Question 1 Correct Mark 1.00 out of 1.00 Flag question Question text The following are five specific functions of a contract management unit, except: a. Inspection and Acceptance b. Procurement Planning and Development of Bidding Documents Unit c. Contract Performance Monitoring d. Billings and Payment Unit e. Contract Development and Review Feedback Your answer is correct. The correct answer is: Procurement Planning and Development of Bidding Documents Unit Question 2 Correct Mark 1.00 out of 1.00 Flag question Question text Which of the following refers to a set of principles, procedures or protocols used to effectively manage contracts or agreements and relationship between entities which involves the proper planning and monitoring of the procurement project during the contract implementation stage, aimed at reducing, eliminating or mitigating financial, legal and other project risks. a. Public Procurement b. Contract Management System c. Billings and Payment d. Contract Performance Monitoring Feedback Your answer is correct. The correct answer is: Contract Management System Question 3 Correct Mark 1.00 out of 1.00 Flag question Question text Which refers to a situation where one’s personal or private interests interfere, or appear to interfere, with his/her official responsibilities and affects his/her ability to make fair and impartial decisions regarding his/her work. a. Conflict of Interest b. Procurement Fraud c. Collusion d. Interlocking Interest Feedback Your answer is correct. The correct answer is: Conflict of Interest Question 4 Correct Mark 1.00 out of 1.00 Flag question Question text The following are the four pillars of a Fraud Management Framework except? a. Anti-Fraud and Governance Leadership b. Anti-Fraud Strategies and Action Plans c. Dealing with Conflict of Interest in relation to Anti-Fraud d. Fraud Risk Assessment and Anti-Fraud Controls Feedback Your answer is correct. The correct answer is: Dealing with Conflict of Interest in relation to Anti-Fraud Question 5 Correct Mark 1.00 out of 1.00 Flag question Question text There are six core values of public organizations based on UNDP’s Ethics at the Organizational Level. These are Integrity, Professionalism, Respect for Diversity, Transparency, Accountability and? a. Results Orientation b. Adherence to Rules c. Ethical Standards d. None of the above Feedback Your answer is correct. The correct answer is: Results Orientation Question 6 Incorrect Mark 0.00 out of 1.00 Flag question Question text Mr. XXX, a fifth-ranking permanent official of the Department of Education, was designated as one of the regular members of the Bids and Awards Committee (BAC) by virtue of DepEd Order No. 033, series of 2022. During one of the biddings for a certain project under the BAC of which Mr. XXX is a member, Bidder AAA, the authorized representative of company Brilliant Solutions, Inc. and who also happens to be the wife of Mr. XXX, submitted a bid for that certain project. In the Sworn Affidavit submitted together with the bidding documents, Bidder AAA disclosed her relationship with Mr. XXX, that, among others, “Mr. XXX is her husband but he is not in any way connected with the company (Brilliant Solutions, Inc.) she represents.” Along the bidding process, Mr. XXX actively attended meetings, participated in the opening of bids, voted and performed his usual duties and responsibilities as a regular member of the BAC. After evaluation of the bids, Bidder AAA’s bid was declared as the Lowest Calculated Responsive Bid (LCRB) and eventually, it was recommended by the BAC for post-qualification. Bidder CCC, aggrieved by the result of the evaluation, contested the decision of the BAC in declaring Bidder AAA’s bid as the LCRB, alleging that the whole bidding process is not fair and unjust because Bidder AAA’s husband is a regular member of the BAC, thus, posits a glaring conflict of interest which may therefore “substantially affect the result of the bidding or any procurement processes, puts it in a position to unduly influence or be given preference in the award of the contract.” Bidder AAA countered that the company she represents complied with Rule XV by virtue of the Sworn Affidavit it executed, stating and disclosing among others, her relationship with Mr. XXX and that Mr. XXX is not in any way connected with her company Brilliant Solutions, Inc. 6. In the given circumstances, is there an ethical issue? a. Yes, because there was conflict of interest on the part of Mr. XXX that puts his wife in a position to have access to information about or influence on the bid of another bidder or influence the decisions of the Procuring Entity regarding the bidding process. Mr. XXX should have inhibited as a member of the BAC. b. Yes, because not only did Bidder AAA comply with Rule XV by disclosing her relationship with Mr. XXX but Mr. XXX, on one hand, performed his duties and obligations pursuant to his designation as a regular member of the BAC. c. Yes, because Mr. XXX has provided advance information to Bidder AAA. d. None, because Bidder AAA complied with Rule XV by disclosing her relationship with Mr. XXX and Mr. XXX correctly assumed his duties and responsibilities as he has no controlling shares with the company of Bidder A. e. None, because there was conflict of interest based on the sole ground that Mr. XXX has no controlling shares in the company. Feedback Your answer is incorrect. The correct answer is: Yes, because there was conflict of interest on the part of Mr. XXX that puts his wife in a position to have access to information about or influence on the bid of another bidder or influence the decisions of the Procuring Entity regarding the bidding process. Mr. XXX should have inhibited as a member of the BAC. Question 7 Correct Mark 1.00 out of 1.00 Flag question Question text When is there conflict of interest in public procurement? a. A bidder may be considered to have conflicting interests with another bidder when they have controlling shareholders in common. b. A bidder receives or has received any direct or indirect subsidy from any other bidder. b. A bidder has the same