Uploaded by Sanaullah_Said

Advacon PTW System

advertisement
Project
Doc. Type
Title
Doc. No.
Client:
:
:
:
:
Buffer Park Project (District-5)
Plan
HSE - Permit to Work System
Contractor:
Rev.:
MC-PH01-SWA-LAE001-ADV-PLN-HSE-000006
PMO:
PMCM:
00
SC:
MISK CITY COMPANY
BUFFER PARK PROJECT (District-5)
Title: HSE - PERMIT TO WORK SYSTEM
MC-PH01-SWA-LAE001-ADV-PLN-HSE-000006-00
Issue Record and Revision History:
Issue date
Rev
Status
Prepared by
For
Approval
Reviewed by:
Approved by:
Eng’r. Jawed Alam
Eng’r. Ahmad Hallaj
Approval Records:
Rev. No.
SC
PM/CM
PMO
CLIENT
Final Approval Code
Date
Prepared by: Advanced Concepts for Contracting Co.
MC-PH01-SWA-LAE001-ADV-PLN-HSE-000006-00
Submitted to: MISK CITY DEVELOPMENT, RIYADH, KSA
MISK CITY
DEVELOPMENT,RIYADH,
KSA
Project Name:
District 5 Buffer Park Project
(HSE)
PERMIT TO WORK SYSTEM
ADV Transmittal No. _
Document Number
Revision No
Date
MC-HSE-ADV-PTW-SYSTEM-PLAN-
Status: For Review & Approval
Project Phase: Construction Stage
Controlled Copy No.
Copy Issued to: MISK CITY FOUNDATION
Prepared By:
Checked & Approved By:
Name
Job Title
Signature
Date
Revision No.
Name of Holder
Project Manager
ADV HSE Office
ADV Quality Office
Client/Client’s Team
ADV Main Office
REVISION HISTORY
Change Description
Date
REGISTER OF CONTROLLED COPY HOLDERS
Copy No.
Purpose
1
Reference
2
Amendments
3
Reference
Reference
4
5
Reference
No. of Copies
1
1
1
1
1
P a g e 1 | 23
1
Purpose.................................................................................................................................... 5
2
Scope ....................................................................................................................................... 5
3
Definitions, and Terms............................................................................................................ 5
4
Responsibilities ....................................................................................................................... 6
5
6
4.1
Project Manager ............................................................................................................... 6
4.2
Construction Manager ...................................................................................................... 6
4.3
Employees ........................................................................................................................ 6
Permit to Work System Workflow ......................................................................................... 7
5.1
Workflow Description ...................................................................................................... 7
5.2
Permit Receiver ................................................................................................................ 8
5.3
Permit Issuer ..................................................................................................................... 8
5.4
Minimum Acceptance for Permit Signatories .................................................................. 8
Types of Permits ..................................................................................................................... 9
6.1
General ............................................................................................................................. 9
6.2
Activities Requiring a Permit to Work ............................................................................. 9
6.3
General Work Permit (cold) ........................................................................................... 10
6.4
Hot Work Permit ............................................................................................................ 10
6.5
Confined Space Permit ................................................................................................... 10
6.6
Electrical Permit ............................................................................................................. 11
6.6.1
Lock out-tag out ...................................................................................................... 11
6.6.2
Execution of Energization, Removal of Tags, Padlock and Restoration of Power 13
6.7
Excavation Permit .......................................................................................................... 13
6.8
Permit issuance and duration ......................................................................................... 14
6.9
Permit closure................................................................................................................. 15
6.10
Layout and Color of Permits ...................................................................................... 15
6.11
Emergency Response .................................................................................................. 16
7
STARRT Card Briefing ........................................................................................................ 17
8
General (Cold) Work Permit................................................................................................. 18
9
Hot Work Permit ................................................................................................................... 19
P a g e 2 | 23
10
Confined Space Work Permit ............................................................................................... 20
11
Excavation Work Permit ....................................................................................................... 21
P a g e 3 | 23
Permit to Work System (Rectification Sheet)
Sr. No
SC Comments
Rectifications
1
Who is permit Issuer
On page 8
2
Who is permit receiver
On page 8
3
Who is the requester and duties of all involved personal
On page 7
4
Types and classification and validity of activity and
applicable permits, permits validity were not addressed
On page 9
On page 15
P a g e 4 | 23
1 Purpose
The Permit to Work (PTW) system is designed to give direction and guidance in term of Health,
Safety, and Environmental (HSE) requirements to Advacon and subcontractor personnel during
the construction activities.
