BORANG PEMERIKSAAN DAN MULATUGAS (T&C) NET ENERGY METERING (NEM) (OPC & LPC)
NAMA PELANGGAN:
TARIKH PEMERIKSAAN:
NO AKAUN:
JAM MULA:
ALAMAT PREMIS:
JAM TAMAT:
MAKLUMAT TEKNIKAL PERPASANGAN SOLAR PV
Voltan pada titik sambungan
RED:
Volts
YELLOW:
Volts
BLUE:
Volts
(sebelum perpasangan)
Voltage at Point of Connection
(before installation)
Voltan pada titik sambungan
RED:
Volts
YELLOW:
Volts
BLUE:
Volts
RED:
Volts
YELLOW:
Volts
BLUE:
Volts
(selepas perpasangan)
Voltage at Point of Connection
(after installation)
Voltan pada Meter TNB
(sekiranya boleh diakses)
Voltage at TNB meter (if
accessible)
Anti-islanding Test
Disconnection Time:
sec
Reconnection Time:
min
PENGESAHAN PENGUJIAN DAN MULATUGAS SISTEM SOLAR PV OLEH ORANG KOMPETEN
Tandatangan:
Nama:
No I/C:
Tarikh:
Cop Syarikat: