Advance Gas Turbine Solutions OTEC Joint Venture Company PETRONAS CARIGALI SDN BHD COMPRESSOR INSPECTION GTC K2400 B11-KA WORKPACK VOL 1 OF 1 Prepared and submitted by: PCSB SK GAS GTS33 Prepared By AGTS PM Siemens Energy PM Name Irwansjatria Ernest Liang Date 10 Jan 2022 10 Jan 2022 Position Signature Reviewed By Section Head (GTS/33) HSE Executive (GSE/1) Endorsed by Turnaround Manager (GTS/24) Field Manager GPD1 Offshore Installation Manager Approved by TA Head GTS/24 WORKPACK CONTENTS /NA 1 INTRODUCTION i. Project Summary √ ii. Organization Chart √ iii. Emergency Response Plan 2 3 Tick - √ √ SCOPE OF WORK (SOW) i. Thrust bearing inspection and shim adjustment √ ii. Thrust balance pipe interface bolts replacement √ MATERIALS & TOOLS i. Table #1 Part list for thrust bearing inspection √ ii. Table #2 Part list for thrust balance pipe bolt replacement √ iii. Table #3 Special tools for thrust bearing inspection √ 1. INTRODUCTION 1.1 Project Summary Compressor inspection on B11 GTC K2450. 1.2 Project Organization Chart PCSB AGTS PM Irwansjatria SESB PM Ernest Liang 1.3 Emergency Response Plan Scope To specify the Emergency, Respond Plan throughout the project. The ERP should contain but not limited to the following content. Objective To ensure the site team are aware of the information and action required to be performed on any case of emergency and able to secure themselves from any danger. ERP Org Chart ECC INCIDENT COMMANDER 013-8103568 Email: skgasecc.ic@petronas.com.my ECC INCIDENT COMMANDER INCIDENT COMMANDER: 013-8103568 GPD TELEPHONE: 017-8117141 UNIT HEAD SABTUNI OSMAN 012-2658956 FM GPD/1 BOBBY RANGGAU 013-8788820 EIC GTS/33 STANISAUS LATERAN 010-3724363 ONSHORE OFFSHORE B11 OSC EMERGENCY RESPONSE TEAM (ERT) PS/MS B11 AGTS FSR / ROVING GANG Legend: Reporting path Indirect Reporting Emergency Contact No 1 Type of emergency & rescue plan Type of Emergency Fire Alarm & Evacuation alarm Medical treatment emergency Rescue Plan Team Lead to instruct for stop work. Head count to confirm all team member are available before proceeding to evacuate the work area towards the mustering station. Team Lead to instruct stop work quickly assess the severity of the IP. Team Lead to assign personnel to notify the OIM/MS/PS /Medic. Medic / Team lead to provide any temporary medical treatment if required. If not, escort IP back to LQ/Medic room. 2. SCOPE OF WORK 2.1 Thrust bearing inspection and shim adjustment 2.1.1 Details scope: i. ii. iii. iv. v. vi. vii. viii. ix. x. xi. xii. xiii. xiv. xv. xvi. xvii. xviii. xix. xx. xxi. xxii. xxiii. xxiv. xxv. xxvi. xxvii. xxviii. xxix. xxx. Isolation Inspect spare parts and tools Remove piping and tubing at non drive end Remove coupling guard Remove coupling spool Temporary tape all open connections (oil lines) Bump check as found thrust clearance Remove coupling hub and vibration probes at drive end Remove thrust bearing housing top half Remove and inspect inboard and outboard thrust bearing Remove outboard thrust bearing o-ring Verify rotor center position Reinstate inboard and outboard thrust bearing (without o-ring) Reinstate thrust bearing housing and check thrust float Remove thrust bearing top half Adjust shim to