Eff. Date : Rev : PROJECT QUALITY PLAN Doc. No: LSE/PQP/Rompin/2022 Page 1 of 20 PROJECT QUALITY PLAN for Cadangan Membina Bangunan Pejabat Teknikal & Stor 1 Tingkat Di Atas Sebahagian Lot PT 771, Mukim Rompin, Daerah Rompin, Pahang Darul Makmur (Contract No.: TNB 2982/2021) Prepared by: Laluan Sepakat Enterprise No. 6, Jalan Makmur Utama, Presint Niaga, Bandar Satelit 26700 Muadzam Shah, Pahang Darul Makmur. Phone : 017-2330434 email : laluansepakat@gmail.com Eff. Date : Rev : PROJECT QUALITY PLAN Doc. No: LSE/PQP/Rompin/2022 Page 1 of 20 TABLE OF CONTENTS Item 1 2 3 PROJECT QUALITY PLAN AMENDMENT AND REVISION RECORDS DISTRIBUTION LIST GENERAL 3.1 3.2 3.3 3.4 4 Scope Quality Policy Project Quality Objectives Project Organization Chart CONTRACT INFORMATION Project Title Contract Sum Authorities Approval Reference No. Date of Site Possession Date of Completion Duration Defect Liability Period Liquidated and Ascertained Damaged Insurance and Performance Bond 5 PROJECT DESCRIPTION 5.1 5.2 5.3 5.4 5.5 6 Scope of Work Pre Construction Stage Construction Stage and Sequence of Works Post Construction Stage Site Layout Plan PROJECT ORGANIZATION 6.1 Client and Consultants Team Particulars 6.2 Local authorities 6.3 Main Contractor’s Team Particulars and Responsibilities 7 PROJECT ADMINISTRATION 7.1 7.2 7.3 7.4 7.5 7.6 7.7 7.8 7.9 7.10 7.11 7.12 7.13 7.14 7.15 7.16 8 Statutory and Regulatory Requirement Control of Documents Control of Records Progress Meetings Inspection and Test Plan (ITP) Inspection and Test Status Work Method Statement Progress Report Work Programme Control of Monitoring and Measuring Devices Internal Quality Audit Control of Non-Conforming Product Inspection and Testing Project Hand Over and Close Out Corrective Action Preventive Action LIST OF APPENDIX Project Organization Chart Site Layout Plan List General Forms List of Inspection & Test Plan (ITP) List of Work Method Statement Master Work Programme List of Inspection Checklists List of Subcontractors and Suppliers QMS Certificate Quality Policy Appendix A Appendix B Appendix C Appendix D Appendix E Appendix F Appendix G Appendix H Appendix I Appendix J Eff. Date : Rev : PROJECT QUALITY PLAN 1.0 Doc. No: LSE/PQP/Rompin/2022 Page 1 of 20 PROJECT QUALITY PLAN AMENDMENT AND REVISIONS RECORD All amendment and revisions in the PQP are summarized below: Pages Revision No Revision Date Revision Details Eff. Date : Rev : PROJECT QUALITY PLAN 2.0 Doc. No: LSE/PQP/Rompin/2022 Page 1 of 20 DISTRIBUTION LIST The following personnel shall be issued controlled copies of this PQP. They shall also be provided with all future amendment and revision to the same. Re-production of these PQP in any form is not permitted unless so authorized by the QA Manager. Name Company Designation Copy No Eff. Date : Rev : PROJECT QUALITY PLAN 3.0 GENERAL 3.1 Scope Doc. No: LSE/PQP/Rompin/2022 Page 1 of 20 This Project Quality Plan (PQP) shall describe in brief about the project and team members who serve this project through a strategy by placing quality as the priority. It shall specify the quality practices (e.g. operating policies, quality management system procedures and work method statements) to be followed in meeting the client’s requirements. 3.2 Quality Policy It is the policy of LALUAN SEPAKAT ENTERPRISE to meet and satisfy the quality requirements of its clients by achieved the following: a) Ensure the continued success of our Customers by meeting and complying with their requirements as well as the relevant statutory and regulatory requirements. b) Ensure our continued success by continuously strive for improvements through a continuous review and improvement of the system effectiveness. c) Ensure that our service is cost effective, reliable, high quality and is delivered on time. 3.3 Project’s Quality Objectives The management and staff at LALUAN SEPAKAT ENTERPRISE shall strive to achieve the following project quality objectives:a) To complete the project on time (extension of time shall not more than 10% of the contract period). b) To complete the project within budgeted costs. c) To achieve 100% close-out of external NCR issued within the specified deadline. 3.4 Project Organization Chart The Project Organization Chart shall be approved by SO. Refer to Appendix A. Eff. Date : Rev : PROJECT QUALITY PLAN 4.4 Doc. No: LSE/PQP/Rompin/2022 Page 1 of 20 CONTRACT INFORMATION Project Title : Cadangan Membina Bangunan Pejabat Teknikal & Stor 1 Tingkat di Atas Sebahagian Lot PT 771, Mukim Rompin, Daerah Rompin, Pahang Darul Makmur Contract No. : TNB 2982/2021 Contract Sum Authorities Approval Ref. No. a) Development Order b) Building Plan : RM 3,392,779.04 Date of Site Possession : 29.03.2022 Date of Completion : 28.09.2023 Duration : 549 days Defect Liability Period : 12 Months : : 55-W0046989-WCA 29/03/2022 - 28/09/2023 d) Contractor All Risk Policy No e) Period f) DLP : : : 55-E0048860-CAR 29/03/2022 - 28/09/2023 Performance Bond (5% of Contract Sum) : RM 112,764.80 Insurance a) Workmen Compensation b) Period c) DLP : : Eff. Date : Rev : PROJECT QUALITY PLAN 5.0 