legal representative as that of another bidder for purposes of this bid. c. A bidder has a relationship, directly or through third parties, to any member of the BAC, the TWG, the Secretariat or any pertinent official in the procuring entity that puts them in a position to have access to information about or influence on the bid of another bidder or influence the decisions of the Procuring Entity regarding this bidding process. d. All of the above. Feedback Your answer is correct. The correct answer is: A bidder has a relationship, directly or through third parties, to any member of the BAC, the TWG, the Secretariat or any pertinent official in the procuring entity that puts them in a position to have access to information about or influence on the bid of another bidder or influence the decisions of the Procuring Entity regarding this bidding process. Question 8 Correct Mark 1.00 out of 1.00 Flag question Question text As a result of public bidding, Supplier ‘Boy Kutsinta Corporation’ or “BoyKuCo” was awarded with a contract with the Department of Education for the project “Procurement of Supply, Delivery, Configuration and Installation of 10,000 units of Laptops, and 5,000 units of Desktop Computer for DepEd Public Senior High Schools”, with the following contract details, among others, to wit: contract price Php650,000,000.00 delivery period 90 calendar days from receipt of the Notice to Proceed delivery site all DepEd public senior high schools payment eligible for advance payment not to exceed 15% of contract price upon submission of bank guarantee equivalent to 15% thereof, initial payment, at least 25% delivered and installed Upon receipt and conforme of the Notice to Proceed on 01 December 2020, BoyKuCo started placing orders to its Supplier-Manufacturers in China for 10,000 units of laptops and 5,000 units of desktop computer equipment. Based on the delivery plan of BoyKuCo, the expected delivery of the first batch of equipment is on January 10, 2021, second batch is February 10, 2021 and last batch on February 20, 2021. On 30 December 2020, BoyKuCo was informed by its suppliermanufacturers that there will be delays in the production of the computer equipment because of shortage in raw materials. On 30 January 2021, BoyKuCo was informed again by its suppliermanufacturers that they are yet to incur more delays due to the month-long holiday in China – Chinese New Year. Due to these two incidents of delay experienced by BoyKuCo which led to certain adjustments in its delivery plan, BoyKuCo requested DepEd for an extension of delivery period for sixty (60) calendar days. BoyKuCo submitted letters from its supplier-manufacturers as proof for its request for delivery period extension. 8. As a Contract Manager, what will be the most practical first step in dealing with this kind of contract implementation incident? a. Inform and indorse the request for extension of BoyKuCo to the End-User Unit and/or other offices concerned and seek its/their recommendation on the matter. b. Refer the matter to the Head of Procuring Entity for appropriate action. c. Study and evaluate the request of BoyKuCo. Based on the facts and proofs submitted as well as the circumstances of the case, issue a recommendation as may be allowed by law, particularly under the revised IRR of RA 9184 and GPPB issuances on contract delivery period extension or suspension. d. Immediately convene all parties to the contract to a meeting for the purpose of discussing practical solutions in addressing the request for extension filed by BoyKuCo. Feedback Your answer is correct. The correct answer is: Inform and indorse the request for extension of BoyKuCo to the End-User Unit and/or other offices concerned and seek its/their recommendation on the matter. Question 9 Correct Mark 1.00 out of 1.00 Flag question Question text As the End-User Unit, what will be your best action on the request for delivery period extension filed by BoyKuCo? a. Study and evaluate the request of BoyKuCo. Based on the facts and proofs submitted as well as the circumstances of the case, issue a recommendation as may be allowed by law, particularly under the revised IRR of RA 9184 and GPPB issuances on contract delivery period extension or suspension. b. Immediately convene all parties to the contract to a meeting for the purpose of discussing practical solutions in addressing the request for extension filed by BoyKuCo. c. Refer the matter to the Legal Unit for appropriate action. d. Refer the matter to the Head of Procuring Entity for appropriate action. Feedback Your answer is correct. The correct answer is: Study and evaluate the request of BoyKuCo. Based on the facts and proofs submitted as well as the circumstances of the case, issue a recommendation as may be allowed by law, particularly under the revised IRR of RA 9184 and GPPB issuances on contract delivery period extension or suspension. Question 10 Correct Mark 1.00 out of 1.00 Flag question Question text To enhance the transparency of the procurement process, the BAC shall invite at least three (3) observers, who shall not have the right to vote, to sit in its proceedings. At least one observer must come from the Commission on Audit, another from a duly recognized private group in a sector or discipline relevant to the procurement at hand, and another from a non-government organization (NGO). The following statements regarding observers are true, except: a. The procuring entity should ensure that the invitation is received by the observers at least five (5) calendar days before the date of the procurement activity. b. The duly recognized private group, from which one observer will be coming from, must be located within the same geographical area of the procuring entity. c. The absence of observers will not nullify the BAC proceedings, provided that they have been duly invited in writing. d. The BAC may determine other relevant criteria which the observers should meet. Feedback Your answer is correct. The correct answer is: The duly recognized private group, from which one observer will be coming from, must be located within the same geographical