Available online at www.sciencedirect.com ScienceDirect Available online at www.sciencedirect.com Procedia Engineering 00 (2017) 000–000 ScienceDirect www.elsevier.com/locate/procedia Procedia Engineering 202 (2017) 88–108 4th International Colloquium "Transformer Research and Asset Management” Bushing Failure- Investigation process & findings Tarik Al Abria, Mohan Lala, Ibrahim Al Balushia, Mohammed Al Zedjalia Oman Electricity Tranmission Company ,P.O BOX:1389 ,Al Khoud P.C:132 ,Omana Abstract Between 28 August 2011 and 8 September 2011, five 33kV OIP bushing failures occurred at JBB Ali Grid Station belongs to Oman Electricity Transmission Company (OETC). Three failures resulted in a complete loss of supply and around 130,000 consumers were reported with a lack of electricity. OETC assigned a third party investigator to conduct a power failure investigation in order to obtain a possible root cause for these failures. The investigation approach or process that were followed included the following phases: • Phase 1: Facts finding and preliminary analysis • Phase 2: Destructive dismantling and laboratory investigation through. • Phase 3: Root cause analysis. From the investigation and buildup of hypothesis, no single most likely cause of failure could be identified. Metal migration and semi-conductive copper sulphide migration in the oil that led to surface contamination of insulation in the stress zone is considered causal factor for bushings insulation degradation. Copper sulphide in bushing was detected caused due to corrosive Sulphur in oil. There has to be another factor influencing the weakened insulation breakdown. The source of this factor can be found in the suspected frequently occurring earth faults in the 33 kV line feeders, leading to a line voltage to ground of 33 kV and transient over voltages due to switching off the faulted feeder. * Tarik Al-Abri. Tel.: +96899501136; fax: +96822309046. E-mail address: tarik.alabri@omangrid.com 1877-7058 © 2017 The Authors. Published by Elsevier Ltd. Peer-review under responsibility of the organizing committee of ICTRAM 2017. 1877-7058 © 2017 The Authors. Published by Elsevier Ltd. Peer-review under responsibility of the organizing committee of ICTRAM 2017. 10.1016/j.proeng.2017.09.697 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 2 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 2 Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 89 All the OIP bushings were supplied in the same patch filled with the same oil and operated in identical service All the OIPsobushings wereofsupplied in the patch filled with theconsidered same oil and operatedstate. in identical service conditions degradation insulation as same chemical process can be in similar Electrically all conditions so degradation insulation as chemical processstresses can beasconsidered in are similar state.inElectrically all bushings were subjected to of identical voltage and load related transformers operated parallel. Thus bushings wereofsubjected identical and as load related stresses as transformers areofoperated parallel. Thus combinations these twotofactors are voltage considered causal factor for frequent breakdown multipleinbushings. combinations of these two factors are considered as causal factor for frequent breakdown of multiple bushings. © 2017 The Authors. Published by Elsevier Ltd. © 2017 The Authors. Published by Elsevier Ltd. Peer-review under responsibility responsibility of Elsevier the organizing organizing committee of of ICTRAM ICTRAM 2017. 2017. Peer-review of the © 2017 The under Authors. Published by Ltd. committee Peer-review under responsibility of the organizing committee of ICTRAM 2017. Keywords: Bushing; tan δ; Bushing failure; contamination; deposits; transients; JBB Ali; Mudhairib; Investigation; Stress Zone; ESM/EDS Keywords: Bushing; tan δ; Bushing failure; contamination; deposits; transients; JBB Ali; Mudhairib; Investigation; Stress Zone; ESM/EDS 1- Introduction 1- Introduction The OETC network voltages comprise of 400KV, 220kV and 132 kV, and include 132kV/33kV substations feeding The network voltagesofcomprise of 400KV, 220kV and 132 kV, 132kV/33kV into OETC the primary substations the distribution companies at 33kV. Oneand of include the substations amongsubstations the OETCfeeding 132kV into the primary substations of the distribution companies at 33kV. One of ittheis substations thesubstation. OETC 132kV network is JBB Ali (132/33kV). Since this substation is a radial substation considered among a crucial This network is is JBB Ali (132/33kV). Since this substation a radial substation itIncoming is considered a crucial substation equipped with two 132/33kV, 125 MVAispower transformers. feeders to the substation. transformerThis are substation is equipped with two 132/33kV, 125 MVAGeneration power transformers. Incoming feeders to the transformer are from the 132kV overhead line from Al-Kamil Power plant. from the 132kVfive overhead lineoccurred from Al-Kamil Power Generation plant. The following incidents in 132/33 kV substation JBB Ali: following five incidents occurred 132/33 substation JBB Ali: 2011 at 19:10 hrs,in125 MVAkV Transformer T2 tripped. •The On 28th August