Commissioning management CIBSE Commissioning Code M: 2003 The rights of publication or translation are reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or by any means without the prior permission of the Institution. © June 2003 The Chartered Institution of Building Services Engineers London Registered charity number 278104 ISBN 1 903287 33 2 This document is based on the best knowledge available at the time of publication. However no responsibility of any kind for any injury, death, loss, damage or delay however caused resulting from the use of these recommendations can be accepted by the Chartered Institution of Building Services Engineers, the authors or others involved in its publication. In adopting these recommendations for use each adopter by doing so agrees to accept full responsibility for any personal injury, death, loss, damage or delay arising out of or in connection with their use by or on behalf of such adopter irrespective of the cause or reason therefore and agrees to defend, indemnify and hold harmless the Chartered Institution of Building Services Engineers, the authors and others involved in their publication from any and all liability arising out of or in connection with such use as aforesaid and irrespective of any negligence on the part of those indemnified. Typeset by CIBSE Publications Department Printed in Great Britain by Page Bros. (Norwich) Ltd., Norwich, Norfolk, NR6 6SA Note from the publisher This publication is primarily intended to provide guidance to those responsible for the design, installation, commissioning, operation and maintenance of building services. It is not intended to be exhaustive or definitive and it will be necessary for users of the guidance given to exercise their own professional judgement when deciding whether to abide by or depart from it. Printed on 100% recycled paper comprising at least 80% post-consumer waste Contents M0 M1 M2 M3 M4 Introduction 1 M0.1 Scope 1 M0.2 Purpose 1 M0.3 Summary of commissioning requirements 1 M0.4 The importance of commissioning 1 M0.5 Other guidance 2 M0.6 Commissioning definitions 2 M0.7 Commissioning records 4 M0.8 Responsibility 4 Legislation 4 M1.1 Safety requirements 4 M1.2 Statutory regulations 4 General considerations 5 M2.1 Commissioning management 5 M2.2 Selection and appointment of a commissioning management organisation (CMO) 5 M2.3 Communications 5 Design for commissionability 6 M3.1 Inherent commissionability 6 M3.2 Design responsibility 6 M3.3 Ease of access 6 M3.4 Design requirements 7 Programming and co-ordination of the commissioning process 7 M4.1 General considerations 7 M4.2 Specifying requirements for commissioning 7 M5 Installation quality assurance 7 M6 Pre-commissioning 8 M6.1 Risk analysis 8 M6.2 Plant ready for commissioning 8 M6.3 Control system requirements for commissioning 9 M7 M8 M9 Commissioning 9 M7.1 Commissioning certification 9 M7.2 Phased completion 9 M7.3 BMS as a commissioning tool 9 Witnessing compliance 9 M8.1 Objective 9 M8.2 Witnessing arrangements 10 M8.3 Witnessing duties 10 Building log book 10 M10 System handover 11 References 11 Appendix MA1: Guidance documents on commissioning specific building services 13 Appendix MA2: Example responsibility matrix 14 Appendix MA3: Designer’s checklist for commissionability 16 Appendix MA4: Example certificate of readiness 17 Index 18 1 Commissioning management M0 Introduction The main objective of commissioning management is to manage the overall commissioning activities, including programming, to achieve the project completion date. The commissioning programmes produced by building services installers and their sub-contractors are frequently over-optimistic and unco-ordinated. They assume that others will co-operate in providing water, gas and electric supplies, a weather-tight building, unobstructed access and a dust-free environment. A risk of project overrun will exist unless the interdependencies of all the building services systems and plant are identified, together with their integration with on-going construction activities. This complex, often highly fragmented part of the construction process demands good management. M0.1 Scope This Code provides an overview of the management arrangements required to ensure that building services systems are commissioned to meet the objectives of Part L of the Building Regulations (1–3). The Code represents standards of good practice which are presented in the form of recommendations and guidance for the building services industry. — a guide for all members of the project team to enable commissioning to be achieved in partnership — a guide to provide an understanding of commissioning management procedures; detailed information on procedures for particular types of installation are provided in other CIBSE Commissioning Codes. It is not intended that contracts or specifications should refer to this Code in its entirety, rather that direct references be made to specific sections of the Code when specifying requirements for systems commissioning. M0.3 Summary of commissioning requirements Building services plant and control systems should be inherently commissionable. This is most likely to be achieved if the requirement is in the brief from the outset, and specialist commissioning advice sought early in the design process. The requirement may be compromised by overdesign. The following summarises the key requirements for successfully commissioned building services systems: — The contractor and client should allow sufficient time for the complete commissioning process and ensure integration into the overall programme. — A commissioning management team should be formed. — Maximum use should be made of off-site precommissioning activities. — Manufacturers of equipment should be involved in the commissioning process. — Compliance with this Code should satisfy building control officers that the commissioning requirements of Part L of the Building Regulations(1–3) have been met. Thorough commissioning procedures should be adopted. — Documentary evidence that the requirements of the Building Regulations have been met should be provided. Compliance with the Code does not confer immunity from relevant statutory and legal requirements. — User feedback should be obtained to confirm the performance of the system(s) and the attainment of required internal environmental conditions. It is applicable to the management of commissioning of all building services systems, particularly those covered by the commissioning requirement of Part L(1–3), including new-build and retrofit applications, for example following major maintenance or replacement of components. Commissioning of specific systems is addressed by other CIBSE Commissioning Codes (see Appendix MA1, including Table MA1.1). M0.2 Purpose The Code is intended to be used as: — a guide to good practice of the commissioning management of building services systems — a tool to assist the definition of commissioning management procedures — a basis for the preparation of commissioning specifications M 0.4 The importance of commissioning The proper commissioning of building services is crucial to ensure the correct operation of the system and its associated building services plant. Part L of the Building Regulations(1–3) requires that all controlled services that fall within the scope of the regulations will be commissioned. Evidence will be required from a suitably 2 Commissioning management qualified person that all services have been commissioned and are operating correctly. The building owner or his/her agent has a statutory duty to ensure compliance with the requirements of Part L(1–3). It is therefore essential that they ensure that the construction programme incorporates a sufficient time element to enable commissioning to be completed prior to handover. Failure to do so may delay completion and handover of the building. Early involvement of a commissioning management organisation ( CMO ) will facilitate the provision of adequate time in the programme. All works approved under Part L of the Building Regulations (1–3) are required to be commissioned in accordance with the design intent. Note: for domestic buildings this applies to heating, ventilation, hot water and external lighting; for nondomestic buildings this applies to heating, ventilation, cooling/refrigeration, lighting, controls and water. — dissatisfied building occupants, possibly affecting their productive capacity and causing excessive energy consumption. Recommended comfort criteria for specific applications are given in CIBSE Guide A: Environmental design(4), Table 1.1. M0.5 Other guidance Guidance concerning the commissioning of building services systems is contained in CIBSE Commissioning Codes and other sources, such as those published by the Building Services Research and Information Association (BSRIA) and the Commissioning Specialists Association (CSA). Details of these publications are given in Appendix MA1. M0.6 Commissioning definitions Balancing The following main factors are influenced by the commissioning of the services: — plant operation within the design parameters specified for the installation, including internal and external design conditions — maintenance of internal design parameters within defined tolerances at all load conditions — minimising the energy consumption of the equipment — future maintenance requirements. The process of adjusting the flow rates of a fluid in a distribution system to achieve the design flow rates within the specified tolerances. Calibration of controls The adjustment of control devices to meet the performance requirements of the system specification. Commissionable system A poorly commissioned system has the potential to compromise the safety of building occupants and maintenance personnel. A system designed, installed and prepared to specified requirements in such a manner as to enable satisfactory commissioning to be carried out. M0.4.1 Commissioning Energy consumption Building services systems that are set up and controlled properly use less energy. This requires that the set-up and operation of the component plant and control systems are checked. Incorrectly commissioned building services systems can use excessive energy due to: (a) unnecessary periods of plant operation (b) poor control to set points. The advancement of an installation from the state of static completion to full working order to the specified requirements. It includes the setting to work of an installation, the regulation of the system and the fine tuning of the system. Commissionability The ability of a system to be commissioned satisfactorily. M0.4.2 Indoor environmental conditions The achievement of satisfactory indoor environmental conditions is crucial in order to provide a healthy and comfortable working environment. A poorly commissioned control system can result in: — failure to achieve desired levels of internal air temperature and humidity — inadequate levels of ventilation — levels of air movement that are too high or too low — excessive noise due to plant cycling — inappropriate lighting levels — unsafe electrical installation Commissioning The advancement of an installation from the stage of static completion to full working order to specified requirements. Commissioning completion certificate A document to confirm that commissioning has been completed. Commissioning engineer The person undertaking the commissioning procedure. Introduction 3 Commissioning management Operation and maintenance manual The planning, organisation, co-ordination and control of commissioning activities. A series of documents detailing the design, mode of operation and maintenance requirements of building services systems. Commissioning management organisation The firm or person appointed to manage the commissioning process, being responsible for overall planning, supervision and witnessing of the results of the integrated commissioning of all installed building services systems. Performance testing The testing of a system, or a grouping of systems, to determine if certain performance criteria are met. Commissioning plan or timetable Portable or test instrument A time schedule for the various works required to complete commissioning. This means an instrument not permanently connected to the installation and which, where appropriate, is recalibrated at required intervals by an approved, independent authority e.g. a laboratory accredited by the National Measurement Accreditation Service (a service of the National Physical Laboratory). Commissioning specialist The firm (or person) appointed to carry out specified duties in connection with commissioning engineering services in accordance with a commissioning specification. Commissioning specification The document which prescribes the detailed requirements with which the various commissioning services have to comply. Note: the specification should refer to drawings, schedules and relevant parts of the Code, manuals, guides and other standards. Design criteria The specified numerical quantity together with allowable tolerances. Energy sources Pre-commissioning Specified systematic checking of a completed installation to confirm its state of readiness for commissioning. Pressure and leakage testing The measurement and recording of a specified pressure retention or loss within a system or system component. Regulation The process of adjusting the rates of fluid flow and heat transfer in a distribution system, to achieve specified values within specified tolerances. All fuels and forms of motive power supplied to the system. Setting to work Fine tuning The process of setting a static system into operation. Local adjustment to the system where usage and system proving have shown such a need. This may also include the re-assessment of control set points and values to achieve optimum performance. Specification Installation The document that prescribes the system design and requirements for commissioning by reference to drawings, information schedules and relevant codes, manuals, guides and standards. A system placed in position as required by the design or specification. Static completion Log book The permanent record of calibration settings and performance test result that is initiated by commissioning engineers and maintained thereafter by responsible persons. Operating levels The set points of all control devices under operating conditions. The state of a system when it is installed in accordance with the specification, i.e. clean and ready for setting to work. In the case of water systems this includes flushing, cleaning, pressure testing, filling and venting. System A set of connected components for heating, cooling, ventilation or air conditioning consisting of plant, distribution ducting, piping and terminal units and arrangements to control their operation. 