Prospecting Scheme
PROSPECTING SCHEME
FOR THE PROPECTING LICENSE OF LIMESTONE
NEAR VILLAGE BAKOT
LIMESTONE DEPOSIT
AT
DISTRICT ABBOTTABAD






1
File No.:
MDW/AD/PL-Limestone (297)/2017
Name of Mineral/Lithology: Limestone
Location Of Granted Lease: Near Village Bakot
Acreage Of Lease Area:
99.173
District:
Abbottabad
Name of the Party/lessee:
M/S Razvi Mining (Pvt)
Prospecting Scheme
1. Date of Offer letter:
25th February 2021
2. Site/Location/Acreage of the Area:
Covering 99.173 acreages near village and Union Council Bakot Tehsil
and District Abbottabad.
3. Nature of a Mineral Prospecting:
Limestone
4. The Prospecting Method To Be Adopted:
The open mining system will be adopted
5. Details of Equipment/Machinery To Be Used:
For the execution of mining, the following machinery and types of
equipment will be mobilized
I.
II.
Earth Movers including Excavator, Jackhammer and Tractor Trolly
For dislocation/cutting a Pneumatic Hand Drilling Machine
III.
Tripod
IV.
Double drum winch
V.
Wheelbarrows and other conventional helpful tools used in
developing of open mining Quarry
6. Staff To Be Employed:
The following technical and non-technical staff will be employed for
running a smooth mining operation
I.
Mine manager
II.
Site incharge
III.
Drilling Crew
IV.
Heavy Machinery operators
V.
2
Security Guard
VI.
Cook
VII.
Others
Prospecting Scheme
7. Facilities To Be Provided To The Staff/Labour:
All possible and basic facilities will be provided to the staff/labour on the
site like health, drinking water, sanitation, daily food, accommodation, etc.
8. Phases Of Prospecting Operations:
Ist Phase: In this phase exploring and searching of location of granite
within lease by keeping both the quality and quantity of the said mineral
and also easily accessibility for running smooth work and its
transportation. For this already site is proposed and shown in the scheme.
2nd Phase: In this phase the mobilization of heavy and others machineries
and mining equipments/tools. Beside this the construction of approach and
access road to location as described in phase 1 and the construction of
labor camp.
9. Road/Labour Camp To Be Constructed:
The Main paved road namely Mansehra-Chilas road is cut across the said
lease. Approach/Access road will be constructed and also labour camp will
be constructed if need
10. Estimation Expenditures:
The below are the estimated expenditures for the completion of the said
phases
a
Cost of Machinery/Equipments:
Rs: 60, 0000/ approx.
b
Cost of Construction of Road/Labor Camp:
Rs: 5, 00,000/ approx.
c
Cost Facilities To Be Provided To The Staff:
Rs: 3, 50,000/ approx.
d
Wages of Staff:
Rs: 2, 50,000/ approx.
e
Miscellaneous Cost:
Rs: 5, 00,000 approx.
11. Proved and Probable reserves:
Mineral reserve estimation already discussed in the geological report.
3
Prospecting Scheme
PREPARED BY
Tufail Ahmad
Registered Geologist
Directorate General of Mines
And Mineral
KhyberPakhtunkhwa
Name of Lessee
M/S Razvi Mining (Pvt) Limited
Village Bakot
District Abbottabad
4