyze this event based on the following media report: SC sets aside compensatory tariff to Tata Power, Adani Power Krishnadas Rajagopal NEW DELHI: , APRIL 11, 2017 20:12 IST A view of the Supreme Court of India. | Photo Credit: R.V. Moorthy Court ordered the CERC to go into the matter afresh and determine what relief should be granted to the power generators. The Supreme Court on Tuesday set aside an Appellate Electricity Tribunal decision allowing power generator giants Adani Power and Tata Power to charge compensatory tariff from their consumers spread across States including Gujarat and Haryana. The tribunal, in a judgment on April 7 last year, permitted the companies to hike the tariff after Indonesia — where they source coal from to power their plants — decided in 2010 to align its coal export prices to international market prices instead of what they have been charging for the past 40 years. The companies had argued that the increased coal prices was a ‘force majeure’ event (an unforeseen situation) provided for in the power purchase agreements (PPAs) entered into between them and distributors. The tribunal had then remanded the case to the Central Electricity Regulation Commission to find out the impact of the ‘force majeure’ event to grant compensatory tariff. On December 6, 2016, the Commission had arrived at a certain determination as to compensatory tariff to be granted on account of force majeure. Setting aside all past orders of the tribunal and the commission, a Bench of Justices P.C. Ghose and Rohinton Nariman held that a change in Indonesian coal export regulations does not measure up to be a force majeure event for which the consumers have to compensate for. “The fundamental basis of the PPAs remains unaltered. Nowhere do the PPAs state that coal is to be procured only from Indonesia at a particular price. In fact, it is clear on a reading of the PPA as a whole that the price payable for the supply of coal is entirely for the person who sets up the power plant to bear. It is clear that an unexpected rise in the price of coal will not absolve the generating companies from performing their part of the contract for the very good reason that when they submitted their bids, this was a risk they knowingly took,” Justice Nariman, who wrote the verdict, held in a 65-page judgment. The court held that “changes in the cost of fuel, or the agreement becoming onerous to perform, are not treated as force majeure events under the PPA itself”. The court further held that force majeure clause cannot be claimed for change in foreign laws, but only for Indian laws. The court ordered the Central Electricity Regulatory Commission to go into the matter afresh and determine what relief should be granted to the power generators. http://www.thehindu.com/news/national/sc-sets-aside-compensatory-tariff-to-tata-power-adanipower/article17928722.ece Pertinent Legal Aspect of Business issues to be explored: 1) What is force majeure event in a contract? Can increase of coal price in Indonesia be considered as a force majeure event? 2) Should ‘change of law/policy’ be considered as force majeure event? Provide reason from the angle of a business manager 3) How will you draft a suitable force majeure clause for your organisation?