4 Commissioning management System proving Measuring, recording, evaluating and reporting on the seasonal performance of the system against design criteria. Testing The measurement and recording of system parameters to assess specification compliance. M0.7 Commissioning records It is essential that the results of all checks and measurements are recorded in writing by the commissioning engineer as commissioning proceeds, together with any appropriate comments. Breaks in the continuity of commissioning operations are likely and proper records will show the state of progress at any particular stage. Good records should include anecdotal comment from the commissioning engineer setting up the system as well as details of the actual system performance The provision of commissioning records is an essential part of the handover information for the building user. Knowledge of the way a system has been set up is a necessary base when considering the scope for any improvements or modifications, including fine tuning. It is recommended that a pro forma for these records be compiled from the relevant Commissioning Code for each particular type of installation. Records of all commissioning activities should include details of tests undertaken and results achieved. It is recommended that the format of record sheets should be agreed before testing and commissioning commences. Record sheets should be completed once only (i.e. not subsequently transcribed by typing since this can lead to errors being introduced). Where hand written records are subsequently transcribed into typed format there should be a formal checking process to validate their accuracy. Records should also include calibration certificates for all instruments used during the commissioning process. Availability of these records will help to demonstrate compliance with the Building Regulations(1–3). M0.8 Responsibility The objective of the particular Commissioning Codes is to prescribe all the procedures entailed in bringing a system into full working order. Requirements for commissioning a particular system will be included in the commissioning specification for the project. Logical areas of involvement for the design engineer, the installation engineer, the specialist or manufacturer and the commissioning engineer are indicated in the particular Codes based on typical practices. An example overall responsibility matrix is shown in Appendix MA2, in this instance based on a management contract. It is stressed, however, that the attribution of responsibility is a contractual matter and that parties involved in any works must comply with the relevant contract requirements. The various tasks included in the Codes are arranged in a deliberate sequence which has been found to be advantageous based on wide, general experience. It is therefore recommended that this sequence be followed. In some cases, where the sequence is of exceptional importance, attention is drawn in the text of the particular Commissioning Code to the need for some tasks to be preceded by others. Some equipment and its operation calls for specialist knowledge. For this reason the design, installation and, particularly, the commissioning of such equipment will generally be required to be carried out by the manufacturer’s specialist personnel, or in close association with them. A number of different skills will be involved and strict attention to formal co-ordination between those involved should be defined in the contract documentation. However, it is recommended that the control of the entire commissioning procedure be vested in a single authority. BSRIA TM 1/88: Commissioning HVAC systems — division of responsibilities (5) suggests appropriate arrangements for projects where a commissioning specialist is to be appointed. M1 Legislation M1.1 Safety requirements The principal contractor, as defined in the Construction (Design and Management) Regulations 1994(6), has the lead responsibility for ensuring safety during the construction process, which includes commissioning. The commissioning manager should support this role and review the commissioning plan to monitor safety aspects. Any areas of concern will need to be raised with the commissioning engineer and agreed with the principal contractor prior to the work being carried out. M1.2 Statutory regulations Applicable legislation includes, but is not limited to, the following: — Building Regulations 2000(1–3) — Health and Safety at Work etc. Act 1974(7) — Management of Health and Safety at Work Regulations 1999(8) — Construction (Design Regulations 1994(6) — Construction (Head Protection) Regulations1989(9) — Construction (Health, Safety and Welfare) Regulations 1996(10) — Confined Spaces Regulations 1997(11) — Workplace (Health, Safety and Welfare) Regulations 1992(12) — Working Time Regulations 1999(13) — Electricity at Work Regulations 1989(14) and Management) 4 Commissioning management System proving Measuring, recording, evaluating and reporting on the seasonal performance of the system against design criteria. Testing The measurement and recording of system parameters to assess specification compliance. M0.7 Commissioning records It is essential that the results of all checks and measurements are recorded in writing by the commissioning engineer as commissioning proceeds, together with any appropriate comments. Breaks in the continuity of commissioning operations are likely and proper records will show the state of progress at any particular stage. Good records should include anecdotal comment from the commissioning engineer setting up the system as well as details of the actual system performance The provision of commissioning records is an essential part of the handover information for the building user. Knowledge of the way a system has been set up is a necessary base when considering the scope for any improvements or modifications, including fine tuning. It is recommended that a pro forma for these records be compiled from the relevant Commissioning Code for each particular type of installation. Records of all commissioning activities should include details of tests undertaken and results achieved. It is recommended that the format of record sheets should be agreed before testing and commissioning commences. Record sheets should be completed once only (i.e. not subsequently transcribed by typing since this can lead to errors being introduced). Where hand written records are subsequently transcribed into typed format there should be a formal checking process to validate their accuracy. Records should also include calibration certificates for all instruments used during the commissioning process. Availability of these records will help to demonstrate compliance with the Building Regulations(1–3). M0.8 Responsibility The objective of the particular Commissioning Codes is to prescribe all the procedures entailed in bringing a system into full working order. Requirements for commissioning a particular system will be included in the commissioning specification for the project. Logical areas of involvement for the design engineer, the installation engineer, the specialist or manufacturer and the commissioning engineer are indicated in the particular Codes based on typical practices. An example overall responsibility matrix is shown in Appendix MA2, in this instance based on a management contract. It is stressed, however, that the attribution of responsibility is a contractual matter and that parties involved in any works must comply with the relevant contract requirements. The various tasks included in the Codes are arranged in a deliberate sequence which has been found to be advantageous based on wide, general experience. It is therefore recommended that this sequence be followed. In some cases, where the sequence is of exceptional importance, attention is drawn in the text of the particular Commissioning Code to the need for some tasks to be preceded by others. Some equipment and its operation calls for specialist knowledge. For this reason the design, installation and, particularly, the commissioning of such equipment will generally be required to be carried out by the manufacturer’s specialist personnel, or in close association with them. A number of different skills will be involved and strict attention to formal co-ordination between those involved should be defined in the contract documentation. However, it is recommended that the control of the entire commissioning procedure be vested in a single authority. BSRIA TM 1/88: Commissioning HVAC systems — division of responsibilities (5) suggests appropriate arrangements for projects where a commissioning specialist is to be appointed. M1 Legislation M1.1 Safety requirements The principal contractor, as defined in the Construction (Design and Management) Regulations 1994(6), has the lead responsibility for ensuring safety during the construction process, which includes commissioning. The commissioning manager should support this role and review the commissioning plan to monitor safety aspects. Any areas of concern will need to be raised with the commissioning engineer and agreed with the principal contractor prior to the work being carried out. M1.2 Statutory regulations Applicable legislation includes, but is not limited to, the following: — Building Regulations 2000(1–3) — Health and Safety at Work etc. Act 1974(7) — Management of Health and Safety at Work Regulations 1999(8) — Construction (Design Regulations 1994(6) — Construction (Head Protection) Regulations1989(9) — Construction (Health, Safety and Welfare) Regulations 1996(10) — Confined Spaces Regulations 1997(11) — Workplace (Health, Safety and Welfare) Regulations 1992(12) — Working Time Regulations 1999(13) — Electricity at Work Regulations 1989(14) and Management) Legislation 5 — Gas Safety (Installation and Use) Regulations 1994(15) — Personal Protective Equipment at Work Regulations 1992(16) — Health and Safety (Display Screen Equipment) Regulations 1992(17) — Provision and Use of Equipment at Work Regulations 1998(18) — Pressure Systems Safety Regulations 2000(19) — Noise at Work Regulations 1989(20) — Notification of Cooling Towers and Evaporative Condensers Regulations 1992(21) — Control of Substances Hazardous to Health Regulations 1999(22) — Water Supply (Water Fittings) Regulations 1999(23) The Commissioning Codes for specific systems include legislation relevant to particular system components. M2 General considerations M2.1 Commissioning management All projects should be assessed to see if there is justification for appointing a commissioning manager. The responsibilities of the commissioning manager can be extensive and various depending on how early the person is appointed and the extent of the brief. If appointed early enough, the commissioning manager’s input at the design stage can make a significant contribution to ensuring the success and timely completion of a project. See BSRIA AG5/2002 (24) , section 6.1, for details of the potential responsibilities which can be placed on the commissioning manager. The calibre of the resources appointed to carry out commissioning management is critical. The detailed knowledge and past experience of competent commissioning management practitioners should include: (a) commissioning procedures for main systems and components (b) the logical sequencing of installation and commissioning activities (c) programming skills and critical path analysis techniques (d) resource planning (e) report writing and administrative skills (f) communication skills (g) pragmatic leadership skills (h) services design principles (i) Commissioning Specialist Association (CSA) level 6 qualifications, or equivalent engineering experience. M2.2 Selection and appointment of a commissioning management organisation (CMO) Commissioning management in the context of this Code is a contracted-for activity in which a specialist company or individual manages the commissioning process. The term commissioning management organisation (CMO) has been adopted in this Code for the organisation providing this role. Selection of the CMO will depend on the nature and size of the project. Options include competitive tender or interview. They should be assessed by their relevant knowledge and experience The assessment should also include how they would tailor their services to meet the activities listed on the responsibility matrix. The role of the CMO and its relationship with the employer and other members of the construction team can be many and varied, depending on how the contract has been established. The contractual relationship of the CMO is very important since it will define its authority and responsibility and, hence, its ability to have an effect. Research in this area has indicated that the structure illustrated in Figure 1 can provide an effective position for the CMO . In this example the CMO is appointed by the principal/main contractor and is part of the project management team. However, each contract will need to define the particular relationships of the parties involved. M2.3 Communications The objective of a CMO is to co-ordinate and oversee the commissioning process. For projects with relatively simple engineering services, the formation of a full commissioning management team may not be appropriate. It is still advisable to use the procedures described in this Code to ensure that commissioning is accomplished in the correct order to ensure certainty of project delivery. If a specialist CMO is not appointed, then it is important that the tasks outlined in this Code are specifically assigned to others within an agreed timetable. Communications between the various parties is vital and it is important that all members of the project team meet at appropriate intervals convened by the CMO. This will enable the installation contractor and commissioning engineers to programme their work and co-ordinate with other activities. Where a CMO has not been appointed, it is important to ensure that communication routes are established and meetings convened on an appropriate basis. The following procedures should be followed: (a) At the start of a project, the various parties should agree on communication routes for commissioning aspects. (b) A framework for a communication network should be drawn up to aid the smooth flow of information. Figure 1 shows an example contractual relationship and communications route in a commissioning situation where a CMO has been appointed. Legislation 5 — Gas Safety (Installation and Use) Regulations 1994(15) — Personal Protective Equipment at Work Regulations 1992(16) — Health and Safety (Display Screen Equipment) Regulations 1992(17) — Provision and Use of Equipment at Work Regulations 1998(18) — Pressure Systems Safety Regulations 2000(19) — Noise at Work Regulations 1989(20) — Notification of Cooling Towers and Evaporative Condensers Regulations 1992(21) — Control of Substances Hazardous to Health Regulations 1999(22) — Water Supply (Water Fittings) Regulations 1999(23) The Commissioning Codes for specific systems include legislation relevant to particular system components. M2 General considerations M2.1 Commissioning management All projects should be assessed to see if there is justification for appointing a commissioning manager. The responsibilities of the commissioning manager can be extensive and various depending on how early the person is appointed and the extent of the brief. If appointed early enough, the commissioning manager’s input at the design stage can make a significant contribution to ensuring the success and timely completion of a project. See BSRIA AG5/2002 (24) , section 6.1, for details of the potential responsibilities which can be placed on the commissioning manager. The calibre of the resources appointed to carry out commissioning management is critical. The detailed knowledge and past experience of competent commissioning management practitioners should include: (a) commissioning procedures for main systems and components (b) the logical sequencing of installation and commissioning activities (c) programming skills and critical path analysis techniques (d) resource planning (e) report writing and administrative skills (f) communication skills (g) pragmatic leadership skills (h) services design principles (i) Commissioning Specialist Association (CSA) level 6 qualifications, or equivalent engineering experience. M2.2 Selection and appointment of a commissioning management organisation (CMO) Commissioning management in the context of this Code is a contracted-for activity in which a specialist company or individual manages the commissioning process. The term commissioning management organisation (CMO) has been adopted in this Code for the organisation providing this role. Selection of the CMO will depend on the nature and size of the project. Options include competitive tender or interview. They should be assessed by their relevant knowledge and experience The assessment should also include how they would tailor their services to meet the activities listed on the responsibility matrix. The role of the CMO and its relationship with the employer and other members of the construction team can be many and varied, depending on how the contract has been established. The contractual relationship of the CMO is very important since it will define its authority and responsibility and, hence, its ability to have an effect. Research in this area has indicated that the structure illustrated in Figure 1 can provide an effective position for the CMO . In this example the CMO is appointed by the principal/main contractor and is part of the project management team. However, each contract will need to define the particular relationships of the parties involved. M2.3 Communications The objective of a CMO is to co-ordinate and oversee the commissioning process. For projects with relatively simple engineering services, the formation of a full commissioning management team may not be appropriate. It is still advisable to use the procedures described in this Code to ensure that commissioning is accomplished in the correct order to ensure certainty of project delivery. If a specialist CMO is not appointed, then it is important that the tasks outlined in this Code are specifically assigned to others within an agreed timetable. Communications between the various parties is vital and it is important that all members of the project team meet at appropriate intervals convened by the CMO. This will enable the installation contractor and commissioning engineers to programme their work and co-ordinate with other activities. Where a CMO has not been appointed, it is important to ensure that communication routes are established and meetings convened on an appropriate basis. The following procedures should be followed: (a) At the start of a project, the various parties should agree on communication routes for commissioning aspects. (b) A framework for a communication network should be drawn up to aid the smooth flow of information. Figure 1 shows an example contractual relationship and communications route in a commissioning situation where a CMO has been appointed. 6 Commissioning management Figure 1 Possible contractual relationships and communications routes Client Project manager (if appointed) Design team Principal/main contractor Commissioning management organisation M&E installing contractor Commissioning supervisor/engineer Specialist suppliers communication route contractual connection M3 Design for commissionability Appendix MA3 provides a designer’s checklist for commissionability M3.1 Inherent commissionability It is important that all those responsible for the design and specification of building services systems are aware of the requirements to ensure that the building services systems are inherently commissionable. Otherwise, it may not be possible to balance and commission systems in accordance with the CIBSE Commissioning Codes. The involvement of a specialist in commissioning at the design stage should be considered, particularly where in-house experience is not sufficiently comprehensive. Further details concerning design for commissionability are provided in Appendix CA1 of CIBSE Commissioning Code C(25). M3.2 Design responsibility Commissioning is not an optional requirement. The designer must accept the implications of the commissioning procedures to which the system will be subjected. To ensure proper commissioning, the designer must provide a particular and definitive commissioning specification setting out clearly what is expected of the commissioning specialist. It should include tolerances on all commissioning parameters. Adequate safety controls and interlocks need to be provided to protect the equipment and personnel during the commissioning process and throughout subsequent operation. The system and equipment should be designed and installed with all necessary components and facilities and with adequate access to permit the required commissioning procedures to be properly carried out. It is the designer’s responsibility to specify not only these components and facilities in detail, but also their precise location in the system to enable them to function as required. Information from the designer should be given either on drawings or in the design specification. The latter should always include a clear description of how it is intended that the system should operate and the design parameters. It is particularly important that the system capacity, controls and safety devices permit stable operation over the specified range of load conditions. The designer should also produce ‘cause and effect’ sheets showing how the design is intended to operate. The success and feasibility of the commissioning procedures will be influenced by the facilities afforded by the design. In the context of the CIBSE Commissioning Codes, the design objective must be to provide a system which is, in all respects, properly matched to the installation as a whole. Oversizing should be avoided and stand-by arrangements should be consistent with the design risk. Design responsibilities for specialist plant such as major refrigeration equipment generally rest with the manufacturer. Design responsibilities for systems rest with the manufacturer, or consultant, or contractor, depending upon the overall contractual arrangements. In the context of this Code the term ‘designer’ applies to the person or organisation having responsibility for the system or for the building engineering services system of which this forms a part. M3.3 Ease of access The design engineer must ensure that safe access is specified to all pressure test points, flow measuring devices, double-regulating valves and concealed items of equipment requiring adjustment during commissioning and maintenance. 6 Commissioning management Figure 1 Possible contractual relationships and communications routes Client Project manager (if appointed) Design team Principal/main contractor Commissioning management organisation M&E installing contractor Commissioning supervisor/engineer Specialist suppliers communication route contractual connection M3 Design for commissionability Appendix MA3 provides a designer’s checklist for commissionability M3.1 Inherent commissionability It is important that all those responsible for the design and specification of building services systems are aware of the requirements to ensure that the building services systems are inherently commissionable. Otherwise, it may not be possible to balance and commission systems in accordance with the CIBSE Commissioning Codes. The involvement of a specialist in commissioning at the design stage should be considered, particularly where in-house experience is not sufficiently comprehensive. Further details concerning design for commissionability are provided in Appendix CA1 of CIBSE Commissioning Code C(25). M3.2 Design responsibility Commissioning is not an optional requirement. The designer must accept the implications of the commissioning procedures to which the system will be subjected. To ensure proper commissioning, the designer must provide a particular and definitive commissioning specification setting out clearly what is expected of the commissioning specialist. It should include tolerances on all commissioning parameters. Adequate safety controls and interlocks need to be provided to protect the equipment and personnel during the commissioning process and throughout subsequent operation. The system and equipment should be designed and installed with all necessary components and facilities and with adequate access to permit the required commissioning procedures to be properly carried out. It is the designer’s responsibility to specify not only these components and facilities in detail, but also their precise location in the system to enable them to function as required. Information from the designer should be given either on drawings or in the design specification. The latter should always include a clear description of how it is intended that the system should operate and the design parameters. It is particularly important that the system capacity, controls and safety devices permit stable operation over the specified range of load conditions. The designer should also produce ‘cause and effect’ sheets showing how the design is intended to operate. The success and feasibility of the commissioning procedures will be influenced by the facilities afforded by the design. In the context of the CIBSE Commissioning Codes, the design objective must be to provide a system which is, in all respects, properly matched to the installation as a whole. Oversizing should be avoided and stand-by arrangements should be consistent with the design risk. Design responsibilities for specialist plant such as major refrigeration equipment generally rest with the manufacturer. Design responsibilities for systems rest with the manufacturer, or consultant, or contractor, depending upon the overall contractual arrangements. In the context of this Code the term ‘designer’ applies to the person or organisation having responsibility for the system or for the building engineering services system of which this forms a part. M3.3 Ease of access The design engineer must ensure that safe access is specified to all pressure test points, flow measuring devices, double-regulating valves and concealed items of equipment requiring adjustment during commissioning and maintenance. Design for commissionability M3.4 7 ensure that commissioning/testing actions are performed correctly and not repeated unnecessarily. Design requirements Efficient operation of any system will depend on effective commissioning in accordance with the commissioning specification. (e) An important design objective is to ensure that balancing requirements are considered fully at the conceptual stage. To facilitate this, design engineers are recommended to ensure that these requirements are taken into account and an unequivocal specification is provided so that satisfactory balancing and commissioning are assured. Early discussions with the commissioning specialist will assist the design engineer. All parties involved in the commissioning process must have documentation procedures for dealing with variations to contract. A change control mechanism should be set up which includes documentary records of what has been changed, how it has been changed, and why. (f) A unique numbering system and use of mnemonics should be used to identify individual work items. (This applies particularly to control system items and devices.) M4 Programming and co-ordination of the commissioning process M4.2 Specifying requirements for commissioning Where possible, the following should be included in the commissioning specification: The main objective of commissioning management is to manage the overall commissioning activities, including programming, to achieve the project completion date. Commissioning activities should therefore be calculated back from the planned completion date. By so doing, clashes of priority with the construction programme can be highlighted and resolved. (a) a clear description of the divisions of responsibility between the various parties (b) pre-commissioning procedures (off-site and onsite) (c) commissioning procedures (on-site) (d) requirements for any point-by-point verification of correct operation M4.1 (e) requirements for evaluation of control loop performance/loop tuning General considerations In order properly to commission a building services system, the commissioning engineer must be provided with comprehensive details relating to its design and specification. In addition, commissioning must be clearly specified and the needs of the commissioning process addressed during initial design to ensure that the commissioning of the system can be performed correctly. Specialist commissioning input at this stage will be beneficial to the process. (f) requirements for the control system (BMS operator workstation), to be used to assist in the commissioning of plant (g) arrangements for management of delays (h) phased completion requirements (i) requirements for demonstration/witness testing to be identified; the witnessing requirements should include the identification of those responsible The following commissioning management actions and considerations should be observed: (j) requirements for witness testing of controls on the basis of a percentage of points or on a point-bypoint basis (it may be appropriate to define witnessing on a controlled plant-by-plant basis); the witnessing requirements should include the identification of