th August 2011 at 19:10 MVA Transformer •• On On 28 3rd September at 19:25 hrs,hrs, 125125 MVA Transformer T1T2 at tripped. JBB Ali substation tripped due to failure of 33kV • On 3rd September at 19:25 of hrs, 125transformers MVA Transformer T1 at JBB due tothat failure of 33kV Y-phase bushing. Outages both at the substation ledAli to substation a black-outtripped in the zone was fed from Y-phase Outages of both transformers at the substation led to amaintenance black-out inteam the zone that was from the JBB bushing. Ali substation. Following this black-out situation, an OETC swapped the fed R phase the JBB of AliT1substation. Following black-out situation, an OETC maintenance swapped2011 the R September at phase 13.26 bushing transformer to the Ythis phase of T2 and energised transformer T2 on 4thteam th bushing of T1 transformer to the Y phase of T2 and energised transformer T2 on 4 September 2011 at 13.26 hrs. • • hrs. This replaced bushing failed however after 18 hours, on 5th September 2011 at 07.36 hrs. This caused second This replaced bushing 18 hours,inonthe 5thshortest September at 07.36 hrs. This caused second subsequent zone black failed out. Tohowever restore after this black-out time 2011 possible, an OETC maintenance team subsequent black out. To restore from this black-out the shortest time possible, OETC maintenance team removed onezone set of identical bushings Mudhairibinsubstation and replaced the an failed bushing of Y phase at th removed set of identical bushings energised from Mudhairib replaced failed of Ybushings, phase at Septemberand 2011 at 3.58thehrs. Thebushing other two T2. This one transformer was eventually on 6 substation th September at 3.58 hrs. The T1 other bushings, T2. This from transformer wassubstation, eventuallywere energised on 6on received Mudhairib assembled T1 at Y and2011 B phase. Transformer wastwo energised on th from at Mudhairib September 1.57 hrs. substation, were assembled on T1 at Y and B phase. Transformer T1 was energised on 7received • • th September at 1.57 hrs. hrs T2 tripped again due to failure of B phase bushing. Following this failure OETC 7On 7th September at 18.33 th On 7 September at 18.33 hrs T2from tripped failure of B phase bushing. this failureT2 OETC replaced all the three bushings T2 again with due threeto new bushings received fromFollowing the manufacturer. was • • replaced all three bushings T2 bushing with three new bushings received the manufacturer. T2 was 18.33from hrs after replacement and was kept atfrom no load. energised on the 8th September th energised on 8 September 18.33 hrs after bushing replacement and was kept at no load. On 8th September at 19.48 hrs T1 tripped due to failure of R phase bushing (5th bushing from the lot of 6 at this at 19.48 T1 tripped due to failure R phase bushing (5th bushing from the lot from of 6 atT2this On 8th September substation). Following this hrs failure OETC replaced the Rofphase bushing of T2 with the bushing taken Y substation). Following OETCsubstation. replaced the R phase bushing of T2 with the bushing taken from T2 Y phase, the one brought this fromfailure Mudhairib phase, the one brought from Mudhairib substation. Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 90 3 Figure 1 shows the schematic representation of the failures. Following these occurrences, a third party was assigned by OETC to conduct a power failure investigation. Figure 1: Schematic representation of the incidents Nomenclature OETC JBB Ali SEM EDS LV PD Oman Electricity Transmission Company Jaalan Bani Bu Ali Scanning Electron Microscope Energy Dispersive Spectrometer Low Voltage Partial Discharge 2- Approach of Failure Investigation In this section, the adopted approach towards the investigation of failure incidents is described. The failure investigation was conducted in three subsequent phases: 2.1 Phase 1: Data collection and preliminary analysis Data collection and preliminary analysis of facts and reporting with recommended plan of action for investigation are part of phase 1. Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 91 4 2.1.1 Data collection Data collection is the key process of the investigation. The status of the failure site was maintained till visit the site and collects necessary evidence and data. All possible available data relevant to the incident were collected via the following channels: − Data request / questionnaire − Interviews with client / stakeholders staff − Visit to failure site − Physical inspection of the available damaged components − Photographs taken during investigative inspection. The following data had been collected: • Failure incidents sequence as shown previously in Figure 1 • SCADA event data • Loading data • Normal operation philosophy The single line diagram of JBB Ali grid station is shown in Figure 2. It can be seen the both 125MVA transformers T1 & T2 are fed through direct connection of 132KV feeders (Al-Kamil 1 & 2). The SLD shows the boundary between OETC and Distribution Company as both transformers are connected to 33KV bus bars with 33KV outgoing OHL feeders which are belong to the distribution company. Figure 2: Single line diagram of JBB Ali Grid Station Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 92 5 The transformers are equipped with oil impregnated paper LV bushings of type COT 170-2500. The nameplate details and failed bushings serial numbers were also collected. 