PROJECT DESCRIPTION 5.1 Scope of Work Doc. No: LSE/PQP/Rompin/2022 Page 1 of 20 - Cadangan Membina Bangunan Pejabat Teknikal & Stor 1 Tingkat di Atas Sebahagian Lot PT 771, Mukim Rompin, Daerah Rompin, Pahang Darul Makmur 5.2 Pre-Construction Stage i) To appoint Senior Project Manager / Project Manager / Senior Project Engineer for the project and establish construction team as per approved Organization Chart. ii) Prepare Work Programme base on the Outline Tender Work Programme submitted during tender stage. iii) Prepare logistic plan for temporary facilities and utilities with consideration of site condition and constraint. iv) To submit necessary documents to relevant authorities for required permits before commencement of work on site. v) We shall submit bond and insurance as required in the contract. vi) Mobilize and set-up temporary facilities and utilities as per approved logistic plan. vii) Procurement of suppliers and subcontractors. Study construction drawings and clarify any queries in advance of construction work to ensure smooth progress of work. viii) To carry out survey work to check on existing site setting out and as-built structures before commencement of work. ix) To prepare Project Quality Plan (PQP) and Project Occupational Safety & Health Plan (POSH) for Implementation on site. 5.3 Construction Stage and Sequence of Works The works are divided to areas and working trades. The sequence of works is as shown in the Work Programme with the consideration of priorities area for sectional handing over, resources and site condition and constraint. i) Structural Works a. Floor area is divided into sections for easy and smooth resources allocation with consideration of floor layout and quantum of work. b. The floor plan is divided into small areas to allow concreting work to be carried out in 10 to 12 days per section. c. Mobile cranes shall be used for hoisting work and casting of the columns and walls. Concrete pump is to be used for concreting the floor slab. Eff. Date : Rev : PROJECT QUALITY PLAN ii) Page 1 of 20 Architectural Works iii) Doc. No: LSE/PQP/Rompin/2022 The Work Programme shows a detailed sequence of work and the time frame shown is based on the possibility to commence work as the building structure is being completed and to complete the works toward the proposed completion date. Work Methodology a. System formwork shall be used for this project. b. Concrete will be supplied by ready mix concrete supplier and poured by using tower cranes, mobile cranes and concrete pump. c. M & E services are under Nominated Sub-Contractor (NSC) and this specialized work will be provided with shop drawing, inspection and test plans, inspection checklists and work method statements before commencement of work. iv) Plant and Machinery Major plants to the deployed for this project are mainly mobile crane and concrete pump, concrete mixer, passenger hoist, refuse chute and etc. 5.4 Post-Construction Stage Any defects identified during these periods shall be handled as per non-conformance procedure. As-Built drawings, certificates, warranties and O & M manual shall be prepared or obtain from subcontractors and NSC upon completion of sub-contract or trade where applicable. Upon completion of the project the project final account shall be finalized. 5.5 Site Layout Plan Please refer to Appendix B for site layout plan. Eff. Date : Rev : PROJECT QUALITY PLAN 6.0 PROJECT ORGANIZATION 6.1 Client’s and Consultants Team Status Client Architect Doc. No: LSE/PQP/Rompin/2022 Page 1 of 20 Company Name, Address, PIC, E-mail, Telephone and Fax. TENAGA NASIONAL BERHAD No. 129, Jalan Bangsar 59200 Kuala Lumpur. PIC: Miss Poh Wee Hoon Designation : Project Manager Project Management & Control Tel 03-2108 3944 Email : wee.hoon@tnb.com.my DBA Akitek (M) Sdn Bhd 58A,Kompleks Damai,Jalan Lumut, Kuala Lumpur, 50400, Kuala Lumpur, WP Kuala Lumpur, Jalan 1/68d, Titiwangsa Sentral, 50400 Kuala Lumpur Phone: 03-4042 6011 PIC: Ar Ibrahim Mohd Hashim / Ar Yusri Amri Yussoff Designation: Architect Consultant H/P : +60163314754 Email : yusri@dbaakitek.com C&S Engineer Arup Jururunding Sdn Bhd Level 26, 1 Powerhouse, No. 1, Persiaran Bandar Utama, Bandar Utama, 47800 Petaling Jaya, Selangor M&E Engineer Phone: 03-7735 2223 Arup Jururunding Sdn Bhd Level 26, 1 Powerhouse, No. 1, Persiaran Bandar Utama, Bandar Utama, 47800 Petaling Jaya, Selangor Phone: 03-7735 2223 PIC:En. Abu Bakar Mohammad Nor Designation :Consultant M&E H/P : 03-77352223 Email : kualalumpur@arup.com / Norhasniah.Kusnin@arup.com Perunding NFL Sdn Bhd 8, Jalan Bangsar Utama 9, Bangsar, 59000 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur Phone: 03-2283 3503 PIC:Afif Designation:Quantity Surveyor H/P :03-22833503 Email :contact@pnfl.com.my Titi Jasa Sdn Bhd PIC :Ramzaa Designation :Consultant Landcape H/P : 03-2693 8263 Email : mailto:tjsb7820@gmail.com Quantity Surveyor Landcape Arch 27, Jalan Medan Tuanku, Medan Tuanku, 50300 Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur Phone: 03-2693 8263 Main Contractor Laluan Sepakat Enteprise No.6, Jalan Makmur Utama, Presint Niaga, Bandar Satelit 26700 Muadzam Shah, Pahang D.M Phone : 017-2330434 PIC : Ir Lawrence Yeap Designation :Consultant C&S H/P : 03-77352223 Email : kualalumpur@arup.com / Bakar.MohammadNor@arup.com PIC : Muhamad Al Hafiz Bin Shafie Designation : Manager H/P : 017 – 2330434 Email : laluansepakat@gmail.com Eff. Date : Rev : PROJECT QUALITY PLAN Doc. No: LSE/PQP/Rompin/2022 Page 1 of 20 6.2 Local Authorities No. 1 2 3 4 5 6 7 8 9 10 Organization Majlis Daerah Rompin Kampung Sepakat Barat, 26800 Kuala Rompin, Pahang CIDB Negeri Pahang (Kuantan) A1, Tingkat Bawah Jalan Seri Kuantan 2 Seri Kuantan Square 25050 Kuantan, Pahang. / / Fax No Tel: 09-414 6677 Fax: 05- 4146077 Tel: 09 – 517 8734 Fax: 09 – 517 8751 Jabatan Bomba dan Penyelamat, Jalan Dato Ibrahim, Bandar Baru Rompin, 26800 Kuala Rompin, Pahang Tel: 09-414 6444 Fax: 09-4141466 Ibu Pejabat Polis Daerah Rompin 26800 Kuala Rompin Rompin, Pahang Tel: 09-4145222 Fax: 09-4147968 Hospital Daerah Rompin Kampung Kolam, 26800 Kuala Rompin, Pahang Tel: 09-414 1543 Jabatan Alam Sekitar Cawangan Rompin Bandar Baru Rompin, 26800 Kuala Rompin, Pahang Tel: 09-414 5522 Fax: 09-414 5524 Telekom Malaysia Berhad 3, Jln Sentosa 1, Kampung Tasik, 26800 Kuala Rompin, Pahang Tel: 09-414 5855 Fax: 09-4146688 Tenaga Nasional Berhad No 49, 51, Jalan Tuan Syed Othman, Bandar Baru Rompin, 26800 Kuala Rompin, Pahang Tel: 09-414 5020 Pengurusan Air Pahang Kampung Pulau Lang, 26800 Kuala Rompin, Pahang Tel: 09-414 6040 Jabatan Perkhidmatan Perbentungan Indah Water Konsortium, Pahang State Office, Kuantan, A1, Lorong Mat Kilau 24/1, 25100 Kuantan Pahang. Tel: 05-517 8734 Fax : 05-517 7452 Eff. Date : Rev : PROJECT QUALITY PLAN Doc. No: LSE/PQP/Rompin/2022 Page 1 of 20 6.3 Main Contractor Team Members Particulars and Responsibilities No. Designation 01. Head of Construction: 02. Project Manager 03. Site Manager Assist superior in planning, implementing and monitoring construction activities and resources. To report nonconformance activities and to discuss with the relevant personnel on corrective and preventive actions. To raise request for information to consultant and follow-up. To check all construction drawings, highlight discrepancies and resolve it. To assist PIC in the overall planning, scheduling and tracking of construction activities. To prepare progress report, logistic planning and method of construction. 04. Arch Coordinator Sn. Site Supervisor Site Supervisor Responsibilities Head of overall project team Oversea the smooth operation on all aspect at project site Liaise with clients and consultants To control and management of the construction team To coordinate of overall construction activities and manpower To meet the scheduled physical progress of project. To schedule, review and monitor progress of work. To review work method statement. To handle and client complaint at the site. Assist superior in inspection and supervision of site work. To check on material receiving check for material deliver. To check before, during and after construction activities. To highlight non-conforming activities to subcontractors during site inspection. To ensure project document and record are kept orderly and available at all times in site office. To prepare Site Diary report on C&S / architectural work. 05.05. QC Manager To coordinate and monitor the overall implementation of quality control system at site. To ensure the PQP is adhere to. To review of project quality assurance requirements. To conduct internal quality audit to jobsite. 06. QC Engineer To update PQP at jobsite as and when required. To coordinate and close out all external and internal NCRs. To carry out Quality Control at job site. Eff. Date : Rev : PROJECT QUALITY PLAN Doc. No: LSE/PQP/Rompin/2022 Page 1 of 20 No. Designation Responsibilities 07. Land Surveyor To plan daily survey work to ensure smooth execution of work. Check setting out of drawing. Set-out the survey control system Oversee the setting out, level, etc. Set-up control point and TBM To establish boundary surveys Main, calibrate and safe keep the survey instruments. To prepare Safety & Health Plan. Promote Occupational Safety and Health Management System awareness to all job sites. Chainman 08. Health & Safety Officer 09. Site Safety Supervisor 10. Machinery Asst. Manager To plan and arrange of machinery to project site. To check and verify all machinery maintenance / repair and rental at project sites. 11. Contract Manager Prepare procurement schedule for subcontractor. Prepare BQ and procurement document for quotation. Tabulate and arrange negotiate / clarify with subcontractor Prepare progress payment to subcontractor. Preparation of V Os for client and subcontractor. 12. Project Planner To establishing and monitoring Master Work Programme. To monitoring and updating of the physical progress and payment claim. Tracking the project status using Primavera and MS project planning. 13. M & E Coordinator To coordinate and plan M& E work at site. Liaises with client, consultants and NSC for M&E works. To implement of safety policy and standards. Organizing safety meetings and inspection. Maintaining safety records. Prepare M&E equipment delivery schedule. To coordinate method statement from NSC. To conduct M&E Coordination meetings and attend site meetings. To raise Request for Information to consultants. To attend site valuation for progress claim. Prepare and coordinate handover process. Prepare M & E Progress Report, claims. Close-up M&E NCRs. Prepare Site Diary and progress report for M&E works. Prepare request for inspection activities. Assist in closing M&E NCRs, progress report, inspection with authorities and attend meeting as required. Arrange inspection and testing & commissioning for M&E works. Check and submit M&E shop drawing and AS-Built Drawings Eff. Date : Rev : PROJECT QUALITY PLAN Doc. No: LSE/PQP/Rompin/2022 Page 13 of 20 7.0 PROJECT ADMISTRATION 7.1 Statutory and Regulatory Requirements The construction of the project shall comply with all current applicable Malaysian Statutory and Regulatory Requirements including but not limited to: i) ii) iii) iv) v) vi) vii) viii) ix) The Town and Country Planning Act 1976 The Uniform Building By-Law 1984 Street, Drainage and Building Act 1974 Factories and Machinery Act 1967 Occupation Safety and Health Act 1994 Fire Services Act Construction Industry Development Board Act Dewan Bandaraya Kuantan Jabatan Keselamatan & Kesihatan Pekerjaan Pahang (JKKP) / DOSH 7.2 Control of Documents The purpose of document control is to describe the way controls are applied to all documentation and data in the project to ensure the correct and appropriate documentation is available as and when required. a) Project related documents which include but may not be limited to :- All approved Construction Drawings / Shop Drawings / As-Built Drawings Instructions (from clients, authorities, architects and engineers). Correspondence (from client, authorities, architects, engineers, subcontractors, suppliers, consultants and internal memo). Contract documents Specifications and standards Inspection and Test records (Test Report, Inspection checklist) Purchase Order / Delivery Order / Mill Certificates Minutes of Meetings Request For Information (RFI) b) All internal generated documents shall have appropriate revision number i.e. work programme, work method statements, inspection and test plan etc. c) All controlled documents for the project (e.g. Site Organization Chart, Master Work Programme) shall be approved by authorized personnel. d) All obsolete documents required for legal or knowledge and preservation purpose shall be suitably identified. The obsolete documents shall bear the “SUPERSEDED” stamp in red and endorse by an authorized person on every page of the documents. e) Drawing Register shall be used to record all construction drawings and as built drawings received at project site. f) List of general forms are prepared to capture all quantity records that generated at jobsites as stated in Appendix C. Eff. Date : Rev : Doc. No: LSE/PQP/Rompin/2022 PROJECT QUALITY PLAN Page 14 of 20 7.3 Control of Records The purpose is to ensure records are identified, collected, indexed and filed and maintained to enable retrieval as required. a) All quality record shall be stored and maintained for minimum retention period as so defined in the Records Retention List. b) Upon completion of project, relevant project quality records shall be identified and archived by the respective custodian. 7.4 Progress Meetings The requirement of the Progress Meeting shall be documented as Minutes of Meeting and the major meetings to be held are as follows (the frequency of meeting listed here are subject to change as and when required). a) The elements of internal communication take into account all stages of construction. They are as stated below: i. ii. iii. b) 7.5 Meetings Training / Briefing / Induction Correspondence – E-mail, Memo, Letter, facsimile, etc. The types and frequencies of meeting during Construction Stage: No Title of Meeting Frequency Chairperson Attendees 1 Client Consultant Meeting Fortnightly SO Client/Consultants/LSE/NSC 2 Site Meeting Fortnightly LSE DBA / Consultant/ NSC 3 Subcontractor/NSC Meeting Fortnightly LSE DBA /Sub-Con/NSC Inspection & Test Plan (ITP) All inspection and test shall be conducted as per the Inspection and Test Plans (ITP). Evidence of conformity with the acceptance criteria is maintained. Inspection and Test Plan shall be available for material sample approval, material receiving, inprocess and final inspection and tests. The inspection and test plan shall define all relevant inspection and test at pre-construction, construction and post construction stages for building work and infra work. LSE shall prepare ITP and forward to relevant consultant for approval. The ITP’s shall contain the following items: Inspection / Test Activity Point of Inspection / Test Responsibility Acceptance Criteria & Frequency Verifying Document Action By Note: Please refer to Appendix D for the List of Inspection and Test Plan for C&S and Architectural works. 