Uploaded by Rovin Antony

ADGAS

advertisement
Permit to Work Standard
AUTHORITY FOR ISSUE
Issue of this document is authorised by GASCO, Senior Vice President (Operations)
Name:
Cyrilles Huijsmans
SVP(O)
Signature:
Date:
June 2009
This document has been produced and approved by HSE Division.
Any enquiries relating to the document should be addressed to HSE Vice President (HSE)
This controlled document has been issued to your position and is NOT a personal copy.
Please ensure it that it is either passed to your successor or returned to HSE Division
should you accountabilities change.
GASCO - Health, Safety and Environmental Division
Permit to Work System Manual
GASCO Health, Safety and Environment Management System
Permit to Work Standard
Policy & Strategic Objectives
Organisation, Resources & Competence
Risk Evaluation & Management
Leadership and
Commitment
Planning, Standards & Procedures
Corrective Actions
Implementation & Monitoring
Audit
Management
Continuous Improvement
GASCO - Health, Safety and Environmental Division
Controlled Copy
Number:
CONTROLLED COPY NUMBER:
CONTROLLED MANUAL DISTRIBUTION LIST
LOCATION
Head Office
AUTHORISED HOLDER
SVP (O)
HSE
HSE/2
CONTROLLED COPY N0.
1
2
3
Habshan/Bab Plant Division
HBS
MCR (Habshan)
MCR (Bab)
4
5
6
Asab Plant Division
OAZ
MCR
7
8
Bu Hasa Plant Division
OHS
MCR
9
10
Ruwais Plant Division
ORS
MCR
11
12
Pipelines Division
PLS
MCR (Maqta)
13
14
GASCO Permit to Work Standard
Rev 2.0 2009
PRELIMINARY SECTION
Page 1 of 15
CONTENTS
PRELIMINARY SECTION
MANUAL CONTENTS LIST (THIS PAGE)
3
AUTHORITY FOR AMENDMENT AND REVISION HISTORY
5
GLOSSARY OF TERMS AND DEFINITIONS
7
CHAPTER
CHAPTER - 1
OBJECTIVES OF THE PTW SYSTEM AND ITS CUSTODIANSHIP
CHAPTER - 2
ORGANISATION
CHAPTER - 3
FRAMEWORK OF THE PTW SYSTEM
CHAPTER - 4
WORKSITE PREPARATIONS
CHAPTER - 5
COMPLETION OF PERMITS AND CERTIFICATES
CHAPTER - 6
ACTIVITY SEQUENCE CONTROL FORM
CHAPTER - 7
TOOLBOX TALKS
CHAPTER - 8
PERMIT CONTROL FACILITY AND ADMINISTRATION OF PTW
CHAPTER - 9
PERMIT TO WORK SYSTEM AUDITING AND REVIEW
CHAPTER - 10
AUTHORISED DEVIATIONS FROM PERMIT TO WORK SYSTEM
GASCO Permit to Work Standard
Rev 2.0 2009
PRELIMINARY SECTION
Page 2 of 15
AUTHORITY FOR AMENDMENT AND REVISION HISTORY
DATE
REVISION
NUMBER
11/12/02
0
14/06/03
1.0
30/11/03
1.01
CHANGE
Reference
Section(s)
Reason for
Change
Signed
Authority
for Issue
AGM(O)
First Issue of new PTW
System Manual - for Pilot
Trial at Bu Hasa
All Sections
N/A
Update and issue of the
new PTW System Manual
as a controlled document
Update of Manual Holders
and Glossary of Terms
All Sections
Introduction of
new GASCO
PTW System
Introduction of
new GASCO
PTW System
Authorisation to Work
Form and procedures;
Activity Risk Assessment
revised for ALARP
explanation and how to
demonstrate ALARP.
Increased
Preliminary
numbers of
Section
(this section) Controlled
Copies of
PTW Manual.
Chapter 3,
Section
3.3.1.2,
3.4.1
3.4.1.4.1
Glossary
updated with
additional
definitions for
terms used in
the Hazard
Management
process.
To provide a
process for
approving
work of a low
risk nature
adjacent to
Pipelines.
GASCO Permit to Work Standard
Rev 2.0 2009
PRELIMINARY SECTION
Page 3 of 15
AUTHORITY FOR AMENDMENT AND REVISION HISTORY
DATE
30/11/03
June 2009
REVISION
NUMBER
1.01
1.02
CHANGE
Reference
Section(s)
Reason for
Change
Paragraph on the routing
of copies of Gas Test
Certificate included.
Chapter 5,
Section 5.2
To clarify
requirements
for distribution
of copies of
the Gas Test
Certificate
New Authorisation to Work
form (ATW) together with
accompanying Procedure.
Chapter 5,
Section 5.9
New Form
and
procedures
for low risk
Pipeline work.
Introduction of Isolation
Confirmation Certificate
Chapter 5
Revision of ATW
flowchart
Chapter 3
(App G)
Improved
management
of isolations
Review of
pipeline
procedure
Signed
Authority
for Issue
AGM(O)
GASCO PTW System Manual
Rev 2.0 Sep. 2009
PRELIMINARY SECTION
Page 4 of 15
AMENDMENT RECORD
The signature of each amendment indicates that the Page Status was correct and
checked before the amendment was incorporated, and that the amendment was correctly
incorporated in accordance with the Amendment Instruction Sheet.
AMENDMENT
NUMBER
PERSON INCORPORATING AMENDMENT INTO
MANUAL
NAME
SIGNATURE
DATE
AMENDED
DESIGNATION
GASCO Permit to Work Standard
Rev 2.0 2009
PRELIMINARY SECTION
Page 5 of 15
GLOSSARY OF TERMS AND DEFINITIONS
A Work Permit that has been accepted by the
Accepting Authority but has yet to be endorsed by
the Area Authority (AA)
Accepted Permit
Acceptor.
The person appointed by the Plant or Pipeline
Vice-President who signs the Acceptance box of
the Permit or Certificate
Activity Risk Assessment (ARA) The process of identifying the hazards associated
with the work to be done (Activity) and specifying
the controls required to reduce the risk to a level
"As Low as Reasonably Practical" (ALARP)
Alarm & Trip Defeat Register
The formal record of all authorised inhibits of alarms
and/or overrides of executive trip functions on equipment and/or systems. The Register is kept in the Main
Control Room under the control of the shift supervision
As Low As Reasonably Practical To reduce a risk to a level which is as low as reasonably
(ALARP)
practicable involves balancing the reduction in risk
against the time, trouble, difficulty and cost of achieving
it. This level represents the point, objectively assessed,
at which the time, trouble, difficulty and cost of further
reduction measures become disproportionate to the
additional risk reduction obtained
The person responsible for monitoring the safety of
Area Authority (AA)
an area and the assets within it, and authorising work
in that area at any particular time. In Operations
Department, this will normally be the Area Operator.
For non-operational areas, the Area Authority is
appointed by the Asset Holder for that particular
area (Maintenance, Engineering or Construction).