those responsible (k) involvement in any complete system and subsystem performance testing (l) system documentation (m) operator training requirements before and during the commissioning period (there may also be a requirement for post handover operator training) (n) post occupancy checks. (a) A commissioning programme should be compiled. This should be co-ordinated with the design and installation programme of the main contractor, who will need to agree the programme as part of the contract conditions (b) The detailed commissioning programme should be prepared as early as possible to allow comment by all interested parties. (c) Appropriate health and safety risk assessments and method statements for the tasks should be completed and submitted to the planning supervisor. (d) A means of monitoring the progress of the commissioning should be established and integrated into the commissioning contractor’s quality management system. Checklists are essential for monitoring the progress of the commissioning. A checklist should be used to record how the job will be commissioned and to monitor progress. Source information for such checklists is provided in Appendix MA1. Proper progress monitoring procedures will help to M5 Installation quality assurance Commissioning does not replace the process of inspection, which should be carried out during manufacture and construction as part of normal, good engineering practice. Design for commissionability M3.4 7 ensure that commissioning/testing actions are performed correctly and not repeated unnecessarily. Design requirements Efficient operation of any system will depend on effective commissioning in accordance with the commissioning specification. (e) An important design objective is to ensure that balancing requirements are considered fully at the conceptual stage. To facilitate this, design engineers are recommended to ensure that these requirements are taken into account and an unequivocal specification is provided so that satisfactory balancing and commissioning are assured. Early discussions with the commissioning specialist will assist the design engineer. All parties involved in the commissioning process must have documentation procedures for dealing with variations to contract. A change control mechanism should be set up which includes documentary records of what has been changed, how it has been changed, and why. (f) A unique numbering system and use of mnemonics should be used to identify individual work items. (This applies particularly to control system items and devices.) M4 Programming and co-ordination of the commissioning process M4.2 Specifying requirements for commissioning Where possible, the following should be included in the commissioning specification: The main objective of commissioning management is to manage the overall commissioning activities, including programming, to achieve the project completion date. Commissioning activities should therefore be calculated back from the planned completion date. By so doing, clashes of priority with the construction programme can be highlighted and resolved. (a) a clear description of the divisions of responsibility between the various parties (b) pre-commissioning procedures (off-site and onsite) (c) commissioning procedures (on-site) (d) requirements for any point-by-point verification of correct operation M4.1 (e) requirements for evaluation of control loop performance/loop tuning General considerations In order properly to commission a building services system, the commissioning engineer must be provided with comprehensive details relating to its design and specification. In addition, commissioning must be clearly specified and the needs of the commissioning process addressed during initial design to ensure that the commissioning of the system can be performed correctly. Specialist commissioning input at this stage will be beneficial to the process. (f) requirements for the control system (BMS operator workstation), to be used to assist in the commissioning of plant (g) arrangements for management of delays (h) phased completion requirements (i) requirements for demonstration/witness testing to be identified; the witnessing requirements should include the identification of those responsible The following commissioning management actions and considerations should be observed: (j) requirements for witness testing of controls on the basis of a percentage of points or on a point-bypoint basis (it may be appropriate to define witnessing on a controlled plant-by-plant basis); the witnessing requirements should include the identification of those responsible (k) involvement in any complete system and subsystem performance testing (l) system documentation (m) operator training requirements before and during the commissioning period (there may also be a requirement for post handover operator training) (n) post occupancy checks. (a) A commissioning programme should be compiled. This should be co-ordinated with the design and installation programme of the main contractor, who will need to agree the programme as part of the contract conditions (b) The detailed commissioning programme should be prepared as early as possible to allow comment by all interested parties. (c) Appropriate health and safety risk assessments and method statements for the tasks should be completed and submitted to the planning supervisor. (d) A means of monitoring the progress of the commissioning should be established and integrated into the commissioning contractor’s quality management system. Checklists are essential for monitoring the progress of the commissioning. A checklist should be used to record how the job will be commissioned and to monitor progress. Source information for such checklists is provided in Appendix MA1. Proper progress monitoring procedures will help to M5 Installation quality assurance Commissioning does not replace the process of inspection, which should be carried out during manufacture and construction as part of normal, good engineering practice. Design for commissionability M3.4 7 ensure that commissioning/testing actions are performed correctly and not repeated unnecessarily. Design requirements Efficient operation of any system will depend on effective commissioning in accordance with the commissioning specification. (e) An important design objective is to ensure that balancing requirements are considered fully at the conceptual stage. To facilitate this, design engineers are recommended to ensure that these requirements are taken into account and an unequivocal specification is provided so that satisfactory balancing and commissioning are assured. Early discussions with the commissioning specialist will assist the design engineer. All parties involved in the commissioning process must have documentation procedures for dealing with variations to contract. A change control mechanism should be set up which includes documentary records of what has been changed, how it has been changed, and why. (f) A unique numbering system and use of mnemonics should be used to identify individual work items. (This applies particularly to control system items and devices.) M4 Programming and co-ordination of the commissioning process M4.2 Specifying requirements for commissioning Where possible, the following should be included in the commissioning specification: The main objective of commissioning management is to manage the overall commissioning activities, including programming, to achieve the project completion date. Commissioning activities should therefore be calculated back from the planned completion date. By so doing, clashes of priority with the construction programme can be highlighted and resolved. (a) a clear description of the divisions of responsibility between the various parties (b) pre-commissioning procedures (off-site and onsite) (c) commissioning procedures (on-site) (d) requirements for any point-by-point verification of correct operation M4.1 (e) requirements for evaluation of control loop performance/loop tuning General considerations In order properly to commission a building services system, the commissioning engineer must be provided with comprehensive details relating to its design and specification. In addition, commissioning must be clearly specified and the needs of the commissioning process addressed during initial design to ensure that the commissioning of the system can be performed correctly. Specialist commissioning input at this stage will be beneficial to the process. (f) requirements for the control system (BMS operator workstation), to be used to assist in the commissioning of plant (g) arrangements for management of delays (h) phased completion requirements (i) requirements for demonstration/witness testing to be identified; the witnessing requirements should include the identification of those responsible The following commissioning management actions and considerations should be observed: (j) requirements for witness testing of controls on the basis of a percentage of points or on a point-bypoint basis (it may be appropriate to define witnessing on a controlled plant-by-plant basis); the witnessing requirements should include the identification of those responsible (k) involvement in any complete system and subsystem performance testing (l) system documentation (m) operator training requirements before and during the commissioning period (there may also be a requirement for post handover operator training) (n) post occupancy checks. (a) A commissioning programme should be compiled. This should be co-ordinated with the design and installation programme of the main contractor, who will need to agree the programme as part of the contract conditions (b) The detailed commissioning programme should be prepared as early as possible to allow comment by all interested parties. (c) Appropriate health and safety risk assessments and method statements for the tasks should be completed and submitted to the planning supervisor. (d) A means of monitoring the progress of the commissioning should be established and integrated into the commissioning contractor’s quality management system. Checklists are essential for monitoring the progress of the commissioning. A checklist should be used to record how the job will be commissioned and to monitor progress. Source information for such checklists is provided in Appendix MA1. Proper progress monitoring procedures will help to M5 Installation quality assurance Commissioning does not replace the process of inspection, which should be carried out during manufacture and construction as part of normal, good engineering practice. 8 Commissioning management An important role of commissioning management is to ensure that all relevant inspection requirements, including the responsible organisation, are identified in the commissioning plan and included in the overall construction programme. Commissioning management should also ensure that all inspections are carried out to an acceptable standard. Before commissioning major plant, the CMO should ensure the following: (a) Water systems: (i) Systems have been cleaned and flushed to remove any debris, appropriate debris collectors and flushing facilities are incorporated. This is essential before commissioning commences. (ii) all plant items are in accordance with the design drawings, specifications and, where applicable, the manufacturers’ instructions A pressure test certificate for the installation is completed. (iii) All regulating, isolating and control valves are in place and operating correctly. (b) correct installation procedures are being followed (iv) (c) standards of installation and site cleanliness are acceptable. Flow measuring devices are in place and in the correct location for accurate measurement (including pressure tappings). (v) The system is vented. (vi) Pump flow rate is adjusted to provide the specified flow rate. (vii) (Where appropriate, completion of proportional balancing to obtain the branch flow rates in the correct ratio (or through the use and setting of self-balancing valves).) The installer should carry out progress inspections in the course of installation to ensure that: (a) Commissioning management should be involved in the benchmarking and establishing standards for site and installation cleanliness. M6 Pre-commissioning (b) M6.1 Risk analysis A risk analysis of the commissioning procedures is an important part of commissioning management and should be obtained from all the parties involved in the commissioning process before any on-site commissioning activities commence. The risk analysis will identify areas of possible risk, degree of risk and potential impact. Where the degree of risk is assessed as significant, method statements of how the work is to be carried out will be required. These need to define step-by-step the specific stages to be undertaken during the commissioning process. They should be obtained from those undertaking the commissioning activities. Generic method statements are unlikely to be suitable, particularly for large and complex installations. The discipline of preparing method statements will help to minimise any risk associated with the commissioning process. M6.2 Air systems: (i) Ductwork air leakage testing, where specified, is performed and certificates issued (see HVCA DW/144(26)). (ii) Systems are cleaned and blown through to remove any debris; appropriate cleaning and inspection facilities are incorporated. This is essential before commissioning commences (see HVCA TM2 (27) and TR17(28)). (iii) Dampers are in the correct location and fully functional. (iv) Fire/smoke dampers are open. (v) Test holes are drilled and sealed with removable plugs. (vi) In situ flow measuring devices (e.g. Wilson Flow Grid) are installed, where specified. (vii) Regulation of the fan(s) to provide the specified flow rate. (viii) (Where appropriate, completion of proportional balancing of regulating dampers so that terminals share the air flow in the correct proportions.) Plant ready for commissioning At this stage a report (including a pre-commissioning checklist) should be obtained, confirming that the system design is commissionable and that all pre-commissioning checks have been completed. This should state that the system as installed is complete and ready for commissioning. It should also be confirmed that the specified level of cleanliness has been achieved. Building services plant (e.g. heating and ventilation installations) should ideally be installed and properly commissioned before starting the commissioning of major capital plant (e.g. boilers and refrigeration plant). Many items of pre-commissioning can be performed before the plant is fully commissioned. (c) Packaged equipment: (i) Plant and controls are fully commissioned and functional, ready for integration with