2.1.1.1 Pre-service history of bushings Six transformers of same type were supplied in a lot against an order to OETC. Two of these six transformers were installed at JBB Ali, another two at Mudhairib grid station and two at Sur grid station. All six transformers were fitted with 33kV bushings. Bushings were routine tested at the manufacturer facility. Thereafter, from the review of available transformer factory test reports and site pre-commissioning test reports it can be stated that bushings were not independently tested for any electrical tests i.e. tan Delta or capacitance test. 2.1.1.2 Post service history Transformer T1 and T2 were commissioned in June 2002. Transformers’ routine maintenance is carried out on two yearly bases. No information could be gathered on last date of bushing visual inspection. There was no record available for off line visual inspection of these bushings. On 11 January 2011 on-line partial discharge (PD) measurements and Infrared measurements were carried out on the transformers. The UHF method was applied to measure PD. No PD activity was detected inside the transformers. Infrared measurements indicated no abnormality. 2.1.1.3 (Recent) maintenance/diagnostics Following the third failure of a bushing, and prior to replacement of the bushing from Mudhairib grid station, OETC maintenance team carried out tan delta and capacitance testing of the R & B bushings at transformer T2 and B bushing at transformer T1. Results are abstracted in tables below. Table 1: Capacitance & Tan delta test results for R & B phase bushings from T2 Table 2: Capacitance & Tan delta test results for B phase bushing from T1 In addition to these measurements on 6 September 2011 transformer T1, T2 turn ratio test was carried out, Transformer oil BDV test was performed, 33kV cable insulation resistance was checked, neutral grounding resistance was tested for its value. All results are within limits. Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 93 6 2.1.1.4 Protection recordings Protection logs of three trip incidents were only available and were collected during site investigation. Following three files were found: − TX diff-2 (failure 28-08-2011 19:10:29) refers to Trip incident 1, Differential current: 0.72A (Y-phase) − TX diff-1 (failure 03-09-2011 19:25:11) refers to Trip incident 2, Differential current: 2.2A (Y-phase) - TX diff-1 (failure 08-09-2011 19:48:53) refers to Trip incident 5, Differential current: 0.389A (R-phase) From the analysis it appears that differential protection relay operated as expected. 2.1.1.5 Site Inspection of Failed Bushings All five failed bushings had been inspected at site. Most of the bushing had exploded oil conservator or top and bottom oil seal damage. In addition, the 2nd failed bushing’s porcelain insulator exploded and others were having broken sheds. In most of the bushings, the copper part inside the conservator was blackened as well as a small part of the copper above oil conservator. The healthy bushing was inspected visually and it is normal. Two oil samples was collected, one from a failed bushing that was not exploded and other sample from T2. The healthy bushing (Figure 3 (f)) was tested for tan delta at 10KV test voltage and the results was 0.299% which is within the acceptable limits. (a) 1st Incident (b) 2nd Incident (c) 3nd Incident Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 94 (f) (d) 4th Incident (e) 5nd Incident 7 Healthy Bushing Figure 3: Inspected failed & healthy bushings 2.1.1.6 Action Plan Following Site Investigation The preliminary observations are that there are number of similarities between the failures: − Bushings are identical of same make, type and model. − Bushings were installed on the transformers installed at one grid station, same make and model. − Bushings failure took place at same grid station though at different transformers operated in parallel. − Both transformer loading patterns were identical and both were not loaded to full capacity. − There was pressure build up in the bushing caused due to internal fault. − Three out of the five failures occurred on Y phase bushings. − Four out of five failures occurred during evening hours (First incident at 19.10; second at 19.25, fourth at 18.33 and fifth at 19.48, only the third incident happened at 07.36) It was recommended to carry out detailed dismantling at OEM factory of all the failed bushings followed by a Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 95 8 destructively dismantling of the un-failed bushing removed from service from JBB Ali substation. During dismantling, samples will be collected of the failed component for a laboratory inspection based on the observations made during the dismantling. The possible tests are: − Testing and analysis of paper, chemical and microscopic (chemical analysis of paper i.e. degree of polymerisation, scanning electron microscope (SEM)) − Testing and analysis of copper − Testing and analysis of oil − Oil sample from a failed bushing has been collected for testing, DGA, Oil chemical and physical properties. − Carry out routine testing of un-failed bushing. − Oil sample from un-failed bushing taken for testing prior to destructive dismantling. 