CHAPTER ONE 1.0 INTRODUCTION Electricity is a vital service to the economy of a nation. It is regarded as one of the major inputs in the production process of nearly all goods and services. It is also necessary to power domestic appliances; therefore it usefulness is vital in the economic growth of a nation and living condition. Electrical power system consists of three major components namely; generation, transmission and distribution systems. No part of these entire components is independent of the other. Without generation there will be no where to get power to use conveniently. Transmission is again very essential and before the power generated gets to the load end, it needs to be distributed effectively. I was opportune to work with Ondo State Development and Property Corporation, an Ondo state government owned establishment that is meant to relieve the huge amount of electricity burden on the major supplier of electricity in Nigeria, Power holding Company of Nigeria (PHCN), formerly called National Electrical Power Authority (NEPA). During my industrial training, I was exposed to the distribution (including ITC) part of the power system component mentioned above, which is the major concern of the establishment. In this report, I will discuss the huge technical experience that I learned as a result of working with Ondo State Development and Property Corporation. There had been grouped into different chapter for the sake of easy assignment to readers and they are as follow; Chapter one: Introduction Chapter two: Background to the establishment 1 1.1 Chapter three: Transformer Chapter four: Substation Chapter five: Inter – town connection Chapter six: Recommendation and conclusion Aim and Objective of SIWES Student industrial work experience scheme (SIWES) is an integral part of some degree and diploma programmes in institution of higher learning in Nigeria. It is aimed at exposing students to the industrial sector in order to acquire essential and relevant practical knowledge in their various fields. The programmed equally had the objective of acquainting student with the practical relevance and application of the basic theoretical principle learnt in school. As an electrical electronic engineering student, the programme is expected to take place outside the school under the supervision of approved electrical engineer (or contractor) or even in an electrical or electronic company. At Ondo State Development and Property Corporation, the establishment where I undertook the industrial training, I was exposed to many practical experiences such as: (i) The technique used in substation (ii) Identification and used of electrical equipment (iii) Testing of transformers (iv) Inter – town connection 2 CHAPTER TWO 2.0 BACKGROUND OF THE ESTABLISHMENT 2.1 Organizational Chart ONDO STATE DEVELOPMENT AND PROPERTY CORPORATION BOARD CHAIRMAN GENERAL MANAGER P.R .O DIRECTOR F& A DIRCTOR PD&C DEPUTY DIRECTOR F&A INTERNAL INTER AUDIT DEPUTY DIRECTOR PD&C HOD P&D CSO HOD ADMIN CHIEF ACCOUNTAN T DIRECTOR O&M HOD CONSTRUCTION HOD PPIMU & DEPUTY DIRECTOR O&M HOD MAINTENANCE HOD OPERATION & MAINTENANCE 3 Foot note: 2.2 F&A: Finance and administration O&M: Operation and Maintenance PD&C: Planning, Design and construction CSO: Chief Store Officer PPIMU: Project Price Inspection and monitoring unit Location of the establishment Ondo State Development and Property Corporation (OSDPC) is situated directly opposite the Akure branch of Federal Collage of Agriculture (FACA) Ado/Owo Road, Akure. The establishment is a three storey building, which comprises the office of the chairman, the General Manager, Directors and staff of the establishment. 2.3 Employment Size The establishment at present has so many workers ranging from engineers, technologist and accountant. It also has many non – professional workers helping in substations and in maintenance section. 2.4 ` Sections in the Establishment i. Planning, design and construction ii. Project price inspection and monitoring unit iii. Account iv Operation and maintenance v. Finance and administration 4 2.5 Planning and Design Work done here include site survey, sketching of drawings, development and printing of drawing obtained from the site by the use of drawing instrument, printing machine, paper – cutting machine and aqueous ammonia for drying. Recently, the use of auto CAD, a computer based software has been incorporated to enhance proper saving of data and to get along with the information technology of today. The construction section of this department is mainly meant for the installation and servicing of transformer, stringing of poles and laying of armoured cables. 2.5.1 Project Prince Inspection and Monitoring Unit This department deals with the control of prices submitted by contractors by checking of accuracy. It also deals with the production of the bill of engineering measurement and evaluation (BEME). 2.5.2 Electrical Services This department deals with the maintenance of public streetlight system, government offices and parastatals. 2.5.3 Operation and Maintenance This is where facilities and equipment are kept for operation and maintenance. 