inboard and outboard thrust bearing for a reduced axial end float within 0.180.28 mm (target can be 0.23 mm). Reinstate top halve thrust bearing housing Verify rotor position and thrust clearance (possibility to use the gas seal insertion tool on drive-end to be verified by SE to create the appropriate axial force to stack the shims) Apply sealant to thrust bearing housing (min 24 hours for sealant curing) Install coupling hub and set axial displacement probe, verify displacement in HMI & Bentley rack, set as required Verify shaft alignment and DBFF, verify pre-stretch and shimming Install coupling spool and shim Reinstate coupling guard Remove temporary tape on open connections Reinstate piping and tubing Pre-start checks De-isolation Pressurization and startup Monitor compressor operating parameter Load compressor and monitor axial displacement 2.1.2 Manpower: 1 FSR, 2 millwrights, 1 rigger/helper during mechanical works of 3-4 days. 2.1.3 Duration: 3-4 days mechanical works, 2-3 days for startup, load and monitoring 2.1.4 Spare parts: refer to Table #1 2.1.5 Special tools: refer to Table #3 2.1.6 General tools: Imperial Hand tools (including combination spanner set, allen key set, plier and screw driver (+) & (-), 2” scrapper, 24” spirit level ruler x 24” steel rule x 1, 12” steel rule, imperial box socket set up to 1 3/8”, inside micrometer (1”), inside micrometer (1m) , depth gauge (12”), dial gauges (0.01mm or better) x 4 and magnetic stand x 4, torque wrench with valid calibration ( below 100Nm), 1 1/2” x 4ft pipe extension. 2.1.7 Consumable: Scotch bright (6pcs), cleaning solvent (3-4 cans WD40), hand glove ( 1 doz), clean cotton rag 10kg, industrial paper towel 1/2 roll, plastic bags, plastic trays x 4, paint marker (white and black x2), plywood x 3 pcs (any thickness above 5mm and around 3’ x 4’ or other readily available matching size), 2” masking tape x 5, stretch film x 1 roll 2.1.8 Overhead crane and tackles (3/8” shackles x 2 and 2m lifting belt x 1 & 1m lifting belt x1) to lift top bearing housing, coupling spool and guard (below 250kg) 2.2 Thrust balance pipe interface bolts replacement 2.2.1 Details scope: i. ii. iii. iv. v. vi. vii. viii. ix. x. xi. xii. xiii. Erect scaffold to access compressor case top Isolation and verify hydrocarbon free Remove the hex head bolt for thrust balance pipes Lift and remove thrust pipe, remove gaskets Temporary tape the connection on case to prevent foreign ingress Clean and surface rust stain on flanges Replace the gasket for the thrust balance pipes with new Lift and reinstate the thrust balance pipe Lightly lubricate bolt thread, install blue coated thrust balance pipe Torque hex head bolt for pipe 16 & 17 to 270 and 300Nm respectively De-isolation Check any sign of leakage during pressurization. Remove scaffold 2.2.2 Manpower: 1 FSR, 1 millwrights & 1 rigger/helper during mechanical works of 1-2 days. 2.2.3 Duration: 1-2 days mechanical works. 