Uploaded by 徐漫书

pdfcoffee.com method-of-statment-of-fire-hydrant-2-pdf-free

advertisement
PROJECT: EARLY WORKS AT KFIP JUBAIL
Date:15-FEB-2014
CONTRACT No: 10006
METHOD of STATEMENT
MST-MECH-004.Rev 00
METHOD STATEMENT For INSTALLATION OF FIRE
HYDRANT AND MONITOR
1. Approved
2. Approved with comments
3. Disapproved
SADARA Review Result
1
Description
METHOD STATEMENT FOR
INSTALLATION OF FIRE
HYDRANT AND MONITOR
2
3
Date
Signature
Rev.
No
Date
Prepared by
Approved By
00
15-feb-2014
Karthick
Subramaniyan
Ragab El
Sayed
Page - 1
PROJECT: EARLY WORKS AT KFIP JUBAIL
Date:15-FEB-2014
CONTRACT No: 10006
METHOD of STATEMENT
MST-MECH-004.Rev 00
CONTENTS
1.0
FRONT COVER
2.0
CONTENTS
3.0
PURPOSE
4.0
SCOPE
5.0
REFERENCES
6.0
Unit Descriptor
7.0
PERFORMANCE CRITERIA
A. Preparation for work
B. Identify installation requirements
C. Install and test system
D. Clean up
8.0
Examples of Application
9.0 Range Statement
a. Unit scope
b. Safety (OH&S
c. Environmental Requirements
d. Quality Assurance
Page - 2
PROJECT: EARLY WORKS AT KFIP JUBAIL
Date:15-FEB-2014
CONTRACT No: 10006
METHOD of STATEMENT
MST-MECH-004.Rev 00
e. Statutory/Regulatory Authorities
f. Tools and equipment
g. Communications
h. Information
10. Evidence Guide
A. Critical aspects of evidence required to demonstrate competency in this unit
B. Relationship to other units
C. Specific knowledge required to achieve the performance criteria
D. The context of assessment
E. Methods of assessment
F. Specific resource requirements for this unit
Page - 3
PROJECT: EARLY WORKS AT KFIP JUBAIL
Date:15-FEB-2014
CONTRACT No: 10006
METHOD of STATEMENT
I
MST-MECH-004.Rev 00
PURPOSE
The purpose of this method of statement is to provide an overview regarding the various
procedures to be adopted during installation " WET" BARELL HYDRANT in Early works inside
KFIP project .This method of statement defines the specific roles of various construction
personnel’s involved in the process of installation " WET" BARELL HYDRANT. This method of
statement gives an overview regarding the various materials and equipment’s used for the
process installation of " WET" BARELL HYDRANT
II
SCOPE
The scope of this method of statement is limited to detail various construction processes
involved in installation of " WET" BARELL HYDRANT
III
REFERENCES
A554-F-PRG-SE-GEN-PHL-001 Sec 3.7
Hydrants shall be wet barrel type and in compliance with local
requirements. All hydrants shall be located near roadways and
accessible under fire conditions.
A554-F-PRG-SE-GEN-PHL-001 Sec 3.7
Hydrant spacing for inside unit battery limit shall not exceed 60 m
around process areas, offsite storage areas and near occupied
buildings. Maximum spacing around other areas shall be 90 m.
A554-F-PRG-SE-GEN-PHL-001 Sec 3.7
Hydrants shall be spaced a minimum of 15 m from the Equipment they
are intended to protect. Also, hydrants shall be no more than 6 m
from roads suitable for access by a fire truck.
Page - 4
PROJECT: EARLY WORKS AT KFIP JUBAIL
Date:15-FEB-2014
CONTRACT No: 10006
METHOD of STATEMENT
MST-MECH-004.Rev 00
A554-F-PRG-SE-GEN-PHL-001 Sec 3.8
Fire monitors shall be provided at strategic locations near and within
fire hazardous areas. Accessibility during a fire and direction of
prevailing wind shall be taken into account when locating the fire
monitors.
A554-F-PRG-SE-GEN-PHL-001 Sec 3.8
The following areas shall have fire monitor coverage:
A. Units containing more than 4 m3 of LPG.
B. Units containing more than 20 m3 of flammable or combustible
liquids.
C. Tank car and tank truck loading or unloading areas.
D. Process Equipment susceptible to runaway reactions during fire
exposure.
E. Cooling towers with combustible internals.
F. Jetties for ship and barge unloading of flammable or combustible
liquids.
A554-F-PRG-SE-GEN-PHL-001 Sec 3.8
Fire monitors shall be located such that all hydrocarbons handling
Equipment shall be protected by at least two monitor streams.
Hydrocarbon handling Equipment not accessible by fire monitor
coverage shall be protected by a water spray system.
A554-F-PRG-SE-GEN-PHL-001 Sec 3.8
Page - 5
PROJECT: EARLY WORKS AT KFIP JUBAIL
Date:15-FEB-2014
CONTRACT No: 10006
METHOD of STATEMENT
MST-MECH-004.Rev 00
Monitors shall have a minimum rated flow of 114 m3/ hrs. (500 gpm) at
6.9 barg (100 psig). High hazard areas may necessitate monitors with
higher discharge flow rates. The effective reach of the fire monitor
shall be 35 m (115 fit). Provisions shall be available to lock the
monitor in place during operation.
G4D-1010-05
Installation of the Guard for the Fire Hydrant & Monitors to be done as
per G4D-1010-05
RT4D-1012-11A & B
Commercial Hydrant with Monitor Gun shall be installed as per RT4D-1012-11A & B
RT4D-1050-03A & B
Fire Hydrant shall be installed as per RT4D-1050-03A & B
Unit Descriptor
This unit specifies the competency required to install fire hydrant and Fire