The Area Authority endorses Permits for each shift in order
to authorise work to proceed. He has the authority to:
•
Control the entry and presence of all
personnel within that area.
•
Stop any person(s) from working if they are
not acting in a safe manner.
•
Stop any work that could adversely affect his area
GASCO Permit to Work Standard
Rev 2.0 2009
PRELIMINARY SECTION
Page 6 of 15
GLOSSARY OF TERMS AND DEFINITIONS
Area Engineer (AE)
The Mechanical, Electrical, Control/Instrument,
Civil or Inspection Engineer for a designated area
Activity Sequence Control (ASC) Form A control document used for those tasks /activities
which must be carried out in a nominated
sequence
Asset Holder (AH)
The Senior Representative of a Department,
responsible and accountable to the Asset Owner
for the integrity and safe condition of the structure,
system and equipment allocated to him, and is
defined separately at each Site or Project
•
The principle Asset Holders are:
•
The Operations Superintendent
•
The Shift Superintendent (Habshan)
•
The Maintenance Superintendent
•
The Technical
(Ruwais)
•
The HSE Superintendent
•
The Construction Manager (for major
construction sites not yet handed over)
Services
Superintendent
GASCO Permit to Work Standard
Rev 2.0 2009
PRELIMINARY SECTION
Page 7 of 15
GLOSSARY OF TERMS AND DEFINITIONS
The person responsible and accountable to the
Asset Holder for the integrity and safe condition of
the structure, system and equipment allocated to
him, and is defined separately at each Site or
Project.
The principle Asset Operators, for
Restricted and Unrestricted (Operational Areas),
are:
Asset Operator (AO)
•
•
•
•
The
Operations
Co-ordinator
(Permit
Validation)
The Shift Controller (Issuing Authority)
The Assistant Shift Controller (Endorsements)
The Pipeline Operations Supervisor
The
principle
Asset
Operators,
for
Unrestricted (non-Operational) Areas, are:
•
•
•
•
The Maintenance, Engineering Authority
The Safety Officer
The Laboratory Authority
The Construction Engineering Authority
Asset Owner
The Plant/ Pipeline Vice-President who is
responsible and accountable to the Senior
Vice-President Operations (SVP (O)), for the
integrity and safe condition of the structure,
system and equipment allocated to him
Authorised Gas Tester (AGT)
A Gas Tester authorised in writing by the Plant or
Pipeline Vice-President, or his nominated deputy,
to undertake gas testing, following satisfactory
completion of training and assessment of
competence
Boundary Isolations
The documented isolations, which effectively
isolate a section of process plant and/ or
equipment from other sections of the plant and/ or
equipment
GASCO Permit to Work Standard
Rev 2.0 2009
PRELIMINARY SECTION
Page 8 of 15
GLOSSARY OF TERMS AND DEFINITIONS
Certified Person by (Electrical)
The Electrical, Mechanical, Instrument or
Operations person, authorised by the Senior
Electrical Engineer to carry out specific functions
for electrical isolation purposes or for access to
Electrical Sub-stations or Switch rooms
Closed Permit
A Permit, which has been closed by a signature
because the job is complete or exceeded its
validity period. The Permit is then no longer valid
for work
Cold Work
Work which will not involve the use of naked
flames nor produce any source of ignition
Competent
A person who has, through training or experience,
the skills and knowledge to undertake a task, and
who is authorised by the Plant or Pipeline
Vice-President to carry out the task as required by
the Permit to Work System
Conflicting Activities
Work activities, which, if carried out concurrently,
could give rise to an unsafe condition
Confined Space
Any area that has limited access or egress, or
which is sufficiently confined to permit the
accumulation of flammable or toxic gases or
vapours, or where an oxygen deficiency or
enrichment could occur
Consequence
An event that results from the release of a hazard
Control
Prevention of hazard being released (including
elimination or avoidance of the hazard) or
containment of the hazardous event
GASCO Permit to Work Standard
Rev 2.0 2009
PRELIMINARY SECTION
Page 9 of 15
GLOSSARY OF TERMS AND DEFINITIONS
The Permit to Work System has custodians, who
are responsible for:
Authorisation for Change, (SVP (O))
Development and Co-ordination (VP HSE)
Implementation ( Plant and Pipeline VP).
Any activity that requires the installation, repair,
removal, replacement, modification, extension or
cleaning of any component part associated with
electrical equipment.
It does not include electrical isolations (switching) in
support of mechanical work unless they involve physical
disconnection of cables or earthing down of equipment
Custodians
•
•
•
Electrical Work
Endorsed Permit
A valid Permit carrying an Endorsement signature
for the current shift period of the Asset Operator
and Area Authority
Endorser
Personnel signing Permits in the role of Endorser
are those who, on a shift-by-shift basis, confirm
that it is safe for a job to be carried out. In effect,
they are directly responsible for the safety of an
area and the assets within it, and for control of
work underway in that area at any particular time
Escalation
An increase in the consequences of a hazardous
event
The Permit that has to be issued whenever any
digging, excavation or boring has to be done,
irrespective of whether it is in a Restricted or
Unrestricted Area
Excavation Permit
Extended Period Isolation
Any isolation, which remains in place, where, for
example, work has commenced on equipment but
has had to be suspended whilst spares are
awaited or if the isolation remains in place after the
associated main work permit closed
Gas Test Certificate
The PTW document which is used to detail the
Gas Test requirements associated with carrying
out a particular task on the Location, and to record
the results of the test(s). This document is
integrated into the Permit to Work and is located
on the back of the Work Permit
GASCO Permit to Work Standard
Rev 2.0 2009
PRELIMINARY SECTION
Page 10 of 15
GLOSSARY OF TERMS AND DEFINITIONS
Hazard
The potential to cause harm (including ill health
and injury) damage to property, products, the
environment or reputation
Hazard Assessment
Refers to both quantitative processes (such as
QRA) and qualitative processes, which produce
information about the hazard and its potential
consequences
Hazard Management Process
The structured hazard analysis methodology
involving Hazard Identification, Risk Assessment,
Control and Recovery measures. To completely
manage a hazard requires all four steps being
executed and recorded
Hazardous Event
An event in which the potential of a hazard to
cause harm is realized
Hazardous Area
Plant area with a hazardous area classification
(Zone 0, 1 or 2) as defined in Institute of Petroleum
CoP 15 as: “A three-dimensional space in which a
flammable atmosphere may be expected to be
present at such frequencies as to require special
precautions for the control of potential ignition
sources including fixed electrical equipment”.
Non-Hazardous Area
Plant area which is not classified as a hazardous
area as defined in Institute of Petroleum CoP 15.
Hot Work
Work that involves a continuous or potential
source of ignition. This is divided into:
•
Hot Work Category 1 – Work involving a
continuous source of ignition
•
Hot Work Category 2 – Work involving a
potential source of ignition
GASCO Permit to Work Standard
Rev 2.0 2009
PRELIMINARY SECTION
Page 11 of 15
GLOSSARY OF TERMS AND DEFINITIONS
H2S Zone
An area of the operational plant or pipeline, within
a restricted area, where there is, or there is
potential for, high levels of H2S (>500ppm mole)
to be present in the process stream. Whenever
work involves breaking into the operating
envelope in an H2S zone, then the area
measuring 10 to 15 metres, horizontal and
vertical, shall be termed the ‘H2S Sterile Area’ and
persons entering this H2S sterile area shall wear a
BA set and a personal monitor.
