Work Manual What “To Do” and what “Not To Do” at Workshop # 1: Receiving Job Sheet / Drawings # 2: Planning /Writing Jobcards # 3: Arranging / Ordering Material # 4: Releasing Job Cards / # 5: Recievig Job & Job Card Over Time & Delivery 1/1 Step # 1 | Receiving Job Sheet / Drawings Receiving JobSheet Invoice # verification Deadline verfication Element Verification (as per element wirting sheet # ESS) Making commitment about delivery to AM / PM (that how much time is needed after all the informations are recieved / provided Tentative Problems Invoice # is not mentioned Deadline is not clear Element specifications are not as per (as per element wirting sheet # ESS) Drawings & Technical informations are not complete Deadline is too short Must "Do" Must follow all the above steps Liaise with your manager if situation occurs not mentioned in this manual. Must "Not Do" Skip any above mentioned step Make any decision if you are not 100% sure about the solution. ny a t e p c c a t Do No eet h s b o J t u o task with LD P / l i m a e y or b Nexus54 L.L.C Job Sheet Tel: 04 - 333 8980, Fax: 04 333 8982 P.O. Box: 294212, Dubai, UAE Name / Address Job # Date: LPO / Ref: Deadline: Mr. Pranav Shah NIRAV DM Dubai - UAE Mobile. 050 2715057 1484 12-Sept-2010 c/o Alex 03-Oct-2010 Project Invoice #: Nirav DM Stand for Int'l Jewellery Wk Item DESCRIPTION Qty. Exhibition S... NIRAV DM JEWELLERY EXHIBITION STAND SIZE 6X3M FOR DUBAI INTERNATIONAL JEWELLERY WEEK (October 72010 ,10-) Flooring SFL-01 Plat... SFL-10 Skir... SFL-02 Car... 1 FLOORING Raised wooden platform 10 cm height. Size 6x3m (on rental) Skirting to place the stand with roller paint finish size 18 rm Carpet for flooring moderate quality (Delta Brand). Size 6x3m Stand Elem... STAND ELEMENTS SER-01 Bac... 1 no(s) Back wall made of wood/MDF 10 cm thick in roller paint finish. Size 6x4m with one display shelf size 2.45x.30x.55m Roller Paint... 1 no(s) Meeting room made of wood/MDF in roller paint finish. size 2x3x4m with sliding door and one built-in display shelf size 2.05x.3x.6m SES-16 Pro... 2 no(s) Product display counter in spray paint finish with glass top cover. Sizes 1.85x.4x1m and 2.5x.4x1m GRAPHICS ODP-01 Vin... 3 no(s) Vinyl cutouts one color (individual letters of self adhesive & pre colored media) Nirav DM logo INP-01 Post... Poster printed (1440 DPI) indoor quality on tear resistant paper with frames fix on the wall 1 no(s) Size 2.15x.8m 1 no(s) Size 2.05x.7m 2 no(s) Size .90x.85 Furniture FURNITURE (on rental) SFR-02 Mee... 2 no(s) Meeting tables SFR-06 Visi... 8 no(s) Visitor's chairs Electricals ELECTRICAL (on rental) White:Printing Department, Pink:Accounts, Yellow:Workshop:Green:Delivery Dept. AM / PC / PM AF Page 1 Comes From: Account Manager / Project Manger / Accounts Goes To: Production forman / Production Manager # 1: Receiving Job Sheet / Drawings Purporting Process | For Graph cis Designer 2/1 Step # 2 | Planning / Writing Jobcards Resolution Verification Counting all the elements Filling the Job Card Arranging material Releasing job card Recieving job card Inspecting job closing job card Tentative Problems Quality is not ok Too much time consumed Unnecessary delay JOB CARD 01/08 Date : 1484 Job No : Name/Team: Carpnter(s) Name Job #: 1484 Estimated Start Time: Estimated End Time: 06.00 pm - 12/12 Actual Start Time: 08.00 am - 12/12 Actual End Time: 04.00 pm - 12/12 Estimatd Hours: Element # 08 hours Total Hour Spent: e OverTim s 02-ho ur 06 hours Description Qty: Reception counter banana hai size 120x80x40 cm 02 Sketch: Must "Do" Must follow all the above steps Liaise with your manager if situation occurs not mentioned in this manual. Must "Not Do" Skip any above mentioned step Make any decision if you are not 100% sure about the solution Accompanied: Working drawing Sample Sketch work Colour drawing Material: Reciever sign: Base material (MDF, Ply, White Wood) Accessories (Hinges, locks, Knobs & tracks etc.) Finishing material i.e. (Veinier, Formica, leaping, paint etc.) Job inspection Comments: Dimensions / Size Finishing Quality Date & Time: Inspector sign: Date & Time: Time Spent Extra Point earned Point scale: 1 - 5 ( 5=excellent, 4=good, 3= acceptable, 2=not good, 1=Very poor) Comes From: Production Manager / Workshop Incharge Goes To: Carpenter / Electrcian / Painter / Mockup / Buildup / Dismentelling # 2: Planning /Writing Jobcards Pre-Printing Process | For Graph cis Designer 2/2 Writing Element Specifications Please Write the element specification in the following manner only: ( qty + scope of work + product specifications + media being used + finishing specifications + installtion method + location to be installed / placed + Size ) i.e. 02 No(s) Supply and Installation of shelveing counter made of MDF / Ply- wood with spray paint finish, to be placed on existing floor in drawing room area size 120x40x60 cm Provided by : Account Manager / Must be mentioned in the Job Sheet Verified by: Production Manager / Forman 01 - Qty 02 - Scope of work ( Delivrery / Colleciton /Instllation etc) 03 - Description of product 04 - Media being used (Made of ) 05 - Finishing specifications (like paint cutting or any finishing method) 06 - Installtion method (how the product going to be fixed or placed) 07 - Location to be installed / placed (in what area / location ) 08 - Size ( WidthxHeightXdepth) Pre-Printing Process | For Graph cis Designer 2/1 AM /PM Production Relationship Client Account Manager 1: Job Sheet: 2: Working Drawings (Clear Informations) 3: Deadline, (Location, Date and Time) 4: Contact Person for Delivery Job Handover Production Meeting / Info Workshop Graphics/Sign Additional Requirement Technical Issue? Fill Extra From Ask Client Inform AM / Accounts / TS Inform AM / PM Amendments / Changes (Inform Client about extra cost and Time) Take permission from AM/PM Inform accounts department / TS (Via Email) Deliver the Job get signed DO (Inform AM /PM & Accounts via Email) + DO Pre-Printing Process | For Graph cis Designer Job Sheet / Communications Job Sheet / Communications t t t t +PCTIFFUDPQZ .PDLVQBQQSPWBM $MJFOUTBQQSPWBMTPG4XBUDIFT 'JOJTIJOH$PEFT 1BJOUT$BSQFUFUD t t t t Breakdown Date Information Schedule / Checklists: -PDBUJPONBQXJUITUBOEEJSFDUJPO (SBQIJDTDIFDLMJTU 4UBOEDPNQPOFOUDIFDLMJTU 'VSOJUVSF &MFDUSJDBM "7$IFDLMJTU T t t t t -PDBUJPONBQXJUITUBOEEJSFDUJPO (SBQIJDTDIFDLMJTU 4UBOEDPNQPOFOUDIFDLMJTU 'VSOJUVSF &MFDUSJDBM "7$IFDLMJTU T Render Images / Working Drawings t t t 8% 8% 8% 8% 8% &MFWBUJPOTBOEøPPSQMBOXJUITJ[FT 1FSTQFDUJWFWJFXXJUI4QFDJöDBUJPOT (SBQIJDTMBZPVUXJUIDMFBSJOEJDBUJPOT t 'MPPSQMBO t 1FSTQFDUJWFWJFXT t 0CKFDUTQFDJöDBUJPOT t &MFDUSJDBMMBZPVUT t (SBQIJDTMBZPVUT Purchase Orders / Extra Forms t 1VSDIBTF0SEFST*OWPJDFT t &YUSB'PSNT$IBOHF'PSNT %JTQPTFBGUFSEJTNBOUMJOH 1BSUJBM'VMMHPJOHCBDLUPDMJFOU *G4UPSBHFXJUIVT UIFOJUTIPVMEBDDPNQBOJFEFYUSBKPCTIFFU Closing Report: t 8IPJTUIFTUBSPGTUBOE 8FBLFTUMJOL t 8IBUXFOUHPPEBOEXIZ t 8IBUXFOUXSPOHBOEXIZ 4VCNJTTJPOUP0.XJUIJOUISFFEBZT t t t %JTQPTFBGUFSEJTNBOUMJOH 1BSUJBM'VMMHPJOHCBDLUPDMJFOU *G4UPSBHFXJUIVT UIFOJUTIPVMEBDDPNQBOJFEFYUSBKPCTIFFU Venue: t t t Project Name: &MFWBUJPOTBOEøPPSQMBOXJUITJ[FT 1FSTQFDUJWFWJFXXJUI4QFDJöDBUJPOT (SBQIJDTMBZPVUXJUIDMFBSJOEJDBUJPOT t 'MPPSQMBO t 1FSTQFDUJWFWJFXT t 0CKFDUTQFDJöDBUJPOT t &MFDUSJDBMMBZPVUT t (SBQIJDTMBZPVUT Breakdown Removal: Breakdown Removal: Venue: Information Schedule / Checklists: t t t 8% 8% 8% 8% 8% Project Name: t +PCTIFFUDPQZ t 'JOJTIJOH$PEFT 1BJOUT$BSQFUFUD Render Images / Working Drawings Buildup Date: Buildup Date: Breakdown Date 2/2 Pre-Printing Process | For Graph cis Designer 3/1 NEXUS54 Request of Change NAME / ADDRESS Date : Time: Existing Job No: Mobile: Stand / Occasion : Company: Mockup Report Tel: 04-333 8980, Fax: 04-3338982 P.O. Box: 294212, Dubai, U.A.E. Visit Date: JOB # D.O. # LPO / Ref: Mockup Date: Requested By: Telephone: Project Changes against initial Agreement Description Qty Amount Invoice #: AM Dear Sir / Madam We are pleased to report the progress of this project is in accordance with the agreed build schedule. The ‘mock up’ has been undertaken for you to check and ensure that everything meets with your expectations. Please note, any changes in design from