2.5.4 Account The account section oversees the running of money, by take a proper record of the income and expenses of the establishment. 5 2.5.5 Finance and Administration Administrative jobs are done here. Financial fund received from government are documented here. Details about this department are located in the organizational chart. 6 CHAPTER THREE 3.0 TRANSFORMER 3.1 Overview of the transformer Electricity generating stations is often thousands of voltage, most especially 16kV. This is a very high voltage when compared to the household need. In reality however, this electrical energy has to be transported to far distances where it will be consumed by the household consumers. Electrical voltages tends to drop in value if it is transported through a far distance and hence the need for finding a way to increase its value so as to cater for the drop in voltage and then make it to be able to travel through far distance. 3.2 Brief theory of transformer 3.2.1 Definition of transformer A transformer is a device that makes arrangement for the transfer of electrical energy from one point to another in a circuit or from one circuit to the other by the principle of electromagnetic induction. It transfers electrical energy from one circuit to another through inductively coupled electrical conductors. A changing circuit in the first circuit (the primary) creates a changing magnetic field; in turn, this magnetic field induces a changing voltage in the second circuit (the secondary). By added a load to the secondary circuit, one can make current flow in the transformer. Thus transferring energy from one circuit to the other. The secondary induced voltage Vs is scaled from the primary Vp by a factor ideally equal to the ratio of the number of turns of wire in their respective windings: 7 Vs Vp = Ns Np By appropriate selections of the numbers of turns, a transformer thus allows an alternating voltage to be stepped down, by making it less. A key application of transformers is to reduce the current before transmitting electrical energy over long distances through wire. Most wires have resistance and so dissipate electrical energy at a rate proportional to the square of the current through the wire. By transforming electrical power to a high – voltage, and therefore low – current from for transmission and back again afterwards, transformer enable the economic transmission of power over long distances. Consequently, transformers have shaped the electricity supply industry, permitting generation to be located remotely from point of demand. All but a fraction of the word’s electrical power has passed through a series of transformers by the time it reaches the consumer. Transformers are some of the most efficient electrical ‘machine’, with some large units able to transfer 99.75% of their input power to their output. Transformers come in a range of size from a thumbnail – size coupling transformer hidden inside a stage microphone to huge units weighing hundreds of tones used to interconnect portions of nation power grids. All operate with the same basic principles, though a variety of designs exist to perform specialized roles throughout home and industry. 3.2.2 Transformer basic principles The transformer is based on two principles: first, that an electric current can produce a magnetic field (electromagnetism) and, second, that a changing magnetic field within a coil of wire induces a voltage across the ends of the coil (electromagnetic induction). By changing the current in the primary coil, one 8 changes the strength of its magnetic field; since the secondary coil is wrapped around the same magnetic field, a voltage is induced across the secondary. FIG1: TRANSFORMER BASIC PRINCIPLES An ideal step – down transformer showing magnetic flux in the core A simplified transformer design is shown to the right. A current passing through the primary coil creates a magnetic field. The primary and secondary coil are wrapped around a core of very high magnetic permeability, such as iron; this ensures that most of the magnetic field lines produced by the primary current are within the iron and pass through the secondary coil as well as the primary coil. 3.2.3 Induction Law The voltage induced across the secondary coil may be calculated from faraday’s law of induction, which state that dɸ bgg dt gjɸ bg ɸ ggj Where Vs is the instantaneous voltage, Ns is the number of turns in the ɸɸ secondary coil and ɸ equals the total magnetic flux through one turn of the coil. Vs = Ns If the turns of the coil are oriented perpendicular to the magnetic field lines, the flux is the product of the magnetic field strength B and the area A through 9 which it cuts. The area is constant, being equal to the cross sectional area of the transformer core, whereas the magnetic field varies with the according to the excitation of the primary. Since the same magnetic flux passes through both the primary and secondary coil in an ideal transformer. The instantaneous voltage across the primary winding equals dɸ bgg dt gjɸ bgg ɸ gjɸ Taking the ratio of the two equations