PROBLEM 1 The following information was taken from the books of Maria Corporation: Month Utility Cost Machine Hour Labor Hours Jan 950 999 502 Feb 1,175 1,022 733 Mar 1,425 1,220 1,090 Apr 1,506 1,283 1,135 May 1,618 1,313 1,186 Jun 1,525 1,261 1,154 Jul 1,675 1,440 1,264 Aug 1,724 1,290 1,323 Sep 1,626 1,335 1,230 Oct 1,575 1,164 1,165 Nov 1,653 1,373 1,237 Dec 1,418 1,124 1,035 (1) Using Hi-Lo method determined the unit cost variable cost and total fixed using: (a) Machine hours (b) Labor Hours (2) Under method of least square and using the independent variable that best forecast the value of the dependent variable, determine how much utility cost will be incurred for the production that requires 1,380 machine hours and 1,250 Labor hours. (Note: use the independent variable that gives the higher coefficient of correlation (r)) ANSWER: A. MACHINE HOURS Machine Hours Variable Cost (b) = (1,675 - 950) / (1,440 - 999) Variable Cost = 1.6440 Fixed Costs (a) = 1,675 - (1.64 X 1,440) Fixed Costs = (692.347) B. Labor Hours Variable Cost (b) = (1,724 - 950) / (1,323 - 502) Variable Cost = 0.9428 Fixed Costs (a) = 1,724 - (0.94 X 1,323) Fixed Costs = 476.738 Fixed Variable Machine Hours (322.872) 1.467 Labor Hours 467.083 0.940 Utility cost budgeted for 1,250 LHrs Correlation 0.88 0.99 1,641.53 PROBLEM 2 Following are the three months incomplete cost of goods sold statement of Kulang Kulang Company: March April May Direct Material Beg 95,000 L 50,000 Add Net Purchases A 170,000 W Total available for use B M 200,000 Less Direct Material End C N X Direct Materials Used 150,000 O 140,000 Direct Labor D 175,000 Y Factory Overhead E P Z Total Manufacturing Cost 300,000 462,500 AA Add Work in Process Beg F Q 37,500 Total goods put into process G R BB Less Work in Process end H S 20,000 Cost of Goods Manufactured I 440,000 CC Add Finished Goods Beg 30,000 T 25,000 Total goods available for sale J 475,000 DD Less Finished Goods end K U 30,000 Cost of Goods Sold 300,000 V 332,500 Overhead is approximately equal to 50% of Labor Cost Answer: a) b) c) d) e) f) g) h) i) j) k) l) m) n) o) 135,000.00 230,000.00 80,000.00 100,000.00 50,000.00 20,000.00 320,000.00 15,000.00 305,000.00 335,000.00 35,000.00 80,000.00 250,000.00 50,000.00 200,000.00 p) 87,500.00 q) 15,000.00 r) 477,500.00 s) 37,500.00 t) 35,000.00 u) 25,000.00 v) 450,000.00 w) 150,000.00 x) 60,000.00 y) 120,000.00 z) 60,000.00 aa) 320,000.00 bb) 357,500.00 cc) 337,500.00 dd) 362,500.00 PROBLEM 3 A certain company incurred a total manufacturing cost of P130,000, distributed as follows: Direct Materials – P60,000, Direct Labor – P40,000, and factory overhead P30,000. At the end of the period it was determined that the work in process increased by P20,000, while the finished goods decreased by P8,000. How much would be the cost of goods sold for the period? ANSWER: TMC Inc WIP COGM Dec in FG COGS 130,000.00 (20,000.00) 110,000.00 8,000.00 118,000.00 PROBLEM 4 The cost of goods manufactured of XXX Corporation for the month was P105,000, while the raw materials used was P50,000. At the end of the month work in process decreased by P20,000, while finished goods increased by P15,000. Labor cost was determined to be 50% of raw materials used. How much would be the cost of goods sold and the factory overhead for the month? ANSWER: DL 25,000.00 FOH 10,000.00 TMC 85,000.00 Dec in WIP 20,000.00 COGM 105,000.00 Inc in FG (15,000.00) COGS 90,000.00 PROBLEM 5 The following information is provided by Maunlad Mfg. Corp.: COGM P Labor Cost FOH FG Beginning FG Ending COGS Raw Materials Used WIP end How much would be the costs of raw materials used? ANSWER: DM + DL + FOH + WIPB + WIPE COGM 300,000.00 100,000.00 50,000.00 80,000.00 60,000.00 470,000.00 375% WIPB 100% 75% WIPB WIPB 470,000 100,000 50,000 30,000 20,000 480,000 500% of WIP end 75% of WIP beginning PROBLEM 6 If the total manufacturing costs for the month is P142,000, while the finished goods beginning and ending were P20,000 and P12,000 respectively. How much would be the costs of Work in Process Beginning and Ending respectively, assuming cost of goods sold is P158,000 and that