8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Term Test 1 Results for Omozojie Inetabor Score for this quiz: 66 out of 75 Submitted Jun 8 at 7:25p.m. This attempt took 120 minutes. Question 1 1 / 1 pts Within a sustainability framework, the economic dimension of the triple bottom line concept goes beyond just profit for the firm but also provides lasting economic benefit to society. Correct! true false Within a sustainability framework, this (economic) dimension goes beyond just profit for the firm but also provides lasting economic benefit to society. Within a sustainability framework, this (economic) dimension goes beyond just profit for the firm but also provides lasting economic benefit to society. Question 2 1 / 1 pts The nature of risks lends them to a three-step risk management process that can be applied to situations where disruptions are possible. There are three steps to the process. Which of the following is not one of those steps? Identify the sources of potential disruptions. https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 1/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Correct! Insure to protect against the risks. Assess the potential impact of the risk. Develop plans to mitigate the risk. This is discussed in the "Risk Management Framework" section. Insurance is not mentioned as one of the steps. This is discussed in the "Risk Management Framework" section. Insurance is not mentioned as one of the steps. 1 / 1 pts Question 3 You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project "direct costs" are given here. Activity Immediate Predecessor Normal Time Crash Time Normal Cost (Direct) Crash Cost (Direct) A None 3 2 $300 $400 B A 3 3 $100 $100 C A 1 1 $200 $200 D B and C 3 2 $400 $550 E D 2 1 $500 $900 F E 3 3 $200 $200 G F 2 2 $100 $100 The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. If you crash this project by one day, What is the total (i.e., direct and indirect) project cost? https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 2/49 8/12/22, 7:12 AM Correct! Omozojie Inetabor's Quiz History: Term Test 1 $2,150 $2,300 $2,400 $2,450 $2,500 The critical path is ABDEFG. The project duration is 3 + 3 + 3 + 2 + 3 + 2 = 16 days. The normal direct cost is $300 + $100 + $200 + $400 + $500 + $200 + $100 = $1,800. The indirect costs are an additional $400 for a total of $2,200. The only activities that can be crashed are A, D, and E. A costs $100/day to crash, D costs $150/day to crash, and E costs $400/day to crash. Reducing the duration of A by one day at an additional cost of $100 is the most economical. Direct costs are now $400 + $100 + $200 + $400 + $500 + $200 + $100 = $1,900. Overall duration of the project is 15 days, and indirect costs are $250. The total cost of crashing this project for one day is $2,150. The critical path is ABDEFG. The project duration is 3 + 3 + 3 + 2 + 3 + 2 = 16 days. The normal direct cost is $300 + $100 + $200 + $400 + $500 + $200 + $100 = $1,800. The indirect costs are an additional $400 for a total of $2,200. The only activities that can be crashed are A, D, and E. A costs $100/day to crash, D costs $150/day to crash, and E costs $400/day to crash. Reducing the duration of A by one day at an additional cost of $100 is the most economical. Direct costs are now $400 + $100 + $200 + $400 + $500 + $200 + $100 = $1,900. Overall duration of the project is 15 days, and indirect costs are $250. The total cost of crashing this project for one day is $2,150. Question 4 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 0 / 1 pts 3/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 The critical path in a CPM analysis is always the shortest path through the network. ou Answered true orrect Answer false The critical path of activities in a project is the sequence of activities that form the longest chain in terms of their time to complete. The critical path of activities in a project is the sequence of activities that form the longest chain in terms of their time to complete. 1 / 1 pts Question 5 A simple project listing of five activities, their predecessors, and their respective time estimates are presented here: Activity Immediate Predecessor Time in Days A None 2 B A 2 C A 1 D B and C 3 E D 1 Using the CPM, which activities have slack in this project? A B Correct! C https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 4/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 D C and E The critical path for this project is ABDE. Activity C has one day of slack in this project. The critical path for this project is ABDE. Activity C has one day of slack in this project. Question 6 1 / 1 pts You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values. What can you conclude? You have incorrectly performed the analysis. Correct! You have multiple critical paths. Only one path is optimal. More than one path is optimal. The project will not be completed by the desired time. https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 5/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 It is possible—and it often happens—that there are multiple paths of the same length through the network, so there are multiple critical paths. It is possible—and it often happens—that there are multiple paths of the same length through the network, so there are multiple critical paths. Question 7 0 / 1 pts A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for Activity D? ou Answered $0 − $5K orrect Answer $5.01K − $10K $10.01K − $15K $15.01K − $20K Over $20K https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 6/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 BCWS values are $19.8K, $11.2K, $8.4K, and $5.6K for a total of $45K.BCWS is computed as cost times planned complete percentage. BCWS values are $19.8K, $11.2K, $8.4K, and $5.6K for a total of $45K.BCWS is computed