7.6 Inspection and Test Status Eff. Date : Rev : PROJECT QUALITY PLAN Doc. No: LSE/PQP/Rompin/2022 Page 15 of 20 The status of any relevant inspection and tests conducted shall be clearly identified in its respective records. The status shall be defined in any of the following terms:Inspection : Test : - Accept - Passed - Reject - Failed 7.7 Work Method Statement The purpose of work method statement is to describe activities and work method that will be utilized to carry out the work and to outline the resources required for the execution of work. Method statement shall be submitted to the consultant for approval prior commencing for work. Work method statement shall contain the following elements: Objective Scope Reference Definitions Responsibilities Materials Handling and storage of materials Equipment Preparation Works Work Methodology Testing ( as and when required) Note: Please refer to Appendix E for the List of Work Method Statements for C&S and Architectural Work. 7.8 Progress Reports The Project Manager shall submit the following report: a) b) Fortnightly Progress Reports as required by the Contract. Site Diary 7.9 Master Work Programme The following is the guideline for the master programme as a monitoring and controlling tool for the project progress of work using MS Project:a) b) c) Initial programme to obtain approval To propose measure to catch up lost time when the work is behind schedule Necessary revise program – subject to consultant approval to incorporate current situation or to suit specific requirement. Note: Refer to Appendix F for Master Work Programme. Eff. Date : Rev : PROJECT QUALITY PLAN 7.10 7.11 7.12 Doc. No: LSE/PQP/Rompin/2022 Page 16 of 20 Control of Monitoring and Measuring Devices All survey instruments, levels, theodolites, pressure gauges shall be calibrated to ensure all inspection, measuring and test equipment used is accurate and appropriate to the task. a) All inspection, measuring and test equipments shall be stored adequately to prevent damage. b) The calibration and testing organization shall be an external organization with adequate facilities and acceptable standard of performance. Record or certificates of the results of calibration and verification are maintained. Internal Quality Audit The purpose is to determine the effectiveness of the Quality Management System (QMS) and Occupational, Safety & Health (OSH) Management System in order to evaluate the need for further improvement and preventive and corrective action. a) Audit will be planned and implemented to ensure periodic check on the level of compliance to the established QMS and OSH at least once a year. b) Internal quality audits shall be carried out by staff not having direct responsibility in the area being audited. c) Audit finding will be reported in the management review meeting for review and prompt action to remedy any deficiencies. Control of Nonconforming Product The purpose is to identified, document, evaluate, segregate of non-conforming products and prevent the inadvertent use of non-conforming product which affects quality. a) b) All nonconforming product shall be dealt by one or more of the following ways:i. By taking action to eliminate the detected nonconformity. ii. By authorizing its use, release or acceptance under concession by relevant authority and, where applicable by the client’s representative. iii. By taking action to preclude its original intended use or application. Nonconformity shall be identified through:i. ii. Formal inspections (in-coming, in-process and final inspection). Client’s comments (limited to product’s workmanship) e.g., letters, memos, defects lists, Non-Conformance Reports (NCR). c) All nonconformities shall be controlled to prevent its unintended use or delivery. The controls and related responsibilities and authorities for dealing with nonconformities shall be as per Procedure for Control of Non-Conforming Product. d) When nonconforming product is corrected it shall be subject to re-verification to demonstrate conformity to the requirements. Eff. Date : Rev : PROJECT QUALITY PLAN 7.13 Doc. No: LSE/PQP/Rompin/2022 Page 17 of 20 Inspection and Testing a) Incoming products and materials and accompanying documentation will be inspected and verified by the site authorized personnel. b) In process and final inspection and testing elements of the project will be conducted in accordance with Inspection and Test Plans. c) The inspection and test plan shall define all relevant inspection and test at pre-construction, construction and post construction stages. d) All relevant inspection checklists are defined in the inspection and test plan and work method statement. e) Inspection and testing will be carried out by sub-contractors, main contractors and client’s representative. f) Record of inspection and test will clearly state whether acceptance criteria have been met. When tests indicate a failure to meet requirements, procedures for control of non-conforming product will apply. g) All external testing that deem necessary must be conducted in independent laboratory and all test results shall be address to relevant consultant for reference. 