2.2 Phase 2: Destructive dismantling and laboratory investigation Dismantling of failed equipment or its components and laboratory investigations of failed components are performed during this phase according to the action plan. All five failed bushings and the healthy bushing were destructively dismantled. Black rings were noticed at different locations of the healthy bushing’s winding. Photographs were allowed to be taken by the manufacturer for the failed bushings only. The following samples were collected during bushings’ dismantling (see Table 3). Table 3: Collected samples during dismantling Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 96 9 2.3 Phase 3: Root Cause Analysis 2.3.1 Analysis of observations on bushings (field and factory inspection) From the review of observations during dismantling and analysis made at five failed bushings it can be stated that: − Four out of five bushings had sudden pressure surge due to fault and caused explosion of oil conservator and oil seal burst. − Four out of five bushings had an exploded winding on the air side of the bushing. − Three out of five failed bushings have the fault location on the upper edge of the ground layer i.e. starting point of upper axial stress zone (see Figure 4). − At one of the bushings, the fault location lies in the upper radial stress zone approaching the radial stress zone. − One of the bushings had a fault in the radial stress zone. However this bushing also showed signs of dielectric breakdown at the location starting point of upper axial stress zone. − No failure was found on the oil side of the bushing. From this basic analysis it can be stated that bushing faults have occurred or initiated at starting point of upper axial stress zone as it is demonstrated in Figure 5. Figure 4: Radial and axial stress zones in a bushing Tarik Al Abri et al. / Procedia Engineering 202000–000 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 97 10 Figure 5: Five Failed Bushings arcing locations Bushing which was not failed but was taken out of service on dated 8 September 2011 by OETC was dismantled at the factory. Evident black rings were observed at the bushing winding, the location of rings was found to match with the concentric zone of radial stress. The prominent rings were found, formed at 540mm in the air side and even on the oil side; at both locations matching with the edge location of the ground layer, while other non-prominent deposits in ring shape were aligned to inner foil edge (see Figure 6). The black ring formation appeared as a deposit in appearance with naked eye and paper sample from that location was later investigated at the lab through EDS. From this basic analysis it can be stated that black ring formation at the outer layer of winding matches the starting point of upper and lower axial stress zone. 2.3.2 Analysis of material test results 2.3.2.1 Oil analysis During the investigation the following oil samples have been taken: − Transformer T2 − Failed bushing − From healthy bushing prior the destructive dismantling of the bushing. Samples were collected before and after the repetition of the routine tests. Al Abri al. / Procedia Engineering 202 (2017) 88–108 TarikTarik Al-Abri et al.et/ Procedia Engineering 00 (2017) 000–000 98 11 Figure 6: Black rings deposits on healthy bushing The following parameters has been tested on all the oil samples: - Dissolved gas analysis (DGA) Corrosive Sulphur content Dibenzyl Disulphide (DBDS) Bushing oil samples were also tested for - Dissolved metal in oil Dielectric Dissipation factor (DDF) Acidity No specific observations were made on an oil sample of the transformer oil. Oil from the failed bushing indicated high energy electric discharges. Water content was found, while breakdown voltage was low. The DDF measurement at 90oC can be stated high. Oil was found non corrosive. Small copper and silicon concentration was detected. Oil from unfailed bushing was analysed and considered oil dissolved gas analysis results as reasonable for 10 years old bushings in service. The results of the investigation show no discharges and/or thermal faults in the bushing. No significant dissolved metal in oil has been found. Oil was detected as non-corrosive and no DBDS was found. DDF test was carried out at 90oC before testing and the value was 0.0561 with 24 GΩ resistivity. After testing value was 0.0450 with 21 GΩ resistivity. Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 99 12 2.3.2.2 Paper analysis Five paper samples were collected from different failed bushings. The following analysis was carried out for the collected samples. - Paper DP testing Degree of Polymerisation (DP) test on the paper sample from the un-failed bushing was performed. Three samples were collected. − − − One from top layer One from middle and One from bottom layer DP was tested and appeared to be 497, 480 and 512 respectively. One sample of the new kraft paper collected during visit to the factory and was also tested with DP value of 1339. The DP vale of paper indicates normal aging of the paper insulation in the bushing. - SEM/EDS Testing Several Scanning Electron Microscopic (SEM)/ Energy Dispersive Spectrometer (EDS) analysis are performed on the paper samples of the failed and unfailed bushings. Paper samples were collected during destructive dismantling. The areas investigated were blackened rings around the paper insulation of the good bushing, near the hole of the paper where the test tap comes out of the bushing, identified particles on the paper and paper near the fault location. Several black fibres are identified in the paper samples. From the stereo microscope this appeared to be a (paper) fibre coming out of the surface of the paper (see Figure 7). Figure 7: Black paper fibre EM/EDS analysis on the deposits found around the hole where the (test tap ground) connection is made from the first capacitive layer to the test tap. Several elements were found in the vicinity of the black hole, such as: Carbon, Oxygen, Chlorine, Zinc, Tin and Lead. Also small amounts of sulphur and calcium are found. The traces of Zinc and Chlorine are most likely to come from the use of soldering water for realizing the soldering of the connection of the test tap. Tin and lead are likely to come from the soldering itself. The origin of carbon is expected from the paper while sulphur is expected from oil or from sealing gaskets. The presence of calcium is unclear, only expected as 100 Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 13 remains from the environment during manufacturing process. Figure 8: Microscopic and SME/EDS picture of paper at Test tap hole Black rings that are available in the healthy bushing (see Figure 9) was analysed through SME/EDS (see Figure 10). An EDS analysis showed that the deposit contains the following major elements, being copper, sulphur, oxygen, zinc and carbon. Incidentally iron have been also found between the paper fibres. (a) (b) Figure 9: (a) Black deposit rings observed (b) SEM/EDS picture – black deposit on paper, elements analysis Another sample of paper with aluminium foil was analysed from a failed bushing which is shown in Figure 10 (a). Since the area near the edge of the aluminium foils is critical, it was decided to analyse this sample. Besides that the damage shows some discharge or treeing like effect on the aluminium foil, see Figure 10 (b). The results of this analysis shows that the majority of elements found are Carbon, Oxygen and aluminium. Negligible amounts are found of Silicon, Sulphur, Calcium and Iron. In this sample no traces of copper is found. Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 (a) 101 14 (b) Figure 10: Paper sample with aluminium foil To have larger picture, one more sample of paper from the fault location of one of the failed bushings had been analysed as shown in Figure 11 (a). (a) Figure 11: Paper sample from fault location (b) The sample taken from one of the failed bushings shown above has been divided into three samples, corresponding to the three burnt paper holes. See Figure 11 (a). The major hole, where the actual fault from the conductor to ground took place, shows the presence of copper (from the conductor), Aluminium (from the Aluminium layers) and Calcium. Other minor elements found are Sulphur and Magnesium. The analysis of the lowest hole with the crack and the most right fault location showed the presence of Carbon, Oxygen, Chlorine, Aluminium and Calcium. Trace amounts of Iron, Sulphur and Copper have been found here. Besides that the most right location also showed the presence of silver particles, indicated as number 2 of the Figure 11 (b). Point number 1 is an Aluminium particle. Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 102 15 One more sample of Darkened paper from the top of a failed bushing was analysed, see Figure 12. The analysis of the deposit showed the presence of sulphur, copper, Carbon and Oxygen. Traces of Aluminium, Zinc, Silicon and Calcium were also found. Figure 12: Blackened paper sample 2.3.2.3 Copper analysis The copper conductor of the healthy bushing has been analysed, since it had been found black deposits around the copper and wanted to know the content of these deposits. The white line in Figure 13 (a) shows the tested copper sample. (a) (b) Figure 13: Copper stud from Healthy bushing A detailed view and element analysis see Figure 13 (b), shows that sulphur has been detected in combination with a majority of copper indicating a likely deposit of copper sulphide. Other elements found are, Carbon, Oxygen and trace amounts of Nitrogen, Zinc and Calcium. A sample of failed bushing was investigated and shows approximately the deposits as above. Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 103 16 2.3.2.4 Healthy Bushing Routine Tests at the factory The healthy bushing was tested for routine tests at the factory with 85% withstand voltage as per IEC 60137-2008 standard. The bushing passed the test successfully. In addition, the bushing was tested for tan delta and capacitance for the bushing as well as for the test tap. The results were compared with factory tests of 18bushings supplied at the same time. Comparative test result analysis for tan delta of all 18 bushings produced in one lot exhibit variation of over 35% while the capacitance value variation is up to 7.37%. The variation in measured values of the test tap capacitance and tan delta is of the order of 20% and 376%, respectively. From this it can be stated that comparative assessment for condition of bushings cannot be implied with test results of tan delta and capacitance values of same family bushings even produced in one lot. While comparing the test results of the healthy bushing from the December 2011 results to 2001 results, the bushing tan delta value was found 40% higher at 10 kV while capacitance value can be stated quite comparative. From the comparison of capacitance values bushing condition can be stated good. Change of over 5% in capacitance value is recommended to take the bushing out of service. The variation in measured values of the test tap tan delta and capacitance is of the order of (-) 75% and (-) 13%. It cannot be used a criterion for condition assessment. 2.3.3 Failure Hypothesis The followed approach of the failure investigation, different failure hypotheses are formulated (including less probable ones) in order to determine the root cause of the failure and to exclude less likely causes. Each failure hypothesis result is weighted on a scale of 0 to 4 for causal factor of failure. Weightage of scale is as following: 0 – Highly unlikely 1 – Unlikely 2 – Possible 3 – Likely 4 – Highly likely The following possible failure scenarios are evaluated to determine the root cause of failure of the bushings: 1- Pre-service related factors No evidence was found of any concerns that can be related to pre-service related factors. Though there were some observations on the paper where some black linings were seen however appeared as paper fibre of that colour. Installation of oil filled bushings with oil level view glass in an enclosed cable box is considered as a matter of concern though could not be related to failure incidents. Pre-service factors are rated at “0” on the scale of 0 to 4 for causal factor of failure, so is considered a highly unlikely cause of failure. Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 104 17 2- Crack in insulation body Cracks in the porcelain may lead to loss of oil while cracks in epoxy insulation may lead to mixing of bushing oil with transformer oil. There were no observations or evidence found on the failed bushings related to a crack in the insulation body. Cracks in the insulation body is rated at “0” on the scale of 0 to 4 for causal factor of failure, so considered as a highly unlikely cause of failure. 3- Leakage of oil The leakage of bushing oil can take place during service life of the bushing due to failure or aging of gaskets, seals or axial movement of the porcelain. Bushings are fitted with oil level observation glass and are designed for installation outdoor in such a way that regular monitoring of the oil level can be done. It was noticed that bushings are installed in a covered cable box where such monitoring is not possible under on line condition of the transformer and is feasible only when the cable box cover are removed and level inspected. No documented record of such inspection was available. Subsequent to the first two failures after each incident the oil level of the surviving bushings was checked by OETC and found in order. To have a situation where the oil was lost in the relatively short period between restoration and failure would have required a major oil leak and there was no evidence to suggest that. Last failed bushing still had oil intact. There was no evident sign of low oil level in any of the failed bushings so leakage of oil is rated at “0” on the scale of 0 to 4 for causal factor of failure, so considered highly unlikely cause of failure. 4- Disconnection of earthing link of test tap A loosely threaded cap can lead to poor contact of the ground connection and can lead to electrical discharges at the test tap location. This will eventually lead to failure of the bushing. In none of the failed bushings such evidence is found. Hence, this cause is rated at “0” on the scale of 0 to 4 for causal factor of failure, so considered as a highly unlikely cause of failure. 5- Loose connections at current carrying joints Loose connections at current carrying joint become a source of heat. This will lead to a gradual oxidation of the contact point and subsequent progressive increase in contact resistance. This process continues and a thermal runaway can originate. There was no evidence of a thermal runaway so this factor is rated at “0” on the scale of 0 to 4 for causal factor of failure, so is considered as highly unlikely. 