Uploaded by gerardcorentin13

Project Management

advertisement
Project Management
Risk Management
Risk Management definitions
RISK MANAGEMENT DEFINITIONS
In the context of projects, risk is the chance that an undesirable event will occur and the
consequences of all its possible outcomes.
The objectives of project Risk Management are to increase the probability and impact of
positive events, and decrease the probability and impact of events adverse to the project.
Risk Management process
Risk Management should use the project WBS as the basis of the analysis.
STEP 1 Identify Risks
-Take a practical approach to Identify Risks
-Use the WBS as your starting point
-Be thorough in your analysis (explore all reasonable possibilities, but don’t be absurd in your
suggestions)
-Continue until all risks are identified
-If more detail is required, assign project team members to investigate
STEP 2 : Perform Quantitative Risk Analysis
Analyze the identified risks and determine which ones are most significant
Typical analysis characteristics for a Risk Event
– Probability of occurrence
– Magnitude of impact
– Ability to detect
Risk analysis
Follow this approach
Gather the Experts
– Use experienced project team members
– Analyze the risks as a group
Conduct Open Discussion
– Discuss each identifyed risk
– Assess each event in terms of Probability Impact
Ability to detect
Tabulate the Results
– Calculate as core for each risk
– Use a Risk Severity Matrix to show results
Prioritize and Assign Risks
– Ensure one project team member owns each risk
– Most probable owner is Work Package owner
Step 3 Risk response development
Plan Risk Responses – 4 types
– Risk Mitigation
Reduce the likelihood of occurrence Reduce the impact
Develop contingency plans
– Transferring Risk
Normally applies to high severity / low probability of occurrence risks Through contract terms
Insurance
– Sharing Risk
Agree to spread risk across parties
– Retaining Risk
Not feasible to do anything else
Project Manager must have a plan ready to execute if the risk occurs
Contingency planning
Technical Risks
– Identify alternative solutions
– Simulate alternative results
– Increase Design Reviews and Testing
Schedule Risk
– Trade-off decisions (Remember the Triple Constraint)
– Use of Slack Time in the schedule
– Schedule buffers
Funding Risks
– Total Budget / Cost
– Cash Flow
– Contingency Funding
Contingency funding
-Budget reserves :identified for specific work packages
Management reserve : covers unforeseen project risks (after budget reserves)
Risk response control
Monitor and Control Risks
– Execute Mitigation Strategies
These tasks MUST be added to the project schedule
Monitor the mitigation execution just as you would any other activity
– Monitor for Triggering Events
Ensure one project team member owns each risk for monitoring activity Report status at
regular project status meetings
– Initiate Contingency Plans
If a triggering event occurs, ensure contingency plan execution
– Continuous Assessment of New Risks
Hold additional risk identification reviews
Every risk consists of:
– An Event
– A Level of Impact
– A Probability of occurrence
Risk Management is a continuous process of identification and assessment that should continue
throughout the project
– Present regularly to the project team and stakeholders
– Continually assess the project for newly identified risks
Risk Management is proactive, not reactive
– Build risk mitigation strategy and plans up front
– Include mitigation plans in the project schedule
– Ensure proper levels of contingency in the schedule and the budget
– Establish a Management Reserve for unforeseen risks
A Waiver is a formalized procedure that, upon approval of the technical rationale behind the
request, allows an exception to some internal rule.
Download