7.14 Project Hand Over and Closed Out The process of handover shall be planned and organized upon completion. Three months prior to the practical completion dates the Project Manager should review and establishing the following: a) b) c) d) e) f) g) h) i) j) k) l) Detailed closed-out construction programme. Review all existing drawings and identify packages/material not procured. Conduct meeting with all subcontractor and NSC to run through close out programme and handover process. To ensure rectification work is completed on defect list. To conduct final joint inspection with client’s representative or consultant. To obtain any necessary approval letters or certificates from any authority. Establish and agree the sign off procedures. Ensure the joint inspection with client’s representative or consultant is carried out. Tracking for the delivery of O & M Manuals, Warranty and As-Built drawings in an agreed format. Spares schedule/list is updated during buying process. Testing and commissioning report or test certificates to be ready. All door keys are to be labeled. A comprehensive schedule of all keys is to be attached. Eff. Date : Rev : PROJECT QUALITY PLAN Doc. No: LSE/PQP/Rompin/2022 Page 18 of 20 7.15 Corrective Action The purpose is to identify causes of non-conformities and the means by which they can be eliminated or minimized and to implement corrective measures to prevent its recurrence. a) LSE takes action to eliminate the cause of nonconformities in order to prevent recurrence. Corrective actions are appropriate to the effects of the nonconformities encountered. A documented procedure defines requirements for: b) i. ii. iii. iv. v. c) 7.16 Reviewing nonconformities (including client complaints), Determining the causes of nonconformities, Evaluating the need for action to ensure that nonconformities do not recur, Determining and implementing action needed, Records of the results of action taken. All corrective actions shall be time bound. Preventive Action The purpose is to identify potential non-conformities and their causes and to evaluate and implement necessary action to prevent its occurrence. a) LSE determines action to eliminate the causes of potential nonconformities in order to prevent their occurrence. Preventive actions are appropriate to the effects of the potential problems. b) Review of preventive actions shall focus on eliminating the causes of potential nonconformities in order to prevent their occurrence. c) A documented procedure defines requirements for: i. ii. iii. iv. v. 8.0 a b c d e f g h i j Determining potential nonconformities and their causes. Evaluating the need for action to prevent occurrence of nonconformities Determining and implementing action needed Records of results of action taken Reviewing preventive action taken. LIST OF APPENDIXES Project Organization Chart Site Layout Plan List General Forms List of Inspection & Test Plan (ITP) List of Work Method Statement Master Work Programme List of Inspection Checklists List of Work Method Statement Master WorkProgramme LSE’s Quality Policy Appendix A Appendix B Appendix C Appendix D Appendix E Appendix F Appendix G Appendix H Appendix I Appendix J Eff. Date : Rev : PROJECT QUALITY PLAN Doc. No: LSE/PQP/Rompin/2022 Page 19 of 20 Appendix A - Project Organization Chart Project Director Muhamad Al-Hafiz B. Shafie Project Manager Mohd Al Hazif B. Shafie Site Engineer Muhammad Fitri Bin Abdul Hadi General Workers 1- Mohd Abdul Momin 2- Mohd Abir 3- Hasan Mehedi 4- Mahbub Rohman 5- Mohd Nozrul Islam 6- Sukamto 7- Mohd Moklasur 8- Mohd Shahin 9- Eko Siswanto 10- Helal 11- Rasudi Ahmad Site Safety Supervisor Mohammed Daniel Bin Khamis Sub-contractor Welding Sub-contractor Piping Sub-contractor Electric Appendix B - Site Layout Plan U U CADANGAN MEMBINA BANGUNAN PEJABAT TEKNIKAL DAN STOR SATU TINGKAT DI ATAS SEBAHAGIAN LOT PT 771, MUKIM ROMPIN, DAERAH ROMPIN, PAHANG DARUL MAKMUR UNTUK TENAGA NASIONAL BERHAD TENAGA NASIONAL BERHAD Pengurus Besar (Perkhidmatan Tanah) Real Estate Ventures Bahagian Korporat Kumpulan Tenaga Nasional Berhad Aras 3, Bangunan Wilayah, No. 129, Jalan Bangsar 59200 Kuala Lumpur TENAGA NASIONAL BERHAD Lead (Project Management & Control) Real Estate Ventures Bahagian Korporat Kumpulan Tenaga Nasional Berhad Aras 1, Bangunan REVBOX, No. 129, Jalan Bangsar 59200 Kuala Lumpur DBA AKITEK (M) SDN BHD Company No : 453724-V 58A Kompleks Damai Jalan Lumut 50400 Kuala Lumpur Tel : (603) 4042 6011 ARUP JURURUNDING SDN BHD Company No : 97905-U Level 26, 1 Powerhouse No. 1, Persiaran Bandar Utama, Bandar Utama, 47800 Petaling Jaya, Selangor Tel : (603) 7735 2223 ARUP JURURUNDING SDN BHD Company No : 97905-U Level 26, 1 Powerhouse No. 1, Persiaran Bandar Utama, Bandar Utama, 47800 Petaling Jaya, Selangor Tel : (603) 7735 2223 PERUNDING NFL SDN BHD Company No : 26961-W Wisma PNFL, Jalan Bangsar Utama 9, Bangsar Utama, 59000 Kuala Lumpur Tel : (603) 2283 3503 TITIJASA SDN BHD Company No : 159619-T No, 27-3 Jalan Medan Tuanku, T I T I J A S A 50300 Kuala Lumpur Tel : (603) 