for Vs and Vp gives the basic equation for ɸ stepping up or stepping down the voltage Vp = Np Vs bgg Vp gjɸ ɸ 3.3 Vs bgg Np gjɸ b ɸ gTypes of transformers g A gvariety of specialized transformer designs has been created to fulfill certain j engineering applications, though they share several commonalities. Several of ɸ the most important transformer types include: auto transformer, polyphase = ɸ transformer, resonant transformer, leakage transformer, instrument transformer and so on. 3.4 Classification of transformers The many uses of which transformers are put lead them to be classified in a number of different ways: By power level: from a fraction of a volt – ampere (VA) to over a thousand MVA; By frequency range: power-, audio-, or radio frequency; My voltage class: from a few volts to hundreds of kilovolts; 10 By cooling type: air cooled oil filled, fan cooled, or water cooled, By application function: such as power supply, impedance matching, output voltage and current stabilizer, or circuit isolation; By end purpose: distribution, rectifier, arc furnace, amplifier output; By winding turns ratio: step – up, step – down, isolating (near equal ratio), variable. By the type of bushing: open bushing and closed bushing type. For the sake of this report, I will discuss the last classification which is the classification by the type of bushing used. Bushing is just like all other porcelain type insulators and its main purpose is for the purpose of insulating the transformer terminals. A picture showing the two types of transformer is shown below: FIG 2: TWO TYPES OF TRANSFORMER 3.4.1 Closed bushing The closed bushing transformer is that transformer in which the bushings are hidden in the transformer. The closed bushing types are often used on 11kV lines and are often used within the town or city. The base height of such transformer at a sub-station is often 2 feet. The picture of a closed bushing transformer is shown below: 11 FIG 3: CLOSED BUSHING TRANSFORMER 3.4.2 Open bushing The open bushing transformer is that transformer in which the bushings are shown on the transformer. The open bushing types are often used on 33kV lines and it is often used for inter – town connection (ITC). The base high of such transformer at a sub-station is often 4 feet. The picture showing different cross section of open bushing transformers are shown below: Fig 4: Cross-sectional view of open bushing transformer 12 Fig 5: Primary terminals of the open bushing transformer Fig 6: Secondary terminals of the open bushing transformer 3.5 Part of a transformer A transformer has a lot of different components that it is made up of some of the components or parts of a transformer are: conservator tank, tap changer, silica gel, name plate etc 3.5.1 The conservator tank: This tank consists of oil of specified grade and level to remove heat from the windings of the transformer. The oil also acts as 13 an insulator between the windings. The picture of a conservator tank is shown below: FIG 7: CONSEVATOR TANK 3.5.2 Tap changer: This is incorporated in power transformer to facilitate easy sections of desired turn ratio thereby regulating the output voltage and also to change phase of power supply. The tap selection varies from one to five depending on the transformer used. The picture of a tap changer is shown below: FIG 8: TAP CHANGER 14 35.3 Silica gel: It extracts moisture from the system and indicates the status of the transformer oil. The picture of a container of silica gel is shown below: FIG 9: TAP CHANGER 3.5.4 Name plate: This is an aluminum sheet that contains all the properties and features of the transformer on it. It contains the rating of the transformer, the type, the name of the manufacturer, the year the transformer was made and so on. The picture showing the name plate is shown below at the left side. FIG 10: NAME PLATE FIG 11: A TRANSFORMER WITH A COVER CUT AWAY The picture at the right shows a three-phase oil-cooled transformer with cover cut away. The oil reservoir is visible at the top. Radiative fins aid the dissipation of heat. 15 3.6 Transformer testing The aid of testing a transformer is to check for its effectiveness in performing the operations it is manufactured for. There are a lot of tests that can be performed on a transformer but the major ones we dealt with at Ondo State Development And Property Corporation, during the period of my industrial training are: earth test, pressure test, ratio test, dielectric oil test. The equipment required for transformer testing include: generator, hi-potronic tester, multimeter etc 3.6.1 Ratio test The essence of ratio test is to know if the transformer windings are correctly placed where they are supposed to be. To perform ratio test, we need a generator and a multimeter. We connect the two terminals of the generator across the terminals of the transformer one after the other. Picking two terminal at a time and then we power the generator. With a multimeter, we take the reading one after the other and record the values. The table below shown one of the tests that we preformed on a transformer. Phase Primary side