this point could cause delay against the agreed delivery date and time. There could also be added costs over and above the agreed contract sum. We aim to move on to the next stage of the build schedule and we kindly request the balance due as per agreed terms and conditions. Best Regards Account Manager Mockup Checklist Flooring Inspected Approved Inspected Approved Inspected Approved Inspected Approved Inspected Approved Inspected Approved Carpet color /code , Parquet / Laminate Basic Projects Elements i.e. Wooden / other elements, steel structure, facia and reception counter etc. Color / Finishes Paint sample / code ( ) Electrical / Fixtures Hereby I agreed that above mentioned request has been made for the change and is not part of initially agreed job. I acknowledged and agreed to pay the cost of above mentioned change without any delay. Lights / Fixtures Furniture Rental furniture for the event Graphics Full Name Company Stamp For Office Use Only Total Project Amount: Signature Comments / Note: (For Clietn’s Use only) Invoice No. Payment Terms & Conditions: Account Manager: Project Manager: Tel : +971 4 333 8980 Fax : +971 4 333 8982 P.O.Box 294212 Dubai, UAE eMail: nexus54@eim.ae Website : nexus54.com White: Design Dept. Yellow: Construction Dept. Green: Finishing Dept. Pink: Accounts Dept. First Party: Authorised Signature Name: Date: Second Party: Authorised Signature Name: Date: CC. Finance department, Project Manager Pre-Printing Process | For Graphcis Designer 3/2 Cutting List Date : Job No : Element Name: Element #: Material to be cut: Ply / MDF MM Size in cm (wxh) Qty: Cutted: Point scale: 1 - 5 ( 5=excellent, 4=good, 3= acceptable, 2=not good, 1=Very poor) Comes From: Carpenter / Forman Goes To: Cutting Master / Cutter Operator Cutting List Date : Job No : Pre-Printing Process | For Graph cis Designer Ply / MDF MM Size in cm (wxh) Qty: Cutted: 3/3 Handover Sheet Tel: 04-333 8980, Fax: 04-3338982 P.O. Box: 294212, Dubai, U.A.E. NAME / ADDRESS Date: JOB # D.O. # LPO / Ref: Project Time: Invoice #: Client’s confirmation: Point scale: 1 - 5This ( 5=excellent, 4=good, 3= acceptable, 2=not good, 1=Very poor) is to be acknowledged that: We are pleased to recive our project accordance with the agreed contract, and state that everything meets with our standard & expectations. Items add on site: Item description Unit price Quantity Total Total amount in capital: Nexus54’s Confirmation The project is completed on time and the quality met our standards. On site supervisor signature: Comments / Note: (For Client's Use only) On site client/authorized signature: Name: Comes From: Project Manger / Site Supervisor (Get Signed by Client) Goes To: Accounts Depoartment Date: Please kindly give us your approval and your kind comment will be highly appreciated! Date: Mobile: CC. Finance department, Project Manager Pre-Printing Process | For Graph cis Designer 3/3 &RPSRQHQW/LVW (YHQW1DPH $UDE3ODVW -RE1R 6WDQG&&+DOO':7& (YHQW'DWH 0RQ-DQ $0 7D\\HE6KHUD] &OLHQW 5LHFHNHUPDQQ$UDE3ODVW [6WDQG$UDE3ODVW 0RFNXS'DWH :HG'HF 30 'RQ%HUJRQLD 0RELOH 0U5RZHQD 'DWH7RGD\ 'HF 4W\ 0DGH 3DLQW ༪ ༪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༪ ༪ ༪ [ ༪ ༪ ༪ ༪ [ [ [ [ [ [ [ [ [ $8',29,68$/ 2Q5HQWDO Comes From: Account Manager / Project Manger Goes To: Production forman / Production Manager Pre-Printing Process | For Graph cis Designer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omes From: Account Manager / Project Manger Goes To: Production forman / Production Manager To fill it and follow Pre-Printing Process | For Graph cis Designer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omes From: Account Manager / Project Manger Goes To: Production forman / Production Manager To fill it and follow Pre-Printing Process | For Graph cis Designer 3/3 -RE1R 1$0(" $ORFDWHG%XGJHW ([SHQVHV7RWDO %DODQFH%XGJHW 3HUFHQWDJH 2YHUDO%XGJHW96([SHQVHV %DVH0DWHULDO 3DLQW )LQLVKHV /DPLQDWHV(WF *ODVV $FUO\OLF $FFHVVRULHV+DUGZDUH (OHFWULFDOV &DUSHW)ORRULQJ 2XWVRXUFHG/DERXU 7UDQVSRUWDWLRQ )XUQLWXUH )ORZHUV /32 7RWDO $PRXQW 6WDWXV Pre-Printing Process | For Graph cis Designer