Isolated
Physically separated from all energy sources or
hazardous materials in such a manner that
inadvertent re-energisation or de-isolation is
excluded
A Permit that has been signed by the Asset
Operator to signify that work may proceed, subject
to
PICW
acceptance
and
subsequent
endorsement
Issue of a Permit
Maintenance/ Engineering Authority The persons formally appointed by the Plant or
Pipeline Vice-President to undertake the duties of
Permit Signatory under the GASCO PTW System.
These may be of any discipline (including
Construction) and include those employed as
contractors
Master Isolation
A Master Isolation is one that establishes isolation
boundaries for major tasks that encompass more
than one process system and/ or piece of
equipment
Method Statement
A more detailed description of the sequence of
Maintenance/ Engineering and/ or Operations
tasks required to complete the specified work
(Maintenance/ Engineering or Operations)
Originator
The person appointed by the Plant or Pipeline
Vice-President, who applies for a Permit and
completes the Permit for approval by the
appropriate Validator subject to the risk
assessment outcome,
GASCO Permit to Work Standard
Rev 2.0 2009
PRELIMINARY SECTION
Page 12 of 15
GLOSSARY OF TERMS AND DEFINITIONS
Permit
In the context of the GASCO PTW System, this
means the Work Permit together with any
supporting Permits or Certificates
Permit Signatory
a formally appointed person for a particular
Location, who is authorised to sign a particular
section of the Permit to Work and supporting
permits/certificates
Permit User
A person who performs work controlled by a
Permit to Work and by default belongs to the same
organization as the Originator
Person in Charge of the Worksite The person appointed by the Maintenance or
Engineering Authority to be in charge of a
(PICW).
Worksite. The PICW is responsible for accepting
permitry issued to the Maintenance/Engineering
Authority by Operations, understanding the
requirements of the permitry and ensuring that the
people performing any work covered by a Permit
comply with the requirements of the Permit to
Work System
Permit Control Facility (PCF)
The physical location at which Permits are issued
and their status displayed
Recovery Measures
Actions taken (either automatically by systems, or
by personnel) in response to a hazardous event in
order to eliminate or reduce its consequences
GASCO Permit to Work Standard
Rev 2.0 2009
PRELIMINARY SECTION
Page 13 of 15
GLOSSARY OF TERMS AND DEFINITIONS
Remedial Action Plan (RAP)
An agreed action plan to address the findings of
PTW Audits
Restricted Area
An area of the plant or pipeline, defined by the
Plant or Pipeline Vice-President, under control of
the duty operations shift or pipeline operations
staff, which has restrictions on the access of
personnel, and which requires the application of
the GASCO PTW System for defined work
activities
Risk
The product of the potential consequence
resulting from the release of a hazard and the
probability of the consequence occurring (Risk =
Consequence x Probability)
Risk Analysis
Refers to the objective process that produces
information about the risks
The process by which the results of a risk analysis
are considered against judgment, standards and
criteria, to show that measures in place are
adequate
The matrix, which GASCO employs as tool to help
categorise the extent of a risk, based on its
consequence and probability of occurrence
An individual who is trained and authorised to
undertake duties of a stand-by nature, e.g. fire and
safety back-up for Hot Work Permit, Category 1 or
Confined Space Entry, where there is a specified
requirement for a stand by person as a worksite
control under the Permit
Systems provided to mitigate the consequences
arising from the release of a hazard. The following
are examples of Safety/ Emergency Systems:
Risk Assessment
Risk Assessment Matrix (RAM)
Stand-by Person
Safety/Emergency Systems.
•
•
•
•
•
•
Fire and Explosion Protection Systems,
Safeguarding Systems,
Fire and Gas Detections Systems,
Fire Control Systems,
Emergency Escape Systems,
Internal and External Communications System
GASCO Permit to Work Standard
Rev 2.0 2009
PRELIMINARY SECTION
Page 14 of 15
GLOSSARY OF TERMS AND DEFINITIONS
Threat
A possible cause that will potentially release a
hazard and produce an incident
Unrestricted (Operational) Area
An area of the plant or pipeline, under control of
the duty operations shift or pipeline personnel,
which does not normally require the application of
the GASCO PTW System, other than for specific,
identified higher risk activities. See Chapter 3. The
appointed Operations Asset Operator, where
required, issues the Permit
Unrestricted (Non-Operational) Area An area of the plant or pipeline, not under the
control of the duty operations shift or pipeline staff,
which does not normally require the application of
the GASCO PTW System, other than for specific,
identified higher risk activities. See Chapter 3. The
appointed Asset Operator, normally Maintenance/
Engineering, where required, issues the Permit
Validator
The Appointed Authority who is responsible for:
•
Reviewing the submitted Permit, together with
supporting documentation;
•
agreeing the required worksite precautions
and controls;
•
Identifying any specific worksite preparation
requirements;
In Restricted (Operational) areas, the person
(normally) undertaking this task is the Operations
Co-coordinator, it can however also be the duty
Shift Controller.
In Unrestricted (Non-Operational) areas it is the
appointed Asset Operator
Validated Permit
A Permit that has been accepted by the Asset
Operator such that worksite preparations can be
made prior to the issuing of the Permit.
GASCO Permit to Work Standard
Rev 2.0 2009
PRELIMINARY SECTION
Page 15 of 15
CHAPTER 1
HSE POLICY, OBJECTIVES OF THE PTW SYSTEM AND ITS CUSTODIANSHIP
CONTENTS
Section
Page
1.1
GASCO HSE POLICY
2
1.2
LEGAL REQUIREMENTS
2
1.3
OBJECTIVE OF THE PERMIT TO WORK SYSTEM
3
1.4
PURPOSE AND SCOPE
4
1.5
CUSTODIANSHIP OF THE PTW SYSTEM
5
1.6
DEVIATIONS FROM THE PTW SYSTEM
6
1.7
CONTROL OF THE PERMIT TO WORK STANDARD
7
Permit to Work Standard
Rev 2.0 2009
CHAPTER 1
Page 1 of 7
HSE POLICY,
OBJECTIVES OF THE
PTW SYSTEM AND
ITS CUSTODIANSHIP
CHAPTER 1
HSE POLICY, OBJECTIVES OF THE PTW SYSTEM AND CUSTODIANSHIP
1.1 GASCO HSE POLICY
The GASCO HSE Policy includes the statement that ‘GASCO shall conduct activities
in a manner designed to minimise HSE risk to a level which is As Low As Reasonably
Practicable (ALARP)’.
Amongst its activities, GASCO requires to carry out work, which may be in
Operational or Non-Operational Areas of Plant facilities or Pipelines. In order to
manage the potential risks associated with this activity to ALARP, GASCO has
developed a Management System of Control, called the “GASCO Permit to Work
(PTW) System”. The GASCO Permit to Work System is described in this Manual.