the work in process ending is 80% of the work in process beginning? ANSWER: total manufacturing cost work in process-b work in process-e cost of goods manufactured finished good-b finished good-e cost of goods sold 142000 40000 32000 150000 20000 -12000 158000 140000+20%=150000 100% 80% 32000=40000*80% 158000-8000 8000=20000-12000 PROBLEM 7 Following were the other overhead cost incurred by UR Corporation for the year ended 2014: 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr Volume of production 20,500.00 18,650.00 19,750.00 25,450.00 Supervisory salaries 102,499.00 99,076.50 101,111.50 111,656.50 Property tax and insurance 22,000.00 22,000.00 22,000.00 22,000.00 Maintenance 61,125.00 56,962.50 59,437.50 72,262.50 Supplies 76,982.50 70,757.25 74,458.75 93,639.25 Depreciation of buildings and equipment 50,000.00 50,000.00 50,000.00 50,000.00 Power 140,425.00 127,752.50 135,287.50 174,332.50 Light and heat 165,175.00 153,427.50 160,412.50 196,607.50 Total 618,206.50 579,976.25 602,707.75 720,498.25 Required: 1) Identify which of the cost items above are Fixed, Variable and Semi-Variable. 2) Using method of least square in separating Semi-Variable, determine how much of the total semi-variable cost is a) Fixed and b) Variable Cost per unit? 3) Under the method of least square, determine how much of the other overhead cost is applicable to production of 22,000 units. 4) Using High and Low method, how much other overhead cost will be applied to production of 22,500 units. ANSWER: 1. Supervisory salaries Property tax and insurance Maintenance Supplies Depreciation of buildings and equip. Power Lights and heat Volume of production Total Semivariable For Semi-Variable Cost b= a= For Total Overhead Cost b= a= Semivariable Fixed Semivariable Semivariable Fixed Variable Semivariable 20,500.00 405,781.50 18,650.00 19,750.00 25,450.00 380,223.75 395,420.25 474,165.75 13.815 122,574.00 20.665 194,574.000 Overhead Cost for the production of 22,000 units Y = 194,574 + 20.665X 649,204.000 Using Hi-Lo b= a= Budgeted Overhead Cost at 22,500 20.665 194,574.00 659,536.50 PROBLEM 8 : Downstream Manufacturing Company realized too late that it had made a mistake locating its controller’s office and its electronic data processing system in the basement. Because of the Typhoon, the Pasig River overflowed on May 2 and flooded the company’s basement. Electronic data storage was beyond retrieval, and the company had not provided off-site storage of data. Some of the paper printouts were located but were badly faded and only partially legible. On May 3, when the river subsided, company accountants were able to assemble the following factory-related data from the debris and from discussions with various knowledgeable personnel. Data about the following accounts were found: • Raw Material (includes indirect material) Inventory: Balance April 1 was P4,800. • Work in Process Inventory: Balance April 1 was P7,700. • Finished Goods Inventory: Balance April 30 was P6,600. • Total company payroll cost for April was P29,200. • Accounts payable balance April 30 was P18,000. • Indirect material used in April cost P5,800. • Other nonmaterial and non-labor overhead items for April totalled P2,500. Payroll records, kept at an across-town service center that processes the company’s payroll, showed that April’s direct labor amounted to P18,200 and represented 4,400 labor hours. Indirect factory labor amounted to P5,400 in April. The president’s office had a file copy of the production budget for the current year. It revealed that the predetermined manufacturing overhead application rate is based on planned annual direct labor hours of 50,400 and expected factory overhead of P151,200. Discussion with the factory superintendent indicated that only two jobs remained unfinished on April 30. Fortunately, the superintendent also had copies of the job cost sheets that showed a combined total of P2,400 of direct material and P4,500 of direct labor. The direct labor hours on these jobs totalled 1,072. Both of these jobs had been started during the current period. A badly faded copy of April’s Cost of Goods Manufactured and Sold schedule showed cost of goods manufactured was P48,000, and the April 1 Finished Goods Inventory was P8,400. The treasurer’s office files copies of paid invoices chronologically. All invoices are for raw material purchased on account. Examination of these files revealed that unpaid invoices on April 1 amounted to P6,100; P28,000 of purchases had been made during April; and P18,000 of unpaid invoices existed on April 30. 