The purpose of this document is to enhance management control over the various work activities
carried out by the Advacon and their subcontractor, which may be potentially hazardous, within
the designated areas known as Construction Areas
2 Scope
This procedure is to be used by members of Advacon Project Management, HSE Department,
Construction Team, PM, Engr. Supervisors and Sub-con who supervise and control of all
activities where a permit to work is necessary.
3 Definitions, and Terms
Permit to Work (PTW): Written permission given to carry out work together with any
supporting Permits.
Issuing Authority: The person appointed and authorized by Advacon to carry out the task as
required by the Permit to Work Procedure, who is responsible for reviewing the submitted
Permit, confirming that the worksite has been examined and all precautions specified to be taken
before work commences have in fact been taken, confirming than no conflict exists with other
Permits.
Receiving Authority: The person appointed and authorized by Advacon to carry out the task as
required by the Permit to Work Procedure, who applies for a Permit and completes the Permit for
approval by the appropriate Authority, accepting the Permit and agreeing with the Issuing
Authority.
Hot Work: Any job, where the heat generated is of sufficient magnitude and intensity to cause
ignition of any flammable liquids, gases, or any other material. Common sources of ignition are
internal combustion engines, gas cutting torches, welding machines, non-flame proof electrical
equipment, grinders, annealing blankets, jack hammers, etc.
Cold Work: Work which will not involve the use of naked flames nor produce any source of
ignition.
Confined Space: Any area that has limited access or egress and not suitable for human
inhabitants, or which is sufficiently confined to permit the accumulation of flammable or toxic
gases or vapors, or where an oxygen deficiency or enrichment could occur.
P a g e 5 | 23
Electrical Work: A job on any electrical equipment or system. Excavation and Civil Work: All
the excavation jobs.
Radiography Work: A work involving use of radioactive source.
4 Responsibilities
4.1
Project Manager
The Project Manager is responsible for all site activities. Appointed personnel will manage most
of the aspect of site activities, including the Permit to Work system and performance. The
Project Manager will delegate the duty of the correct application of Advacon’s Permit to Work
Procedure to Construction Manager.
4.2
Construction Manager
The Construction Manager will be responsible for ensuring the effective administration of this
procedure within Construction site activities and shall ensure that this procedure is properly
implemented at site. The Construction Manager shall ensure that all work is carried out under the
controls of the Permit to Work System. Further to this, the Construction Manager shall:
•
•
•
•
•
•
Provide a safe and healthful environment for all personnel working on the project.
Ensure that sufficient funds and recourses are made available to ensure the continuity of
this procedure for the duration of the works.
Ensure the proper coordination of construction activities between ADVACON and
subcontractors (if any).
Verify that the subcontractor is providing the correct information and equipment for the
scope of work.
Ensure training is given to all persons requiring how to use a Permit to Work.
Nominate personnel and authorize them to perform the duties of permit to Work
Signatories.
4.3
Employees
All employees shall comply with the requirements of the Permit to Work Procedure. Any person
found to be in breach of the procedure or deviates from any written instruction shall be subject to
disciplinary action, which may lead to dismissal and action being taken against the individual
under the current local Legislation.
P a g e 6 | 23
5 Permit to Work System Workflow
5.1
Workflow Description
Each permit shall be completed according to the workflow shown in Figure.
1. The Receiving Authority (Site Engineer/Supervisor) is the in charge of the scope of work
to be executed. The description of the work to be carried out supplying all relevant
information inclusive of drawings method statements and risk assessments in support of
the permit application.
2. The Advacon Issuing Authority (HSE Team) check the new permits, specifying
the safety equipment that shall be used and defines any special applicable
instruction.
3. The authorized Issuing Authority check for existing permits for revalidation and
supervision. If none, issue new PTW.
4. The Receiving Authority, carrying out all preliminary checks required by the
Issuer and will sign the PTW to verify that all requirements have been met and
that the work area is in a safe condition for the work to commence.
5. Performer (Supervisor/Foreman) carries out and supervises the works in
compliance with the relevant permit prescription; once completed such activities
notify to Issuer the permit closure.
Figure 1: Permit to Work System Flowchart
In the following paragraphs each step is described in detail.