6- Issues related to insulation oil • Oil contamination From the available site test records on two out of five failed bushings and from the testing of the unfailed bushing at factory, no such evidence could be found. This factor is rated at “0” on the scale of 0 to 4 for causal factor of failure, so considered as a highly unlikely cause of failure. • Deterioration in oil quality while in service Dielectric dissipation factor values as per IEC 60422 were found in acceptable range. Change of DDF with temperature is expected though there is an observation that oil DDF adopted a sharp rise with temperature that gives Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 105 18 an indication of possibilities of presence of polar compounds. Further, the presence of oil decomposition products such as sludge was noted during EDS investigation of the copper stem from un-failed bushing. Despite the fact that the sample was degreased, still considerable amounts of carbon were present. With above evidences this factor can be considered as a contributing factor to a limited extent so rated at “1” on the scale of 0 to 4 for causal factor of failure, so considered as an unlikely cause of failure. • Corrosive sulphur Bushings were filled with a type of mineral oil. Oil sample from the bushing was tested negative following IEC 62535 to determine whether oil is corrosive. DiBenzyl DiSulphide (DBDS) content was also found below detectable limit of 5 mg/kg. DBDS is the most common compound identified out of the identified few corrosive sulphur compounds so is normally tested along with corrosive test. Following test standards oil was found non corrosive. It is known that no single corrosive sulphur compound is responsible for corrosive Sulphur issues that are present in transformer oil. There can be number of different sulphur compounds present in the oil as sulphur compounds are present in crude oil. Few compounds/species are known to degrade from stable into reactive. Responsible factors identified for this process are service time, oxygen deficient environment (bushings under investigation are nitrogen blanketed) and temperature. SEM/EDS investigation of deposits over the copper stud (blackened area) gives ‘positive identification’ of copper sulphide (Cu2S), it is important to notice that the amount of sulphur is often equal or sometimes even higher than the amount of copper. Presence of copper and sulphur at paper samples was also found and presence of copper sulphide could not be ruled out. From above forensic investigation evidences it can be stated that bushing was affected with corrosive sulphur though the oil was tested “non-corrosive” following standard laboratory tests. With all mentioned facts taken together, corrosive sulphur is considered as a contributing factor in the failure. It can therefore be rated as “2” on the scale of 0 to 4 for causal factor of failure, so classified as possible cause of failure. • Metal migration in oil SEM/ EDS investigation of paper samples indicated that the black ring formed at the winding mainly contains − Copper − Sulphur − Zinc Some particles containing iron, calcium, magnesium could also be found. Traces of silicon and aluminium were also found at a few locations. The black ring is the accumulation of semi-conductive, conductive and polar particles. All these particles deposited on the surface of the winding paper during the service life of the bushing. The migration of metal particles took place with in the oil. It was noticed that deposition of these insoluble products occurred in areas of high electrical stress. Four out of five failed bushings’ fault locations matches with the location of deposits found on the winding at the unfailed bushing. The surface contamination can reduce the electrical strength of the insulation system. The rate of deposition in all the bushings operating in similar conditions at a substation can hypothetically Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 106 19 be considered same. This applies to the state of deposits within the bushings prior to failure, which could not be established. Deposition appeared to follow a pattern like treeing over the paper surface. The Oil DGA result could be stated normal for such bushing with no indications of partial discharges. Conclusion could be made that even if bushing had visible evidence of electrical treeing or presence of deposition of copper or sulphur, oil DGA may not indicate any gases related to partial discharge. These particles deposition formed a progressive close/semi close ring across the winding during the service life of 10 years. The deposition of metal and (semi)conductive particles initiated partial discharges under the influence of voltage. The fact remains that PD intensity during testing of the un-failed bushing at the factory was recorded below detection limit of 2pC so hypothesis shall only be considered with other contributing factors. The known fact is that five bushing failed with in a span of ten days, the logic of chemical process taking place in all the bushings operating in similar conditions at a substation can only support this hypothesis. The premature failure at OETC bushing have been caused due to deposition of metal, (semi)conductive particles and oil decomposition products at the active core of the bushing in the stress zone. The migration of metal and semi conductive particles has taken place in oil during the service life of the bushing. From this hypothesis, migration of metal is rated as “3” on the scale of 0 to 4 for causal factor of failure, so classified as likely cause of failure. Though, it shall be considered with other contributing factors. • Failure due to network transients Lightning