1. Calculate the cost of direct material used in April. 2. Calculate the cost of raw material issued in April. 3. Calculate the April 30 balance of Raw Material Inventory. 4. Determine the amount of under applied or over applied overhead for April. 5. What is the Cost of Goods Sold for April? ANSWER: Downstream Manufacturing Company Cost of Goods Sold Statement For the month of April 2016 Raw Material 4/1 Add Net Purchases Total Raw Materials Available for use Less Raw Materials 4/30 Raw Materials Used Less Indirect Materials Used Direct Materials Used Direct Labor Factory Overhead Applied Total Manufacturing Cost Add Work in Process 4/1 Total Goods put into process Less Work in Process 4/30 Cost of Goods Manufactured Add Finished Goods 4/1 Total Goods Available for Sale Less Finished Goods 4/30 Cost of Goods Sold Normal Add Under Applied FOH COGS - Actual 4,800.00 28,000.00 32,800.00 7,984.00 24,816.00 5,800.00 19,016.00 18,200.00 13,200.00 50,416.00 7,700.00 58,116.00 10,116.00 48,000.00 8,400.00 56,400.00 6,600.00 49,800.00 500.00 50,300.00 FOH - Rate IM IL OOH FOH - C 3.00 5,800.00 5,400.00 2,500 13,700.00 Under Applied 500.00 DM 2,400.00 DL 4,500.00 FOH - A 3,216.00 PROBLEM 9 Micro Corp. uses 1,000 units of Chip annually in its production. Order costs consist of P10 for placing a long-distance call to make the order and P40 for delivering the order by truck to the company warehouse. Each Chip costs P100, and the carrying costs are estimated at 15.625%. Required: 1. Compute the economic order quantity for Chip and the total order costs and carrying costs for the year. 2. Determine the best order quantity if Chip is purchased only in multiples of 25 units and that the storage space is limited to 100 units. (Round answers to the nearest whole Peso.) ANSWER: EOQ = 80 Ordering Costs = No. of orders X cost per order No. of orders = annual requirement / order size 12.5 Ordering Costs = 625 Carrying Costs = Average Invty X Carrying Cost per unit Average Invty = Order Size/2 + Safety Stocks 40 Carrying Costs = 625 Order Size No. of orders Average Invty. Total Carrying Costs Total Ordering Costs Total Ordering and Carrying Costs 25 50 75 100 40.00 12.5 20.00 25 13.33 37.5 10.00 50 195.31 390.63 585.94 781.25 2,000.00 1,000.00 666.67 500.00 2,195.31 1,390.63 1,252.60 1,281.25 PROBLEM 10 Ofilyang Company uses Material NGEE to produce NGAA. Inventory at the beginning of June 2012 was 400 units of NGEE, valued at P1.80 each. Further, receipts and issuances of NGEE during the month were as follows: Units Unit Cost June 8, receipts 500 P2.10 June 14, receipts 600 ? June 25, Issuance 1,250 The company uses moving average method of stock valuation. 1. If the average unit cost at the issuance date was P1.932. What was the cost per unit of the June 14, receipts? 2. Assuming the company uses FIFO perpetual method of stock valuation, and that the total cost of Material NGEE issued was P2,470. What will be the costs of the June 14, receipts? Stock Card Qty Received Unit Cost Amount Issued Qty Unit Cost Amount Qty Balance Unit Cost Amount 400 1.800 720 500 2.100 1050 900 1.967 1770 600 1.880 1,128.00 1500 1.932 2,898.00 1250 1.932 2,415.00 PROBLEM 11 Charleston Company has developed the following data to assist in controlling one of its inventory items: Economic order quantity ........................................................................ Average daily use ................................................................................... Maximum daily use................................................................................ Minimum daily use…………………………….. .................................. Working days per year ........................................................................... Cost of carrying inventory ..................................................................... Lead time ............................................................................................... 1000 100 120 50 250 P1.00 liters liters liters liters days per liter per year 7 working days Required: Compute the following: (1) Order point (OP) = Lead Time Usage (LTU) + Safety Stocks (SS) = 840 (2) Average inventory = Order Size (OS)/2 + SS = 1000/2 + 140 = 640 (3) Maximum inventory assuming normal lead time and usage/Normal Maximum Inventory = OP – LTU + OS = 840 – 700 + 1,000 = 1,140 (4) Cost of placing one order; using EOQ; P20 (5) Absolute Maximum Inventory = OP – (LT X Min Daily Use) + OS ; = 840 – (7 X 50) + 1,000 = 1,490 ANSWER: Safety Stock = 140 Leadtime usage = 700 Order Point 840 Average Invty = 640 Normal Maximum Inventory = 1140 Cost of placing one order = 20 Absolute Maximum Inventory = 1490 PROBLEM 12 Warner Co. uses 6,000 units of material per year at a cost of P4 per unit. Carrying costs are estimated to be P1.125 per unit per year, and order costs amount to P60 per order. As an incentive to its customers, Warner will extend quantity discounts according to the following schedule: Minimum Order 500 1,000 2,000 List Price P4 4 4 Discount 2% 4 6 Net Price P3.92 3.84 3.76 Required: (1) (2) (3) Determine the economic order quantity (800) (ignoring quantity discounts) and the total annual order cost, carrying cost, and materials costs at EOQ (considering quantity discounts). Compute the annual order cost, carrying cost, materials cost, and total cost at each discount level. (Round to the nearest peso.) Identify the order size, choosing from one of the three discount levels, that will minimize the total cost. ANSWER: EOQ = Ordering Costs Carrying Costs Material Cost/Costs of Purchases Total Cost 800 450 450 23520 24420 Order Size 500 No. of orders Average Invty. Total Carrying Costs Total Ordering Costs Total Material Costs 12.00 Total Costs 1000 6.00 250 2000 3.00 500 Cost per order Carrying cost per unit 60 1.125 1000 281.25 562.50 1,125.00 720.00 360.00 180.00 23,520.00 23,040.00 22,560.00 24,521.25 23,962.50 23,865.00 EOQ PROBLEM 13 The following data refer to various annual costs relating to the inventory of a single-product company: Unit transportation-in on purchases ............................................................................... Storage per unit............................................................................................ Insurance per unit ........................................................................................ Annual interest foregone from alternate investment of funds ..................... Annual number of units required ................................................................. What is the annual carrying cost per unit? ANSWER: P0.30 = (0.12 + 0.10 + 800/10,000) P .20 .12 .10 P 800.00 10,000 PROBLEM 14 The following information relates to Hudson Company's Material A: Annual usage in units .................................................................................. 7,200 Working days per year................................................................................. 240 Normal lead time in working days .............................................................. 20 Maximum lead time in working days .......................................................... 45 Assuming that the units of Material A will be required evenly throughout the year, the safety stock and order point would be: _750 : 1,350__. SS = 7,200/240 X (45 – 20) OP = LTU + SS = (7,200/240 X 20) + 750 ANSWER: Computation of Maximum Safety Stock Usage Variation Safety Stock = (Maximum Usage - Normal Usage) X Leadtime Normal = Average Leadtime Variation Safety Stock = (Maximum Leadtime - Normal Leadtime) X Daily(Normal) Usage Usage and Leadtime Variation Safety Stock = [(Max Usage - Normal Usage) X Leadtime] + [(Max Leadtime - Normal Leadtime) X Max Usage] 750 Order Point/Reorder Point = [daily usage X leadtime] + Safety Stocks 1350 PROBLEM 15 Penguin