P a g e 7 | 23
5.2
Permit Receiver
The Permit Receiver (Site Engineer/Supervisor) is in-charge of the scope of work to be executed.
The Receiver shall complete the description of the work to be carried out supplying all relevant
information inclusive of drawings method statements and risk assessments in support of the
permit application. Site Engineers or supervisors at the site are permit receivers, and they will
comply with the permit requirements
The Permit Receiver has the following responsibilities:
•
•
•
•
•
It is the Receiver's responsibility to ensure that adequate information and resources are
available to perform the work safely.
To ensure compliance with the conditions stipulated on the permit.
It is the responsibility of the Receiver to supervise the work group and ensure that the
workers use appropriate tools and equipment.
To inform Advacon’s Issuing Authority of any changes in the condition of the job or
the surrounding area, or of any delay in starting the work, so as not to infringe upon
any safety factors.
Notify Advacon’s Issuing Authority (HSE Team) upon completion of the work.
5.3
Permit Issuer
Construction Manager shall ensure that there are sufficient signatory’s onsite to fulfill the role
of approving the Permit to Work. No work can commence without the approving authority’s
signature. Permits will be issued by the HSE personal responsible for the area.
The Issuer of the Permit to Work has the following responsibilities:
• Check the completeness and reliability of the submitted forms.
• Specify the required worksite precautions and controls.
• Detail required safety equipment.
• Identify any worksite preparation requirements, if deemed necessary.
• Ensure that Certificates (attached to Permits as required) for Confined Space work,
excavation and electrical works are duly signed off by authorized engineers.
• Ensure that permits are authorized on the day of use.
• Ensure that permits are closed on the day of use.
No work can commence without the approving authority’s signature.
5.4
Minimum Acceptance for Permit Signatories
The key steps of validating, issuing, accepting, and endorsing of Permits is done by person who
has been assessed as competent. A permit signatory is someone who has been authorized and has
had sufficient training, knowledge, and experience to sign.
P a g e 8 | 23
6 Types of Permits
6.1
General
A written permit to work system provides formal written procedure and formal actions to
ensure that
potentially hazardous activities are carried out as safely as possible. The work permit is a
written document which authorizes persons to carry out the work concerned warns of possible
dangers and clearly states the precautions to be taken for the job to be carried out safely.
The permit ensures that full consideration is given to the hazards and risks, and that these are
properly dealt with, prior to commencement of the work.
The permit to work shall clearly specify the particular equipment and the construction area
involved, the extent of work allowed the conditions to be observed and the duration of the
permit. Whenever there is any doubt regarding the requirements for specific types of
permits, the HSE team should be consulted.
The instructions in the procedure are the minimum requirement and are mandatory.
Personnel must always comply with them and are not permitted to make arbitrary changes.
The present procedure considers the following permits:
• General Work Permit (cold)
• Hot Work Permit
• Confined Space Permit
• Electrical Work Permit
• Excavation Work Permit
6.2
Activities Requiring a Permit to Work
A Permit to Work will be required for the following activities:
• Any activity on live electrical equipment.
• Areas electrically classified.
• Closure of site roads to enable excavation and similar activities to be carried out.
• Confined space work (i.e., any work inside a manhole etc.).
• Connection to the electrical supply.
• Connection to the water supply.
• Crane Lifts; lifting operations over living lines / equipment.
• Disconnecting or opening of any closed pipeline or vessel containing flammable or
other hazardous material.
• Erection of site huts and lay down areas.
• Excavation and trenching.
• Facilities for the storage of cylinder gases, highly flammable liquids, paint or
similar hazardous materials.
• Hot work of any type, where heat is used or generated.
P a g e 9 | 23
•
•
Isolation/lock-out/tag-out.
Working in hazardous zoned areas.
6.3
•
•
•
•
•
General Work Permit (cold)
The general Work Permit shall be utilized for all activities requiring a Permit to Work,
other than those capable of generating or using sources of ignition.
The general Work Permit will facilitate all activities from scaffold erection to
those controlling activities such as pressure testing.
The general Work Permit has the facility to be validated for a period of 07 consecutive
days.
Revalidation of any Permit to Work shall remain at the discretion of Construction
Manager and only if all Permit Signatories are in agreement, that there is no significant
change in condition, changes in work schedule or there is no significant changes in
personnel.