or switching impulses can lead to bushing insulation failure. The day of the incidents was without any thunders / lightning and none of the bushing appeared to be failed at the time of reported switching. The known fact is that all the 33kV feeders from the substation are through overhead lines with short parts of cables used for road crossings. It could be observed that there have been instances of 33kV overhead lines conductor falling, jumper broken, cable lugs burnt that leads to ground faults. Single phase ground fault with resistive grounding will increase the phase-to-ground voltage of the remaining two phases to phase to phase voltage. Review of protection log indicates changes in HV currents along with measurable changes at 33 kV side, that makes us to develop an opinion that first fault occurred just after a fault occurred somewhere else (deeper in) the 33kV network though no feeder trip recorded at that instance. On 28th August 2011 at 15:04.45 there was a reported incident at Al-Kamil feeder 7L5 feeder tripping at distance protection that is about 4 hours prior to first bushing failure. Though it was reported to be an incident of jumper broken, phase of that jumper was not reported. It is likely that an over voltage affected the bushing at this incident and initiated the process of electrical discharges leading to first incident of failure, knowing the fact that bushings insulation were affected due to deposition of semi-conductive and conductive particles. In case of earth faults on 33kV feeders, if considered frequent, all the bushings will be stressed with a root 3 higher voltage as transformers are operated in parallel. Bushings with degraded insulation may cause a set of bushings to fail in a short period as experienced at OETC. Assumption is made that number of ground faults has significantly Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 107 20 increased in a period prior to the first fault. Assumption is made based on limited data received from the distribution company. From this hypothesis, network transients are considered as a likely factor under the prevailing insulation condition of the bushings so is rated as “3” on the scale of 0 to 4 for causal factor of failure. • Harmonics JBB Ali substation feeds BBC (British Broad Casting) relay station, a relay station contains power electronics and therefore the load will contain harmonics. No record of harmonic content was available. The load of BBC feeder was stated to be of the order of 7 – 8 MW. Load comparing to the capacity of the bushing is low. An important fact remains that out of the eighteen bushings supplied and installed at three different substations, only bushings installed at JBB Ali substation failed at the same period of time. The factor cannot be ruled out completely so rated at “1” on the scale of 0 to 4 for causal factor of failure, hence considered as an unlikely cause of failure. The resume of the evaluations of the failure hypotheses as discussed and elaborated above is presented in Table 4 as below. Table 4: Failure hypotheses Tarik Al Abri et al. / Procedia Engineering 202 (2017) 88–108 Tarik Al-Abri et al. / Procedia Engineering 00 (2017) 000–000 108 21 3- Conclusion In conclusion, five bushing failures were taken place in 125MVA transformer at JBB Ali grid station belong to OETC. To find the root cause analysis of the failure, an investigation was initiated. The investigation approach or process that were followed included the following phases: • Phase 1: Facts finding and preliminary analysis • Phase 2: Destructive dismantling and laboratory investigation. • Phase 3: Root cause analysis. From the investigation and developed hypotheses, no single most likely cause of the failures could be identified. Despite that a likely cause of failure is migration of metal in the oil leading to surface contamination of insulation in the stress zone it was also contributed by the presence of corrosive sulphur products i.e. copper sulphide. All the bushings can be considered in same state of insulation degradation due to this chemical process occurred in identical service condition and life time of the bushings. Since the above mentioned mechanism will probably not lead to a direct breakdown of five bushings within a span of two weeks, there has to be another factor influencing the failure of weakened insulation. The source of this factor can be found in the frequently occurring earth faults in the 33 kV line feeders, subjecting all the bushings to a line voltage to ground of 33 kV and transient over voltages due to switching off the faulted feeder, knowing that both transformers are operated in parallel during the service life. The combination with the surface contamination in the bushings deteriorated the dielectric withstand capability of the bushings leading to a frequent breakdown of multiple bushings. Acknowledgements We would like to thank Dr. Adil Al-Busaidi, Sr. manager-Asset Management & Planning Department and Ahmed Al-Rahbi, Manager-Asset Performance Management who motivated us to participate and contribute to Cigre. References [1] KEMA, Power failure investigation: Transformer bushings failure at JBB Ali Substation, 2nd Edition, 2012.