Company manufactures winter jackets. Setup costs are P2.00. Penguin manufactures 4,000 jackets evenly throughout the year. Using the economic order quantity approach, the optimal production run would be 200 when the cost of carrying one jacket in inventory for one year is: _____. ANSWER: 200 = \ 2 X 4,000 X 2 X PROBLEM 16 Leo Company manufactures specialized farming tools. Transactions and information related to inventory accounts for January 2017 were as follows: Materials Beginning Balance Part X 1,000 units @ P102.50 Part Y 500 units @ P50.25 Part Z 750 units @ P20.35 Leo applies EOQ in controlling the investment in its inventory. For the year 2017, Leo estimated that 40,000, 25,000 and 30,000 units respectively will be used for the years estimated production. The ordering costs which are normally incorporated to the final unit cost of the materials were estimated to be P250, P175, and P325 for Part X, Part Y and Part Z respectively, while carrying costs which is accounted as an expense was estimated 3%, 5% and 4% of the purchase price for Part X, Part Y and Part Z respectively. Other information related to materials were: Order Usage per Day Lead-Time (days) Size Min Normal Max Min Normal Max Part X 2,550 100 160 200 2 4 6 Part Y 1,850 75 100 125 1 3 5 Part Z 4,900 100 120 150 2 3 4 Work in Process Beginning Balance Job 309 Job 312 Job 313 Materials Part X 45 units 150 units 85 units Part Y 35 units 60 units 48 units Part Z 40 units 80 units 54 units Labor @ P45/hr P1,980 P2,340 P1,035 Overhead is applied at P50 per hour which is inclusive of P5 allowance for defects. Cost charged for the current month -----------------------Job Number---------------------------309 312 313 314 315 316 Materials in units Part X 555 550 615 700 430 350 Part Y 395 370 382 420 350 130 Part Z 80 40 66 120 100 70 Labor Hrs. 54 48 77 112 65 45 Prior to the completion of Job 314, due to a customer request a minor adjustment which requires an additional material for Part X and Part Z of 10 units and 15 units respectively and 3 hours of labors were made. While for Job 309, 312, and 313, 2% of the jobs were found defective and were considered spoiled from which recoverable amount is estimated at 80% of the total cost incurred. The defects on these jobs were due from power interruptions. At the end of the month Job 315 and Job 316 were still in process, while the remaining goods units from the completed jobs were delivered and billed to the customer at 50% above costs. Compute for the following: 1) Carrying Cost per unit and Total Purchase Price of Part X, Part Y and Part Z. (rounded to 3 decimal places) 2) Final Unit Costs of Part X, Part Y and Part Z. (rounded to 3 decimal places) 3) Cost of Direct Materials, Direct Labor, and Factory Overhead charged to work in process for the month. 4) Sales Value per completed Jobs. 5) Safety Stock and Reorder Point 6) Materials Inventory End Prepare the Journal entry for 7) Issuance of Materials 8) Costs of reworks 9) Spoiled Goods 1) Billing and Delivery ANSWER: Part X Part Y Part Z Part X Purchase Price Add Purchase Order Costs 102.525 51.132 20.304 0.098 0.095 0.066 Unit Costs 102.623 51.227 20.370 (2) Unit Carrying Cost 3.076 2.557 0.812 (1) Safety Stock 560.00 325.00 240.00 Reorder Point 1,200.00 625.00 600.00 102.631 Part X 555 550 615 700 430 350 3,200.00 Part Y 395 370 382 420 350 130 2,047.00 Part Z 80 40 66 120 100 70 476.00 Order Size Qty on Hand Materials end 1000 2,200.00 2550 350.00 2,890.00 102.623 296,580.47 500 1,547.00 1850 303.00 2,153.00 51.227 110,291.73 750 274.00 259.00 20.35 5,270.65 412,142.85 Purchase Price Part X 102.525 Part Y 51.132 Part Z 20.304 Part Z 102.533 51.140 20.300 0.098 0.095 0.066 Total Invty 1/1 Part Y 51.235 20.366 Qty Received 5,100.00 3,700.00 - Total Purchase Price 522,877.50 189,188.40 - (1) Total Issued From Beg Fro Purch. Direct Materials Reworks TMC 3,200.00 102,500.00 225,770.60 328,270.60 1,026.23 2,047.00 25,125.00 79,248.17 104,373.17 476.00 9,686.60 - 9,686.60 Part X Part Y Part Z Total 329,296.83 104,373.17 305.55 9,992.15 442,330.37 443,662.15 Direct Labor 18,045.00 135 18,180.00 Factory