1.2 LEGAL REQUIREMENTS
The United Arab Emirates Law No. 8, for year 1980, on Conservation of Petroleum
Resources Chapter V, Articles 91 & 92, and Ministerial Order No. 32 for year 1982,
Protection of Employees Against Occupational Hazards Article-1, state that:
“Every employer shall provide adequate preventative equipment to protect workers
against the dangers of employment accidents and occupational diseases that may
occur during the work and also against fire hazards that may result from the use of
machines and other equipment. He shall also adopt all other preventative methods
ordered by the Ministry of Labour and Social Affairs.”
“Every worker shall use the protective equipment and the clothing supplied to him for
this purpose, shall comply with all the instructions given by the employer to protect
him against hazards and shall not take any action liable to hamper compliance with
such instructions.”
“Every employer shall display detailed instructions in a conspicuous position at the
work place indicating the measures to be taken to prevent fire and protect the workers
against the hazards to which they may be exposed while performing their work.”
The GASCO PTW system is a key part of the measures implemented by GASCO to
comply with these legal requirements.
Permit to Work Standard
Rev 2.0 2009
CHAPTER 1
Page 2 of 7
1.3 OBJECTIVE OF THE PERMIT TO WORK SYSTEM
The prime objective of the GASCO PTW system is to ensure that potentially
hazardous work is properly controlled and co-ordinated. It is the means of providing
written instructions and authorisation to people carrying out such work.
It is a key part of the measures taken to safeguard people doing the work, others who
may be affected by the work, and the facilities themselves.
It uses documents to define the work, the associated hazards and the precautions to
be taken for those hazards, and includes a system of authorised signatories for the
preparation of the documents.
It defines the roles and responsibilities of persons in the GASCO Organisation, and
those of Contractor management, with respect to the GASCO PTW System.
Permit to Work Standard
Rev 2.0 2009
CHAPTER 1
Page 3 of 7
1.4 PURPOSE AND SCOPE
The purpose of the GASCO PTW System is to ensure that a safe working
environment is achieved by providing management control over the various work
activities, which may be potentially hazardous.
The PTW System provides a formal and controlled process that identifies and
communicates hazards and risks associated with planned work and ensures that
appropriate precautions and control measures are implemented so that the work can
proceed and be completed safely.
It is important to note that a Permit to Work is not a permission to carry out hazardous
work. It is an essential part of a procedure that provides instructions on how to carry
out any potentially hazardous work safely and in a managed, controlled way. The
PTW System has the following key features:
•
It allows personnel to be aware of the potentially hazardous activities being
undertaken under PTW by providing a systematic overview. The specific
arrangement for the display of Permits allows identification of potentially
conflicting work tasks, both on a geographical and time basis;
•
It defines the controls required to prevent threats from releasing hazards during
the work as well, as the recovery controls that will mitigate the effects should a
hazard be released;
•
It sets limits to the duration and extent of the work;
•
It encourages formal and careful attention to safe systems of working by requiring
the signature of specified individuals, who must confirm satisfactory completion of
the various stages of the Permit lifecycle, viz:
o
Hazard Assessment and Risk Assessment
o
Precautions and Controls
o
Worksite Preparations
o
Handover and Handback
Permit to Work Standard
Rev 2.0 2009
CHAPTER 1
Page 4 of 7
1.5 CUSTODIANSHIP OF THE PTW SYSTEM
The GASCO PTW System requires that appropriate ‘Custodians’ within the GASCO
Organisation undertake responsibility for the PTW System.
The Principle Custodian, responsible for authorising all changes to the GASCO PTW
System, is the Senior Vice-President Operations, (SVP (O)).
The Custodian responsible for the development of the PTW System and the
co-ordination across GASCO is the GASCO HSE Vice-President (HSE).
Custodians responsible for the implementation of the PTW System are the Plant and
Pipeline Vice-Presidents (the Asset Owners).
Permit to Work Standard
Rev 2.0 2009
CHAPTER 1
Page 5 of 7
1.6 DEVIATIONS FROM THE PTW SYSTEM
Deviation from the PTW System may be necessary in special circumstances, but the
safety of personnel, the protection of the environment and assets must not be
jeopardised. Once the situation is normalised, the PTW System must be re-applied.
If anybody involved in the PTW System is unsure of a course of action, he must
consult a higher authority and not take risks.
Any planned deviations from the procedures contained in this document must be
requested by the Plant or Pipeline Vice-President, in writing, to the Senior
Vice-President Operations (SVP (O)).
Approved derogations will be issued as a Supplementary PTW procedure, authorised
by SVP (O) and approved for issue by the Plant or Pipeline Division Manager for
subsequent inclusion in Chapter 10 of the PTW System Manual.
The PTW Supplementary procedure will normally only apply to the location that has
requested derogation from the procedure. The Supplementary PTW procedure will
inculde a description of the deviation and the expiry and is to be issued, by the Plant
or Pipeline Division Manager, to all registered holders of the PTW System Manual at
that location.
During the validity period of the authorised derogation, the PTW Suppliementary
procedure is to be filed in the Deviation Chapter of the PTW System Manual by each
respective manual holder.
The required validity period of any PTW Supplementary procedure is to be agreed
with SVP (O). Upon reaching the expiry date, unless further approval is obtained in
writing from the SVP (O) for an extension to the original expiry date, the PTW
Supplementary procedure is to be rescinded and copies removed by the registered
holder of each controlled copy of the PTW System Procedures Manual at that
location.
Permit to Work Standard
Rev 2.0 2009
CHAPTER 1
Page 6 of 7
1.7 CONTROL OF PTW SYSTEM MANUAL
Only controlled copies of the PTW System Manual are to be used.
The latest revision of the PTW System Manual will be available on the GASCO
Intranet for all staff.
To ensure that the PTW Manuals in circulation are current the following document
management procedure is to be complied with:
•
Hard copies of the PTW Manual will be circulated to registered holders only. Each
copy of the PTW Manual will have a unique number and will be registered as a
controlled copy.
No uncontrolled copies of Manuals, or sections of Manuals, should be made;
The PTW Manual is designed in Sections to allow easy revision and update
without the need for reissue of the complete manual. Each section will have a
revision number and effective issue date;
Only the register holders of the PTW Procedures Manual will be issued with
updates; A transmittal note will accompany original manuals, and subsequent
revisions to manuals, to each holder of the controlled copy of the manual
The holder of the controlled copy of the manual has the responsibility for:
•
Inserting revisions,
•
Removing and destroying superseded pages,
•
Updating the history page at the front of the controlled manual;
•
Completing the amendment record;
•
Completing the return section of the transmittal note to HSE/S;
•
Advising all his staff who are ‘users’ of the PTW System with regard to the
changes.