monitor systems. Work associated with this unit is undertaken within the
plumbing and services sector in accordance with relevant SADARA
standards. It has application to the fire services stream.
PERFORMANCE CRITERIA
1.
1 . Preparation
for work
1. Design drawings and job specifications are obtained from relevant
authority
2. OH&S requirements associated with fabricating and installing fire
hydrant and Fire monitor systems, and the workplace environment,
are adhered to throughout the work
3. Quality assurance requirements are identified and adhered to in
accordance with workplace requirements
4. Tasks are planned and sequenced in conjunction with others involved
Page - 6
PROJECT: EARLY WORKS AT KFIP JUBAIL
Date:15-FEB-2014
CONTRACT No: 10006
METHOD of STATEMENT
MST-MECH-004.Rev 00
in or affected by the work
5. Tools and equipment for fabricating and installing fire hydrant and
Fire monitor systems, including personal safety equipment, are
selected and checked for serviceability
6. Work area is prepared to support the efficient fabrication and
installation of fire hydrant and Fire monitor systems
2 . Identify installation requirements
1. System requirements are identified from job design
criteria, specifications and standards
2. Piping and materials are selected in accordance
with standards, design drawings/job specifications
and authorities' requirements
3. Below ground piping and materials are checked to
ensure compliance with standards and authorities'
requirements
4. Required materials and equipment are identified
and ordered/collected in accordance with workplace
procedures
5. Materials and equipment are checked for
compliance with standards, docket/order form and
for acceptable condition
3 . Installation and test system
1. System is set out in accordance with drawings,
specifications and job instructions
2. Pipe supports and fixings are installed to plans and
manufacturers' specifications
3. Piping and materials are installed in accordance
with the design drawings, job specifications and
standards
4. Pipework is connected to the water source in
accordance with standards and authorities'
requirements
5. Piping system is tested in accordance with
standards and job specifications
6. Test data is recorded in the format required by the
Page - 7
PROJECT: EARLY WORKS AT KFIP JUBAIL
Date:15-FEB-2014
CONTRACT No: 10006
METHOD of STATEMENT
MST-MECH-004.Rev 00
job specifications and quality assurance procedures
4 . Clean up
1. Work area is cleared and materials disposed of or
recycled in accordance with State or Territory
legislation and workplace procedures
2. Tools and equipment are cleaned, checked,
maintained and stored in accordance with
manufacturers' recommendations and workplace
procedures
3. Documentation is completed in accordance with
workplace requirements
Key Competency
Examples of Application
How can information be collected,
analyzed and organised?
Communicate ideas and information in
simple English to enable confirmation of
work requirements, passage of information
and requests to other workers during
operations and the reporting and recording
of work outcomes
Collect, organize, interpret and understand
the information required to Install fire
hydrant and Fire monitor systems, including
work instructions, manufacturers'
instructions, material safety data sheets,
drawings and sketches and equipment
instructions
Plan and organize activities associated with
fabricating and installing fire hydrant and
Fire monitor systems, including the
scheduling and use of equipment, materials
and tools to avoid backtracking and rework
Work with others and in a team by
recognising dependencies and using co-
How are ideas and information
communicated within this
competency?
How are activities planned and
organised?
How are problem solving skills
applied?
Page - 8
Performance
Level
1
2
2
1
PROJECT: EARLY WORKS AT KFIP JUBAIL
Date:15-FEB-2014
CONTRACT No: 10006
METHOD of STATEMENT
MST-MECH-004.Rev 00
operative approaches to optimize
satisfaction and productivity
How are mathematical ideas and
techniques used?
Use mathematical ideas and techniques to
collate applicable data, complete
measurements and calculations, calculate
material requirements and establish accuracy
checks used in relation to the fabrication and
installation of fire hydrant and hose reel
systems
1
How is use of technology applied?
Establish safe and effective work processes
which anticipate likely problems and
blockages and systematically work around
these to avoid or minimise reworking and
avoid wastage
1
How is team work used within this
competency?
Use workplace technology related to the
Installation of fire hydrant and Fire monitor,
including the use of calculators, levelling
systems, tools and equipment and the
reporting/recording of results
Range Statement
Unit scope