Permits to Work shall clearly specify the particular equipment and the construction
area involved the extent of work allowed the conditions to be observed and the
duration of the permit.
6.4
Hot Work Permit
The Hot Work Permit shall be utilized for all activities requiring a Permit to Work, capable of
generating or
using sources of ignition. Some examples include:
• Electrical welding and use of welding machine,
• Flame cutting,
• Grinding (producing sparks)
6.5
Confined Space Permit
A confined space entry permit is required to allow personnel to enter a confined space such as a
blade, trench, tank, vessel, etc.
When hot work, cold work, electrical work, and/or energy isolation work is carried out in a
confined space, an additional permit(s) (as required by the type of work) must be applied.
Entry into confined spaces is subject to special requirements being put into place prior to the
commencement of work. This will include but not be limited to:
• Condition monitoring
• Presence of a Safety Watch Person
• PPE/RPE
• Emergency Escape Plan
P a g e 10 | 23
6.6
Electrical Permit
An electrical permit is required for work on electrical systems
where there is a possibility of contacting energized electrical conductors. Some
examples include:
• Work involving the installation or repair of electrical conductors,
• Connection or disconnection of electric motors,
• Reaching into any panel, transformer or other electrical enclosure which may have
energized circuits, capacitors, wiring, etc.
6.6.1 Lock out-tag out
De-energization (Isolation) may be required prior to installation, inspection, repair, cleaning or
dismantling. Where a job involves isolation of equipment, there shall be a work permit for the job
and a lockout and tag-out procedure shall be followed:
A lockout generally involves:
• Stopping all energy flows (for example, by tuning off switches or valves on supply
lines).
• Locking switches and valves.
• Securing the machine, device or power transmission line in de-energizer state.
Electrical isolation may be required to immobilize machinery or to protect personnel working
in electrical equipment. Situations involving electrical isolation including rotating machinery
and machinery with moving parts and entry into vessel which contain stirrers or agitators.
Electrical isolation should be performed only by a competent electrical engineer.
Energization may be required for executing pre-commissioning electrical test. Where a job
involves temporary energization, there should always be a work permit for the job and a
power on and power off procedure should be followed.
• The padlock has to be provided with a tag reporting:
• ID number as recorded in the isolation logbook.
• Date and time of lock out.
• Name and signature of the individual who installed the padlock and the reason of the
installation.
• Warning tags has to be properly secured with wire to the isolation points to ensure the
same does not fall off.
An example of a Warning Tag and Tag-out and lock-out are shown in Figure 3.
P a g e 11 | 23
Figure 3. Example Warning Tag and Tag-out/Lock-out tags.
If the equipment is provided with an electrical isolation facility available on the field (e.g.
start/stop button or other switchgear) then the Competent Electrical Engineer should attempt
electrical start test in the field. This is to ensure that the equipment is no longer live and to
verify that the electrical isolation is effective. The Competent Electrical Engineer then, shall
fit a second numbered padlock, together with a “Danger: Do Not Operate” tag, to the local
electrical isolation point.
In situation where it is not possible to lockout or chain off an isolating device, isolation may be
accomplished by removal of fuses, disconnection of electrical cables or physical removal of a
component of the system supplying energy to the equipment. The point of physical interruption
shall be identified with a dedicated tag.
If other organizations or individuals working on equipment shall also install their locks and
tags at locations have to be fit. In that case multiply lockout clips (Hasps) shall be used if
necessary. When all padlocks will be removed energization will be possible. An example of
Hasps is shown in Figure 4.
Figure 4. Example HASP
P a g e 12 | 23
The Competent Electrical Engineer shall report all actions on the substation logbook for record
purpose. As a general rule other discipline engineers cannot interfere with any electrical
isolation work to be executed inside the substation for safety reasons and nobody (with the only
exception of the Competent Electrical Engineer) can take or keep the padlock keys for their
scopes.
Field HSE Supervisor should hold spare keys for all Lock Outs. This ensures no keys will go
missing.
6.6.2 Execution of Energization, Removal of Tags, Padlock and Restoration of Power
The case where ENERGIZATION is required, the Competent Electrical Engineer shall proceed
to energize the equipment. The following procedure covers the energization for safe execution of
the pre-commissioning electrical tests.
• If a padlock and a tag are installed (to show that the switchgear is isolated) the Competent
Electrical Engineer shall remove both of them.