area of the procuring entity. Question 11 Correct Mark 1.00 out of 1.00 Flag question Question text The BAC may issue a Supplemental/Bid Bulletin at least seven (7) days before the deadline for the submission and receipt of bids in any of the following occasions, except: a. In amending any provision of the bidding documents b. In responding to requests for clarification and interpretation from bidders c. In reflecting the adjustment in the approved budget for the contract (ABC) pursuant to any applicable law or other acts of the Government which takes effect before the deadline of the submission of bids d. In effecting the amendments to the bidding documents in a previous bidding to a succeeding bidding for the same project following a failure of bidding Feedback Your answer is correct. The correct answer is: In effecting the amendments to the bidding documents in a previous bidding to a succeeding bidding for the same project following a failure of bidding Question 12 Correct Mark 1.00 out of 1.00 Flag question Question text A procuring entity invited bids for the procurement of service vehicles. In response, a bidder submitted a letter requesting for a clarification on the technical specifications as regards the indicated Japan make and model and suggested the consideration of a vehicle make from another country. Rule on whether or not the indicated country of origin can be a valid technical specification. a. Yes, the indicated country of origin is a valid technical specification pursuant to the “End User Choice” principle. b. No, the indicated country of origin violates domestic preference c. No, the PE is precluded from requiring specific country of origin as part of the technical specifications. d. Yes, the PE can rightfully set the objectives and standards for its project and may refuse to accept the delivery of an item that is not compliant with the technical specifications. Feedback Your answer is correct. The correct answer is: No, the PE is precluded from requiring specific country of origin as part of the technical specifications. Question 13 Correct Mark 1.00 out of 1.00 Flag question Question text Y Agency is in need of a service provider for its mailing services (project). Z Agency (Servicing Agency) is a government agency that has the mandate to deliver the services required to be procured by Y Agency. Z Agency signified its intention and capability to undertake the project through a Certification which states among others that it has the mandate to render the services required for the project, that it has the absorptive capacity to undertake the project, that it owns or has access to all the necessary tools and equipment required for the project, and that it will not sub-contract the project. Based on the assessment and recommendation of the End-User unit, the BAC issued a Resolution recommending the use of Agency-to-Agency agreement to the HOPE. How should the HOPE act on the Resolution? a. The HOPE should not approve the Resolution because there was no underlying reason to support a Negotiated Procurement through Agency-to-Agency such as an immediate action is necessary to procure the project b. The HOPE should not approve the Resolution because the BAC did not negotiate with the Servicing Agency first before the latter issued a Certification that it complies with the conditions for Agency-to-Agency. c. The HOPE should not approve the Resolution because the End-User unit did not justify to the BAC that the resort to Agency-to-Agency is more efficient and economical to the government. d. The HOPE should approve the Resolution because all of the conditions for Agency-to-Agency have been met Feedback Your answer is correct. The correct answer is: The HOPE should not approve the Resolution because the End-User unit did not justify to the BAC that the resort to Agency-to-Agency is more efficient and economical to the government. Question 14 Correct Mark 1.00 out of 1.00 Flag question Question text A contract for procurement of goods, infrastructure and consulting services may be terminated for default. Any of the following conditions shall constitute as a ground for termination for default, except: a. Outside of force majeure, the supplier fails to deliver or perform any or all of the goods within the periods specified in the contract, or within any extension thereof, and such failure amounts to at least 10% of the contract price b. Due to the contractor’s fault and after the contract time has expired, it has incurred a negative slippage of 10% or more in the completion of work c. As a result of force majeure, the consultant is unable to deliver or perform a material portion of the outputs and deliverables for a period of not less than thirty (30) calendar days after the consultant’s receipt of the notice from the PE stating that the circumstance of force majeure is deemed to have ceased d. The contractor sub-lets the any part of the contract works without approval of the procuring entity Feedback Your answer is correct. The correct answer is: As a result of force majeure, the consultant is unable to deliver or perform a material portion of the outputs and deliverables for a period of not less than thirty (30) calendar days after the consultant’s receipt of the notice from the PE stating that the circumstance of force majeure is deemed to have ceased Question 15 Correct Mark 1.00 out of 1.00 Flag question Question text Termination of contract for the procurement of goods may be allowed other than those attributable to the supplier. The procuring entity, by written notice sent to the supplier, may terminate the contract, in whole or in part, at any time for its convenience. Under the law, the procuring entity has several options in termination of contract for convenience. Which of the following is not among the PE’s options allowed by law? a. For goods not yet performed or ready for delivery, the procuring entity may elect to have any portion delivered or performed and paid at the contract terms and prices b. The goods that have been performed or are ready for delivery within thirty (30) calendar days after the supplier’s