Overhead 19,490.00 135 19,625.00 Direct Materials Job 315 Job 316 Total Qty Total Costs Part X 430 350 780 80,045.94 Part Y 350 130 480 24,588.96 Part Z 100 70 170 3,459.50 Direct labor 4,950.00 FOH - A 5,500.00 Work in Process End 118,544.40 Sales Value Job 309 Job 312 Job 313 Job 314 Part X 61,500.00 71,762.92 71,825.65 72,862.33 Part Y 21,607.50 21,866.41 21,980.71 21,515.34 Part Z 2,442.00 2,442.00 2,442.00 2,747.25 Total Materials Labor Cost Factory Overhead Total manfacturing Costs 85,549.50 96,071.32 96,248.36 97,124.92 4410 4500 4500 5175 4900 5000 5000 5175 94,859.50 105,571.32 105,748.36 107,474.92 Less Spoiled 1,897.19 2,111.43 Final cost of completed 92,962.31 103,459.89 103,633.39 Add Markup 46,481.16 51,729.95 Total Sales Value 139,443.47 155,189.84 155,450.09 161,212.38 SGI FOH-C 1,517.75 379.44 WIP Accounts Receivable Sales Cost of Goods Sold Work in process 2,114.97 51,816.70 1,689.14 422.29 53,737.46 1,691.97 422.99 6,123.58 611,295.77 611,295.77 407,530.52 407,530.52 4,898.87 1,224.72 PROBLEM 17 On December 31, 2015 KTV Co., with outstanding share capital of P60,000 had the following assets and liabilities: Cash P 10,000 Accounts Receivable 20,000 Finished Goods 12,000 Work in Process 4,000 Materials P 8,000 Prepaid Expense 1,000 Property, Plant and Equipment 60,000 Current Liabilities 35,000 During 2016, the retained earnings account increased 50% as a result of the year’s business. No dividends were paid during the year. Balances of accounts receivable, prepaid expenses, current liabilities, and share capital were the same on December 31, 2016, as they had been on December 31, 2015.Inventories were reduced by exactly 50% except for finished goods inventory, which was reduced by 33 1/3%. Plant assets(net) were reduced by depreciation of P8,000, charged ¾ to factory overhead and ¼ to administrative expense. Sales of P120,000 were made on account, costing P76,000. Direct labor cost was P18,000, Factory overhead was applied at a rate of 100% of direct labor costs, leaving P4,000 underapplied that was closed to cost of goods sold account. Total marketing and administrative expenses amounted to 10% and 15% of gross sales respectively. Required: Prepare the statement of financial position and income statement with note showing details of cost of goods sold. ANSWER: 1. KTV Co. Statement of Financial Position As of the year ended December 31, 2016 Cash Accounts Receivable Inventories Prepaid Expenses Total Current Assets (3.00) Note - 1 Note - 2 38,000.00 20,000.00 14,000.00 1,000.00 73,000.00 Property, Plant and Equipment Total Assets 52,000.00 125,000.00 Current Liabilities Share Capital Retained Earnings 35,000.00 60,000.00 30,000.00 125,000.00 Note - 3 2. KTV Co. Income Statement For the year ended December 31, 2016 Net Sales Less Cost of Sales - actual Gross Profit Less Expenses Selling Administrative Net Income 120,000.00 80,000.00 40,000.00 12,000.00 18,000.00 30,000.00 10,000.00 Cost of Sales Materials 1/1 Add Purchases Total Materials available for use Less Materials 12/31 Direct materials used Direct Labor Factory Overhead Total Manufacturing Cost Add Work in process 1/1 Total Goods put into process Less Work in process 12/31 Cost of goods manufactured Add Finished Goods 1/1 Total Goods available for sales Less Finished Goods 12/31 Cost of Goods Sold Normal Add underapplied overhead Cost of goods sold actual Note 1 - Cash Collection Payments Purchases Direct Labor Factory Overhead - Control Selling Administrative Net increase in cash Cash Beginning Cash ending 8,000.00 30,000.00 38,000.00 4,000.00 34,000.00 18,000.00 18,000.00 70,000.00 4,000.00 74,000.00 2,000.00 72,000.00 12,000.00 84,000.00 8,000.00 76,000.00 4,000.00 80,000.00 120,000.00 30,000.00 18,000.00 16,000.00 12,000.00 16,000.00 92,000.00 28,000.00 10,000.00 38,000.00 PROBLEM 18 Argonne Rigging manufactures its product to customer specifications and uses a job order system. The processing of a unit of product requires the use of one pound Material AAA and ½ pound of Material BBB, and at completion about 2% of the materials used becomes a scrap and are normally sold to at P5 per