as cost times planned complete percentage. Question 8 1 / 1 pts You are looking at a chart that has the terms BCWS, BCWP, and AC indicating lines on the chart. What kind of chart are you looking at? Gantt chart PERT chart Bar/milestone chart Total program cost breakdown Correct! EVM chart See Exhibit 4.5. See Exhibit 4.5. Question 9 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 1 / 1 pts 7/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here: Activity Designation Immediate Predecessor Time in Days Break down both machines A None 3 Clean machine 1 B A 3 Clean machine 2 C A 3 Re-set machine 1 D B 4 Re-set machine 2 E C 2 F D and E 1 G F 2 Re-calibrate both machines Final test Using CPM, which activities make up the critical path? Correct! A, B, D, F, G A, C, E, F, G A, C, B, F, E A, D, E None of these choices are correct There are only two paths, ABDFG and ACEFG. ABDFG takes 13 days, while ACEFG takes 11 days. ABDFG is the critical path. There are only two paths, ABDFG and ACEFG. ABDFG takes 13 days, while ACEFG takes 11 days. ABDFG is the critical path. https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 8/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Question 10 1 / 1 pts Which of the following is a partial measure of productivity? Correct! Output ÷ Materials Output ÷ (Labor + Capital + Energy) Output ÷ All resources used Output ÷ Inputs All of these choices are correct See Exhibit 2.4 for sample partial measures. See Exhibit 2.4 for sample partial measures. Question 11 1 / 1 pts If a single estimate of the time required to complete an activity is not reliable, the best procedure is to use a mean and standard deviation (or variance) for each activity. true Correct! false https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 9/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 If a single estimate of the time required to complete an activity is not reliable, the best procedure is to use three time estimates. If a single estimate of the time required to complete an activity is not reliable, the best procedure is to use three time estimates. Question 12 1 / 1 pts The activity direct costs associated with a project might include giving workers overtime to complete a project in less than the expected time. Correct! true false The costs associated with expediting activities are termed activity direct costs and add to the project direct cost. Some may be worker related, such as overtime work, hiring more workers, and transferring workers from other jobs; others are resource related, such as buying or leasing additional or more efficient equipment and drawing on additional support facilities. The costs associated with expediting activities are termed activity direct costs and add to the project direct cost. Some may be worker related, such as overtime work, hiring more workers, and transferring workers from other jobs; others are resource related, such as buying or leasing additional or more efficient equipment and drawing on additional support facilities. Question 13 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 1 / 1 pts 10/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 A listing of immediate predecessor activities is important information in a CPM analysis for which of the following reasons? Correct! It specifies the relationships in the CPM network of activities. It provides useful timing information. It includes cost information. It is the probability information required in the final step of CPM. None of these choices are correct The immediate predecessors are the activities that need to be completed immediately before an activity. They, therefore, specify relationships in the CPM network. The immediate predecessors are the activities that need to be completed immediately before an activity. They, therefore, specify relationships in the CPM network. Question 14 0 / 1 pts A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the schedule performance index for the project? Less than zero orrect Answer 0 − 1.05 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 11/49 8/12/22, 7:12 AM ou Answered Omozojie Inetabor's Quiz History: Term Test 1 1.051 − 1.10 1.11 − 1.15 Over 1.15 BCWP÷ BSWS = 46.4÷ 45 = 1.03 BCWP÷ BSWS = 46.4÷ 45 = 1.03 Question 15 1 / 1 pts In CPM analysis, it is generally expected that the relationship between activity direct costs and project indirect costs will be which of the following? Positively related Optimally related Correct! Negatively related Not related Fractionally related https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 12/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Because activity direct costs and project indirect costs are opposing costs dependent on time, the scheduling problem is essentially one of finding the project duration that minimizes their sum or, in other words, finding the optimum point in a time-cost trade-off. Because activity direct costs and project indirect costs are opposing costs dependent on time, the scheduling problem is essentially one of finding the project duration that minimizes their sum or, in other words, finding the optimum point in a time-cost trade-off. Question 16 0 / 1 pts Operations risk is the likelihood of a disruption that would impact the ability of a company to continuously supply products or services. ou Answered true orrect Answer false Supply chain risk is the likelihood of a disruption that would impact the ability of a company to continuously supply products or services. Supply chain risk is the likelihood of a disruption that would impact the ability of a company to continuously supply products or services. Question 17 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 1 / 1 pts 13/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 If the material usage per unit of final product decreases to half of the current usage, then the firm will 1. double the material productivity. 