receipt of Notice to Terminate shall be accepted by the procuring entity at the contract terms and prices c. For goods not yet performed or ready for delivery, the procuring entity may elect to cancel the remainder and pay to the supplier an agreed amount for partially completed or performed goods and for materials and parts previously procured by the supplier d. The goods that have been performed or are ready for delivery within thirty (30) calendar days after the supplier’s receipt of Notice to Terminate shall be accepted by the procuring entity at the settled terms and prices after successful negotiation and mutual agreement Feedback Your answer is correct. The correct answer is: The goods that have been performed or are ready for delivery within thirty (30) calendar days after the supplier’s receipt of Notice to Terminate shall be accepted by the procuring entity at the settled terms and prices after successful negotiation and mutual agreement Question 16 Correct Mark 1.00 out of 1.00 Flag question Question text Which among the following instances does not require or justify the conduct of inspection by item or 100% inspection? a. The goods to be inspected consist of parts and components that must be examined exhaustively b. Inspection by sampling was conducted, and the rejection rate is high c. Inspection by sampling was conducted, and the number of defective items was lower than the acceptable quality level d. The goods to be inspected are electrical, electronic and mechanical equipment or devices Feedback Your answer is correct. The correct answer is: Inspection by sampling was conducted, and the number of defective items was lower than the acceptable quality level Question 17 Correct Mark 1.00 out of 1.00 Flag question Question text X Agency procured 3,250 units of laptops for delivery and distribution to its 10 field offices. The project consists of 2 lots and the contracts were awarded to Supplier A. Upon request by Supplier A for a pre-delivery inspection, X Agency constituted and deployed its inspectorate team to conduct the inspection of the goods at Supplier A’s warehouse. In performing their duties, the inspectors made use of the sampling plan which provides the following details: Lot No. Qty. 1 2 Sample Size AQL* Percentage Qty. Percentage Qty. 1,625 10% 163 5% 8 1,625 10% 163 5% 8 *Acceptable Quality Level (AQL) is a statistical measurement that sets the percentage of the maximum acceptable number of defective goods in a given sample size. After the inspection, there were 8 units from Lot 1 and 11 units from Lot 2 which were found to be non-compliant with the technical specifications and/or with defects. If you are the Team Leader of the inspectorate team, which of the following actions will you recommend? a. Accept the entire quantity of Lot 1 and 2 b. Accept only the quantity that passed the inspection for both lots c. Accept the entire quantity of Lot 1 and reject the entire quantity of Lot 2 d. Reject the entire quantity of Lot 1 and 2 Feedback Your answer is correct. The correct answer is: Accept the entire quantity of Lot 1 and reject the entire quantity of Lot 2 Question 18 Correct Mark 1.00 out of 1.00 Flag question Question text The Inspection and Acceptance Report (IAR) is a report submitted by the inspectorate team and the supply and/or property custodian on the inspection and acceptance, respectively, of the procured supplies, goods or equipment. In accomplishing the IAR, which among the following statements is true? a. At least two (2) members of the inspectorate team must sign the “Inspection” portion of the IAR b. The supply and/or property custodian must sign first before the members of the inspectorate team c. The IAR must bear three (3) dates, namely: 1) date of the IAR; 2) date of inspection; and 3) date of acceptance d. The IAR must state the warranty period of the procured goods Feedback Your answer is correct. The correct answer is: The IAR must bear three (3) dates, namely: 1) date of the IAR; 2) date of inspection; and 3) date of acceptance Question 19 Correct Mark 1.00 out of 1.00 Flag question Question text A _______ is an agreement enforceable by law between two or more persons to do or abstain from doing some act or acts, their intention being to create legal relations and not merely exchange mutual promises. It is also described by the law as “a meeting of minds between two persons whereby one binds himself, with respect to the other, to give something or to render some service a. Crime b. Damages c. Contract d. Quasi-delict Feedback Your answer is correct. The correct answer is: Contract Question 20 Correct Mark 1.00 out of 1.00 Flag question Question text It is the effective and efficient monitoring of contract activities to ensure that goods, services and/or works contracted by the purchasing entity are delivered in a timely manner, at the agreed cost and to the specified requirements: a. Contract Award b. Procurement Planning c. Bid Solicitation d. Contract Management Feedback Your answer is correct. The correct answer is: Contract Management Question 21 Correct Mark 1.00 out of 1.00 Flag question Question text It is an essential element of contract management that is undertaken to ensure that the key objectives of contract management are achieved, and it is usually done during the initial transition period between contract award and the start of contract implementation. This process is intended to provide an opportunity to establish common understanding and goals in undertaking the procurement contract: a. Pre-Signing Conference b. Pre-Award Conference c. Pre-Implementation Conference d. Pre-Week Conference Feedback Your answer is correct. The correct answer is: Pre-Implementation Conference Question 22 Correct Mark 1.00 out of 1.00 Flag question Question text 22. Julia Montemayor is a newly appointed Undersecretary in the Department of Migrant Workers, a newly-created department of the Philippine government. Julia has been designated by the Secretary as the Undersecretary for Procurement, and she will be the one in-charge of managing the procurement activities of the said