pound. Recent order from Michaels Company was for 10,000 pulleys, and the job was assigned number 1001. Following are the transactions and other informations related to the job: Inventory of materials before the production process starts is consist of 500 pounds of Material AAA at P15 per pound and 125 pounds of Material BBB at P10 per pound. During the month the company acquired 10,100 pounds of Material AAA P15.50 per pound and 6,000 pounds of Material BBB at P9.75 per pound, freight cost incurred for the delivery was P3,248. Issued for production the required materials using FIFO and incurred labor cost of P160,000 of which P15,000 are indirect labor. Applied overhead at 150% of direct labor cost. Prior to the completion 2% of the units processed were found defective, of which 80% can be reworked by incurring additional labor cost of P5 per unit, and the remaining defective goods are sold as seconds at P35 per unit. Remaining good units after the reworks made were accepted by Michaels and these were billed at 75% profit on cost. Scrap materials were recovered and 70% of which were sold. Required: Prepare all necessary journal entries (round unit cost to 3 decimal places). ANSWER: Materials Accounts Payable 218,298.00 218,298.00 Work in Process Materials 206,470.88 Payroll Accrued Payroll 160,000.00 Work in Process Factory Overhead Control Payroll 145,000.00 Work In Process Factory Overhead Applied Charged to specific job/All production Work In Process/Factory Ovehead Control Payroll Factory Overhead Applied Charged to Specific job Spoiled Goods Inventory Work In Process Charged to All jobs Spoiled Goods Inventory Factory Overhead Control Work In Process 217,500.00 206,470.88 160,000.00 15,000.00 160,000.00 217,500.00 2,000.00 800.00 1,200.00 1,400.00 1,400.00 1,400.00 875.88 2,275.88 Scrap Materials (10,000 X 1.5 X 2% X P5) Work In Process/FOHC Cash Scrap Materials 1,500.00 1,500.00 1,050.00 1,050.00 Accounts Receivable Sales 994,124.03 Cost of Goods Sold Work in Process 568,070.88 Material AAA Material BBB Material AAA Material BBB 568,070.88 Purc. Cost Ratio 156,550.00 0.0151 58,500.00 0.0151 215,050.00 Freight Total 2,364.45 158,914.45 883.55 59,383.55 3,248.00 218,298.00 Beginning 7,500.00 1,250.00 Current Purch. 149,473.00 48,247.88 Material AAA Material BBB DM DL FOH Rework 994,124.03 Beginning Current Purch. Total 7,500.00 149,473.00 1,250.00 48,247.88 206,470.88 WIP - Specific Job 206,470.88 145,000.00 217,500.00 2,000.00 568,070.88 DM DL FOH Rework Total 156,973.00 49,497.88 206,470.88 156,973.00 49,497.88 1,400.00 Spoiled 1,500.00 Scrap Selling Price 994,124.03 Cost 568,070.88 Gross Margin 426,053.16 160,000.00 WIP - All Production 206,470.88 2,275.88 145,000.00 217,500.00 566,694.99 56.897 Unit Cost 15.734 9.897 991,716.24 TEST I - MULTIPLE CHOICE – PROBLEMS - Show all supporting computations, present it in good format. Boxed your final answer on your computation and indicate your letter choice in capital letter. (NO COMPUTATIONS, NO POINTS) (3 pts. Each) 1. The following costs relate to Antonietta Industries for the last quarter: Conversion cost ₱ 435,000 Direct materials 215,000 Manufacturing overhead 190,000 Selling and administrative expense 185,000 What is Antonietta’s prime cost for last quarter? A. ₱ 460,000 B. ₱ 410,000 C. ₱405,000 Conversion cost Manufacturing Overhead Direct Materials 435,000.00 (190,000.00) 215,000.00 Prime cost 2. 3. Antonietta’s total manufacturing cost is A. ₱ 460,000 B. ₱ 645,000 460,000.00 C. ₱650,000 435,000.00 215,000.00 Total manufacturing cost 650,000.00 Selling and administrative expenses A D. ₱840,000 Conversion cost Direct Materials Antonietta’s total period cost is A. ₱ 185,000 B. ₱ 275,000 D. ₱375,000 C. ₱400,000 C D. ₱620,000 185,000.00 A 4. Jasmine Co. produced 5,500 outdoor chairs for Job Order No. 610. Total material cost was ₱51,700. Each chair required 2.2 hours of direct labor at ₱8.90/hour. A total of ₱53,845 of factory overhead was traced to Order 610. What is the prime cost per unit of this order? A. ₱ 19.58 B. ₱ 28.98 C. ₱29.37 D. ₱38.77 Direct Labor 5,500 x 2.2 hrs x P8.90/hr Direct Materials 107,690.00 51,700.00 Prime cost Divided no. of chairs produced 159,390.00 5,500 Prime cost per unit 5. 