Secondary side RY RY 229 YB 169 BR 58 Ry 8.6 Yb 2.2 Br 6.1 Rn 4.8 Yn 3.5 Bn 1.0 YB 113 228 110 7.3 7.2 0.0 2.3 4.8 2.3 BR 56 167 224 2.3 8.4 6.0 1.0 3.5 4.7 When the generator terminals are placed on the red and yellow phase of the transformer and the multimeter reading is taken from the phases, we have a reading of 229 Volts. Because the transformer works by the principle of electromagnetic induction, part of this voltage is induced into the blue phase 16 and hence we have 169Volts and 58volts as the readings on the YB and BR phases respectively. For a good transformer, the sum of this induced voltage should be approximately equal to the main phase voltage. A tolerance of 5v is often allowed. This same thing happens when the generator terminals are placed on the YB and BR phases. The readings on the secondary side are much lower in values than those of the primary side because we are considering step down transformer. 3.6.2 Pressure test Pressure test can be performed on either the transformer or HT lines. The essence of the pressure test is to know if the transformer or the lines is capable of withstanding the voltage at which it is rated. It also helps to know if the transformer can withstand electrical surges. To perform pressure test, we need a hi-potronic tester, a generator, and a multimeter. Often, to perform a pressure test, we inject twice the voltage rating of the transformer into it with the help of hi-potronic tester. To perform a test, we power the hi-potronic tester using a generator and then connect the tester to the transformer and start injecting voltage into the transformer, starting from 0volts. The knob of the hi-potronic tester is adjusted little by little increasing the voltage. As the voltage injected into the transformer increases the knob becomes tight and hard to turn. For a 33kv transformer, we intend to inject 66kV. If the reading trips off before getting to 40kV, then we conclude that the transformer is bad and had to be worked upon. If however, it is able to withstand more than 40kV and up to that 66kV, then we conclude that the transformer is good. This same principle applies to the pressure test on HT lines. The tables below illustrate the explanation above. 17 Table of pressure test on 11kV transformer (i) High voltage/ primary side Terminals Induced voltage Time taken Remark Red phase 22,000 60 Okay Yellow phase 22,000 60 Okay Blue phase 22,000 60 Okay (ii) Low voltage/secondary side Terminals Induced voltage Time taken Remark Red phase 2,000 60 Okay Yellow phase 2,000 60 Okay Blue phase 2,000 60 Okay Neutral 2,000 60 Okay (iii) Pressure test on 11kV HT line Terminals Induced voltage Time taken Remark Red phase 22,000 60 Okay Yellow phase 22,000 60 Okay Blue phase 22,000 60 Okay 3.6.3 Earth resistance test A good soil for a sub-station should have a resistance in the range of 1 to 5 ohms. The earth test is used to test the effectiveness of the earthed materials at the sub-station. The earth tester or earth meter is used to measure the resistance of each of the component of the sub-station to earth. Good test should give a 18 result in the range of 0 to 10 ohms. The table below shows a typical reading obtained from a certain earth test. Sub-station earthing system Result (ohms) Remark Lightning arrester 8 Okay Neutral earthing 7 Okay Transformer frame 9 Okay Channel iron 8 Okay Feeder pillar 8 Okay 3.6.4 Dielectric strength (oil) testing Transformer oil is used in transformer for two purposes: (i) it insulates the windings of the transformer and (ii) it serve as coolant to the transformer by absorbing the heat produced. The instrument used for testing the capability of the transformer oil is called the dielectric tester. The instrument and its component parts are shown below: FIG 12: DIELECTRIC STRENGTH OIL TESTING 19 The transformer oil should have a high dielectric strength so as to provide adequate insulation between the transformer windings. The transformer oil tester uses the working principle a capacitor. The equipment has two plates as indicated in figure 3.the gap that should be between these two plates depends on the ratings of the transformer for which the oil is to be used. Using the steridard rule, we use 2mm for 11kV and 2.5mm for 33kV transformers. After the measurement with the steridard rule, we place the plates into its glass container and rinse with a sample of the transformer oil. We then drop the two indicating capsules into the glass container and cover with the plate. We then put the entire structure into the dielectric tester as shown in figure 2. We energize the oil placing a contain voltage across the plate by pressing the stir button. The two indicating capsule start rotating indicating that electric field is established across the plates of the dielectric tester. When the rotation stops, we then switch the selector knob to manual. We have manual and automatic options. By manual is meant that we do the test by ourselves. But in the case of automatic, the equipment does the testing automatically. After selecting manual, placing the knob at different voltage levels of 500V, 2kV and 3kV we press the raise button and then start looking at the reading displayed. When a spark is noticed inside the dielectric plates, we take the reading and press the trip button. We do this for 500V, 2kV and 3kV noting is readings. We then switch the selector button to automatic and press the start test button. Whenever the spark appears, the equipment trip itself automatically and we can then take the reading, doing the same thing for 500V, 2kV and 3kV. For 11kV transformer, reading from 12kV upward are satisfactory while for 33kV transformer, reading from35 to 40kV upward are satisfactory. 