Inspection 4 Industry LLC ,, It _ i Home GeHerall INS 14I Academy 1-- --- Fix Equipment ) ' '7\ t: , Rotary Equipment iti E & I Equipment Services Get In Touch -- ,.-P - - 1g Inspection The Piping Inspection article provides you with information about the inspection of piping and piping testing in a construction site, as well as in operating plants. definition pp '-jt,•4 Based on API Code, the definition of pipe is a pressure-tight cylinder used to convey a fluid or to transmit a fluid pressure. If you look to the refinery or chemical plant, you can see the jungle of pipes which are connecting the vessels together. Statistic shows that 40 % of total mechanical failures in the units are because of the process piping. This article provides you information about site inspection of process piping as well as important points on in-service inspection in process plants. What is the Process Piping Inspection Requirements at the Construction Site? The construction code for process piping is ASME B31.3 Code and it covers the minimum requirements for design, materials, fabrication, inspection, testing, and commissioning. With the above explanation, your inspection and test plan (ITP) for process piping needs to meet the requirements of ASME B31.3 Code. ASME B31.3 refers you to the other ASME code sections for some activities. For example for welding refer to the ASME Code Section IX, pipe fitting design and selection to the ASME B16.5 and for Nondestructive testing to ASME Code Section V. The process piping design and construction is not under the ASME Code scheme of stamped items. It means there is not certification for construction contractors by ASME, and it is the responsibility of owner to select a qualified and experienced contractor for its process piping construction project. This is the reason that in the ASME B31.3 code you cannot see the wording of "Authorized Inspector," and instead the words "owner inspector" have been used. The owner inspector can be the owner's own qualified inspector or the inspector of a third party inspection company under contract with the owner. Throughout the ASME Construction codes, when you see the words "authorized inspector," you notice there is an ASME Stamp scheme there. Contrary to the ASME B31.3, the ASME Baia code for power piping (boiler external piping) have the ASME stamp scheme. The construction contractor must be certified by the ASME organization and must hold the "PP" stamp. So the wording for inspector in the ASME B31.1 is "authorized inspector," which means that this person has specific qualifications and a commission card from NBIC. For more details, review the Pressure Vessel Certification article. The certification process for the power piping contractor is similar to the pressure vessel. The detail of inspection requirement in the construction field is addressed in the process piping inspection and test plan. Inspection and Test Plan for Process Piping Related Video Impact Testing on ASME B31.3 Pi CI ************ ********** ***************** ********** ******************1 ******* *** ****** ***** Hydrostatic & Pneumatic Test PrE ICI *******************************************************************1 ********************* What Is In-Service Inspection Requirement for Process Piping? The In-Service Inspection code for your process piping is API SID 570. The title of the code Is Piping Inspection Code: In-service Inspection. Rating. Repair, and Alteration of Piping Systems, The other API recommendation practices and codes are also necessary to be used In coniunctlon with this Coda Some of these Recommend Practices are: • API RP 574 Inspection Practices for PION System Components, • API RP 577 'Melding Inopeclien and Metallurgy, • API RP 571 Damage Mechanism Affecting Fbaid Equipment In the Refining Industry, API 578 Malarial Verification Program for New and Eafirling Moy Piping Systems ASME construction and referenced code sections also might be used such as ASME B31.3 and ASME Code Section IX. For repair, the requirement of API STD 570, or ASME PCC-2 need to be met. The title of ASME-PCC-2, which was first published in 2006 is: "Repair of Pressure Equipment and Piping." The API 570 Piping Inspectors are qualified persons to do the piping system inspection. The API 570 Training Course is 6 days video training program and available online and is the Prep course for API 570 Piping nspector Exam. Besides the student that successfully pass this training course exam, receive 141 academy certificate with 48 hours training credit. Calculate Piping Design Thicknes CI ************ ********** ***************** ********** ******************1 ******* *** ****** ***** Minimum Required Thickness Cal Ila ******************** API 570 Short Long Term Corrosil NJ ****** **** ***** ** Flange