other plant/systems. (ii) Control equipment inputs/outputs are in the specified format for connection to the main control system. (iii) Support services such as power and balanced water supplies are provided. Full details relating to the commissioning of air and water systems are provided in the CIBSE and BSRIA commissioning publications, which are listed in Appendix MA1. Pre-commissioning M6.3 Control system requirements for plant commissioning As a minimum, the control system should be precommissioned to allow the building services plant to operate under ‘manual’ running conditions. Issues concerning the use of control systems as a plant commissioning tool are outlined in CIBSE Commissioning Code C(24). M7 Commissioning Guidance concerning the commissioning of building services systems is contained in CIBSE Commissioning Codes and other sources, such as those published by BSRIA and the Commissioning Specialists Association. Further details of these are provided in Appendix MA1. M7.1 Commissioning certification When the commissioning procedures have been satisfactorily completed, the commissioning specialist should certify that the system has been commissioned in accordance with the project specification and the relevant commissioning codes. The certificate should be countersigned by the designer, the CMO and the accepting authority who may be the contractor, design engineer, client or some other witnessing authority. The certificate should be accompanied by the appropriate supporting documentation, together with copies of the static completion certificates. The design of pro forma record sheets for the various requirements for commissioning records and certification is a matter for agreement between parties and is outside the scope of this Code. However, as a minimum, the basic information stated in the specific CIBSE Commissioning Codes should be detailed. M7.2 Phased completion Phased completion may be a requirement of the contract where a large and/or complex building services installation is to be commissioned. Phased completion will need the checking and handover procedures to be broken down into manageable packages. The approach to phased completion will depend on the nature of the building and its engineering services. Where installed, a BMS can act as a commissioning aid when phased completion is adopted, however the availability of the BMS for use during the commissioning process is likely to be determined by the terms of the contract, and not be a matter of choice by the commissioning management organisation. Where there is the possibility of phased completion being required, it is important that, as early as possible in the contract, all the systems to be completed and commissioned early and ready for the employer’s use are identified and agreed with the employer. 9 It is therefore essential to identify which systems are to be operational to allow phased completion and also how to prove them as complete and ready for operation as independent entities. A ‘certificate of readiness for employer’ (COR) can be a useful tool as part of this process. The COR is a series of documents that gather together all of the submittal data, tests reports, snag lists etc. and present them in such a way as to show that a particular system is complete and ready to be set to work as designed and specified. The COR is designed to enable all parties to identify a particular mechanical or electrical system that is essential for operation of the project and may need early completion but which either contractually or logically cannot be identified as complete before the issue of a certificate of (partial) completion. One example of where such a document could be applied is on a shell and core contract. Here the M&E systems have to be handed over to another contractor to enable the fitout work to be completed. It may be only after the end of the defects liability period that the M&E systems are fully commissioned and running. An example format for a certificate of readiness for employer is shown in Appendix MA4. M7.3 BMS as a commissioning tool Where the control system is a BMS , it can provide a monitoring facility which can help the commissioning process. In particular, a BMS can demonstrate that the controls are working correctly, by logging their performance and producing real-time data. In this role, and once correctly set up and approved, the data logging and display functions of a correctly functioning BMS can be used to monitor and record the operation of the building services plant. In particular the BMS can: (a) monitor plant operating conditions, e.g. display sensor readings by using trend logs and dynamic trending (b) indicate whether items of plant are operating correctly (c) record and document test results. M8 Witnessing compliance M8.1 Objective The objective is formally to witness, on behalf of the client or his/her representative, the degree to which the requirements of the commissioning specification have been met. The commissioning management programme prepared by the CMO should establish check points when witnessing will occur; for example, when sections of an installation are deemed complete and suitable for witnessing, attendance at plant and system demonstrations, signing off certificates of completion. Pre-commissioning M6.3 Control system requirements for plant commissioning As a minimum, the control system should be precommissioned to allow the building services plant to operate under ‘manual’ running conditions. Issues concerning the use of control systems as a plant commissioning tool are outlined in CIBSE Commissioning Code C(24). M7 Commissioning Guidance concerning the commissioning of building services systems is contained in CIBSE Commissioning Codes and other sources, such as those published by BSRIA and the Commissioning Specialists Association. Further details of these are provided in Appendix MA1. M7.1 Commissioning certification When the commissioning procedures have been satisfactorily completed, the commissioning specialist should certify that the system has been commissioned in accordance with the project specification and the relevant commissioning codes. The certificate should be countersigned by the designer, the CMO and the accepting authority who may be the contractor, design engineer, client or some other witnessing authority. The certificate should be accompanied by the appropriate supporting documentation, together with copies of the static completion certificates. The design of pro forma record sheets for the various requirements for commissioning records and certification is a matter for agreement between parties and is outside the scope of this Code. However, as a minimum, the basic information stated in the specific CIBSE Commissioning Codes should be detailed. M7.2 Phased completion Phased completion may be a requirement of the contract where a large and/or complex building services installation is to be commissioned. Phased completion will need the checking and handover procedures to be broken down into manageable packages. The approach to phased completion will depend on the nature of the building and its engineering services. Where installed, a BMS can act as a commissioning aid when phased completion is adopted, however the availability of the BMS for use during the commissioning process is likely to be determined by the terms of the contract, and not be a matter of choice by the commissioning management organisation. Where there is the possibility of phased completion being required, it is important that, as early as possible in the contract, all the systems to be completed and commissioned early and ready for the employer’s use are identified and agreed with the employer. 9 It is therefore essential to identify which systems are to be operational to allow phased completion and also how to prove them as complete and ready for operation as independent entities. A ‘certificate of readiness for employer’ (COR) can be a useful tool as part of this process. The COR is a series of documents that gather together all of the submittal data, tests reports, snag lists etc. and present them in such a way as to show that a particular system is complete and ready to be set to work as designed and specified. The COR is designed to enable all parties to identify a particular mechanical or electrical system that is essential for operation of the project and may need early completion but which either contractually or logically cannot be identified as complete before the issue of a certificate of (partial) completion. One example of where such a document could be applied is on a shell and core contract. Here the M&E systems have to be handed over to another contractor to enable the fitout work to be completed. It may be only after the end of the defects liability period that the M&E systems are fully commissioned and running. An example format for a certificate of readiness for employer is shown in Appendix MA4. M7.3 BMS as a commissioning tool Where the control system is a BMS , it can provide a monitoring facility which can help the commissioning process. In particular, a BMS can demonstrate that the controls are working correctly, by logging their performance and producing real-time data. In this role, and once correctly set up and approved, the data logging and display functions of a correctly functioning BMS can be used to monitor and record the operation of the building services plant. In particular the BMS can: (a) monitor plant operating conditions, e.g. display sensor readings by using trend logs and dynamic trending (b) indicate whether items of plant are operating correctly (c) record and document test results. M8 Witnessing compliance M8.1 Objective The objective is formally to witness, on behalf of the client or his/her representative, the degree to which the requirements of the commissioning specification have been met. The commissioning management programme prepared by the CMO should establish check points when witnessing will occur; for example, when sections of an installation are deemed complete and suitable for witnessing, attendance at plant and system demonstrations, signing off certificates of completion. 10 Commissioning management It should be noted that under Part L of the Building Regulations(1) there is a requirement for demonstrations to be planned and witnessed. M8.2 Witnessing arrangements M8.2.1 Witnessing period In deciding the detailed requirements for witnessing commissioning, the interaction of various aspects of an installation in determining its overall performance must be borne in mind. For example, the commissioning of a water distribution system might be witnessed against the requirements of CIBSE Commissioning Code W(29) and the project specification. However, witnessing the performance of heat exchangers connected to the water distribution systems would interact with the commissioning of air distribution and automatic control systems as well as of boiler and refrigeration plant. Witnessing is thus an all-embracing and interactive task and this must be reflected in the agreed written format. Particular arrangements for witnessing The following are essential arrangements for witnessing: (a) the provision of a definitive statement of the site attendance availability of the witnessing agent (b) the standards required (c) the extent of witnessing which will be performed (d) additional requirements in the event of defaults (e.g. the number of additional items which must be witnessed for every one which fails to comply). M8.2.4 (a) be satisfied that, throughout the installation and balancing process, the requirements of the commissioning specification and the appropriate commissioning code have been met (b) check the flow rate at any selected flow measurement point using a similar instrument and compare with the data recorded by the commissioning engineer and with the designer’s requirements, which should include any permitted tolerance (c) check performance of all plant and systems (d) visually inspect any part of the system covered by this section to ensure that certification is correct (e) countersign and endorse as necessary the certificate of the appointed commissioning specialist verifying that systems have been balanced in accordance with the specification requirements (f) where required, complete a separate witnessing certificate confirming satisfaction, one copy of which is handed to the commissioning specialist (g) check correct operation of the control system (h) check the correct operation of life safety systems. (a) the means to be used to demonstrate that fluid mass or volume flow rates are within the specified tolerances (b) co-ordination requirements where the performance aspects to be witnessed interact with other systems or equipment the running and monitoring period of the prove its functionality. M9 Building log book In accordance with Building Regulations Approved Document L2(3), the owner/occupier ‘should be provided with a log book giving details of the installed building services plant and controls, their method of operation and maintenance, and other details that collectively enable energy consumption to be monitored and controlled.’ The requirement to produce a building log book needs to be set out in the design specification. Responsibility for its preparation and for ensuring its completion by a specified period within the contract programme should be included in the commissioning specification. The CMO is well placed to ensure that a satisfactory building log book, that complies with the requirements of Part L of the Building Regulations(1). The contents of a building log book could include: Witnessing liaison The witnessing agent should liaise in detail with the installer and the commissioning specialist, as necessary, with regard to: (c) Witnessing duties may be undertaken by the CMO or other organisation appointed by the client. Witnessing requirements All requirements for witnessing should be expressed in an agreed written format, copies of which should be made available to the commissioning specialist. This format must contain full details of the tolerances applicable to all parameters. Similarly, consideration should be given to permissible tolerances on repeatability of measurement readings. M8.2.3 Witnessing duties The witnessing agent should: A specific period of time for client witnessing should be indicated in the initial project programme, with a written contingency allowance. M8.2.2 M8.3 BMS to (a) a description of the building, including its intended use (b) a schedule of the floor areas of each zone categorised by environmental service type (c) the purpose of the individual building services systems (d) the location of the relevant plant and equipment (e) the installed capacities (input power and output rating) of the services plant (f) simple descriptions of the operational and control strategies of the energy consuming services 10 Commissioning management It should be noted that under Part L of the Building Regulations(1) there is a requirement for demonstrations to be planned and witnessed. M8.2 Witnessing arrangements M8.2.1 Witnessing period In deciding the detailed requirements for witnessing commissioning, the interaction of various aspects of an installation in determining its overall performance must be borne in mind. For example, the commissioning of a water distribution system might be witnessed against the requirements of CIBSE Commissioning Code W(29) and the project specification. However, witnessing the performance of heat exchangers connected to the water distribution systems would interact with the commissioning of air distribution and automatic control systems as well as of boiler and refrigeration plant. Witnessing is thus an all-embracing and interactive task and this must be reflected in the agreed written format. Particular arrangements for witnessing The following are essential arrangements for witnessing: (a) the provision of a definitive statement of the site attendance availability of the witnessing agent (b) the standards required (c) the extent of witnessing which will be performed (d) additional requirements in the event of defaults (e.g. the number of additional items which must be witnessed for every one which fails to comply). M8.2.4 (a) be satisfied that, throughout the installation and balancing process, the requirements of the commissioning specification and the appropriate commissioning code have been met (b) check the flow rate at any selected flow measurement point using a similar instrument and compare with the data recorded by the commissioning engineer and with the designer’s requirements, which should include any permitted tolerance (c) check performance of all plant and systems (d) visually inspect any part of the system covered by this section to ensure that certification is correct (e) countersign and endorse as necessary the certificate of the appointed commissioning specialist verifying that systems have been balanced in accordance with the specification requirements (f) where required, complete a separate witnessing certificate confirming satisfaction, one copy of which is handed to the commissioning specialist (g) check correct operation of the control system (h) check the correct operation of life safety systems. (a) the means to be used to demonstrate that fluid mass or volume flow rates are within the specified tolerances (b) co-ordination requirements where the performance aspects to be witnessed interact with other systems or equipment the running and monitoring period of the prove its functionality. M9 Building log book In accordance with Building Regulations Approved Document L2(3), the owner/occupier ‘should be provided with a log book giving details of the installed building services plant and controls, their method of operation and maintenance, and other details that collectively enable energy consumption to be monitored and controlled.’ The requirement to produce a building log book needs to be set out in the design specification. Responsibility for its preparation and for ensuring its completion by a specified period within the contract programme should be included in the commissioning specification. The CMO is well placed to ensure that a satisfactory building log book, that complies with the requirements of Part L of the Building Regulations(1). The contents of a building log book could include: Witnessing liaison The witnessing agent should liaise in detail with the installer and the commissioning specialist, as necessary, with regard to: (c) Witnessing duties may be undertaken by the CMO or other organisation appointed by the client. Witnessing requirements All requirements for witnessing should be expressed in an agreed written format, copies of which should be made available to the commissioning specialist. This format must contain full details of the tolerances applicable to all parameters. Similarly, consideration should be given to permissible tolerances on repeatability of measurement readings. M8.2.3 Witnessing duties The witnessing agent should: A specific period of time for client witnessing should be indicated in the initial project programme, with a written contingency allowance. M8.2.2 M8.3 BMS to (a) a description of the building, including its intended use (b) a schedule of the floor areas of each zone categorised by environmental service type (c) the purpose of the individual building services systems (d) the location of the relevant plant and equipment (e) the installed capacities (input power and output rating) of the services plant (f) simple descriptions of the operational and control strategies of the energy consuming services Building log book (g) a copy of the report confirming that the building services have been satisfactorily commissioned (h) operating and maintenance instructions including provisions enabling the specified performance to be sustained during occupation (i) 11 References 1 Building Regulations 2000 Statutory Instruments 2000 No. 440 as amended by the Building (Amendment) Regulations 2001 Statutory Instruments 2001 No. 3335 (London: The Stationery Office) (2000/2001) a schedule of building’s energy supply meters including fuel type, location, identification and description 2 Conservation of fuel and power in dwellings Building Regulations 2000 Approved Document L1 (London: The Stationery Office) (2001) (j) a design assessment of the carbon emissions and comparable performance benchmarks 3 Conservation of fuel and power in buildings other than dwellings Building Regulations 2000 Approved Document L2 (London: Stationery Office) (2001) (k) the measured air permeability of the building. 4 Environmental design CIBSE Guide A (London: Chartered Institution of Building Services Engineers) (1999) 5 Commissioning of HVAC systems — division of responsibilities BSRIA TM1/88 (Bracknell: Building Services Research and Information Association) (1988) System handover is the point where, to all intents and purposes, the engineering systems are determined to be complete and ready for the client. Once completion has been certified, the client takes over responsibility for the systems. 6 Construction (Design and Management) Regulations 1994 Statutory Instruments 1994 No. 3140 (London: The Stationery Office) (1994) 7 Health and Safety at Work etc. Act 1974 (London: The Stationery Office) (1974) The CMO can play a key role at this stage by co-ordinating the activities needed to be achieved to reach this point, in accordance with the commissioning programme. The careful planning, organisation, co-ordination and control of the commissioning activities alongside other project processes are the key functions of the CMO. This role has been identified as an essential function that needs to be made the specific responsibility of a designated party, e.g. the CMO, to ensure certainty of delivery of the project, particularly where it is large and complex. 8 Management of Health and Safety at Work Regulations 1999 Statutory Instruments 1999 No. 3242 (London: Her Majesty’s Stationery Office) (1999) 9 Construction (Head Protection) Regulations 1989 Statutory Instrument 1989 No. 2209 (London: The Stationery Office) (1989) 10 Construction (Health, Safety and Welfare) Regulations 1996 Statutory Instruments 1996 No. 1592 (London: The Stationery Office) (1996) 11 Confined Spaces Regulations 1997 Statutory Instruments 1997 No. 1713 (London: The Stationery Office) (1997) 12 Workplace (Health, Safety and Welfare) Regulations 1992 Statutory Instruments 1992 No. 3004 (London: The Stationery Office) (1992) 13 Working Time Regulations 1999 Statutory Instruments 1999 No. 3372 (London: The Stationery Office) (1999) 14 Electricity at Work Regulations 1989 Statutory Instruments 1989 No. 635 (London: The Stationery Office) (1989) 15 Gas Safety (Installation and Use) Regulations 1994 Statutory Instruments 1994 No. 1886 (London: The Stationery Office) (1994) 16 Personal Protective Equipment at Work Regulations 1992 Statutory Instruments 1992 No. 2966 (London: The Stationery Office) (1992) 17 Health and Safety (Display Screen Equipment) Regulations 1992 Statutory Instruments 1992 No. 2792 (London: The Stationery Office) 18 Provision and Use of Equipment at Work Regulations 1998 Statutory Instruments 1998 No. 2306 (London: The Stationery Office) (1998) 19 Pressure Systems Safety Regulations 2000 Statutory Instruments 2000 No. 128 (London: The Stationery Office) (2000) M10 System handover The CMO may also co-ordinate the training of client and other personnel in the operation and maintenance of the installed systems as part of the handover process. It has been found beneficial to support this with a report to the client on the effectiveness of the training provided. A further role of the CMO, which has been found to be beneficial to the client, is for the CMO to maintain a presence on site for a period (e.g. six months) after handover, possibly on a part time basis. This is to resolve any issues which may arise after handover and to provide a focal point to ensure liaison continues to take place between all parties involved in the construction process Detailed information on responsibilities of parties during the handover process are given in BSRIA TN15/95: Handover information for building services(30). After handover there are several areas where a CMO can be called upon. Examples include: — recommissioning of the building services during subsequent stages of the life of the building — following major changes or adaptations — periodic validation of control system settings, particularly where occupation or use has changed 20 Noise at Work Regulations 1989 Statutory Instruments 1989 No. 1790 (London: The Stationery Office) (1999) — periodic building checks as required 21 — decommissioning of the building or specific services Notification of Cooling Towers and Evaporative Condensers Regulations 1992 Statutory Instruments 1992 No. 2225 (London: The Stationery Office) (1992) 22 — mothballing the building prior to a period when the building is out of use. Control of Substances Hazardous to Health Regulations 1999 Statutory Instruments 1999 No. 437 (London: The Stationery Office) (1999) Building log book (g) a copy of the report confirming that the building services have been satisfactorily commissioned (h) operating and maintenance instructions including provisions enabling the specified performance to be sustained during occupation (i) 11 References 1 Building Regulations 2000 Statutory Instruments 2000 No. 440 as amended by the Building (Amendment) Regulations 2001 Statutory Instruments 2001 No. 3335 (London: The Stationery Office) (2000/2001) a schedule of building’s energy supply meters including fuel type, location, identification and description 2 Conservation of fuel and power in dwellings Building Regulations 2000 Approved Document L1 (London: The Stationery Office) (2001) (j) a design assessment of the carbon emissions and comparable performance benchmarks 3 Conservation of fuel and power in buildings other than dwellings Building Regulations 2000 Approved Document L2 (London: Stationery Office) (2001) (k) the measured air permeability of the building. 4 Environmental design CIBSE Guide A (London: Chartered Institution of Building Services Engineers) (1999) 5 Commissioning of HVAC systems — division of responsibilities BSRIA TM1/88 (Bracknell: Building Services Research and Information Association) (1988) System handover is the point where, to all intents and purposes, the engineering systems are determined to be complete and ready for the client. Once completion has been certified, the client takes over responsibility for the systems. 6 Construction (Design and Management) Regulations 1994 Statutory Instruments 1994 No. 3140 (London: The Stationery Office) (1994) 7 Health and Safety at Work etc. Act 1974 (London: The Stationery Office) (1974) The CMO can play a key role at this stage by co-ordinating the activities needed to be achieved to reach this point, in accordance with the commissioning programme. The careful planning, organisation, co-ordination and control of the commissioning activities alongside other project processes are the key functions of the CMO. This role has been identified as an essential function that needs to be made the specific responsibility of a designated party, e.g. the CMO, to ensure certainty of delivery of the project, particularly where it is large and complex. 8 Management of Health and Safety at Work Regulations 1999 Statutory Instruments 1999 No. 3242 (London: Her Majesty’s Stationery Office) (1999) 9 Construction (Head Protection) Regulations 1989 Statutory Instrument 1989 No. 2209 (London: The Stationery Office) (1989) 10 Construction (Health, Safety and Welfare) Regulations 1996 Statutory Instruments 1996 No. 1592 (London: The Stationery Office) (1996) 11 Confined Spaces Regulations 1997 Statutory Instruments 1997 No. 1713 (London: The Stationery Office) (1997) 12 Workplace (Health, Safety and Welfare) Regulations 1992 Statutory Instruments 1992 No. 3004 (London: The Stationery Office) (1992) 13 Working Time Regulations 1999 Statutory Instruments 1999 No. 3372 (London: The Stationery Office) (1999) 14 Electricity at Work Regulations 1989 Statutory Instruments 1989 No. 635 (London: The Stationery Office) (1989) 15 Gas Safety (Installation and Use) Regulations 1994 Statutory Instruments 1994 No. 1886 (London: The Stationery Office) (1994) 16 Personal Protective Equipment at Work Regulations 1992 Statutory Instruments 1992 No. 2966 (London: The Stationery Office) (1992) 17 Health and Safety (Display Screen Equipment) Regulations 1992 Statutory Instruments 1992 No. 2792 (London: The Stationery Office) 18 Provision and Use of Equipment at Work Regulations 1998 Statutory Instruments 1998 No. 2306 (London: The Stationery Office) (1998) 19 Pressure Systems Safety Regulations 2000 Statutory Instruments 2000 No. 128 (London: The Stationery Office) (2000) M10 System handover The CMO may also co-ordinate the training of client and other personnel in the operation and maintenance of the installed systems as part of the handover process. It has been found beneficial to support this with a report to the client on the effectiveness of the training provided. A further role of the CMO, which has been found to be beneficial to the client, is for the CMO to maintain a presence on site for a period (e.g. six months) after handover, possibly on a part time basis. This is to resolve any issues which may arise after handover and to provide a focal point to ensure liaison continues to take place between all parties involved in the construction process Detailed information on responsibilities of parties during the handover process are given in BSRIA TN15/95: Handover information for building services(30). After handover there are several areas where a CMO can be called upon. Examples include: — recommissioning of the building services during subsequent stages of the life of the building — following major changes or adaptations — periodic validation of control system settings, particularly where occupation or use has changed 20 Noise at Work Regulations 1989 Statutory Instruments 1989 No. 1790 (London: The Stationery Office) (1999) — periodic building checks as required 21 — decommissioning of the building or specific services Notification of Cooling Towers and Evaporative Condensers Regulations 1992 Statutory Instruments 1992 No. 2225 (London: The Stationery Office) (1992) 22 — mothballing the building prior to a period when the building is out of use. Control of Substances Hazardous to Health Regulations 1999 Statutory Instruments 1999 No. 437 (London: The Stationery Office) (1999) Building log book (g) a copy of the report confirming that the building services have been satisfactorily commissioned (h) operating and maintenance instructions including provisions enabling the specified performance to be sustained during occupation (i) 11 References 1 Building Regulations 2000 Statutory Instruments 2000 No. 440 as amended by the Building (Amendment) Regulations 2001 Statutory Instruments 2001 No. 3335 (London: The Stationery Office) (2000/2001) a schedule of building’s energy supply meters including fuel type, location, identification and description 2 Conservation of fuel and power in dwellings Building Regulations 2000 Approved Document L1 (London: The Stationery Office) (2001) (j) a design assessment of the carbon emissions and comparable performance benchmarks 3 Conservation of fuel and power in buildings other than dwellings Building Regulations 2000 Approved Document L2 (London: Stationery Office) (2001) (k) the measured air permeability of the building. 