Permit to Work Standard
Rev 2.0 2009
CHAPTER 1
Page 7 of 7
ORGANISATION
CHAPTER 2
ORGANISATION
CONTENTS
Section
Page
2.1
MANAGEMENT OF THE PTW SYSTEM
2.1
Roles and Responsibilities
2.1.1
Senior Vice-President Operations (SVP (O))
2.1.2
HSE Vice President (VP HSE)
2.1.3
Plant and Pipeline Vice Presidents
2.1.4
Department Superintendent
2.1.5
HSE Superintendents
2.2
COMPETENCIES and RESPONSIBILITIES OF SIGNATORIES
FOR PERMIT AND SUPPORTING PERMITS AND CERTIFICATES,
INCLUDING DEPUTIES
2.2.1
2
2
2
2
2
3
4
Personnel who sign Permits and Certificates and their
Responsibilities
2.2.1.
ORIGINATOR
2.2.2
MAINTENANCE/ENGINEERING REVIEWER
2.2.3
VALIDATOR
2.2.4
ISSUER
2.2.5
ACCEPTOR
2.2.6
ENDORSER
2.2.7
PERSON IN CHARGE OF THE WORKSITE (PICWS)
2.2.8
PERSONS WHO SIGN FOR
ISOLATION/DE-ISOLATIONS ON THE ICC
2.2.9
AUTHORISED GAS TESTER (AGT)
2.3
CONTRACTOR MANAGEMENT REPONSIBILITIES
2.4
TRANSFER OF RESPONSIBILITIES – SHIFT HANDOVER
2.5
TRAINING TO SUPPORT THE PTW SYSTEM
2.6
AUTHORISATION OF PTW SIGNATORIES
5
5
5
6
7
8
9
10
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 2
Page 1 of 16
CHAPTER 2
ORGANISATION
MANAGEMENT OF THE PTW SYSTEM
The GASCO PTW System is managed through the line under the principles of custodianship.
2.1 Roles and Responsibilities
2.1.1 2.1.1 Senior Vice-President (Operations) (SVP (O))
SVP (O) is the principal custodian of the PTW System and is
responsible for:
•
Authorizing all changes to the PTW System Manual
•
Derogation for deviations to the PTW procedures
•
An annual review of the implementation of PTW System
2.1.2 Vice President HSE (VP HSE)
VP HSE is the custodian of the standards specified in the PTW System
Manual and responsible for:
(i)
Providing advice in GASCO on all aspects of the PTW System.
(ii)
Conducting Level 2 Audits of the PTW System (see Chapter 9,
Sect. 9.3.3).
(iii)
An annual review of the PTW System and proposing any
necessary changes to SVP (O) for authorisation.
2.1.3 Plant and Pipeline Vice-Presidents Responsibilities as
Site Custodians
The Plant or Pipeline Vice-President, who is the Asset Owner, is
responsible for:
(i)
The effective implementation and compliance of the PTW System
on that Plant or Pipeline.
(ii)
Preparation of Drawings are to identify Restricted Areas,
Unrestricted Areas, Hazardous Areas (Electrical classification
zones) and H2S Zones;
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 2
Page 2 of 16
(iii)
Providing a comprehensive training programme for all users,
PICWS and Permit signatories is in place and that competence
standards are both established and maintained as defined in
Chapter 2
(iv)
Appointing persons who are required to sign Permits, with their
responsibilities and limits of authority clearly defined in writing;
(v)
Ensuring that the planning and administration of Permitry is
properly coordinated;
(vi)
Ensuring that the audit programme for the PTW System is carried
out as per plan and that corrective actions resulting from audit
findings are carried out;
(vii) Ensuring that Activity Risk Assessments (ARA) and the
associated Activity Sequence Control (ASC) for activities in the
High Risk categories (see Chapter 3, Section 3.5.1) are reviewed
and approved
(viii) Requesting any deviations from the manual, in writing to the SVP (O)
(ix)
Defining the PTW Manual Holders and identifying the copy
number and registration of the holder
(x)
Complying with the PTW Audit requirements defined in Chapter 9
2.1.4 The Department Superintendent
The Senior Representative of a Department, who is the Asset Holder, is
responsible and accountable to the Asset Owner for the integrity and
safe condition of the systems and equipment allocated.
Under the PTW System, their duties include, but are not limited to:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
Assisting the Plant or Pipeline Vice-President with the
implementation and administration of work under the PTW System;
Deputising for the Plant or Pipeline Vice-President as the Asset
Owner when authorised and appointed in writing to do so;
Reviewing and issuing Permits requiring the higher level
authorisation of the Asset Holder;
Reviewing and approving Activity Risk Assessments within his
sphere of responsibility.
Implementing the layout of the Permit Control Facility as stated in
Chapter 8 of the Permit Manual.
Complying with the PTW Audit requirements defined in Chapter 9
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 2
Page 3 of 16
2.1.5 HSE Superintendents
The HSE Superintendents fulfils an important advisory role to the
Operations and Engineering Line. Their responsibilities include:
•
Provision of expert advice to the Operations and Maintenance/
Engineering Line for jobs being executed under a Work Permit,
particularly when the risk is judged high or medium using the Risk
Assessment Matrix (RAM);
•
Provision of resource, including training and HSE personnel so that
the HSE controls identified in Permitry can be monitored and assured;
•
Support to the Plant or Pipeline Vice-President in maintaining
standards, and monitoring adherence to standards, by audit and
follow-up;
•
Maintaining records of all Level 1 audits and the updating of status in
the Remedial Action Plan (RAP).
•
Acting as focal point for all communications relating the PTW and
maintaining the register of any approved derogations from the PTW
System;
•
Keeping a register, for PTW purposes, of all personnel trained and
authorised by the Plant or Pipeline Vice-President;
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 2
Page 4 of 16
2.2 COMPETENCIES AND RESPONSIBILITIES OF SIGNATORIES FOR
PERMITS AND SUPPORTING PERMITS AND CERTIFICATES,
INCLUDING DEPUTIES
2. 2.1. ORIGINATOR
2.2.1.1 Competence
The Originator must demonstrate to the Plant/Pipeline
Vice-President (or his nominated deputy) that he is competent to:
(i)
Adequately describe any work to be undertaken on the
Permit and on Supporting Permits
(ii) Participate in Risk Assessments for any work he may
originate including the necessary controls
(iii) Identify those risk assessments which require higher level signature
(iv) Updating ARA when required
(v) Signing the Work Permit agreeing with the statement on BOX 6 of
the Work Permit
(vi) Identify what supporting permits/certificates are included
in the PTW System and explain when they are required
(vii) Explain the PTW process after origination
2.2.1.2 Responsibilities
(i) Describing on the Permit and on Supporting Permits the
work to be undertaken, the hazards associated with the
work, and the necessary controls in boxes 1 to 6 inclusive
(ii) Where the work is complex, it may be necessary to
support the permitry with a Maintenance or Engineering
Method Statement, or Activity Sequence Control form
(ASC) or both. In such cases the Originator should include
these in the permitry package
(iii) Discussing and agreeing the work scope, equipment to be
used and Permitry details with the Authorised Maintenance/
Engineering Authority who will then present the Permitry at
the daily PTW Meeting for validation by the Asset Operator.
