Uploaded by 流星辰

Homework Assignments 6

advertisement
Homework Assignments
Chapter 6
請用手寫,拍照並轉PDF,合併檔案後上傳至作業區
Chapter 6
1. What are the seven main processes involved
in project time management? Describe the
key work for each process.
2. What is Critical Chain Scheduling? What is
Theory of Constraints? What Is a buffer?
What are the different types and how are
they used?
3. Consider the following table.
Activity
Initial
Node
Final
Node
Estimate
Duration
Activity
Initial
Node
Final
Node
Estimate
Duration
A
B
C
D
1
1
1
2
2
3
4
3
10
12
8
4
G
H
I
J
4
4
5
5
5
6
6
8
4
8
6
12
E
2
5
8
K
6
7
8
F
3
4
6
L
7
8
10
a. Draw an AOA network diagram representing the project. b.
What is the critical path and how long is it? c. Draw a PDM
network diagram and show the early and late start and finish
dates for each task. d. Calculate free float(FF) and total float
(TF) for each task. e. How can a project manager use the
critical path to shorten a project schedule?
3
Download