20 The table below shows an interpretation of a test performed on 33kV transformer oil: SAMPLE OF BVP AT GAP QUALITY OF REMARK OIL UNDER 2.5mm OIL TEST STERIDARD New oil Over 50Kv Extremely Acceptable Over 40kV Clean Acceptable Over 40kV Clean To be purified Contaminated Oil from TX Over 40 kV Clean Acceptable which has been in Over 30kV Less clean Useable (to be (contaminated) purified or changed) service 21 CHAPTER FOUR 4.0 Substation A substation may be defined as an assembly of electrical apparatus, which transforms electrical energy (AC) from one voltage to level to another. Therefore, substations are vital links in any power system delivering electric power from the generator station to the consumers. 4.1 Factors to be considered before sitting a substation There are many factors to consider before sitting a substation, some of which are: i. Topography: nature of the land on which the sub-station is to situated must put into consideration. Such land may not be rocky and the soil resistance must not be greater than 1.6 ii. Location: a sub-station should be centrally located in the community. It should be so in order to give room for even distribution of load. iii. Load demand: size of the community determines the load demand. This in effect determines the type and ratings of the transformer to be installed. iv. Nature of transmission line: the type of transmission line from which the substation is connected determines the type of transformer that will be used for example, to supply 300kVA electric power to a community, the type of transformer windings for a 33kV line will definitely be different from that of 11kV line. Diagrams showing a typical substation are shown below: FIG 13: SUBSTATION 22 FIG 14: SUBSTATION EXTENSION 4.2 Division of substations Depending on the purpose, substation is divided into four major divisions. i. Step up substations 16kV to 330kV ii. Primary substations 330kV to 132kV iii. Secondary substations 132kV to 33kV iv. Distribution substations a. 33kV to 11kV b. 11kV to 415kV For the sake of my practical experience and personal experience I will limit this chapter to distribution substation mainly 11kV to 415V. 4.3 Installation of 11kV/415VA distribution substation The distribution substation is a place where the 11kV primary distribution voltage is stepped down to the secondary distribution voltage of 415V, three phases or 240V single phase for use by the consumers. 23 The p[power to the consumers is fed from the distribution substations through a network of low tension(LT) overhead lines, cable mains and sub main and service lines. 4.4 Component of distribution substation A distribution substation is made up of indoor and outdoor equipment. Outdoor equipment are devices that installed outside. They withstand heavy downpour and very high temperature for the sun and water view. The device include the distribution transformer of any power rating, feeder pillar, J &P fuse, lightning arresters, cable, insulators, sectional (H) pole, etc. i. Distribution transformer: It is the equipment that transforms the high voltage of the primary side of the network to the secondary side. Voltage on the primary side of the transformer is 11kV. This is stepped down to give 415V on the secondary side of the transformer, which is the L. V. side of the transformer. The dropper armoured cable carries the incoming electrical energy into the transformer. FIG15: DISTRIBUTION TRANSFORMER 24 ii. Feeder pillar: Feeder pillar is a box – like equipment containing a set of conductors inside it which connect the substation to the distributors serving a certain allotted area from which tapings are taken. The feeder pillar has some armoured cable attached to it. These include the incoming feeder cable which contains the three phases and neutral coming from the transformer. It also has some outgoing feeder cables connected to the leg of feeder pillar. The number of these cables is determined by the number of legs that the feeder pillar has. The cable that carries the feeders up to the distributing poles is called the up riser cable. Feeder pillar are shown below: FIG 16: FEEDER PILLAR iii. Cable: Armoured cable are the most type of cable used in a substation. The cable used in the construction of a distribution substation depends greatly on the capacity of the transformer. The picture below shows a role of armoured cable 25 FIG 17: ARMOVRED CABLE Transformer sizes and cable used for incoming (dropper cable) outgoing (feeder pillar incoming feeder) servicing are: Transformer size Feeder cable (H.T) Outgoing cable (L. T.) 50kVA 70mm2 35mm2 100kVA 70mm2 35mm2 200kVA 150mm2 70mm2 300kVA 300mm2 185mm2 315kVA 300mm2 185mm2 500kVA 500mm2 300mm2 Cable sizes their current carrying capacity is shown below: Cable Current carrying capacitor 35mm2 140A 70mm 200A 150mm2 335A 185mm2 (single core) 380A 185mm2 (3 core or 4 core) 370A 300mm2 550A 500mm2 750A 26 iv. Lightning arrester: Lightning arrester acts as safety values designed to discharge electric surges resulting from lightning strokes, switching, or other disturbances \,which is otherwise flash over insulators or puncture insulation, resulting in a line outage or a possible failure of equipment. They are designed to pass enough transient energy to prevent dangerous reflection and to cut off the flow of current through the arrester at the first current zero after the discharge of the transient. FIG 18: LIGHTNING ARRECTOR The lightning arrester consists of spark gaps in series with nonlinear resistor, the whole assembly housed inside hermitically spaced porcelain bushing. A line lead soldered to the metal cap spun over the phase conductor. The earth terminal at the button of the arresters is connected to the group. Earth terminal of all the three lightning arresters are joined together and connected to the earth [provided specially lightning arresters. The lightning arrester discharges down to the earth the high voltage lightning surge wave while it acts as an insulator for the system voltage. Thus, the lightning arrester protection results in the maximum continuity of electric supply service to the consumer, low maintenance and greatly, reduced distribution operating costs. The lightning arresters are erected on the top of the sectional pole structure for the protection of the transformer against lightning. Lightning arresters are designed by the following: 27 a. Rated voltage b. Rated frequency c. Rated current 28 CHAPTER FIVE 5.0 Installation of lines 5.1 Inter-town connection (ITC) network Inter- town connect (ITC) in electrification is the networking of two or more towns or states. It basically involves the high tension (HT) line i.e. at the voltage level of around 132kV, 33kV and 11kV. 5.2 Pole type i. High tension pole: This is used for carrying 33kV and 11kV lines. It haqs a length of 33ft, base diameter of 30cm and top diameter of 15cm. the first hole is 8cm from the top where the cross arm is screwed. The next three holes are 12cm apart. The holes are 2cm wide. These holes are meant for the spindle of the insulators such as the tension insulator, pot insulator and so on. ii. Low tension pole: It is 28ft long; with base diameter of 24cm and upper diameter of 13cm. the first hole is 18cm from the top while the next holes are 20cm apart with the holes being 2cm wide. There are cases where we have dual carriage poles, a single pole that carries both the high tension and low tension lines at the same time. Its name is derived from the function it performs which is the carriage of two lines at the same time. 5.2.1 Advantage of concrete pole over wood and steel poles i. It is stronger than wood ii. Termite cannot affect it iii. It is more economical than steel iv Unlike steel, it does not conduct electricity so cannot be affected by leakage current 29 5.2.2 Disadvantage of concrete poles over steel and wooden poles i. It is not as strong as steel ii. It takes time to be produced than wooden pole iii. It is more expensive than wooden pole 5.3 Processes involved in installation of high tension lines High tension (HT) is the name given to high voltage level e.g. 11kV, 33kV, etc. during inter-town connection of high voltage electrification between towns; all the processes mentioned below are needed to be followed. 1. Survey of site In the surveying of site for ITC, the terrain of that area or route to be affected should be taken into consideration. The terrain include: sloppy areas, bends, swampy areas, hills, bridges, junctions ……. The number of kilometer from the starting point of the project to the hook-up point is noted. This is used to calculate the number of poles to be used during the project. The route is journeyed and a true meter is used to measure the distances from point to point, junction to junction and place to place. The same thing applies to hilly and rocky areas. Along the route, all existing lines are also taken into consideration. The picture of a true meter is shown below: FIG 19: TURE METER 30 2. Clearing of site This process involves cutting of grasses and felling of trees along the proposed transmission route and creating paths for erecting the high tension poles. The grasses can be cut manually or mechanically by the use of mower. Bulldozer is however used for the felling of trees and thick bush. Clearing of bushes and grasses is necessary for proper visibility during sitting and pegging. 