NB. The Permit Originator may, in some cases, also be the
Maintenance/ Engineering Authority.
2.2.2 MAINTENANCE/ENGINEERING REVIEWER
2.2.2.1 Competence
The Maintenance/Engineering Reviewer must demonstrate to
the Plant/Pipeline Vice-President (or his nominated deputy) that
he is competent to:
(i)
(ii)
(iii)
Review and approve various work scopes defined by the
Permit Originator on Work Permits and other Permitry
Participate in Risk Assessments
Identify those risk assessments which require higher level signature
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 2
Page 5 of 16
(iv) Explain the purpose of the Daily PTW Planning Meeting
(v)
Explain the PTW process after origination
2.2.2.2 Responsibilities
(i)
(ii)
(iii)
Reviewing and approving various work scope defined by
the Permit Originator
Agreeing with the associated risk assessment
Certifying that the equipment to be used during the work
has been inspected and is suitable for use
(iv) Presenting the PTW to the Daily PTW Planning Meeting
(v)
Maintaining overall responsibility for the work being done
whilst delegating worksite responsibilities to Permit
Acceptors
(vi) Informing the Permit Originator of any changes made to
the Permitry
2.2.3 VALIDATOR
2.2.3.1 Competence
This is the Asset Operator. In Operations it is normally (for
planned work during normal office hours) the Operations
Co-ordinator. In the absence of the Operations Co-ordinator,
the Shift Controller may also validate Permits, where the work
is of an urgent or unplanned nature, or where Permits are
submitted outside of normal office hours, e.g. at weekends.
(For Pipelines Division the Validator will be the Operations
Coordinator/Supervisor)
The Validator must demonstrate to the Plant/Pipeline
Vice-President (or his nominated deputy) that he is competent to:
(i)
Participate in Risk Assessments for any work he may have
to review as part of the validation process, including the
necessary controls
(ii)
Identify those risk assessments which require higher level
signature
(iii)
Explain the purpose of the Daily PTW Planning Meeting
(iv) Explain the PTW process after validation
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 2
Page 6 of 16
(v)
2.2.3.2
Chair the Daily PTW Planning Meeting and explain its purpose
Responsibilities
(i)
Chairing the daily PTW Meeting and agreeing the permitry
requirements with the Maintenance/ Engineering Authority; This
includes timing and consideration of the risk assessment, the
controls necessary for the work to be undertaken,
(ii)
Confirming that the work can be accepted into the Operations area
subject to worksite preparations (Validation);
(iii) Identifying the required worksite preparations;
(iv) Checking that Permits has been examined for potential conflict,
both on a geographical and time basis;
(v) Handing over of the permitry to the Operations Asset Operator (the
Shift Controller) for worksite preparations.
2.2.4. ISSUER (the Asset Operator or, for higher risk work, the Asset Holder)
2.2.4.1
Competence
The Issuer must demonstrate to the Plant/Pipeline Vice-President (or
his nominated deputy) that he is competent to:
(i)
Explain the outcome of risk assessments for work which he
authorizes by issuing a work permit
(ii)
Identify those risk assessments which require higher level
signature
(iii) Explain the PTW process before and after issuing the permit,
including shift change
(iv) Communicate the necessary information to PICWs
2.2.4.2
Responsibilities
The Asset Operator is responsible for handing over the equipment to
Maintenance or Engineering, and for accepting equipment back into his
control, under the PTW System. In Operations the Asset Operator is the
duty Shift Controller. His responsibilities include:
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 2
Page 7 of 16
(i)
Confirming that the worksite has been examined and all
precautions specified (including isolations required) to be
taken before work commences have in fact been taken,
and will remain effective while the Permits remain in force;
including isolations in accordance with the Isolation
Standard.
(ii)
Confirming that no conflict exists with other Permitry
and/or activities;
(iii)
Advising the Area Authority that the Permitry is ready for
Endorsement;
(iv) Accepting back the Permitry (for further Endorsement or
Closure)
(v)
Ensuring that before a Permit is closed any precautions
and
isolations,
and/or
equipment
or
system
inhibits/overrides, are withdrawn and the systems they are
part of returned to normal;
(vi) Ensuring the shift/worksite handover procedure is properly
followed if the work lasts more than one shift/ work period;
(vii) Ensuring all Permits are displayed to reflect their current
status within the Permit Control Facility;
(viii) Ensuring that for work which has been suspended, that
there is no conflict with any other permit or activity, prior to
endorsement by the Area Authority at the worksite;
(ix) Issuing and endorsing the Permit, where work is in a
common area, or with no defined Area Authority, e.g. Main
Control Room.
(x)
Accepting the equipment back into Operations and
authorising of any equipment de-isolations.
The Shift Controller may delegate responsibilities to the
Assistant Shift Controller, where considered appropriate,
except for Permit Issue and Permit Closure.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 2
Page 8 of 16
2.2.5. ACCEPTOR (Authorised Maintenance /Engineering Authority)
2.2.5.1
Competence
The Authorised Maintenance /Engineering Authority must demonstrate
to the Plant/Pipeline Vice-President (or his nominated Deputy) that he
is competent to:
(i)
Explain typical risks in the work place for the type of work he is
allocated to be in charge of
(ii)
Explain that he has understood the role of the Issuing Authority
during the handover process
(iii) Communicate to others in the work party by a toolbox talk
(iv) Explain what to do if a problem or emergency arises
(v) Explain what happens when the work is completed
(vi) Explain what happens when the work is not finished at shift
change or end of the working day
(vii) Explain the purpose of the different categories of PICW
2.2.5.2
Responsibilities
(i)
Accepting the Permitry on behalf of the Work Party
(ii)
Confirming to the Issuing Authority that he understands:
•
•
The work to be done
The precautions identified on the Permit to Work and
associated Risk Assessment
(iii) Agreeing with the Issuing Authority the Toolbox Talk requirements as to:
•
•
•
Who undertakes it;
•
Whether a Formal Toolbox Talk record is required.
Who attends it;
When and where it is undertaken, including the requirement for
any repeat, or additional Toolbox Talks;
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 2
Page 9 of 16
(iv) Instructing the PICWS on the required worksite presence, and the
content of the issued Permit. The worksite presence will be
defined as follows:
• Category A - Continuous presence of PICWS
•
Category B - May be absent for short periods (the actual
period of absence to be specified for each job)
•
Category C - Only occasional visits of the PICWS required
(iv)
Ensuring the PICWS can communicate effectively with the
workgroup, i.e. that there are no language/ literacy issues.
(v)
Ensuring permitry is displayed at the worksite.
(vi)
Ensuring the PICWS understands the actions to be taken if the
work has to be suspended, either normally, or in the event of a
site incident or emergency situation arising;
(vii)
Returning permitry to the Permit Control Facility at the end of
the work period, and collecting re-endorsed permitry for the
next work period;
(viii)
Confirming the worksite is clear, and affected equipment is in a
safe condition, prior to formal handback to the Asset Operator
when work is completed.