2. increase the multifactor productivity. 3. decrease capital productivity. 4. have no effect on productivity. I II Correct! both I and II III IV Labor productivity will not change. Material productivity doubles, since the denominator is halved. There is no effect on capital productivity. Labor productivity will not change. Material productivity doubles, since the denominator is halved. There is no effect on capital productivity. 1 / 1 pts Question 18 A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here: Activity Designation Immediate Predecessor Time in Days Break down both machines A None 3 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 14/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Clean machine 1 B A 3 Clean machine 2 C A 3 Re-set machine 1 D B 1 Re-set machine 2 E C 2 Re-calibrate both machines F D and E 1 Final test G F 2 Using CPM, what is the latest finish time for the last activity in this project (i.e., the total time to complete the project)? 9 days 10 days Correct! 11 days 12 days 13 days There are two paths, ABDFG and ACEFG. ABDFG takes 10 days, while ACEFG takes 11 days. ACEFG is the critical path. There are two paths, ABDFG and ACEFG. ABDFG takes 10 days, while ACEFG takes 11 days. ACEFG is the critical path. Question 19 1 / 1 pts A simple project listing of five activities, their predecessors, and their respective time estimates are presented here: Activity Immediate Predecessor Time in Days https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 15/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 A None 3 B A 2 C A 1 D B and C 3 E D 4 Using CPM, what is the latest finish time for the last activity in this project (i.e., the total time to complete the project)? 10 days 7 days 8 days Correct! 12 days 9 days The critical path is ABDE. The total time for these activities is 12 days. The critical path is ABDE. The total time for these activities is 12 days. Question 20 1 / 1 pts In a Gantt chart, the horizontal axis is usually which of the following? Activities https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 16/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Cost Profit Correct! Time Milestones See Exhibit 4.4A. See Exhibit 4.4A. Question 21 0 / 1 pts In a CPM analysis, if you subtract the late finish from the early finish, the result is the activity's slack time. orrect Answer true ou Answered false The difference between the late start time and early start time is the slack time.This is always equal to the late finish time minus the early finish time. The difference between the late start time and early start time is the slack time.This is always equal to the late finish time minus the early finish time. https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 17/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Question 22 1 / 1 pts A major competitive dimension that forms a company's strategic operational competitive position in their strategic planning is which of the following? Correct! Cost or price Focus Automation Straddling Activity-system mapping Cost or price is one of the competitive dimensions mentioned in the text. Cost or price is one of the competitive dimensions mentioned in the text. Question 23 1 / 1 pts A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWP for Activity C? $0 − $5K https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 18/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Correct! $5.01K − $10K $10.01K − $15K $15.01K − $20K Over $20K BCWP values are $22K, $12.6K, $9K, and $2.8K for a total of $46.4K. BCWP is computed as cost times actual complete percentage. BCWP values are $22K, $12.6K, $9K, and $2.8K for a total of $46.4K. BCWP is computed as cost times actual complete percentage. 1 / 1 pts Question 24 You have the following time and cost information for use in a time-cost CPM scheduling model. Activity Normal Time Crash Time Normal Cost Crash Cost A 3 2 $400 $ 600 B 5 3 $600 $ 1200 C 4 1 $300 $ 1500 What are the three costs per unit of time to expedite each activity? A = $300, B = $200, C = $300 A = $100, B = $200, C = $400 A = $200, B = $200, C = $200 A = $100, B = $400, C = $300 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 19/49 8/12/22, 7:12 AM Correct! Omozojie Inetabor's Quiz History: Term Test 1 A = $200, B = $300, C = $400 Using (Crash cost − Normal cost) ÷ (Normal time − Crash time) = Cost per unit of time, A = (600 − 400) ÷ (3 − 2) = $200; B = (1,200 − 600) ÷ (5 − 3) = $300; and C = (1,500 − 300) ÷ (4 − 1) = $400. (See Exhibit 4.11.) Using (Crash cost − Normal cost) ÷ (Normal time − Crash time) = Cost per unit of time, A = (600 − 400) ÷ (3 − 2) = $200; B = (1,200 − 600) ÷ (5 − 3) = $300; and C = (1,500 − 300) ÷ (4 − 1) = $400. (See Exhibit 4.11.) Question 25 1 / 1 pts A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the cost performance index for the project? Less than zero 0 − 1.05 1.051 − 1.10 1.11 − 1.15 Correct! Over 1.15 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 20/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 BCWP÷ AC = 46.4÷ 45 = 1.16 BCWP÷ AC = 46.4÷ 45 = 1.16 Question 26 0 / 1 pts An activity has an optimistic time of 16, a most likely time of 25, and a pessimistic time of 40. What is the expected time for the activity? 15 − 20 ou Answered 20.01 − 25 orrect Answer 25.01 − 30 30.01 − 35 Over 35 ET = ( a + 4 m + b) ÷ 6 = 26 ET = ( a + 4 m + b) ÷ 6 = 26 Question 27 1 / 1 pts Sustainability means meeting a firm's current needs without excessively compromising the ability of future generations to meet their own needs. true https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 21/49 8/12/22, 7:12 AM Correct! Omozojie Inetabor's Quiz History: Term Test 1 false By adding "sustainability" to the concept (of strategy), we add the requirement to meet these current needs without compromising the ability of future generations to meet their own needs. (Excessively is not mentioned.) By adding "sustainability" to the concept (of strategy), we add the requirement to meet these current needs without compromising the ability of future generations to meet their own needs. (Excessively is not mentioned.) Question 28 1 / 1 pts In a multifactor measure of productivity, the denominator of the ratio would include all resources used or all inputs. true Correct! false In a multifactor measure of productivity, the denominator includes several but not all inputs. In a multifactor measure of productivity, the denominator includes several but not all inputs. Question 29 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 1 / 1 pts 22/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 A tracking Gantt chart superimposes the current schedule onto a baseline plan so deviations are easily noticed. Correct! true false A tracking Gantt chart superimposes the current schedule onto a baseline plan so deviations are easily noticed. A tracking Gantt chart superimposes the current schedule onto a baseline plan so deviations are easily noticed. 1 / 1 pts Question 30 Various financial data for SunPath Manufacturing for 2019 and 2020 follow. 2019 Output: Sales Inputs: Labor 2020 $ 300,000 $ 330,000 40,000 43,000 Raw Materials 45,000 51,000 Energy 10,000 9,000 Capital Employed 250,000 262,000 Other 2,000 6,000 What is the percentage change in SunPath's total productivity measure between 2019 and 2020? −9.22 2.33 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 23/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 −0.53 Correct! 2.88 10.39 Total productivity for 2019 is $300,000 divided by the sum $40,000 + $45,000 + $10,000 + $250,000 + $2,000 or 0.8646. Total productivity for 2020 is $330,000 divided by the sum of $43,000 + $51,000 + $9,000 + $262,000 + $6,000 or 0.8895. The difference between 2019 and 2020 is 0.0249 and the percentage difference is 0.0249 divided by 0.8646 = 0.0288 or 2.88%. Total productivity for 2019 is $300,000 divided by the sum $40,000 + $45,000 + $10,000 + $250,000 + $2,000 or 0.8646. Total productivity for 2020 is $330,000 divided by the sum of $43,000 + $51,000 + $9,000 + $262,000 + $6,000 or 0.8895. The difference between 2019 and 2020 is 0.0249 and the percentage difference is 0.0249 divided by 0.8646 = 0.0288 or 2.88%. Question 31 1 / 1 pts Popular project management software used in mid-sized projects is Microsoft Word. Microsoft Primavera. Correct! Microsoft Project. Microsoft Excel. None of thesechoices are correct https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 24/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 See section on project management information systems. See section on project management information systems. Question 32 1 / 1 pts The Gantt chart is an example of a project control chart. Correct! true false Exhibit 4.4A is a sample Gantt chart, sometimes referred to as a bar chart, showing both the amount of time involved and the sequence in which activities can be performed. Exhibit 4.4A is a sample Gantt chart, sometimes referred to as a bar chart, showing both the amount of time involved and the sequence in which activities can be performed. Question 33 1 / 1 pts The ability to rapidly and inexpensively switch production from one product to another enables what are sometimes referred to as? Economies of scale Economies of size https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 25/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Economies of shape Correct! Economies of scope Economies of shipping Flexible manufacturing systems and simple, easily set-up equipment permit rapid low-cost switching from one product to another, enabling what are sometimes referred to as economies of scope. Flexible manufacturing systems and simple, easily set-up equipment permit rapid low-cost switching from one product to another, enabling what are sometimes referred to as economies of scope. Question 34 1 / 1 pts When developing an operations and supply chain strategy, which of the following is an important product-specific criterion to consider? Correct! Technical liaison and support Learning curve Competitor's product performance Production lot size Total quality management https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 26/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Technical liaison and support. A supplier may be expected to provide technical assistance for product development, particularly during the early stages of design and manufacturing. Technical liaison and support. A supplier may be expected to provide technical assistance for product development, particularly during the early stages of design and manufacturing. Question 35 1 / 1 pts If all you knew about a production system was that total daily output was 400 units and the total labor necessary to produce the 400 units was 350 hours, and the total materials used were 425 units, what kind of productivity measure(s) could you use to compute productivity? Partial measure Multifactor measure Total measure Correct! Partial measure and Multifactor measure Multifactor measure and Total measure Partial measure and multifactor measure is the most correct of the answers. You could use either a partial or a multifactor measure or both kinds of measures. Partial measure and multifactor measure is the most correct of the answers. You could use either a partial or a multifactor measure or both kinds of measures. https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 27/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Question 36 1 / 1 pts A process has a total measure of productivity of 1.41 and total inputs of 9,050. What was the output? 3,750 Correct! 