4 Environmental design CIBSE Guide A (London: Chartered Institution of Building Services Engineers) (1999) 5 Commissioning of HVAC systems — division of responsibilities BSRIA TM1/88 (Bracknell: Building Services Research and Information Association) (1988) System handover is the point where, to all intents and purposes, the engineering systems are determined to be complete and ready for the client. Once completion has been certified, the client takes over responsibility for the systems. 6 Construction (Design and Management) Regulations 1994 Statutory Instruments 1994 No. 3140 (London: The Stationery Office) (1994) 7 Health and Safety at Work etc. Act 1974 (London: The Stationery Office) (1974) The CMO can play a key role at this stage by co-ordinating the activities needed to be achieved to reach this point, in accordance with the commissioning programme. The careful planning, organisation, co-ordination and control of the commissioning activities alongside other project processes are the key functions of the CMO. This role has been identified as an essential function that needs to be made the specific responsibility of a designated party, e.g. the CMO, to ensure certainty of delivery of the project, particularly where it is large and complex. 8 Management of Health and Safety at Work Regulations 1999 Statutory Instruments 1999 No. 3242 (London: Her Majesty’s Stationery Office) (1999) 9 Construction (Head Protection) Regulations 1989 Statutory Instrument 1989 No. 2209 (London: The Stationery Office) (1989) 10 Construction (Health, Safety and Welfare) Regulations 1996 Statutory Instruments 1996 No. 1592 (London: The Stationery Office) (1996) 11 Confined Spaces Regulations 1997 Statutory Instruments 1997 No. 1713 (London: The Stationery Office) (1997) 12 Workplace (Health, Safety and Welfare) Regulations 1992 Statutory Instruments 1992 No. 3004 (London: The Stationery Office) (1992) 13 Working Time Regulations 1999 Statutory Instruments 1999 No. 3372 (London: The Stationery Office) (1999) 14 Electricity at Work Regulations 1989 Statutory Instruments 1989 No. 635 (London: The Stationery Office) (1989) 15 Gas Safety (Installation and Use) Regulations 1994 Statutory Instruments 1994 No. 1886 (London: The Stationery Office) (1994) 16 Personal Protective Equipment at Work Regulations 1992 Statutory Instruments 1992 No. 2966 (London: The Stationery Office) (1992) 17 Health and Safety (Display Screen Equipment) Regulations 1992 Statutory Instruments 1992 No. 2792 (London: The Stationery Office) 18 Provision and Use of Equipment at Work Regulations 1998 Statutory Instruments 1998 No. 2306 (London: The Stationery Office) (1998) 19 Pressure Systems Safety Regulations 2000 Statutory Instruments 2000 No. 128 (London: The Stationery Office) (2000) M10 System handover The CMO may also co-ordinate the training of client and other personnel in the operation and maintenance of the installed systems as part of the handover process. It has been found beneficial to support this with a report to the client on the effectiveness of the training provided. A further role of the CMO, which has been found to be beneficial to the client, is for the CMO to maintain a presence on site for a period (e.g. six months) after handover, possibly on a part time basis. This is to resolve any issues which may arise after handover and to provide a focal point to ensure liaison continues to take place between all parties involved in the construction process Detailed information on responsibilities of parties during the handover process are given in BSRIA TN15/95: Handover information for building services(30). After handover there are several areas where a CMO can be called upon. Examples include: — recommissioning of the building services during subsequent stages of the life of the building — following major changes or adaptations — periodic validation of control system settings, particularly where occupation or use has changed 20 Noise at Work Regulations 1989 Statutory Instruments 1989 No. 1790 (London: The Stationery Office) (1999) — periodic building checks as required 21 — decommissioning of the building or specific services Notification of Cooling Towers and Evaporative Condensers Regulations 1992 Statutory Instruments 1992 No. 2225 (London: The Stationery Office) (1992) 22 — mothballing the building prior to a period when the building is out of use. Control of Substances Hazardous to Health Regulations 1999 Statutory Instruments 1999 No. 437 (London: The Stationery Office) (1999) 12 Commissioning management 23 Water Supply (Water Fittings) Regulations 1999 Statutory Instruments 1999 No. 1148 (London: The Stationery Office) (1999) 35 Commissioning of water systems in buildings BSRIA AG2/89.2 (Bracknell: Building Services Research and Information Association) (1998) 24 Automatic control systems CIBSE Commissioning Code C (London: Chartered Institution of Building Services Engineers) (2001) 36 Commissioning of air systems in buildings BSRIA AG3/89.2 (Bracknell: Building Services Research and Information Association) (1998) 25 Dicks M Commissioning Management: How to achieve a fully functioning building BSRIA AG 5/2002 (Bracknell: Building Services Research and Information Association) (2002) 37 Commissioning of pipework systems — design considerations BSRIA AG20/95 (Bracknell: Building Services Research and Information Association) (1996) 26 Specification for sheet metal ductwork — low, medium and high pressure/velocity systems HVCA DW/144 (London: Heating and Ventilating Contractors Association) (1998) 38 Commissioning of VAV systems in buildings BSRIA AG1/91 (Bracknell: Building Services Research and Information Association) (1991) 27 Guide to good practice — internal cleanliness of new ductwork installations HVCA TM2 (London: Heating and Ventilating Contractors Association) (1991) 39 Pre-commissioning cleaning of water systems BSRIA AG 8/91 (Bracknell: Building Services Research and Information Association) (1991) 28 Cleanliness of ventilation systems — guide to good practice HVCA TR17 (London: Heating and Ventilating Contractors Association) (1998) 40 White water balancing CSA Guidance Note GN/1 (Horsham: Commissioning Specialists Association) 29 Water distribution systems CIBSE Commissioning Code W (London: Chartered Institution of Building Services Engineers) (2003) 41 Automatic balancing devices CSA Guidance Note GN/2 (Horsham: Commissioning Specialists Association) 42 Variable volume water systems CSA Guidance Note GN/3 (Horsham: Commissioning Specialists Association) 43 Bacteria within closed circuit/pipework systems CSA Guidance Note GN/4 (Horsham: Commissioning Specialists Association) 44 Standard specification for the commissioning of mechanical engineering services installations for buildings CSA Technical Memorandum TM/1 (Horsham: Commissioning Specialists Association) 45 Health and safety legislation affecting commissioning CSA Technical Memorandum TM/5 (Horsham: Commissioning Specialists Association) 46 Water treatment and the commissioning engineer CSA Technical Memorandum TM/9 (Horsham: Commissioning Specialists Association) 30 Handover information for building services BSRIA TN15/95 (Bracknell: Building Services Research and Information Association) (1995) 31 Air distribution systems CIBSE Commissioning Code A (London: Chartered Institution of Building Services Engineers) (2002) 32 Boilers CIBSE Commissioning Code B (London: Chartered Institution of Building Services Engineers) (2002) 33 Lighting CIBSE Commissioning Code L (London: Chartered Institution of Building Services Engineers) (2003) 34 Refrigerating systems CIBSE Commissioning Code R (London: Chartered Institution of Building Services Engineers) (2002) Appendix MA1: Guidance documents on commissioning specific building services 13 Appendix MA1: Guidance documents on commissioning specific building services CIBSE Commissioning Codes: — Code A: Air distribution systems(31) — AG8/91: Pre-commission cleaning of water systems(39) — AG5/2002: Commissioning management — how to achieve a fully functioning building(24) Boilers(32) — Code B: — Code C: Automatic controls(25) — Code L: Lighting(33) — Code R: Refrigerating systems(34) — GN/1: White water balancing(40) — Code W: Water distribution systems(29) — GN/2: Automatic balancing devices(41) — GN/3: Variable volume water systems(42) — GN/4: Bacteria within closed circuit/pipework systems(43) The Commissioning Specialists Association publishes the following Guidance Notes and Technical Memoranda: Further commissioning guidance is provided in the following BSRIA publications: — AG2/89.2: The commissioning of water systems in buildings(35) — — AG3/89.2: The commissioning of air systems in buildings(36) TM/1: Standard specification for commissioning and commissioning management(44) — TM1/88: Commissioning responsibilities(5) TM/5: Health and safety legislation affecting commissioning(45) — TM/9: Water treatment and the commissioning engineer(46) — HVAC systems — division of — AG20/95: Commissioning of pipework systems — design considerations(37) — AG1/91: Commissioning of VAV systems in buildings(38) The scope and relationships between these various publications is set out in Table MA1. Table MA1.1 Building services commissioning: summary of codes and guidance Subject Publication title Commissioning management CIBSE Commissioning Code M: Commissioning management BSRIA AG5/2002: Commissioning management — how to achieve a fully functioning building(24) CSA TM/1: Standard specification for commissioning and commissioning management(44) CSA TM/5: Health and safety legislation affecting commissioning(45) Air systems CIBSE Commissioning Code A: Air distribution systems(31) BSRIA AG3/89.2: The commissioning of air systems in buildings(36) BSRIA TM1/88: Commissioning of HVAC systems — division of responsibilities(5) BSRIA AG1/91: Commissioning of VAV systems in buildings(38) Boilers CIBSE Commissioning Code B: Boilers(32) Controls CIBSE Commissioning Code C: Automatic controls(25) Lighting CIBSE Commissioning Code L: Lighting(33) Refrigeration CIBSE Commissioning Code R: Refrigerating systems(34) Water systems CIBSE Commissioning Code W: Water distribution systems(29) BSRIA AG8/91: Pre-commission cleaning of water systems(39) BSRIA AG20/95: Commissioning of pipework systems — design considerations(37) BSRIA AG2/89.2: The commissioning of water systems in buildings(35) CSA GN/1: White water balancing(40) CSA GN/2: Automatic balancing devices(41) CSA GN/3: Variable volume water systems(42) CSA GN/4: Bacteria within closed circuit/pipework systems(43) CSA TM/9: Water treatment and the commissioning engineer(46) 14 Commissioning management Appendix MA2: Example responsibility matrix Activity number Activity description Commissioning Building services management organisation contractor (BSC) (CMO) Action, and advise CE. Advise MC of any Coordinate any comments comments. from BSC and MC. Main contractor (MC) Consulting engineer (CE) 1 Review design drawings and specifications for commissioning requirements. 2 Review installation drawings and technical submissions from BSC for commissioning requirements. 3 Review installations with Supervise inspection of respect to compliance with installations, and issue specifications and drawing reports to MC. intent for commissioning. 4 Production of detailed Procure information from Submit information, and coordinated commission- BSC. Prepare programme, liaise with CMO. ing programme, including discuss with MC, and issue revisions and updating. to all parties for comment. 5 Production of detailed Guide and assist in their Discuss format and Receive, review and commissioning method production. Review and content with CMO. Produce approve. Liaise with statements, including pre- accept content. Liaise with method statements. CE/CMO. commissioning, setting to MC/CE. work, and interface tests. Review, comment and accept. 6 Testing and preProcure procedures from commissioning, including BSC and suppliers for off-site works testing. (As approval. Witness and requested) validate tests and results. Review/comment and approve. Carry out spot checks. Review, comment and accept. Spot check as required. 7 Production of project specific test sheets. Prepare and issue pro Liaise with CMO. forma sheets, including interface and performance tests. Receive, review and approve. Review, comment and accept. 8 Monitor and report on commissioning progress. Prepare spreadsheets to be Assist CMO during used to monitor all monitoring process. progress. Issue and update at regular intervals. Receive and review reports, Review and comment. and circulate. Monitor progress, and manage any programme changes. 