2.2.6.1 ENDORSER (the Asset Operator and the Area Authority)
2.2.6.1 Competence
The Endorser must demonstrate to the Plant/Pipeline
Vice-President (or his nominated Deputy) that he is competent to:
(i)
Describe why he may/may not sign the endorsement
(ii)
Explain the purpose and structure of the PTW system
2.2.6.2 Responsibilities
2.2.6.2.1 The Asset Operator responsible for re-endorsing Permitry
will normally be the Assistant Shift Controller.
His responsibilities include:
(i)
Confirming there is no conflict with other Permits or activity prior
to Worksite endorsement;
(ii)
Updating the status display in the PCF;
(iii)
Advising the Shift Controller of any potential conflict situations.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 2
Page 10 of 16
2.2.6.2.2 The Area Authority (in Operations, this is the Area Operator)
is responsible for the continued safety of the worksite.
He is responsible for:
(i)
Confirming the safety of the worksite and to note on the Permit the
date and time the work may commence;
(ii)
Examining the worksite when work is suspended, and before it is
restarted, and finally when the work is completed to ensure that it
is in a safe condition;
NB. For each shift period, he is to endorse only after the Asset Operator
has checked for potential conflict and initialed the endorsement box.
2.2.7 PERSON IN CHARGE OF WORKSITE (PICWS)
2.2.7.1 Competence
The PICW must demonstrate to the Plant/Pipeline Vice-President (or
his nominated Deputy) that he is competent to:
(i)
Explain what hazards exist in the area which he is to work
(ii)
Explain how the PTW system helps to control the hazards
(iii) Why a tool box is given
(iv) What he must do if the job does not proceed as described on the
Permit
(v) Describe the parts of the Permit he has to sign
2.2.7.2 Responsibilities
The PIWCS is responsible for ensuring the conditions and precautions
in the Permit are adhered to. He is responsible for:
(i)
Ensuring he, and every member in his work party attends the
Toolbox Talk and understands the work scope, hazards and
controls prior to his endorsement at the worksite;
(ii)
Advising the Authorised Maintenance/ Engineering Authority of
any language/ literacy problems in his workgroup;
(iii) Liaising with the Area Authority on progress;
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 2
Page 11 of 16
(iv) Ensuring that the controls specified on the Permit are maintained
(v) Displaying the worksite copy of the Permit and any supporting
permits or certificates at the worksite
(vi) Complying with the worksite presence requirements defined in
Box 3 on the Work Permit
(vii) Ensuring work stops in the event of a site emergency
(viii) Confirming that the worksite has been left safe at work completion
in the endorsement period.
2.2.8 PERSONS WHO SIGN FOR ISOLATIONS/DE-ISOLATIONS ON THE
ISOLATION CONFIRMATION CERTIFICATE
These are Electrical, Mechanical, Instrument and Operations
personnel who are authorized to carry out, and sign for, their
respective discipline isolations and de-isolations on the
Isolation Confirmation Certificate
2.2.8.1 Competence
The competence required for the trades and operators
performing the isolations/de-isolations is defined by their
respective line management.
2.2.8.2 Responsibilities
(i)
Ensuring that isolations/de-isolations are completed as per
the Issuing Authority request
(ii)
Trades and operators performing the isolations must
complete the Isolation Confirmation Certificate legibly
2.2.9 AUTHORISED GAS TESTER (AGT)
2.2.9.1 Competence
Persons may be appointed Authorised Gas Tester after
successfully completing a GASCO approved Authorised Gas
Tester Course
2.2.9.2 Responsibilities
The AGT is responsible for:
(i)
Recording on the Gas Test Certificate (incorporated on the
back of the worksite copy of the PTW) the times and results
of initial gas tests and any requested follow-up gas tests;
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 2
Page 12 of 16
(ii)
Where applicable, obtaining the Counter Signature of the Area
Authority on the Gas Test Certificate after the initial, and any
subsequent gas test;
(iii) Taking immediate steps to prevent or halt work if gas tests results
are outwith the expected range, and bringing it to the attention of
the Area Authority and/or the Asset Operator
2.3 CONTRACTOR MANAGEMENT RESPONSIBILITIES
The Management of Contracting Companies is responsible for:
(i) Ensuring that all Contractor site management and their workforce
understand and adhere to the standards of the GASCO PTW
System;
(ii)
Ensuring that all contractor supervisors and employees attend
GASCO training on the GASCO PTW System and procedures and
are aware of any specific arrangements made for a job, area or
location in which they are to work;
(iii) Ensuring that all contractor supervisors and employees
understand why these systems and procedures exist and the need
for them to be followed precisely;
(iv) Setting up a system to monitor contractor training in PTW
Systems, understanding of them, and, where practicable, their
every day use (noting that training, and authorisation, of
Contractor PTW Users, PICWS and Signatories will be provided
by GASCO).
2.4 TRANSFER OF RESPONSIBILITIES – SHIFT HANDOVER
Shift Handover can be one of the most vulnerable times for the PTW
System. The failure to pass on information, or the correct information, has
been shown to be the cause of many accidents. There must be sufficient
overlap to allow proper review and discussion of all permitry on the facility.
The Shift Controller is to ensure that the PCF status display boards reflect
at all times the current status of Permits on the facility. There should be a
formal record in the shift handover logbooks of all relevant information
pertaining to permits and any worksite preparations/ de-isolations.
Permits may be transferred between shifts providing the endorsement of
the Permit is done. (see Chapter 5) This is a two-step process, which
requires:
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 2
Page 13 of 16
2.5
(i)
An acknowledgement and approval step by the Shift Controller, or
Assistant Shift Controller, who should carry out a cross-check with
other Permits and activities for conflict prior to signing in Box 13, in
the Endorsement Section of the Permit, as the Asset Operator;
(ii)
A confirmation check as to the continued safety of the worksite by
the oncoming Shift Area Operator prior to his endorsing Box 13,
as the Area Authority.
TRAINING TO SUPPORT THE PTW SYSTEM
2.5.1 Level of training courses
There are 3 levels of PTW training courses;
1. Permit User. For persons who work under the Permit to
Work system but do not sign any permits
2. Permit signatory. For persons who have to sign a permit,
excepting PICWs and toolbox talk attendees
3. PICW. For persons who have worksite responsibilities
whilst the work is in progress
2.5.2 Trainers for the PTW courses
Trainers for the PTW courses are appointed by the
Plant/Pipeline Vice-President
2.5.3 Objectives of the PTW Training Courses
2.6
The Objectives of each course is detailed in Appendix X.
Each course must have an element of assessing the
understanding of trainees and a formal pass/fail outcome
•
The minimum standard in the assessment is 70% of the
total marks available.
•
Should a student not attain the minimum standard he may
be allowed to re-sit the examination once without further
training after a period of not less than one week.
•
The student is not to have the same examination paper set
at the second attempt.
•
Should the student not reach the required standard at the
second attempt then period of 3 months is required for further
tuition and experience
Authorisation of Permit Signatories
Persons who have satisfactorily attended a PTW Training Course and
satisfied the Division Plant Vice-President (or his Nominated Deputy)
as to competence will be formally appointed to their role. The
appointment should be in writing with the name and signature of the
person authorizing the appointment included.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 2
Page 14 of 16
Appendix X
X 1. Objectives of the Users Course.