12,761 18,104 21,850 Not enough information to calculate Productivity is output ÷ input or 1.41 = x ÷ 9,050. Then solve for x. Productivity is output ÷ input or 1.41 = x ÷ 9,050. Then solve for x. Question 37 1 / 1 pts For an activity in a CPM analysis, the early start time is 8 and the late start time is 10. Which of the following statements is true? The late finish is 12. The early finish is 10. Correct! The slack for this activity is 2. The duration of this activity is 2. https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 28/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 The activity is on the critical path. The difference between the late start time and early start time is the slack time. The difference between the late start time and early start time is the slack time. Question 38 1 / 1 pts An activity-system map is which of the following? A network guide to route airlines A listing of activities that make up a project Correct! A diagram that shows how a company's strategy is delivered to customers A facility layout schematic noting what is done where A timeline displaying major planned events Activity-system maps such as the one for IKEA show how a company's strategy is delivered through a set of tailored activities. Activity-system maps such as the one for IKEA show how a company's strategy is delivered through a set of tailored activities. Question 39 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 1 / 1 pts 29/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Which of the following is a total measure of productivity? Output ÷ Materials Output ÷ (Labor + Capital + Energy) Output ÷ Labor Correct! Output ÷ Inputs All of these choices are correct See Exhibit 2.4 for two total measures of productivity. See Exhibit 2.4 for two total measures of productivity. Question 40 1 / 1 pts For an activity in a CPM analysis, the early finish time is 20 and the late finish time is 20. Which of the following statements is true? The activity's late start must happen before its early start. Correct! The activity is on the critical path. The slack for this activity is 20. The duration of this task is zero. The duration of this task is 20. https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 30/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 The critical path is the longest sequence of connected activities through the network and is defined as the path with zero slack time. Because the critical path has zero slack time, each activity on the path must have zero slack time. It follows that an activity with zero slack time (e.g., early start = late start = zero) is on the critical path. The critical path is the longest sequence of connected activities through the network and is defined as the path with zero slack time. Because the critical path has zero slack time, each activity on the path must have zero slack time. It follows that an activity with zero slack time (e.g., early start = late start = zero) is on the critical path. 0 / 1 pts Question 41 Various financial data for SunPath Manufacturing for 2019 and 2020 follow. 2019 Output: Sales Inputs: Labor 2020 $ 300,000 $ 330,000 40,000 43,000 Raw Materials 45,000 51,000 Energy 10,000 9,000 Capital Employed 250,000 262,000 Other 2,000 6,000 What is the percentage change in the labor partial productivity measure for SunPath between 2019 and 2020? −9.22 orrect Answer 2.33 ou Answered −0.53 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 31/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 2.88 10.39 The labor partial productivity measure for 2019 is $300,000 divided by $40,000 or 7.5. For 2020 it is $330,000 divided by $43,000 or 7.67. The percentage change between 2019 and 2020, then, is (7.67 − 7.5) ÷ 7.5 or 0.17 divided by 7.5 = 2.33%. The labor partial productivity measure for 2019 is $300,000 divided by $40,000 or 7.5. For 2020 it is $330,000 divided by $43,000 or 7.67. The percentage change between 2019 and 2020, then, is (7.67 − 7.5) ÷ 7.5 or 0.17 divided by 7.5 = 2.33%. Question 42 1 / 1 pts What is the process called where a company seeks to match the benefits of a successful position while maintaining its existing position in offering customers a variety of differing services? Operations capability analysis Correct! Straddling Order qualifying Order winning Inter-functional analysis https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 32/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Straddling occurs when a company seeks to match the benefits of a successful position while maintaining its existing position. Straddling occurs when a company seeks to match the benefits of a successful position while maintaining its existing position. 1 / 1 pts Question 43 In a partial measure of productivity, the denominator of the ratio would include all resources used or all inputs. true Correct! false In a partial measure of productivity, the denominator includes only a single input. In a partial measure of productivity, the denominator includes only a single input. 1 / 1 pts Question 44 A simple project listing of five activities and their respective time estimates are presented here: Activity Immediate Predecessor Time in Days A None 1 B A 2 C A 1 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 33/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 D B and C 3 E D 2 Using CPM, which activities make up the critical path? A, C, D, E Correct! A, B, D, E A, C, B, D, E A, D, E None of these choices are correct There are two paths: ABDE and ACDE. ABDE will take 8 days, while ACDE will take 7 days. ABDE, therefore, is the critical path for this project. Activity C is off the critical path because there is one day of slack in that activity. There are two paths: ABDE and ACDE. ABDE will take 8 days, while ACDE will take 7 days. ABDE, therefore, is the critical path for this project. Activity C is off the critical path because there is one day of slack in that activity. Question 45 1 / 1 pts A firm's business practices toward its labor force pertain mainly to the economic aspect of the triple bottom line concept. true Correct! false https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 34/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Social responsibility pertains to fair and beneficial business practices toward labor, the community, and the region in which a firm conducts its business. Social responsibility pertains to fair and beneficial business practices toward labor, the community, and the region in which a firm conducts its business. 