2693 8263 CANARY DESIGN SDN BHD Company No : 365928-X 35, Jalan Chan Chin Mooi, 53200 Kuala Lumpur Tel : (603) 4021 9258 N SITE PLAN SCALE 1 : 400 CONSTRUCTION DRAWING 1 2 3 4 5 6 7 8 9 10 Appendix C -ListGeneralForms As-Built Drawing Register Project : Cadangan Membina Bangunan Pejabat Teknikal Dan Stor 1 Tingkat Di Atas Sebahagian Lot PT771, Mukim Rompin, Daerah Rompin, Pahang Darul Makmur (CONTRACT TNB 2982/20221) ABDR Number : LSE/DNROMPIN/ABDR/ARC/001 DRAWING No. Issue Date: TITLE STATUS * Sign By Contractor : Name : Designation : * STATUS A - Approved. Please submit 7 sets for endorsement. B - Approved subject to comments. Please re-submit 7 sets after incorporating comments. C - Rejected. Please re-submit. Consultant’s Signature / Stamp : Endorsed By SO : Signed : Date : Signed : Date : Note: 1) 2) The approval of this submittal does not constitute a variation to the Contract in terms of either time or cost, however if you deem otherwise kindly raise a Notification Of Potential Change within 7 working days of the approval. No work is to be commenced until the approved shop drawings are signed by the Relevant Consultant. INSPECTION REQUEST Project : Cadangan Membina Bangunan Pejabat Teknikal Dan Stor 1 Tingkat Di Atas Sebahagian Lot PT771, Mukim Rompin, Daerah Rompin, Pahang Darul Makmur (CONTRACT TNB 2982/20221) From : Laluan Sepakat Enterprise IR No. : LSE/DNROMPIN/IR/ARC/01 To Date : Time : : Superintending Officer (S.O.) Attn.: Ar Ibrahim Mohd Hashim We formally request inspection and attendance by your R.E *and/or* Inspector of Works for the following : Location : Type of Works : Date / Time of Required Inspection : Reason for Request : Relevant Drawings or Documentation : Signed By Contractor : Name : Received By : Administrative Date : Signed : Time : (Designation) INSPECTION REPORT The works above have been examined and are accepted** / not accepted** as having been executed in accordance with the specification, drawings and approved method statement. COMMENTS Inspected By: Date: Signed : Time CC: PSD, TNB Note: * ** DBA (AR) AJSB (C&S) AJSB (M&E) PNFL (QS) Others Delete whichever not applicable This approval shall not relieve the Contractor of any of his contractual and/or statutory obligations under the Contract MATERIAL APPROVAL FORM Project : To : Attn: Cadangan Membina Bangunan Pejabat Teknikal Dan Stor 1 Tingkat Di Atas Sebahagian Lot PT771, Mukim Rompin, Daerah Rompin, Pahang Darul Makmur (CONTRACT TNB 2982/20221) MAF NO: Contractor : Laluan Sepakat Enterprise Date Submitted: Name: Signature : Manufacturer / Supplier: Brand: Kuari Endau Rompin Sdn Bhd Kuari Endau Rompin Spec. / Drawing Ref: Contract Specification / Drawing Brochure / Catalogue & Technical Data Sample, ID Tag No: …………………… Others: Material Description: Lead Time Delivery (Weeks) : Crusher Run *Action: *Action By (Date): * To be filled by the Superintending Officer Approval Status* : (A) Authorise the Main Contractor to proceed with procurement, manufacture, fabrication and/or construction no. resubmittal is required. (B) Authorise the Main Contractor to proceed with procurement, manufacture, fabrication and/or construction, provided that the work is performed in accordance with the comments. Re-submittal of required samples/documents within two weeks in accordance with the comments in the document. (C) Indicates the Main Contractor shall NOT proceed with procurement, manufacture, fabrication and/or construction. A full submittal is required in accordance with the comments. Notes : 1. Direction provided to the Main Contractor to proceed with procurement, manufacture, fabrication and/or construction does not relieve the Main Contractor of his responsibilities under the Conditions of the Contract. 2. The approval of this submittal does not constitute a variation to the Contract in terms of either time or cost, however if you deem otherwise kindly raise a Notification Of Potential Change within 7 working days of the approval. 3. This approval shall not relieve the Contractor of any of his contractual and/or statutory obligations under the Contract. Comments: Endorsed By SO: Action Party: Signature: Date: Verified By PSD: Signature: Date: CC: PSD,TNB Signature: Date: DBA (AR) AJSB (C&S) AJSB (M&E) PNFL (QS) Others REQUEST FOR INFORMATION Project : Cadangan Membina Bangunan Pejabat Teknikal Dan Stor 1 Tingkat Di Atas Sebahagian Lot PT771, Mukim Rompin, Daerah Rompin, Pahang Darul Makmur (CONTRACT TNB 2982/20221) RFI Number : LSE/DNROMPIN/RFI/001 Issue Date : To : Superintending Officer Attn.: Ar Ibrahim Mohd Hashim *Subject : From : Laluan Sepakat Enterprise Summary : Attachments : Name Designation : : Signed : Note : This reply does not constitute a variation to the Contract in terms of either time or cost, however if you deem otherwise kindly raise a Notification of Potential Change within 7 days of this reply. Reply : Attachments : Replied by : Endorsed by SO : Signed : Date : Signed : Date : CC: PSD,TNB DBA (AR) AJSB (C&S) AJSB (M&E) PNFL (QS) Others SAFE WORK METHOD STATEMENT Project : Cadangan Membina Bangunan Pejabat