The unit requires the fabrication, installation and testing of fire hydrant pipework from a
main, or branch into main, to a Fire monitor system
Site location for work application may be either domestic or commercial, and may be a
new worksite, or an existing structure being renovated, extended, restored or maintained
Safety (OH&S)
Page - 9
PROJECT: EARLY WORKS AT KFIP JUBAIL
Date:15-FEB-2014
CONTRACT No: 10006
METHOD of STATEMENT



MST-MECH-004.Rev 00
OH&S requirements are to be in accordance with Territory legislation and regulations
and may include protective clothing and equipment, use of tools and equipment,
workplace environment and safety, handling of materials, use of fire fighting equipment,
use of first aid equipment, hazard control and hazardous materials and substances
Personal protective equipment is to include that prescribed under legislation, regulation
and workplace policies and practices
Safe operating procedures are to include but not be limited to recognising and preventing
hazards associated with the use of tools and equipment, trip hazards, service lines,
surrounding structures and facilities, hazardous materials, working in proximity to others,
worksite visitors and the public
Environmental Requirements

Environmental requirements are to cover water quality management and may include
waste management, stormwater protection and clean-up protection
Quality Assurance

Quality assurance requirements include SADARA Standards Organisation, internal
company quality assurance policy and risk management strategy, Environment Protection
Authority (EPA), site safety plan and workplace operations and procedures
Statutory/Regulatory Authorities

Statutory/regulatory authorities may include statutory plumbing authority and the local
council statutory authority
Tools and equipment

Tools and equipment are to include hand and power tools, manual excavation equipment,
trench shoring equipment, measuring equipment, levelling equipment welding equipment
and elevated work platform
Page - 10
PROJECT: EARLY WORKS AT KFIP JUBAIL
Date:15-FEB-2014
CONTRACT No: 10006
METHOD of STATEMENT

MST-MECH-004.Rev 00
Tools and equipment including lifting/load shifting equipment may also include
mechanical excavation equipment, ladders, hand trolleys, rollers, forklifts, scaffolds,
elevating work platforms, chain blocks, hoists and jacks
Information