2.2.4 Spare parts: refer Table #2 2.2.5 Special tools: NONE 2.2.6 General tools: Imperial Hand tools (1/2” drive box socket set including 1 ¾” box socket, 1 ¾” slogging wrench, torque wrench with valid calibration (within range of 250 to 350 NM), 2lb hammer, 2” x 4ft pipe extension, ultrasonic leak detector or LDAR 2.2.7 Consumable: Scotch bright (2pcs), cleaning solvent (1-2 cans WD40), hand glove ( 1 doz), clean cotton rag 2kg, industrial paper towel 1/10 roll, plastic bags, plastic trays x 1, paint marker (white and black x1), plywood x 4 pcs (any thickness above 5mm and around 3’ x 4’ or other readily available matching size), 2” masking tape x 4, stretch film x 1 roll, snoop leak detector 2.2.8 Overhead crane and tackles (1/2” shackles x 3 and 3m lifting belt x 2) to lift top bearing housing (below 250kg). The bracket to secure pipe for shipment and lifting could be used for pipe lifting. Double lanyard PPE. 3. MATERIALS AND TOOLS 3.1 Table #1 Part list for thrust bearing inspection No Item # in Dwg Part # 1 4 002-272-276 O’RING (Thrust Bearing Cover) 2 22 099-010-021 LOCTITE 515 3 27 002-272-126 O’RING (Journal/rework thrust Bearing Housing) SPIRAL WOUND GASKET 4,5MM 4'' 150# SPIRAL WOUND GASKET & RINGS 4.5MM 1.5'' LOCKING CABLE TIE (SEE NOTE # 3) - PANDUIT #PLT.6SM-C 12.00 LEG SHIM PACK IN HALVES .062 11.0 THK O-RING, AS 568 - #202 - 234 I.D. X .139 C/S, VITON FEED TUBE w/O-RINGS, FT-5 4 1000537236 5 1000537237 6 13.2 7 11 267353-012 8 9.1 052701 9 3.2 10 6 266575-002D1 1000527153 11 6 1000527156 12 6 1000527159 13 6 1000527160 14 6 1000527161 15 059391 1000537235 16 17 18 19 20 31 28 30 29 4 423-749-063 423-749-064 002-272-249 002-272-254 371706-005 21 5 383168-003 22 Part description Qty 1 6pack 1 1 1 10 2 12 12 FLAT GASKET ITEM 1 DWG 546901-201 FLAT GASKET ITEM 2 DWG 546901-201 FLAT GASKET ITEM 3 DWG 546901-201 FLAT GASKET ITEM 4 DWG 546901-201 FLAT GASKET ITEM 5 DWG 546901-201 SPIRAL WOUND GASKET 4,5MM 2'' 150# Back-up ring (coupling hub) Back-up ring (coupling hub) O-ring (coupling hub) O-ring (coupling hub) 12.00(6-SHOE)CCW LEG THR SHOE, CRCU; 65 % OFFSET, LSR, HST (OUTBOARD) 12.00(6-SHOE)CCW LEG THR SHOE, CRCU; 65% OFFSET DR/INSTR, LSR,HST Hylomar 2 1 2 1 2 4 2 2 2 2 4 2 Remarks Thrust bearing assb 1000520766 Thrust bearing assb 1000520766 Thrust bearing assb 1000520766 Thrust bearing oil supply interface Thrust bearing oil supply interface Thrust bearing 1000520777. Non SE part #. Thrust bearing 1000520777. Non SE part #. Thrust bearing 1000520777. Non SE part #. Thrust bearing 1000520777. Non SE part #. Item # 6 (546-905-001) of Coupling guard 546-900-201 Item # 6 (546-905-001) of Coupling guard 546-900-201 Item # 6 (546-905-001) of Coupling guard 546-900-201 Item # 6 (546-905-001) of Coupling guard 546-900-201 Item # 6 (546-905-001) of Coupling guard 546-900-201 Coupling guard 546-900-201 pipe connection Rotor assembly 1000520790 Rotor assembly 1000520790 Rotor assembly 1000520790 Rotor assembly 1000520790 Item # 4 of thrust bearing dwg 1000520777. Non SE part #. Item # 5 of thrust bearing dwg 1000520777. Non SE part #. 