Teknikal Dan Stor 1 Tingkat Di Atas Sebahagian Lot PT771, Mukim Rompin, Daerah Rompin, Pahang Darul Makmur (CONTRACT TNB 2982/20221) SWMS Number : LSE/DNROMPIN/SWMS/001 Issue Date : To : Superintending Officer (SO) Attn.: Ar Ibrahim Mohd Hashim From : Laluan Sepakat Enterprise c.c : PSD, TNB - Client DBA - Architect AJSB (C&S) - C&S Engineer AJSB (M&E) - M&E Engineer PNFL - Quantity Surveyor Others - IOW * To be filled by Superintending Officer (SO) Action / Summary : Attachments : Signed By Contractor: Name : Designation : Consultant’s Reply : Endorsed by SO: Signed : A- Approved. BC- Approved subject to comments as attached and to re-submit. Rejected. Please re-submit. - See Attached List Signed : Date : Note: Date : 1) The approval of this submittal does not constitute a variation to the Contract in terms of either time or cost, however if you deem otherwise kindly raise a Notification Of Potential Change within 7 working days of the approval. This approval shall not relieve the Contractor of any of his contractual and/or statutory obligations under the Contract. 2) No work is to be commenced until the above is approved and signed by the S.O. Shop Drawing Register Project : Cadangan Membina Bangunan Pejabat Teknikal Dan Stor 1 Tingkat Di Atas Sebahagian Lot PT771, Mukim Rompin, Daerah Rompin, Pahang Darul Makmur (CONTRACT TNB 2982/20221) SDR Number : LSE/DNROMPIN/SDR/ARC/001 DRAWING No. Issue Date: TITLE STATUS * Sign By Contractor : Name : Designation : * STATUS A - Approved. Please submit 4 sets for endorsement. B - Approved subject to comments. Please re-submit 4 sets after incorporating comments. C - Rejected. Please re-submit. Consultant’s Signature / Stamp : Endorsed By SO : Signed : Date : Signed : Date : Note: 1) 2) The approval of this submittal does not constitute a variation to the Contract in terms of either time or cost, however if you deem otherwise kindly raise a Notification Of Potential Change within 7 working days of the approval. No work is to be commenced until the approved shop drawings are signed by the Relevant Consultant. SUBMITTAL FORM Project Title: Cadangan Membina Bangunan Pejabat Teknikal Dan Stor 1 Tingkat Di Atas Sebahagian Lot PT771, Mukim Rompin, Daerah Rompin, Pahang Darul Makmur (CONTRACT TNB 2982/20221) Ref Number: Issue Date: To: Attn: From: c.c: PSD, TNB - Client ARUP (M&E) – M&E Engineer DBA - Architect PNFL – Quantity Surveyor ARUP (C&S) – C&S Engineer Others – IOW Summary: Signed By Contractor: Name: Designation: *To be filled by Architect or SO Action/Comment: *Action By (Date): Attachment: Consultant’s Reply: A – Approved Endorsed By Architect/SO: B – Approved subjects to comment, please re-submit C – Rejected, please re-submit D – See Attached List Signature: Signature: Date: Date: Appendix G -List Of Inspection Checklists Cadangan Membina Bangunan Pejabat Teknikal Dan Stor 1 Tingkat Di Atas Sebahagian Lot PT771, Mukim Rompin, Daerah Rompin, Pahang Darul Makmur (CONTRACT TNB 2982/20221) REQUEST FOR INSPECTION Discipline: Fabrication For Cabin Ref. No LSE/2022/RP/RFI/001 Date 15/05/2022 Section: Temporary Cabin The following works are/will be ready for inspection/testing at Time: Works are intended to commence at Time : 10.00 a.m 3.00 p.m hrs. Date: hrs. Date: 15 Mei 2022 16 Mei 2022 DESCRIPTION OF WORKS Location: Preliminaries Works Type of work: Fabrication of site Cabin Sketches (If required) Acknowledge received by Name & Signature NOTIFICATION STATUS BY SUPERVISING ENGINEER Inspection passed. Work are allowed to proceed Remedial works listed below to be completed but no further inspection require Remedial works listed below to be completed and re-inspection is required Supervising Engineer’s Remarks: Prepared and Submitted By Approved By (Client’s / Consultant’s Representative) Signature Signature Name Name Designation Designation Date Date Note: This RIN must be forwarded 24 hours before Inspection Work. Appendix J - LSE’sQualityPolicy OBJEKTIF KESELAMATAN DAN KESIHATAN PEKERJAAN Untuk menyingkirkan dan mengawal hazad tempat kerja. Untuk menyediakan pekerja dengan informasi keselamatan, penyeliaan dan latihan secukupnya untuk menghadapi hazad tempat kerja yang bakal mereka jumpa. Untuk memastikan kualiti keselamatan, kesihatan serta kebajikan untuk semua pekerja dalam keadaan yang baik. Tarikh : 20/5/2022 POLISI KESELAMATAN DAN KESIHATAN DALAM PEKERJAAN Laluan Sepakat Enterprise memastikan bahawa: berdedikasi secara penuh dalam Semua pekerja dijaga secara selamat sepenuhnya di dalam aspek kesihatan, keselamatan dan kebajikan ketika di tapak bina/ketika melakukan aktiviti berkaitan tugas kerja. Sesiapa yang memasuki tapak bina kami sebagai klien, pekerja sementara, atau pelawat tidak terdedah dengan sebarang risiko keselamatan dan kesihatan ketika urusan mereka dijalankan di tapak bina. Segala peraturan dan keperluan undang-undang dipatuhi. Kecederaan serta penyakit disebabkan oleh aktiviti kerja atau persekitaran tempat kerja dapat dibendung. Kami akan berterusan meningkatkan kualiti dalam aspek praktikal keselamatan dan kesihatan. Tarikh : 20/5/2022