Department. Assuming that Usec. Julia is considering developing a Contract Management System (CMS) for the procurement activities of the Department of Migrant Workers. Which among the following is the correct cycle that she should follow to ensure that the Department’s contracts are properly managed? a. Contract Development -> Contract Review -> Notice of Award -> Contract Signing -> Notice to Proceed -> Contract Implementation b. Contract Development -> Notice to Proceed -> Notice of Award -> Contract Review -> Contract Signing -> Contract Implementation c. Contract Implementation -> Notice to Proceed -> Contract Signing -> Notice of Award -> Contract Review -> Contract Development d. Contract Signing -> Contract Development -> Notice to Proceed -> Contract Review -> Contract Implementation -> Notice of Award Feedback Your answer is correct. The correct answer is: Contract Development -> Contract Review -> Notice of Award -> Contract Signing -> Notice to Proceed -> Contract Implementation Question 23 Correct Mark 1.00 out of 1.00 Flag question Question text The Department of Migrant Workers previously entered into a contract with supplier, Stoic Corp., for the delivery of COVID-19 antigen test kits. However, the actions of the said supplier during the implementation of the contract shows that there was a material breach of the entire contract and the same had not been rectified despite the several opportunities given by Usec. Julia and by the Department. It was also shown that the agreement allows cancellation of the contract for any breach. What can Usec. Julia recommend to the procuring entity with regard to the contract of Stoic Corp.? a. Contract Disallowance b. Termination of Contract c. Implementation of Contract d. Contract Suspension Feedback Your answer is correct. The correct answer is: Termination of Contract Question 24 Correct Mark 1.00 out of 1.00 Flag question Question text Mr. Manuel, an officer of a certain Department in the Philippine national government. Mr. Manuel is in charge of the Contract Management System (CMS) in relation to the procurement activities of said Department. He has been tasked by the Secretary in monitoring the implementation of contracts for the Department. In connection to his task of maintaining a sound Contract Management System, Mr. Manuel was asked by the Secretary to report on his plans in mitigating the risk of little or no enforcement of contract deliverables in the outstanding contracts of the Department with its current suppliers. The following are ways to mitigate the said risk, except for: a. Responsible staff monitors all activities under the contract to ensure that all work is carried out in accordance with the agreed order/ contract specification b. Logistics arrangements and procedures are put in place and actively managed to avoid congestion, downtime/demurrage and claims c. Contract assets are recorded in a standard data system and tracked to avoid unauthorized use or disposal d. Suppliers’ claims for payment are adequately verified by the purchasing entity in accordance with the agreed contract e. All of the above Feedback Your answer is correct. The correct answer is: All of the above Question 25 Correct Mark 1.00 out of 1.00 Flag question Question text The Department contracted One For the Road, Inc., for the delivery of Science and Mathematics learning materials for Grade 7. Mr. Manuel was asked by the representative of One For the Road, Inc. if the contract between them and the Department is already complete. The following are indicators of a complete contract, except: a. There are outstanding disputes between the supplier and the procuring entity b. A certificate of acceptance/compliance had been issued c. The Performance Security is returned in accordance with the terms of the contract and the security instrument d. All payments due to the supplier are made in a timely manner and the Purchase Order is closed immediately Feedback Your answer is correct. The correct answer is: There are outstanding disputes between the supplier and the procuring entity Question 26 Correct Mark 1.00 out of 1.00 Flag question Question text During a meeting with a supplier for a procurement contract for the delivery of sign pens to be used by the Department, one of the authorized representatives of the supplier shouted at the Department’s staff, saying “wala naman sa kontrata at sa pinag-usapan natin iyang mga hinihingi ninyo sa amin eh. Sana hindi na lang kami nag-bid!”, and immediately left the meeting. This fit was reported to the Secretary, and the latter asked Mr. Manuel, as the head of the Contract Management Division, to formulate ways to improve the Department’s relationship with its current and future suppliers so that the same situation will never happen again. Which of the following should be implemented by Mr. Manuel? a. The Department’s interests are of utmost importance; and the suppliers must adjust to the needs of the Department b. The Department should maintain an open and constructive relationship with its suppliers; and regular contract review meetings or discussions should be held by the Department with the supplier c. The suppliers should always deliver more than what is obligated in the contract because it is for the public good; and once the contract has been signed, suppliers should no longer be entertained d. The suppliers shall deliver only what it can deliver, even if it is less than what is obligated in the contract; it is important to properly communicate and take care of the Department’s relationship with its suppliers Feedback Your answer is correct. The correct answer is: The Department should maintain an open and constructive relationship with its suppliers; and regular contract review meetings or discussions should be held by the Department with the supplier Question 27 Correct Mark 1.00 out of 1.00 Flag question Question text The Project Procurement Management Plan (PPMP) is a guide document in the procurement and contract implementation process, as well as a vital reference in procurement monitoring prepared by each end-user units during the __________ stage of the