3.2 Table #2 Part list for thrust balance pipe bolt replacement No 1 Item # in Dwg Part # 000-148-903 Part description SPIRAL WOUND GASKET Qty Remarks 4 Gasket for thrust pipe 1000532527 (B11-K-PUR-AGTS-000P-DWG-0001 Rev. C) & 1000532528 (B11-K-PUR-AGTS000-P-DWG-0002 Rev. C) 000-201-728 2 HEX HEAD BOLT 32 Hex head bolt for thrust pipe 1000532527 (B11-K-PURAGTS-000-P-DWG-0001 Rev. C) & 1000532528 (B11-KPUR-AGTS-000-P-DWG-0002 Rev. C) 3.3 Table #3 Special tools for thrust bearing inspection No 1 2 3 4 5 6 7 Item # Part # 538-484-205 595-195-204 091-015-005 000-028-952 524-560-208 000-005-319 Part description Bearing Housing Lifter Assembly Tools Assembly for Mounting & Dismounting Gas Seal Assembly Lubri-Silk Synthetic Grease Alignment jig/ laser alignment tool Hydraulic Pump Assembly Kit Threaded Rod Assembly Screw Qty 1 1 1 1 1 1 1 Remarks General Comments Others (Additional Workscope) Activity Remarks Inspection Performed By Field Service Rep Date Please list Works not done due to customer or Incomplete Due to Unavailability of Parts Item Priority Code Description X B Part Description Urgent (Do not use machine until complete) Within 6 months or 4000 Hours Part Number A C Qty Priority As soon as possible (Next Service) Plan as appropriate to coincide with other works ID Task Mode 1 Task Name Duration Thrust Bearing Inspection Schedule Start Finish Jan 30, '22 M 9 days Mon 2/14/22 Tue 2/22/22 2 Preparation 2 days Mon 2/14/22 Tue 2/15/22 3 isolation 2 days Mon 2/14/22 Tue 2/15/22 4 FSR mob to offshore 1 day Mon 2/14/22 Mon 2/14/22 5 Inspect spare parts and tools 1 day Tue 2/15/22 Tue 2/15/22 4 days Wed 2/16/22Sat 2/19/22 6 Mechanical Work 7 Remove piping/tubing 0.25 days Wed 2/16/22 Wed 2/16/22 8 Remove coupling guard, spool, hub and DE probes 0.5 days Wed 2/16/22 Wed 2/16/22 9 Bump check and remove thrust bearing case top 0.25 days Wed 2/16/22 Wed 2/16/22 10 Remove and inspect inboard and outboard thrust bearing, 0.5 days verify rotor position Thu 2/17/22 Thu 2/17/22 11 Reinstate inboard and outboard thrust bearing (without o-ring) with housing & verify thrust end play 0.5 days Thu 2/17/22 Thu 2/17/22 12 Adjust shim to inboard and outboard thrust bearing for a reduced axial end float within 0.18-0.28 mm (target 0.23 mm). Reinstate bearing assembly and verify thrust end play 0.25 days Fri 2/18/22 Fri 2/18/22 0.25 days Fri 2/18/22 Fri 2/18/22 14 Apply sealant to thrust bearing housing (min 24 hours for sealant curing) 0.13 days Fri 2/18/22 Fri 2/18/22 15 Install and set axial displacement probe, loop check 0.25 days Fri 2/18/22 Fri 2/18/22 16 Verify shaft alignment and DBFF, verify pre-stretch and shimming 0.37 days Fri 2/18/22 Sat 2/19/22 17 Install coupling hub, spool, shim and guard 0.5 days Sat 2/19/22 Sat 2/19/22 18 Reinstate piping and tubing 0.25 days Sat 2/19/22 Sat 2/19/22 4.12 days Fri 2/18/22 Tue 2/22/22 13 19 Preparation and startup 20 Pre-start check (Seal gas system) 0.5 days Fri 2/18/22 21 Pre-start check (lube oil & others) 0.5 days Sun 2/20/22 Sun 2/20/22 22 De-isolation 0.5 days Sun 2/20/22 Sun 2/20/22 23 Pressurization and startup 1 day Mon 2/21/22 Mon 2/21/22 24 Loading and monitoring 1 day Tue 2/22/22 Tue 2/22/22 Project: Thrust Bearing Inspect Date: Mon 12/27/21 T W T F S Feb 6, '22 S M T W T F S Feb 13, '22 S M Sat 2/19/22 Task Project Summary Manual Task Start-only Deadline Split Inactive Task Duration-only Finish-only Progress Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress Summary Inactive Summary Manual Summary External Milestone Page 1 T W T F S Feb 20, '22 S M T W T F S Feb 27, '22 S