Face Finish Defect Accept What are the Important Items in the Piping Inspection? These are only important points or a summary of points for the process piping in-service inspection and should not be assumed as the entire piping inspection procedure. A piping inspection procedure is a comprehensive document, which need to cover inspection methods to be employed, equipment and material to be used, qualification of inspection personnel involved and the sequence of the inspection activities at the minimum. You may use the following content as a summary of points for the in-service inspection of the piping system. • Creating a piping inventory list indicating the line number, pipe specification class, rating, schedule, pipe origin location (from) and pipe destination location (to) • Creating piping isometric sketches to facilitate inspection and the recording of corrosion monitoring locations (CMLs) • Dividing whole unit piping into piping circuits based on process condition and potential degradation mechanism • Selecting appropriate NDE techniques for each piping circuit based on the circuit damage mechanism • Determination of CMLs points in piping isometric sketches based on the potential for general or localized corrosion and service specific damage mechanisms • Determination of piping service class based consequence of failure and instruction stated in API 570 or based on the Risk Based Inspection method. • Carry out external inspection for corrosion, leaks, previous temporary repairs, clamps, coating breakdown, insulation misalignment, damage, pipe vibration, support deterioration specifically in touch points and to air to soil interface, pipe hanger distortion or breakage and frizz damage • External thickness measurement on CMLs on each piping circuit • Corrosion rate calculation based on metal loss in a specific time interval • Retirement thickness calculation based on the minmium required thickness and minimum required structural thickness • Remaining life calculation based on the available thickness for corrosion and the corrosion rate value • Determination of piping circuit inspection interval based remaining life calculation and piping service class • Determination of piping inspection interval for non-thinning damage mechanism • Making supplementary inspection with the proper NDE method for piping circuits susceptible to creep cracking • Making supplementary inspection with the proper NDE method for piping circuits susceptible to the creep cracking • Making supplementary inspection with the proper NDE method for piping circuits susceptible to environmental cracking from Chloride SCC, Polythionic acid SCC, Caustic SCC, Amine SCC, Carbonate SCC, Hydrogen blistering and hydrogen induced cracking (HIC), etc. • Application of other NDE methods if it is necessary: 1. PEC (pulsed eddy current), LRUT (long range UT), LREM (long range electromagnetics), RT for wall thickness loss, and CUI and neutron backscatter and infra-red thermography for detection of wet insulation 2. MT (magnetic particle), WFMT (wet fluorescent magnetic particle), PT (penetrant testing), EC (eddy current), UT shear wave, AUT (automated UT), TOFD (time of flight diffraction), RT, ACFM (alternating current field measurement), AET (acoustic emission) for investigating cracking 3. Thermography for detection of fouling and hot spots • Internal inspection in opened flanges for deposition, corrosion, localized corrosion, erosion, etc. • Internal inspection of clad or lined piping for disbanding, bulging and cracking • Internal inspection of refractory lined piping for erosion, deterioration of anchors, undercutting of refractory and coke build up behind refractory • Flange joint inspection for distortion and leakage and flange face inspection, ring groove and gasket for corrosion, erosion , cracking and mechanical damage • Internal inspection of dismantled valve for corrosion, erosion, mechanical damage and cracking • Specific attention and internal inspection of critical check valves • Inspection of injection points for localized corrosion • Inspection of dead legs for corrosion • Corrosion under insulation inspection of piping in susceptible temperature (-12° to 175° C) either by advance NDT or by removal of insulation and making visual inspection • Making appropriate reporting and report keeping and implement proper system for quick access to the records Related Articles Boiler Inspection, Heat Exchanger Inspection, Pressure Vessel Inspection, Above Ground Storage Tank Inspection, Valve Inspection, Heater Inspections Return from Piping Inspection to Inspection for Industry Home Did you find this article useful? Click on below Like and G+i buttons! New! Comments Have your say about what you just read! Leave me a comment in the box below. flFacebook 0 Twitter