Information sources may include but not be limited to verbal or written and graphical
instructions, signage, work schedules/plans/specifications, work bulletins, charts and hand
drawings, memos, material safety data sheets, diagrams or sketches
Safe work procedures relating to the fabrication and installation of fire hydrant and Fire
monitor systems
Regulatory/legislative requirements, particularly those pertaining to plumbing regulations,
building codes, OH&S and environmental requirements
Manufacturers' specifications and instructions
Organisation work specifications and requirements
Instructions issued by authorised organisational or external personnel
Relevant SADARA Standards
National Fire Protection Association (NFPA) and Factory Mutual Performance based
Codes of Practice
Evidence Guide
Critical aspects of evidence required to demonstrate competency in this unit



Locate, interpret and apply relevant information, standards and specifications to Install
fire hydrant and Fire monitor systems
Apply safety requirements throughout the work sequence, including the use of personal
protective clothing and equipment
As a minimum, given the specifications of a fire hydrant and Fire monitor system, install
a leakfree hydrant and Fire monitor system from an existing branch in a water supply,
using steel piping to design criteria and standards, ensuring:
o correct identification of location, design and details of proposed installations
o correct selection and use of appropriate processes, tools and equipment
o completing all work to specification
Page - 11
PROJECT: EARLY WORKS AT KFIP JUBAIL
Date:15-FEB-2014
CONTRACT No: 10006
METHOD of STATEMENT
MST-MECH-004.Rev 00
o

compliance with regulations, standards and organisational quality procedures and
processes
Communicate and work effectively and safely with others
Relationship to other units


AMCC Carry out OH&S requirements
Where related units form an integral part of workplace responsibilities and roles, they can
be assessed concurrently
Specific knowledge required to achieve the performance criteria

A knowledge of:
o the SI system of measurements
o workplace and equipment safety requirements
o the relevant statutory and authority requirements related to the Installation of Fire
hydrant and Fire monitor systems
o materials and assemblies relevant to the installation of Fire hydrant and Fire
monitor systems
o characteristics and the application of different pipe fittings and fixture supports,
including fixing and joining techniques
o excavation processes and procedures
o levelling and alignment processes
o pressure test systems and procedures
o the process of Fire hydrant and Fire monitor systems
o JSA's/Safe work method statements
Page - 12
PROJECT: EARLY WORKS AT KFIP JUBAIL
Date:15-FEB-2014
CONTRACT No: 10006
METHOD of STATEMENT
MST-MECH-004.Rev 00
The context of assessment





The application of competency is to be assessed in the workplace or realistically simulated
workplace
Assessment is to occur under standard and authorised work practices, safety requirements
and environmental constraints
Assessment of essential underpinning knowledge, other than confirmatory questions, will
usually be conducted in an off-site context
Assessment is to comply with relevant regulatory or SADARA Standards requirements
Methods of assessment







Assessment must satisfy the endorsed assessment guidelines of the Building and
Construction industry's Plumbing and Services Training Package
Assessment methods must confirm consistency and accuracy of performance together with
application of underpinning knowledge
Assessment must be by direct observation of tasks, with questioning on underpinning
knowledge and it must also reinforce the integration of key competencies
Assessment methods must confirm the ability to access and correctly interpret and apply
the essential underpinning knowledge
Assessment may be applied under project related conditions (real or simulated) and
require evidence of process
Assessment must confirm a reasonable inference that competency is able not only to be
satisfied under the particular circumstance, but is able to be transferred to other
circumstances
Assessment may be in conjunction with assessment of other units of competency,
including those listed above
Specific resource requirements for this unit

The following resources should be made available:
o workplace location or simulated workplace
o tools and equipment appropriate to the fabrication and installation process
o calculators or equivalent
o support materials appropriate to the activity
o specifications in the form of a job or work order
o research resources including systems information and data
Page - 13
Download