3. Sitting and pegging Sitting is done to ensure a straight line in places where the poles will be erected. Sitting involved the use of site rods made steel or alternatively, we make use of straight pegs with the top painted red for proper visibility through a certain distance. Craftsmen will then have to place themselves at certain distance apart usually called the span (a span is the distance between two poles) each man with his own sitting rod/peg. The distance is measured with the use of true meter (also called meter wheel). The span length for residential areas is 45m and non – residential area is 90m. After a number poles ranging between six and ten, there should be a sectional poles (H poles). A section is defined from one H-pole to another H-pole; the technical name for an H-pole is the sectional pole. Section is placed in between the network so as to give room for isolation of lines in case the network needed to be worked upon in future. After sitting and getting a straight line of sight for the poles, pegging is the next step. Pegging involves the use of wooden peg driven into the soil with the top painted red. This is the point where the pole will be erected. 31 4. Digging of holes Digging of holes is done manually by the use of long digger and long packing spade for packing the earth deposits removed as result of the hole dug. The depth of the hole for high tension line is 6ft while that of low tension line is 4ft. The holes are that deep so as to give room for stability of the poles. 5. Erection of holes A mobile crane called ‘HIAB’ does the erection of poles mechanically. Part of the vehicle made of hydraulic system is used for lifting the pole into the hole. The poles are guarded into the holes by human effort. A strong wire string is tied round the pole and the ‘HIAB’ with the help of the mechanical system lift the pole into the hole. The hole is then covered and hammered until the pole is firmly erected so that there is assurance of stability and resistance to wind and vibration. 6. Dressing of poles Poles are dressed shortly after erection. Dressing involves the fixing of channel iron or cross arm, tie-strap, pot insulators and all other accessories on the pole. 7. Stringing of conductor The size of conductors used for 33kV transmission line is 150mm2 Aluminum bare conductor. The conductors are laid down at the side of the pole according to the phases i.e. R- Y- B and the conductors are taken to the top of the pole with the able men. There are two sectional poles in every section. When the conductor is hung up at the first pole, the will be pulled towards the second sectional pole with the help of pull lift; the phases will then be pulled and tensioned without sagging. 32 8. Earthing Earthing is every essential in any installation. So al the metallic part of the pole, basically the channel iron used has to be earthed. Copper conductor is connected to the channel iron at the top of the pole. It is passed down and connected to the earth rod, which is driven down four feet beneath the earth. A picture showing bundles of copper conductor is shown below. FIG 20: EARTHING CONDUCTOR 9. Testing Testing is very important in any installation. After the completion of ITC, all the component of the transmission line like pot insulator, lightning arrester etc must be tested to be assured of the effectiveness of the system. The test carried out on this system is called pressure test on HT line, the procedure foe doing the step is already explained under the section on transformer testing. 10. Hooking up This is the final stage and it involves the connection of the line to the existing network. 33 5.3 Installation materials and accessories The following materials are accessories used in the installation of lines. Here, both the high tension and low tension accessories will be considered. 1. Poles The concrete electric poles used are majorly of two types namely; the high tension and low tension types. The use of concrete type is mainly because of its rigidity and resistance to pest which affects the wooden type. For a high –tension transmission line, the length of the pole used is 33ft (10m) and for a low tension, the length is used is 28ft (8.5m). The concrete has longer span, resistant to fire, termites or chemicals. 2. Channel iron Channel iron is also referred to as the cross arm. It is a metallic iron on which the spindle, pot insulator and conductors are placed. It comes in different types; the angle channel iron, which is used when a line is to be drawn at an angle, the straight channel iron and U-channel iron type. As for the straight channel iron, the length differs according to the voltage level under consideration. It is 6ft for 11kV and 9ft for 33kV lines. A picture of the channel iron is shown below FIG 21: CHANNEL IRON 3. Spindle 34 The spindle is made of iron or steel that carries the pot insulator on the channel iron or the wooden cross arm. They are threaded so that the insulator can be securely screwed on it. A picture of the spindle hooked into a pot insulator is shown below: FIG 22: SPINPLE 4. J- hook This hook is used to for hanging the disc insulator on the channel iron either the suspension type or other types. 