9 Progressive installation Monitor, witness, and Implement testing, prepare Monitor progress. Carry tests and pre-commission. ensure accurate recording records, and demonstrate. out spot checks. of all results, in accordance with method statements. Review, comment and accept. Spot checks as required. 10 Pipework system flushing, Monitor, witness, and Implement activities, cleaning and dosing. ensure accurate recording prepare records, and issue of all results, in accordance analysis reports. with method statements. Monitor progress. Carry out spot checks. Review, comment and accept. Spot checks as required. 11 Setting to work of plant and systems, commissioning and performance testing in accordance with programme. Monitor progress. Witness Carry out spot checks, and as required. witness activities on a selective basis. 12 Prepare testing and Action and submit to MC. commissioning reports, incorporating all plant and system test results. Liaise with MC and supply Monitor progress. Issue all relevant documendirectives/instructions to tation. Action adjustments BSC as appropriate. to system performance as advised or instructed by MC. Review, comment, and accept. Issue directives to MC as appropriate. 13 Prepare ‘models’ for record documents/drawings, and O&M manual format. Statutory demonstrations Monitor preparation, and comment on submissions via MC. Manage and coordinate the demonstration of all life safety systems as required, to the statutory authorities. Submit information, and liaise with CMO. Monitor progress. Liaise with client. Issue directives to BSC as appropriate. Monitor progress. Attend demonstrations. Review, comment and accept. Prepare final record documents Receive, collate, and com- Submit record documents ment on submissions by for approval, and liaise BSC. Advise on CDM issues. with MC. Update to suit comments. Issue to client, and coordinate all comments with BSC. Review, comment and accept. 14 15 Action, and advise MC/CE. Direct BSC, giving guidance as necessary. Witness activities, and ensure accurate recording of results. Liaise and assist all parties. Review comments and action as appropriate. Prepare and submit for Coordinate, supervise and review. Action any direct/instruct as comments as instructed by appropriate. MC. Receive CMO reports, and action as necessary. Submit information and liaise with CMO. Complete outstanding works schedules. Execute all planned activities. Demonstrate selected items to MC/CE as directed. Execute all planned activities in conjunction with the MC. Review, comment and issue directives to MC if applicable. Coordinate, supervise, and Review, comment and direct/instruct as issue directives to MC if appropriate. applicable. Review programme with Review, comment and regard to impact on accept. construction process. Issue comments and approve. Review, comment and attend demonstrations. Appendix MA2: Example responsibility matrix Activity number Activity description 16 Client/end user awareness and liaison 17 Client/end user training programme. Commissioning management organisation (CMO) Coordinate activities, and advise the client of all potential operational implications. Coordinate and manage BSC contractual obligations. Prepare programme. 15 Building services contractor (BSC) Main contractor (MC) Consulting engineer (CE) Liaise with MC, and be responsive to the client/end user’s needs. Liaise with the client/end user. Monitor status. Liaise with CMO. Coordinate the activities of specialist suppliers. Monitor progress and participate. Liaise with client/end user. Review, comment and accept. Participate as required. 16 Commissioning management Appendix MA3: Designer’s checklist for commissionability The following checklist is applicable to all sizes of installations: (a) Has the appointment of a CMO been considered? (b) Has the appointment of a commissioning specialist been considered? (c) Can the system be commissioned in accordance with the specification and CIBSE Commissioning Codes? (d) Can the installed services be adequately and safely maintained after handover? (e) Have validation checks at manufacturers’ works been allowed for on the major plant items? (f) Have patented systems been checked or tested rather than assumed to be working? (g) Has sufficient detail design information been provided especially in respect of control regimes, including set-points, system flow rates and plant capacities? Issues which impinge upon the commissionability of building services systems include the following: (a) Appropriate control strategies and set points: control strategies must be appropriate for the building services systems and intended application. (b) Packaged systems: ideally, as much use as possible should be made of ‘packaged’ systems which use pre-configured and pre-commissioned control equipment and are suitable for use in the intended climatic conditions. (c) Interaction with existing or other control equipment: most instances of integration involve the use of gateways. It is important that any gateway is fully developed and appropriate for the intended control and/or monitoring application. The impact of the complexity and timescale of the integration on the overall commissioning process should be carefully considered. (d) Fire alarm system: any interaction with fire alarm systems will require the approval of a fire officer or building control officer. The overall impact of this on building occupation should be considered. In practice, most fire or building control officers will only accept interaction with an autonomous fire alarm system, i.e. where the fire alarm system continues to operate as normal should the integration with the building control system fail. (h) Is the specification definitive in its content of the commissioning responsibilities, acceptance criteria and tolerances? (i) Is the specification adequately detailed in respect of protection of plant and equipment during transportation, installation, commissioning and testing? (e) Has a feedback procedure been implemented to recognise and address design problems that manifest during commissioning and testing in order to prevent repetition on future projects? Sensor type and location: it is important that the correct type and accuracy of sensor is used for the intended application(10). Advice should be sought from sensor manufacturers concerning application and installation issues. (f) Access to control equipment: adequate access to control equipment must be provided. This should include access to field control devices which may be installed in control cabinets, air handling units and terminal devices. Adequate access should also be allowed for the checking and removal of sensors and actuators. (g) Adequate control system specification details: these are essential for the commissioning process. Further information on the necessary documentation are provided in CIBSE Commissioning Code C (25), section C3.2. (j) The following can simplify system commissioning. (a) provide correct design information to allow the selection of appropriate devices (b) design for self balancing wherever possible (c) balance pressure drops across sub-branches and terminal units (d) avoid using different terminal units on the same branch (e) use reverse return pipework layouts (f) use automatic balancing valves (g) use variable speed drives for fan and pump regulation where appropriate (h) use computer analysis to determine settings for pre-set valves. In addition to the above issues, which directly relate to control systems, it is essential that the building services systems are inherently controllable in terms of their fundamental design, sizing and commissioning. The commissioning of the control system can be simplified if the commissioning of the building services systems are simplified. Appendix MA4: Example certificate of readiness 17 Appendix MA4: Example certificate of readiness READY FOR EMPLOYER’S USE Certificate number: Job number: Project: Floor: Building: Zone area: System: Base shop drawing: Rev: Date: See attached A4-size copy of relevant part of drawing and system schematic Activity Checked 1 Water pipe hydraulic tests 2 Water pipe cleaned and treated 3 Duct pressure tests 4 Ductwork cleaned 5 Electrical cable insulation tests 6 Switchgear/starter functions 7 Air balance and volume checks 8 Water balance and volume checks 9 Base system pre-commissioning complete 10 Building automation system proved 11 Fire alarm system proved 12 Building security system proved 13 Commissioning complete (If necessary with simulated thermal conditions) 14 Architectural snagging complete 15 Mechanical snagging complete 16 Electrical snagging complete Date The system detailed in this certificate has been completed satisfactorily, tested in accordance with the inspection procedure attached and is ready for use for the purpose for which it was designed and as described in the contractual documents Remarks: Signed: for trade contractor Date: Signed: for consultant Date: Signed: for commissioning manager Date: INDEX Index Terms Section Links M3.3 6 MA3 16 Air leakage testing M6.2 8 Air systems M6.2 8 definition M0.6 2 design for commissionability M3.4 7 MA2 14 pre-commissioning M6.2 8 witnessing duties M8.3 10 M4.2 7 M7.3 9 M8.2 10 M2.1 5 M0.8 4 M10 11 M4.2 7 M7.3 9 M8.2 10 M0.1 1 M0.4 1–2 M0.7 4 M0.1 1 M0.4 1–2 M0.7 4 A Access B Balancing BMS (building management systems) BSRIA AG 5/2002: Commissioning management BSRIA TM 1/88: Commissioning HVAC systems: division of responsibilities BSRIA TN 15/95: Handover information for building services Building management systems (BMS) Building Regulations 2000: Approved Document L1 Building Regulations 2000: Approved Document L2 log books M9 10 witnessing M8.1 10 M6.2 8 Building services plant commissioning This page has been reformatted by Knovel to provide easier navigation. Index Terms Section Links M0.6 2 M0.7 4 air leakage tests M6.2 8 calibration M0.7 4 completion M0.6 2 M7.1 9 pressure tests M6.2 8 readiness for employer M7.2 9 MA3 15 static completion M7.1 9 witnessing M8.3 10 Change control mechanisms M4.1 7 Checklists M4.1 7 M6.2 8 MA2 14 M3.1 6 M6.3 9 M8.2 10 CIBSE Guide A: Environmental design M0.4 2 Cleaning M6.2 8 checklists MA2 14 definition M0.6 2 design for M3 6 C Calibration definition Calibration certificates Certificates CIBSE Commissioning Code C: Automatic controls CIBSE Commissioning Code W: Water distribution systems CMO— see Commissioning management organisation Commissionability MA2 14 M0.3 1 M0.6 2 M7 9 building services plant M6.2 8 definition M0.6 2 importance of M0.4 1–2 programming and co-ordination M4 7 M0.6 2 M7.1 9 M0.6 2 requirement for Commissionable system definition Commissioning Commissioning completion certificates Commissioning engineer definition This page has been reformatted by Knovel to provide easier navigation. Index Terms Commissioning management contractual relationship Section Links M0 1 M2.2 5–6 M2.3 6 definition M0.6 3 quality assurance M5 7–8 Commissioning management organisation definition M0.6 3 handover M10 11 log books M9 10 pre-commissioning M6.2 8 selection and appointment M2.2 5 witnessing duties M8.3 10 Commissioning manager M2.1 5 Commissioning plan M0.6 3 M5 8 M0 1 M4.1 7 M10 11 M8.1 9 M8.2 10 M0.6 3 M0.6 3 M4.2 7 MA2 14 M3.2 6 M3.4 6 Commissioning programmes witnessing Commissioning records — see Documentation Commissioning specialist definition Commissioning specification designers’ duties log books M9 10 witnessing duties M8.3 10 Communications M2.3 5–6 Completion certificates M0.6 2 M7.1 9 M1.1 4 Contract variations M4.1 7 Contractual relationships M2.2 5–6 M2.3 6 MA2 14 Commissioning timetable — see Commissioning plan; Commissioning programmes Construction (Design and Management) Regulations 1994 Control strategies This page has been reformatted by Knovel to provide easier navigation. Index Terms Section Links Control systems M6.3 9 commissioning specification M4.2 7 specification MA2 14 witnessing duties M8.3 10 M6.2 8 M6.2 8 M0.6 3 M3 6 see also Building management systems (BMS) Control valves D Dampers Design criteria definition Design for commissionability MA3 16 M3.2 6 Designers’ checklist MA2 14 Documentation M0.3 1 M0.7 4 contract variations M4.1 7 design M3.2 6 witnessing requirements M8.2 10 M6.2 8 M0.4 2 M0.6 3 M6.2 8 M0.6 3 Fire alarm systems MA2 14 Fire dampers M6.2 8 Flow measurement devices M6.2 8 Flow rates M6.2 8 M8.2 10 M8.3 10 M6.2 8 Designer definition see also Certificates; Checklists; Guidance documents Ductwork E Energy consumption Energy sources definition F Fans Fine tuning definition Flushing This page has been reformatted by Knovel to provide easier navigation. Index Terms Section Links Gateways MA2 14 Guidance documents MA1 13 M0.7 4 M10 11 Indoor environmental conditions M0.4 2 Inspections M5 G H Handover Health and safety — see Safety I 7–8 Installations definition M0.6 quality assurance M5 Isolating valves 3 7–8 M6.2 8 M0.6 3 L Leakage testing definition Legislation M1 4–5 Life safety — see Safety Log books M0.6 M9 3 10–11 M Maintenance manual definition Method statements Monitoring M0.6 3 M4.1 7 M6.1 8 M4.1 7 M7.3 9 M0.6 3 M0.6 3 O Operating levels definition Operation and maintenance manual definition This page has been reformatted by Knovel to provide easier navigation. Index Terms Section Links M6.2 8 MA2 14 M0.6 3 M4.2 7 M7.2 9 M0.6 3 M0.3 1 M4.2 7 M0.3 1 M6 8 checklists M6.2 8 control systems M6.3 9 definition M0.6 3 in commissioning specification M4.2 7 M6.2 8 M0.6 3 M4 7 M10 11 M6.2 8 P Packaged equipment Performance testing definition Phased completion Portable instrument definition Post-occupancy checks Pre-commissioning Pressure test certificates Pressure testing definition Programming and co-ordination Proportional balancing — see Balancing Pump flow rates Q Quality assurance M5 7–8 R Records — see Documentation Regulating valves M6.2 8 M0.6 3 M6.2 8 M0.8 4 MA4 16–17 M2.1 5 M5 8 M10 11 M3.2 6 M4.2 7 Regulation definition Reports pre-commissioning Responsibilities commissioning managers’ designers’ specification This page has been reformatted by Knovel to provide easier navigation. Index Terms Section Links Risk assessments M4.1 7 M6.1 8 S Safety M1 4–5 M4.1 7 designers’ duties M3.2 6 witnessing duties M8.3 10 MA2 14 definition M0.6 3 Smoke dampers M6.2 8 M0.6 3 M0.6 3 M7.1 9 M0.6 3 M0.7 4 M10 11 M0.6 4 M6.2 8 M0.6 3 M0.6 4 M0.7 4 M3.2 6 M8.2 10 M10 11 Valves M6.2 8 Venting M6.2 8 Sensors Setting to work Specification definition see also Commissioning specification Static completion definition Static completion certificates System definition see also Commissionable system definition System handover System proving definition T Test holes Test instrument definition Testing Tolerances Training V This page has been reformatted by Knovel to provide easier navigation. Index Terms Section Links Water systems M6.2 8 Witnessing M4.2 7 W M8 9–10 This page has been reformatted by Knovel to provide easier navigation.