PROJECT 2016 CHEAT SHEET THINGS TO DO ONE TIME 1. File Tab>> Options >> Schedule: 1. Scheduling options for this project: All New Projects 2. New Tasks created: Auto scheduled. 2. Resource Tab >> Leveling options >> Remove checks at bottom >> OK THINGS TO DO EVERY TIME 1. Set up calendar if needed: Project >> Change Working Time 2. Add: Phases Tasks Durations Set link relationships – make sure every task is linked to something Look for non-standard links: (Double click tasks and check predecessors.) Start to Start Finish to Finish. 3. Set Obvious Constraints (“must finish by”, “must start on”, ect) 4. Add Resources: View >> Resource Sheet (then return to Gantt Chart) 5. Assign Resources: Resource Tab >> Assign Resources Enter in % of available time the resource will spend on the task Check to see if the duration still makes sense 6. Check for over allocations: View >> Resource Usage Learn iT! Anytime | San Francisco | Santa Clara | New York | Remote Training | www.LearnItAnytime.com | 415.963.0250 7. Over allocated? 1. Fix it yourself by changing assignments (50% assigned here, 50% assigned there), or by juggling resources 2. Resource >> Level All (remove check boxes on bottom) 3. Check leveling to see what moved 8. Project >> Project Info >> Set Start Date Learn iT! Anytime | San Francisco | Santa Clara | New York | Remote Training | www.LearnItAnytime.com | 415.963.0250