5. Disc insulator Disc insulator is used with high tension lines. It can be used on a T-pole but it is often used on a sectional pole for the sake of allowing isolation in case of future problem with the circuit. The picture of a disc insulator is shown below: FIG 23: DIS INSULATOR 35 6. Pot insulator The pot insulators are mainly porcelain or ceramic types that carry the aluminum conductor on the poles. The sizes vary according to their ratings and voltage level to be transmitted. The picture of a pot insulator is shown below: FIG 24: POT INSULATOR 7. Bolt and nut This is used foe fastening the channel iron or wooden cross arm and tie strap to the pole. 8. Earth rod and earth wire The metal is made of metal especially iron. It is used earthing the poles and substation by burying it into the general mass of the earth so that it can prevent electric shock buy providing a path for the leakage current. The earth wire is made of copper and it is connected to the earth rod. 9. Aluminum conductor This is used the transmission of electric power from one point to the other. The conductors used are of various sizes ranging from 70mm2, 100mm2, 150mm2 depending on the area of use for high tension line, 100mm2 or 150mm2 is used 36 while for low tension line 70mm2 is used. For street lighting, we use 35mm2. The picture below shows a bundle of aluminum conductor. FIG 25: ALUMINUM CONDUCTOR 10. Jumper spindle The jumper spindle is used to jump from one side of the sectional pole to the other for continuity purpose. A bi-metal line tap can also be used for this purpose. 11. Complete stay A complete stay comprises of the stay rod, stay wire, stay insulator, stay block and stay plate. The stay holds the pole firmly to the ground and the stay insulator on it prevents current from flowing through the wire by isolating it. The stay wire is made of galvanized steel. 12. Tie strap This holds the channel iron or the wooden cross arm firmly on the pole. It is usually attached to the cross arm by means of carriage bolts and to the pole by a long screw. 37 13. Tension clamp This accessory is pistol-like in shape; it serves as a link between the conductor and the disc insulator. It is used for clamping conductor to the insulator and it helps to tension the aluminum conductor by clamping it down with the use of U-type bolts and nut. 14. Shackle This is another porcelain made insulator used on the LT line. It is used along with a D-iron that holds it so that it could roll inside the D-iron so as to ensure easy stringing of the cable that is passed through it. The combination is bolted to the pole. Separate picture of the D-iron and the shackle are shown below: FIG 27: SHACKLE FIG 26: D-IRON 38 CHAPTER SIX 6.0 Recommendation and conclusion 6.1 Recommendations It is known fact that theory without practical experience renders a profession sterile. As fundamental engineering principles and thinking processes are the best studied and developed in an academic environment, understanding of practical application is better acquired by direct experience. This balance of academic and practical training was attained during my stay in Ondo State Development and Property Corporation. Basically, I will like to make the following recommendations: a. The students under industrial training should make sure that they make use of the period by reading books on the area of specialization of their industries. This will ensure a forecast of application of theoretical knowledge and hence make them better prepared for the challenges that may arise during the training. b. The departmental lecturers should make it a point of duty to visit the student under training. This will infuse seriousness and dedication into the student. c. The industrial training unit in collaboration with the department should always assist students in securing industrial placement so that any student who cannot gat placement opportunity early can be bailed out of such challenges. d. The company/industries should give more encouragement to students by making use of them in all area of operations and by allowing them to handle some projects in order to enhance their practical knowledge. 39 e. The students training allowance should be increased by the federal government so as to make student meet the demand of the present economic situation in the country and this should be made available to students as early as possible after the training. 6.2 Conclusion The students’ industrial work experience scheme undertaken at Ondo State Development and Property Corporation has given me opportunity to have board knowledge in the planning and designing of sites, testing of substation devices and transformers. Also, it has helped me to acquire professional ethics of my discipline. Through this, I was able to gain knowledge on how to be customer friendly. Generally, the SIWES programme has actually achieved its aim and objectives and its continuity should be encouraged for soild technological background for the subsequent undergraduates. 6.3 References 1. http://en.wikipedia.org 2. Electrical technology by Eng. Olorunsola Abiodun Joseph 3. Electrical installation theory and practical by Eng. Olorunsola Abiodun Joseph 4. Ondo State Development and Property Corporation monthly lecture manuals. 40