budget cycle: a. budget preparation b. budget accountability c. budget execution d. budget legislation Feedback Your answer is correct. The correct answer is: budget preparation Question 28 Correct Mark 1.00 out of 1.00 Flag question Question text ABC in government procurement means: a. Appropriation of Budget Ceiling b. Appraisal Budget for the Contract c. Approved Budget for the Contract d. Approved Budget Ceiling Feedback Your answer is correct. The correct answer is: Approved Budget for the Contract Question 29 Correct Mark 1.00 out of 1.00 Flag question Question text A document which refers to the entirety of the procurement activities that will be undertaken by the procuring entity within the calendar year is called ___________: a. None of the above b. Annual Procurement Plan (APP) c. Project Procurement Management Plan d. Work and Financial Plan Feedback Your answer is correct. The correct answer is: Annual Procurement Plan (APP) Question 30 Correct Mark 1.00 out of 1.00 Flag question Question text Goods, supplies and materials, and equipment used in the day-to-day operations of Procuring Entities are referred to as: a. Non-expendable supplies b. Expendable supplies c. Goods and materials d. Common use supplies and equipment Feedback Your answer is correct. The correct answer is: Common use supplies and equipment Question 31 Correct Mark 1.00 out of 1.00 Flag question Question text The selection of the method of procurement is dependent on the presence or absence of specific conditions of other methods of procurement. One of these methods does not require elaborate bidding documents, and where the supplier is simply asked to submit a price quotation or a pro forma invoice together with the conditions of sale. This method of procurement is called: a. Small Value Procurement b. Negotiated procurement c. Direct Contracting d. Limited Source Bidding Feedback Your answer is correct. The correct answer is: Direct Contracting Question 32 Correct Mark 1.00 out of 1.00 Flag question Question text One important activity in procurement planning is scheduling, which is defined as the process of examining all program activities and their relationships to each other in terms of realistic constraints. It is therefore imperative to consider procurement timelines in determining project milestones. The maximum allowable time for the procurement of Goods and Services is: a. 141 calendar days b. 136 calendar days c. 180 calendar days d. 156 calendar days Feedback Your answer is correct. The correct answer is: 136 calendar days Question 33 Correct Mark 1.00 out of 1.00 Flag question Question text One of the characteristics of a good budget which is a vital consideration in procurement planning to ensure consistency with government fiscal measures is fiscal disciplines which means: a. spending on the right things b. hard control on the level of spending c. spending at the right costs d. all of the above Feedback Your answer is correct. The correct answer is: hard control on the level of spending Question 34 Correct Mark 1.00 out of 1.00 Flag question Question text A tool in project costing and determination of ABC which provides a structured accounting of resources and associated cost elements from “cradle to grave” is called: a. Analogous costing b. Parametric estimating c. Bottom-up estimating d. Life-cycle costing Feedback Your answer is correct. The correct answer is: Life-cycle costing Question 35 Correct Mark 1.00 out of 1.00 Flag question Question text Select the best course of action. You may write down a brief statement to support your answer at the bottom of this page or attach additional sheet, if necessary. The Bureau of Learning Resources - Cebu (BLR-Cebu) submitted its Indicative PPMP, together with their procurement requests and concomitant documents necessary to commence the conduct of Early Procurement Activities (EPA) in September of the current year (2021) consistent with the National Expenditure Plan (NEP) for Fiscal Year 2022, details of which are as follows: Title of Procurement Project Estimated Budget a) Supply, distribution, Installation, configuration, Testing, Commissioning, Training and Maintenance of TVL Tools and Equipment Packages to Public Senior High Schools (MOOE) 17,000,000.00 b) Supply, distribution, Installation, configuration, Testing, Commissioning, Training and Maintenance of TVL Tools and 275,000,000 Equipment Packages to Public Senior High Schools (Capital Outlay) The Indicative Annual Procurement Plan for CY 2022, which includes the said projects was duly approved by the Head of the Procuring Entity (HoPE) in October 2021, thus, the Bids and Awards Committee (BAC) proceeded with the procurement after determining the readiness of the project as proposed. An Invitation to Bid was posted reflecting the above amounts as ABC, wherein four (4) prospective bidders submitted its bid. All bidders were found eligible, and compliant after the detailed evaluation of bids. The bidder with the Lowest Calculated Bid was post-qualified; its bid price amounted to Php 14.45M and 233.75M, respectively. The BAC, through its Secretariat prepared the recommendation immediately after post-qualification, short of award, hence, approval by the HoPE and award of contract shall be made only upon approval of the CY 2022 General Appropriations Act. The CY 2022 was finally approved on December 28, 2021; however, it reflected a reduction in the appropriations for the above-mentioned Line Items of 10% of the approved budget reflected in the NEP. Thereafter, the BLR-Cebu submitted a memorandum informing the BAC, thru the Procurement Management Service and OASPA, that the FY 2022 LTE-TVL Allocation List shall be revised due to changes in the approved appropriation based on GAA, and also due to the change in the List of JDVP recipient schools as provided by the Bureau of Curriculum Development. As a policy, JDVP recipient schools depending on the specializations of learners under JDVP will not be provided with TVL tools and equipment to avoid duplication of investment and waste of resources. As a result, the items, quantity and ABC of the