0 / 1 pts Question 46 You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project "direct costs" are given here. Activity Immediate Predecessor Normal Time Crash Time Normal Cost (Direct) Crash Cost (Direct) A None 3 2 $300 $400 B A 3 3 $100 $100 C A 1 1 $200 $200 D B and C 3 2 $400 $550 E D 2 1 $500 $900 F E 3 3 $200 $200 G F 2 2 $100 $100 The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs)? 16 days https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 35/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 orrect Answer 15 days ou Answered 14 days 13 days 12 days The critical path is ABDEFG. The project duration is 3 + 3 + 3 + 2 + 3 + 2 = 16 days. The normal direct cost is $300 + $100 + $200 + $400 + $500 + $200 + $100 = $1,800. The indirect costs are an additional $400 for a total of $2,200. The only activities that can be crashed are A, D, and E. A costs $100/day to crash, D costs $150/day to crash, and E costs $400/day to crash. Reducing the duration of A by one day at an additional cost of $100 is the most economical. Direct costs are now $400 + $100 + $200 + $400 + $500 + $200 + $100 = $1,900. Overall duration of the project is 15 days, and indirect costs are $250. The total cost of crashing this project for one day is $2,150. To crash the project to a 14-day duration, one can now select between activity D at $150/day or E at $400/day. Reducing the duration of D by one day at an additional cost of $150 is the most economical. Direct costs are now $400 + $100 + $200 + $550 + $500 + $200 + $100 = $2,050. Overall duration of the project is 14 days, and indirect costs are $200. The total cost of crashing this project for two days is $2,250. To crash the project to a 13-day duration, one can only crash activity E at $400/day. Direct costs are now $400 + $100 + $200 + $550 + $900 + $200 + $100 = $2,450. Overall duration of the project is 13 days, and indirect costs are $100. The total cost of crashing this project for three days is $2,550. The lowest cost is 15 days. The critical path is ABDEFG. The project duration is 3 + 3 + 3 + 2 3 2 16 d Th l di t t i $300 $100 $200 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 36/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 + 3 + 2 = 16 days. The normal direct cost is $300 + $100 + $200 + $400 + $500 + $200 + $100 = $1,800. The indirect costs are an additional $400 for a total of $2,200. The only activities that can be crashed are A, D, and E. A costs $100/day to crash, D costs $150/day to crash, and E costs $400/day to crash. Reducing the duration of A by one day at an additional cost of $100 is the most economical. Direct costs are now $400 + $100 + $200 + $400 + $500 + $200 + $100 = $1,900. Overall duration of the project is 15 days, and indirect costs are $250. The total cost of crashing this project for one day is $2,150. To crash the project to a 14-day duration, one can now select between activity D at $150/day or E at $400/day. Reducing the duration of D by one day at an additional cost of $150 is the most economical. Direct costs are now $400 + $100 + $200 + $550 + $500 + $200 + $100 = $2,050. Overall duration of the project is 14 days, and indirect costs are $200. The total cost of crashing this project for two days is $2,250. To crash the project to a 13-day duration, one can only crash activity E at $400/day. Direct costs are now $400 + $100 + $200 + $550 + $900 + $200 + $100 = $2,450. Overall duration of the project is 13 days, and indirect costs are $100. The total cost of crashing this project for three days is $2,550. The lowest cost is 15 days. Question 47 1 / 1 pts Which of the following is a graphic project report used in project management? Project proposal Approved project plan https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 37/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Humphrey chart Equipment and supplies chart Correct! Cost and performance tracking schedule See Exhibit 4.4D. See Exhibit 4.4D. Question 48 1 / 1 pts Risk mapping involves assessment of the probability or relative frequency of an event against the aggregate severity of the loss. Correct! true false Risk mapping involves assessment of the probability or relative frequency of an event against the aggregate severity of the loss. Risk mapping involves assessment of the probability or relative frequency of an event against the aggregate severity of the loss. Question 49 1 / 1 pts Various financial data for SunPath Manufacturing for 2019 and 2020 follow. https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 38/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 2019 Output: Sales Inputs: Labor 2020 $ 300,000 $ 330,000 40,000 43,000 Raw Materials 45,000 51,000 Energy 10,000 9,000 Capital Employed 250,000 262,000 Other 2,000 6,000 What is the percentage change in the multifactor labor and raw materials productivity measure for SunPath between 2019 and 2020? −9.22 2.33 Correct! −0.53 −2.88 10.39 The multifactor labor and raw materials productivity measure for 2019 is $300,000 divided by the sum $40,000 + $45,000 or 3.53. For 2020 it is $330,000 divided by the sum $51,000 + $43,000 or 3.51. The percentage change between 2019 and 2020, then is (3.51 − 3.53) ÷ 3.529 or −0.018 divided by 3.529 = −0.53%. The multifactor labor and raw materials productivity measure for 2019 is $300,000 divided by the sum $40,000 + $45,000 or 3.53. For 2020 it is $330,000 divided by the sum $51,000 + $43,000 or 3.51. The percentage change between 2019 and 2020, then is (3.51 − 3.53) ÷ 3.529 or −0.018 divided by 3.529 = −0.53%. Question 50 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 1 / 1 pts 39/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 One of the assumptions made using CPM is that project activities can be identified with clear beginning and ending points. Correct! true false From the text, we are assuming that the activity times are known. Hence, each activity must have clear beginning and ending points. From the text, we are assuming that the activity times are known. Hence, each activity must have clear beginning and ending points. Question 51 1 / 1 pts The valuations in an earned value management analysis must be either profits or revenue. true Correct! false The valuations could be based on either a value measure (revenue or profit) or a cost measure. The valuations could be based on either a value measure (revenue or profit) or a cost measure. Question 52 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 1 / 1 pts 40/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 PERT is an abbreviation for which of the following methodologies? Product evaluation, result, and treatment Programming and evaluation realization technology Correct! Program evaluation and review technique Process evaluation and review technology It is a name, not an abbreviation for anything. The program evaluation and review technique (PERT) was developed for the U.S. Navy's Polaris missile project. The program evaluation and review technique (PERT) was developed for the U.S. Navy's Polaris missile project. Question 53 1 / 1 pts Which of the following is not a major strategic operational competitive dimension that forms a company's competitive position? Cost or price Delivery speed Delivery reliability Correct! Management acumen Coping with changes in demand https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 41/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 The operational competitive dimensions that form a company's competitive position are listed in the text. Management acumen is not mentioned. The operational competitive dimensions that form a company's competitive position are listed in the text. Management acumen is not mentioned. Question 54 1 / 1 pts In the time-cost CPM model, cost is assumed to be a linear function of time. Correct! true false We assume a linear relationship between time and cost. This assumption is common in practice and helps us derive the cost per day to expedite. We assume a linear relationship between time and cost. This assumption is common in practice and helps us derive the cost per day to expedite. Question 55 1 / 1 pts You are managing a project and need to cut the cost of the project. You decide to transfer workers to another job to cut the project's costs. Costs https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 42/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 associated with transferring the workers are an example of project indirect costs. true Correct! false The costs associated with expediting activities are termed activity direct costs and add to the project direct cost. Some may be worker related, such as overtime work, hiring more workers, and transferring workers from other jobs; others are resource related, such as buying or leasing additional or more efficient equipment and drawing on additional support facilities. The costs associated with expediting activities are termed activity direct costs and add to the project direct cost. Some may be worker related, such as overtime work, hiring more workers, and transferring workers from other jobs; others are resource related, such as buying or leasing additional or more efficient equipment and drawing on additional support facilities. Question 56 1 / 1 pts You know when you have arrived at the optimal solution in using the timecost CPM scheduling model analysis when what happens? You have found the critical path. You have run out of crash time. You no longer have a linear relationship with costs. Correct! You have reached the minimum total cost. https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 43/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 You have run out of crash costs. See Exhibit 4.11. See Exhibit 4.11. Question 57 1 / 1 pts The total output from a production system in one day is 900 units and the total labor necessary to produce the 900 units is 900 hours. Using the appropriate productivity measure, what is the resulting productivity ratio? Correct! 1.000 1.428 0.700 0.411 None of thesechoices are correct 900 units divided by 900 hours equals 1.0 units per hour. 900 units divided by 900 hours equals 1.0 units per hour. Question 58 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 0 / 1 pts 44/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for the project? $0 − $15K $15.01K − $30K orrect Answer $40.01K − $45K ou Answered $45.01K − $60K Over $60K BCWS values are $19.8K, $11.2K, $8.4K, and $5.6K for a total of $45K.BCWS is computed as cost times planned complete percentage. Project BCWS is the sum of activity BCWS values. BCWS values are $19.8K, $11.2K, $8.4K, and $5.6K for a total of $45K.BCWS is computed as cost times planned complete percentage. Project BCWS is the sum of activity BCWS values. Question 59 1 / 1 pts Larry's Auto Body Repair Shop had revenues that averaged $60,000 per week in April and $50,000 per week in May. During both months, the shop employed six full-time (40 hours ÷ week) workers. In April the firm also had four part-time workers working 25 hours per week, but in May there were only two part-time workers and they only worked 10 hours per week. https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 45/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 What is the percentage change in labor productivity from April to May for Larry's Auto Body Repair? −20.00% −15.82% Correct! 