28.98 B Using the information in No. 26, what is the conversion cost per unit of this order? A. ₱ 19.58 B. ₱ 28.98 C. ₱29.37 D. ₱38.77 Direct Labor 5,500 x 2.2 hrs x P8.90/hr Factory Overhead 107,690.00 53,845.00 Conversion cost Divided no. of chairs produced 161,535.00 5,500 Conversion cost per unit 29.37 C 6. Using No. 12 information, what is the unit cost of this order? A. ₱ 37.88 B. ₱ 38.77 C. ₱28.09 D. ₱36.99 Direct Labor 5,500 x 2.2 hrs x P8.90/hr Direct Materials Factory Overhead 107,690.00 51,700.00 53,845.00 Conversion cost Divided no. of chairs produced 213,235.00 5,500 Unit cost per order 38.77 B 7. The following cost data were taken from the records of JGG manufacturing company: Depreciation on factory equipment ₱ 1,000 Depreciation on sales office 500 Advertising 7,000 Freight out (shipping) 3,000 Wages of production workers 28,000 Raw materials used 47,000 Sales salaries and commissions 10,000 Factory rent 2,000 Factory insurance 500 Materials handling 1,500 Administrative salaries 2,000 Based upon this information, the manufacturing cost incurred during the year was: A. ₱ 18,500 B. ₱ 80,000 C. ₱ 80,500 D. ₱ 83,000 Depreciation on factory equipment ₱ 1,000 Wages of production workers 28,000 Raw materials used 47,000 Factory rent 2,000 Factory insurance 500 Materials handling 1,500 Manufacturing cost ₱ 80,000 B 8. Joy Corp. manufactures plastic coated metal clips. The following were among Joy’s 2014 manufacturing costs: Wages: Machine operators ₱200,000 Maintenance workers 30,000 Factory foreman 90,000 Materials used: Metal wire ₱500,000 Lubricant for oiling machinery 10,000 Plastic coating 380,000 In 2014, Joy’s direct labor and direct materials amounted to: Direct Labor Direct Materials Direct Labor Direct Materials A. ₱ 230,000 ₱ 510,000 C. ₱320,000 ₱880,000 B. 220,000 500,000 D. 200,000 880,000 Direct labor ₱200,000 Direct materials (₱500,000 + 380,000) 880,000 D TEST II – PROBLEM SOLVING Celsius Company manufactures a product that requires the use of a considerable amount of natural gas to heat it to a desired temperature. The process requires a constant level of heat, so the furnaces are maintained at a set temperature for 24 hours a day. Although units are not continuously processed, management desires that the variable cost be charged directly to the product and the fixed cost to the factory overhead. The following data have been collected for the year: Units Cost Units Cost January ………............ 2,400 ₱4,400 July……………………….. 2,200 ₱4,250 February……………….. 2,300 4,300 August………………….. 2,100 4,100 March…………………… 2,200 4,200 September……………. 2,000 3,950 April……………………… 2,000 4,000 October………………… 1,400 3,400 May……………………… 1,800 3,800 November…………….. 1,900 3,700 June……………………… 1,900 3,900 December…………….. 1,800 4,050 1. Separate the variable and fixed elements, using the high-low method. Compute for the variable cost per unit. 2. Determine the variable cost to be charged to the product for the year. (Hint: First determine the number of annual units produced) 3. Determine the fixed cost to be charged to factory overhead for the year. 1. High-low method High volume................................................................................... Low volume ................................................................................... Change ....................................................................................... Units 2,400 1,400 1,000units Variable cost per unit: ₱1,000 1,000 = ₱1.00 per unit 5 pts. Fixed cost 1,400 Units Total cost................................................................................. ₱ 3,400 Variable cost, $1.00 per unit ................................................... 1,400 Fixed cost ................................................................................ ₱ 2,000 Cost ₱ 4,400 3,400 ₱ 1,000 2,400 Units ₱ 4,400 2,400 ₱ 2,000 2. Variable cost charged to product: 24,000 units ₱1.00 per unit = ₱24,000. 5 pts. 3. Fixed cost charged to factory overhead: ₱2,000 per month 12 months = ₱24,000. 5 pts. 5 pts.