project will drastically change vis-à-vis the requirements in the bidding documents. The appropriate action to be taken by the BAC based on specific considerations is: a. Proceed with the recommendation to award the contract to the LCRB to comply with the early procurement activities requirement since the bid amount is within the appropriated amount for the project based on GAA b. Recommend cancellation of the bidding to the HoPE considering that the ABC reflected in the IB and Bidding Documents is higher than the approved appropriation in the GAA c. Cancel the project and rebid after EU submits the revised requirements, i.e. list of items, technical specifications, revised ABC within the mandatory period d. Recommend award of the contract, subject to amendments of the contract to be finalized during contracting Feedback Your answer is correct. The correct answer is: Cancel the project and rebid after EU submits the revised requirements, i.e. list of items, technical specifications, revised ABC within the mandatory period Question 36 Correct Mark 1.00 out of 1.00 Flag question Question text Splitting of Government Contracts or the division or breaking up of GoP contracts into smaller quantities and amounts, or dividing contract implementation into artificial phases for the purpose of circumventing the provisions of GPRA is prohibited. However, in one case, the Procuring Entity splits the procurement contract into five (5) different lots to encourage participation and reduce the effects of failure of bidding. The internal auditor of the procuring entity issued an Audit Observation Memorandum (AOM) stating that it violated the rule on splitting of contracts as mandated by Section 54 of Republic Act 9184 and its IRR. Which of the instances below amounts to splitting of contracts contemplated under RA 9184? a. dividing a contract into sub-contracts for the purpose of evading the necessity of public bidding b. dividing the procurement project into lots for the purpose of attracting more bidders c. dividing or breaking up a procurement project into smaller quantities and amounts for the purpose of homogenizing the items and packaging them into lots. d. none of the above Feedback Your answer is correct. The correct answer is: dividing a contract into sub-contracts for the purpose of evading the necessity of public bidding Question 37 Correct Mark 1.00 out of 1.00 Flag question Question text In one of its procurement contracts, the Procuring Entity has to terminate a contract on the ground that it has lost interest in the winning bidder’s performance and found a supplier who is better in terms of equipment and facilities. The Procuring Entity cited the following grounds for cancellation or termination of procurement activities. 1. The project is no longer necessary as determined by the end-user unit. 2. The source of funds for the project has been withheld or reduced through no fault of the Procuring Entity. 3. The Procuring Entity is no longer interested in the performance of the winning bidder. 4. The physical and economic conditions have significantly changed so as to render the project no longer economically, financially, or technically feasible, as determined by the end-user unit. 5. The Procuring Entity has found a supplier who can better execute the procurement contract. Are the grounds enumerated by the Procuring Entity valid to cancel or terminate the procurement activity? a. Yes, all stated grounds are valid b. No, only grounds number 1, 2, 3, & 4 are valid c. No, only grounds number 3 & 4 are valid d. All grounds are invalid e. No, only grounds number 3 & 5 are invalid Feedback Your answer is correct. The correct answer is: No, only grounds number 3 & 5 are invalid Question 38 Correct Mark 1.00 out of 1.00 Flag question Question text Bidders “A” & “B” were declared ineligible for bidding while, bidder C failed to submit required documents during the “Post-qualification Procedure”. Hence, bidder “D” who has the highest bid is declared the bidder with the Lowest Calculated Responsive Bid (LRCB). During the award, bidder “D” has determined that its bid is too low hence refuses to accept the award of contract. Based on the following circumstances, the BAC members are planning to issue a resolution to declare a failure of bidding. The BAC Chair however said that there is no failure of bidding because the bidding was successfully conducted albeit failed because Bidder “D” refuses to accept the award. From the above instances which of the following is NOT a ground for the declaration of failure of bidding? a. The bidder with the LCRB, HRRB, SCRB or SRRB refuses, without justifiable cause, to accept the award of contract and no award is made b. No bids are received c. All prospective bidders are declared ineligible d. All bids fail to comply with all the bid requirements or fail post-qualification e. None of the above Feedback Your answer is correct. The correct answer is: None of the above Question 39 Correct Mark 1.00 out of 1.00 Flag question Question text Which of the following is a major concern in procurement planning? a. Lack of or insufficient proper market study b. Lack of or insufficient cost-benefit analysis c. Lack of or limited training or experience in drafting TORs d. a and b only e. a and c only f. All of the above Feedback Your answer is correct. The correct answer is: All of the above Question 40 Correct Mark 1.00 out of 1.00 Flag question Question text In the Alternative Methods of Procurement of R.A. 9184, this method is resorted to when the project involves the procurement of highly specialized types of goods and consulting services where only a few supplies/consultants are known to be available a. Shopping b. Limited Source Bidding c. Repeat Order d. Direct Contracting e. Negotiated Procurement Feedback Your answer is correct. The correct answer is: Limited Source Bidding Question 41 Correct Mark 1.00 out of 1.00 Flag question Question text During the post-qualification procedure, the BAC requested its Secretariat to issue a letter to Bidder “A” to clarify certain aspects of its bid offer. The Secretariat however refused