8.98% 2.30% −25.00% Labor productivity is output (revenue) divided by hours of labor input. For April, revenue per week was $60,000 and labor hours were 4× [(40× 6) + (25× 4)]. This is 60,000 ÷ 1,360 or $44.12 per hour of labor. For May, revenue per week was $50,000 and labor hours were 4× [(40× 6) + (10× 2)]. This is 50,000 ÷ 1,040 or $48.08 per hour of labor a difference of $3.96 per hour. The percentage change in productivity between April and May, then, is 3.96 ÷ 44.12 = 0.0898 × 100 = 8.98%. (Note: this analysis assumes four weeks in each month and equal productivity for each hour worked.) Labor productivity is output (revenue) divided by hours of labor input. For April, revenue per week was $60,000 and labor hours were 4× [(40× 6) + (25× 4)]. This is 60,000 ÷ 1,360 or $44.12 per hour of labor. For May, revenue per week was $50,000 and labor hours were 4× [(40× 6) + (10× 2)]. This is 50,000 ÷ 1,040 or $48.08 per hour of labor a difference of $3.96 per hour. The percentage change in productivity between April and May, then, is 3.96 ÷ 44.12 = 0.0898 × 100 = 8.98%. (Note: this analysis assumes four weeks in each month and equal productivity for each hour worked.) Question 60 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 1 / 1 pts 46/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs. Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost A None 3 2 $200 $400 B A 4 3 $300 $600 C A 1 1 $200 $200 D B and C 3 2 $500 $550 E D 2 1 $500 $900 What are the total time of this project and total normal cost? Total time is 13 days, total cost is $1,200. Correct! Total time is 12 days, total cost is $1,700. Total time is 11 days, total cost is $1,600. Total time is 10 days, total cost is $1,750. Total time is 9 days, total cost is $1,700. The critical path is ABDE, a total of 12 days. Normal cost is $200 + $300 + $200 + $500 + 500 = $1,700. This is the sum of the "normal cost" column. (Even though activity C is not on the critical path, it still needs to be performed and paid for.) The critical path is ABDE, a total of 12 days. Normal cost is $200 + $300 + $200 + $500 + 500 = $1,700. This is the sum of the "normal cost" column. (Even though activity C is not on the critical path, it still needs to be performed and paid for.) Question 61 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 5 / 5 pts 47/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 Why would subcontractors for a government project want their activities on the critical path? Under what conditions would they try to avoid being on the critical path? Your Answer: In a government project, a subcontractor might wish to have their activities on the critical path because of various reasons. This can be a situation where in the early completion of projects ,the cost incentives are available, then the subcontractor may want these activities on the critical path. The duration a project takes to be completed is determined by the critical path. For this reason, having these activities on the critical path would ensure that the subcontractor can received additional money or resources for project completion. There are some who want to have their activities off the critical path. This might be when there are individual errors on the part of the subcontractor. In this case, the subcontractor might want the activities off the critical path. Question 62 5 / 5 pts What are some major capacity considerations in a hospital? How do they differ from those of a factory? Your Answer: Capacity planning can be seen as the process by which firms calculate the amount of production resources needed to fulfill customer demand. Capacity considerations that are usually considered for hospitals are size and composition of nursing staff, how many beds are available, balance between operating room and intensive care units and ER's A major differences between hospital and factory capacity is that a hospital can add capacity easily by adding more staff and beds. A factory is usually technologically limited and therefore must plan well in advance to add capacity. General uncertainty that surrounds the demand for hospital services is much greater than what would be faced by a factory. Factory management generally has the ability to backlog demand in such https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 48/49 8/12/22, 7:12 AM Omozojie Inetabor's Quiz History: Term Test 1 a way as to achieve more efficient levels of capacity utilization than does a hospital. Question 63 5 / 5 pts What is meant by triple-bottom-line strategy? Give an example of a company that has adopted this type of strategy. Your Answer: Based on this strategy, a firm can stay running and profitable in long run. This strategy focus on sustainable practices to support the environment, people associated with the firm and the financial gains. The organizational success for this strategy is measured based on social, ecological and economic. Global company adopting triple bottom strategy are Better World Books and Method home. For Better World Books, they were started by college friends in Indiana. Better world books sells used books and donates a portion of income to fund literacy programs. Another company is the Method home. Method home makes products from recycled plastic which waste were recovered from ocean, uses solar tracking trees in parking, makes home use products which are toxin free, though not tried on animal yet. Quiz Score: 66 out of 75 https://q.utoronto.ca/courses/266690/quizzes/254707/history?version=1 49/49