• The Competent Electrical Engineer will give power to the equipment.
• As soon as the equipment is energized the Component Electrical Engineer shall
hung a tag “IN SERVICE” close to the switchgear, as shown in Figure 5.
The Competent Electrical Engineer shall report all actions on the substation logbook for record
purpose.
Figure 5. Example of “In Service” tag.
6.7
Excavation Permit
An Excavation permit is required for any excavation or ground disturbance activity that
involves digging, trenching, excavating, or removing soil or ground.
P a g e 13 | 23
A designated spotter will be added to the permit when mechanical equipment is being used
to excavate or disturb the ground such as trenchers, backhoes, excavators, etc. This will ensure
adequate observation is being conducted to prevent hitting underground utilities and to
detect any unusual objects or sounds.
6.8
Permit issuance and duration
The Permit to Work will involve the following steps shown below:
1. Conduct a thorough risk assessment and determine who is at risk, what control measures are
necessary to eliminate the hazards, and the level of residual risk.
2. Prepare a written system of work identifying the following:
•
List Isolation / Pre-work precautions
•
List prohibited activities (communicate to others as necessary)
•
List Plant and Equipment required
•
List Personnel Protective Equipment to be used
•
List sequence of events as planned with identified hazards/residual risks and controls
clearly defined
•
Emergency procedures for all foreseeable risks (ensure that procedures are conveyed to
competent persons and fully understood)
3. Discuss the hazards and controls necessary to prevent them from occurring with those who
will be required to operate under the Permit to Work (for example during Toolbox Talks and
STARRT card).
4. Ensure that those conducting the task know that the safe system must be followed in full, and
that no other methods or sequence of work are allowed (i.e., work must stop, all persons
withdrawn, and the safe system reviewed by the Authorized Person). If the safe system is found
to be flawed, then the Permit must be cancelled, the system of work reassessed, a new Permit
raised, and those conducting the task re-briefed.
5. Ensure that the permit is displayed at the work site, to provide information to all those who
need to know.
6. Ensure that the work area is clean, tidy, and that all safety devices have been replaced and are
functioning correctly, prior to inspection by the Authorized Person.
The Permit to Work can be invalidated under any of the following conditions:
•
•
•
The conditions on the permit are not complied with.
Area or unit conditions change, e.g., venting or spillages of hazardous materials occurred,
etc.
Any time an emergency or alarm raises at the site, ALL PERMITS ARE
SUSPENDED. This confirms that personnel are disengaged from the work and that all
P a g e 14 | 23
work activities cease during an emergency or perceived emergency.
The validity of the Permit:
DOCUMENT
VALIDITY PERIODS
Work Permit (cold)
7 days
Hot Work Permit
1 day / one shift
Confined Space Permit
1 day / one shift
Excavation Work Permit
7 days
Electrical Work Permit
No validity period
Figure 6. Permit Validity Period
6.9
Permit closure
The Permit to Work will be considered to be closed when Advacon’s Issuing Authority (HSE
Team) signs the completion section of the Permit to Work (after receiving the confirmation on
the Permit to Work that the work is complete). Acceptance of this signature is conditioned to:
• Completion of the work according to the instructions.
• Cleanliness of work area, including the removal of all the work equipment.
• Re-installation of all safety conditions.
6.10
Layout and Color of Permits
The Permits to Work are in A4 format and for visibility purposes, to aid identification of
documents, different colors are used on the border of Permits as per Figure 7.
DOCUMENT
BORDER COLOUR
REFERENCE
Black
Attachment 1
Red
Attachment 2
Confined Space Permit
Dark Green
Attachment 3
Excavation Work Permit
Brown
Attachment 4
Blue
Attachment 5
Work Permit (cold)
Hot Work Permit
Electrical Work Permit
Figure 7. Permit and Certificate Identification Color Codes
P a g e 15 | 23
6.11
Emergency Response
Should any situation on site arise where there is a risk to personnel then the work shall cease
immediately, and the response taken shall be in accordance with Advacon’s Emergency
Response Plan.
P a g e 16 | 23
7 STARRT Card Briefing
P a g e 17 | 23
8 General (Cold) Work Permit
P a g e 18 | 23
9 Hot Work Permit
P a g e 19 | 23
10 Confined Space Work Permit
P a g e 20 | 23
11 Excavation Work Permit
P a g e 21 | 23
Download