to issue a letter because of the “No Contact Rule” in procurement. Under Section 32 of the 2016 Revised IRR of R.A. 9184, it stated that, “Members of the BAC, its staff and personnel, Secretariat and TWG, as well as Observers, are prohibited from making or accepting any communication with any bidder, regarding the evaluation of their bids until the issuance of the Notice of Award”. Is the “No Contact Rule” absolute? a. Yes, the BAC Secretariat is correct for refusing to issue a letter of communication with Bidder “A” b. No, the BAC Secretariat may ask in writing the bidder for a clarification of its bid c. Yes, the BAC Secretariat is precluded in asking the bidder for a clarification of its bid. d. No. the BAC Secretariat may ask the bidder through a personal SMS (message). e. None of the above Feedback Your answer is correct. The correct answer is: No, the BAC Secretariat may ask in writing the bidder for a clarification of its bid Question 42 Correct Mark 1.00 out of 1.00 Flag question Question text Bidder “A” submitted the lowest bid, while bidder “B” and “C” is the second and third lowest respectively. During the evaluation of documents, it appears, based on the financial documents submitted, that Bidder “A” lacks the financial capacity to undertake the project, hence, was declared disqualified. Thus, Bidder “B” was subjected to post-qualification. During postqualification procedure, the BAC issued a resolution to post-disqualify bidder “B” for noncompliance with the technical specifications of the project. However, bidder “B” contended that it be given a chance to rectify its bid offer since he was already declared as the lowest bidder and the only requirement he has to satisfy is the requirement on technical specifications. Is bidder “B” correct in its argument? a. No, the bid of bidder “B” bid offer is not responsive and modification of bid is not allowed. b. Yes, bidder “B” is the lowest bidder, and he may not be disqualified if its bid offer does not conform with the technical specifications of the project. c. Yes, bidder “B” may be given the chance to rectify its bid offer d. No, bidder “B” cannot rectify its bid because this is not allowed to second lowest bidders Feedback Your answer is correct. The correct answer is: No, the bid of bidder “B” bid offer is not responsive and modification of bid is not allowed. Question 43 Correct Mark 1.00 out of 1.00 Flag question Question text During the Covid-19 Pandemic, Procuring Entity “A” resorted to the use of “emergency casesnegotiated procurement” for the lease of real properties for use as quarantine centers, evacuation sites, medical relief and aid distribution locations, warehousing facilities, or similar temporary disaster emergency response facility. Negotiated procurement under emergency cases may be justified based on the following circumstances, except? a. That the emergency procurement was resorted to avoid imminent danger to life or property during a state of calamity. b. That the emergency procurement was resorted to avoid imminent loss of the budget due to being unutilized at the end of the budget year. c. That the emergency procurement was resorted to restore vital public services, infrastructure facilities and other public utilities d. That the emergency procurement was resorted to avoid imminent loss of services, social and economic disruption and environmental degradation Feedback Your answer is correct. The correct answer is: That the emergency procurement was resorted to avoid imminent loss of the budget due to being unutilized at the end of the budget year. Question 44 Correct Mark 1.00 out of 1.00 Flag question Question text The following are five specific functions of a contract management unit, except: a. Contract Development and Review b. Procurement Planning and Development of Bidding Documents Unit c. Contract Performance Monitoring d. Inspection and Acceptance e. Billings and Payment Uni Feedback Your answer is correct. The correct answer is: Procurement Planning and Development of Bidding Documents Unit Question 45 Correct Mark 1.00 out of 1.00 Flag question Question text Which of the following refers to a set of principles, procedures or protocols used to effectively manage contracts or agreements and relationship between entities which involves the proper planning and monitoring of the procurement project during the contract implementation stage, aimed at reducing, eliminating or mitigating financial, legal and other project risks. a. Contract Management System b. Contract Performance Monitoring c. Public Procurement d. Billings and Payment Feedback Your answer is correct. The correct answer is: Contract Management System Finish review Pr e vi o u s a c t i vi t y ◄ Announcements Jump to... Jump to... Skip Quiz navigation Quiz navigation Question1This pageQuestion2This pageQuestion3This pageQuestion4This pageQuestion5This pageQuestion6This pageQuestion7This pageQuestion8This pageQuestion9This pageQuestion10This pageQuestion11This pageQuestion12This pageQuestion13This pageQuestion14This pageQuestion15This pageQuestion16This pageQuestion17This pageQuestion18This pageQuestion19This pageQuestion20This pageQuestion21This pageQuestion22This pageQuestion23This pageQuestion24This pageQuestion25This pageQuestion26This pageQuestion27This pageQuestion28This pageQuestion29This pageQuestion30This pageQuestion31This pageQuestion32This pageQuestion33This pageQuestion34This pageQuestion35This pageQuestion36This pageQuestion37This pageQuestion38This pageQuestion39This pageQuestion40This pageQuestion41This pageQuestion42This pageQuestion43This pageQuestion44This pageQuestion45This page Show one page at a timeFinish review Stay in touch Office of the Undersecretary for Administration (OUA) Administrative Service(AS) Information and Communications Technology Service (ICTS) Disaster Risk Reduction and Management Service(DRRMS) Bureau of Learner Support Services (BLSS) Baguio Teachers Camp (BTC) Central Security & Safety Office (CSSO) Department of Education, Central Office, Meralco Avenue, Pasig City Rm 519, Mabini Bldg. http://training.deped.gov.ph edtech@deped.gov.ph