Attendees will be able to:
•
•
Describe how work is allowed on GASCO sites
•
•
Identify the person who will tell them what the permit says
•
Explain what they should do if they think what they are doing is
not safe
•
Explain what happens to the permit when the work is finished for
the day
•
Explain what happens when an alarm sounds while they are
working
Identify a work permit and describe where it can be found before
work starts
Explain how they know it is safe to start work
X2. Objectives of the Permit Signatory Course.
Attendees will be able to:
•
Demonstrate they understand the purpose and scope of the PTW
System (as defined in Chapter 1 of the Manual)
•
Demonstrate they understand the responsibilities of all
signatories to the PTW system and be able to list in detail their
own specific responsibilities
•
Explain what work can be done without a Permit (including
unrestricted areas) and why
•
Describe what other permits, certificates and forms support the
main Work Permit
•
•
Explain the risk assessment process in the PTW System
Explain the validity period for a PTW and what happens when
work stops at the end of the workday
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 2
Page 15 of 16
X3.
•
•
Explain the isolation procedure
•
Explain the role of the PCF
•
•
Explain the PTW auditing system
Explain when a toolbox talk is required and what the talk should
include
Describe at least 1 incident that has occurred in GASCO (or
ADNOC) where failure to follow the PTW Procedure was
identified as a cause
Objectives of the PICW Course
Attendees will be able to:
•
•
Explain why GASCO operates a PTW System
•
•
•
Explain their responsibilities as a PICW
•
What they do with the Permit when work is complete, or work
stops, at the end of the workday
•
Explain what they will do if the job is not proceeding as was
explained to them
•
What happens to the Permit if an emergency occurs
Identify the person who will explain to them the requirements of
the Work Permit which they will be in charge of
Demonstrate where they sign a permit for starting/finishing work
What they do with the Permit when it is handed to them
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 2
Page 16 of 16
FRAMEWORK
OF THE PTW SYSTEM
CHAPTER 3
FRAMEWORK OF THE PTW SYSTEM
CONTENTS
Section
Page
3.1 INTRODUCTION
3
3.2 AREA CLASSIFICATION
3.2.1 Restricted Areas
3.2.1.1 H2S Zones
3.2.2 Unrestricted Areas
3
3
3
3
3.3 CONTROL OF WORK WITHIN CLASSIFIED AREAS
3.3.1 Work within Restricted Areas not requiring a Permit
3.3.1.1 Control of Work (not requiring a Permit) in Restricted Areas
3.3.1.2 Control of Work in the Vicinity of Pipelines
3.3.2 Control of Work in Unrestricted areas requiring a Permit
3.3.2.1 Authorisation of Work in Unrestricted Areas
3.3.3 Work Requiring a Permit
3.3.4 Permits covering more than one Work Activity
3.3.5 Work which Requires Interface Procedures
3.3.5.1 Interface Procedures between Asset Operators/ Area Authorities
3.3.5.2 Interface Procedures for ADCO within GASCO Controlled Areas
3.3.5.3 Interface Procedures for GASCO within ADCO Controlled Areas
3.3.5.4 Interface Procedures in a Joint Pipeline Corridor
3.3.5.5 Requirements for Identification of PTW Interface Areas with ADCO
5
5
6
6
7
7
8
9
10
10
11
12
12
3.4 RISK MANAGEMENT PROCESS FOR WORK
3.4.1 Introduction to the Activity Risk Assessment Process
3.4.1.1 Assessing Risks
3.4.1.2 Controlling Risks
3.4.1.3 Demonstrating ALARP
3.4.2 Performing an Activity Risk Assessment for previously assessed activities
3.4.3 Performing a New Activity Risk Assessment
3.4.4 Activities Covered by Individual Competencies
3.4.5 Responsibilities for the Activity Risk Assessment Process
13
13
14
15
16
17
17
20
21
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 1 of 42
CHAPTER 3
FRAMEWORK OF THE PTW SYSTEM
CONTENTS
Section
Page
3.4.6 Linking the ARA and the Permit to Work
21
3.4.7 Visibility of Permits
29
3.4.8 Layout and Colour of Permits
30
3.4.9 Permit Signatories
31
3.5 RULES GOVERNING PERMITRY
33
3.5.1 Permit Validity Period
33
3.5.2 Permit Endorsement Periods
33
3.5.3 Maximum Number of Permits
33
3.5.4 Stoppage of Work Following an Alarm
34
3.5.5 Changes to Permit Details
35
APPENDICES
APPENDIX A SCHEMATIC GASCO/ ADCO PTW INTERFACE
36
APPENDIX B FLOWCHART OF ARA PROCESS
37
APPENDIX C GASCO RISK ASSESSMENT MATRIX (RAM)
38
APPENDIX D ACTIVITY RISK ASSESSMENT WORKSHEET GUIDELINES
39
APPENDIX E ACTIVITY RISK ASSESSMENT WORKSHEET
40
APPENDIX F WORK PERMIT LIFECYCLE/ SIGNATORY RESPONSIBILITIES
41
APPENDIX G FLOWCHART FOR DETERMINING PIPELINE PTW REQUIREMENTS 42
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 2 of 42
CHAPTER 3
FRAMEWORK OF THE PTW SYSTEM
3.1 INTRODUCTION
For the purposes of this Permit to Work System, work can be described as an activity
that comprise one or more tasks. It is implicit that the work has been agreed as
necessary, having been through the planning stage of the work management process.
The Permit to Work System is concerned with authorising and managing this work.
The issue of a Permit does not, by itself, make a job safe. Those preparing for the work
can only achieve that, together with those supervising and executing the work. In
addition to the PTW System other precautions may need to be taken, e.g. in relation to
Plant Operations and Worksite Preparation phases. All levels in the organisation must
clearly understand both the PTW System and their roles within it.
3.2 Restricted and Unrestricted Areas
GASCO facilities handle both flammable and hazardous materials. To differentiate
those areas where these specific hazards exist; the GASCO PTW System requires
that each Plant and Pipeline Division classify specific areas as either a Restricted Area
or an Unrestricted Area. Additionally, there is a requirement to further define zones
within the Restricted Areas where there is an identified Hydrogen Sulphide (H2S)
hazard.
Each Plant or Pipeline Vice-President is responsible for producing a plot plan of the
site or pipeline, indicating the Restricted and Unrestricted Areas and highlighting any
H2S hazard zones.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 3 of 42
3.2.1 Restricted Areas
These are areas, defined by the Plant or Pipeline Vice-President, under control of
the duty operations shift or pipeline operations staff, which has restrictions on the
access of personnel, and which requires the application of the GASCO PTW
System for defined work activities. Examples are:
(i).
(ii).
(iii).
Operating areas of the Plant and thus require precautions and controls.
These may, or may not, include access roads;
Areas deemed to be hazardous under Hazardous Area Electrical
Classification and, therefore, requiring further controls;
Critical for the operation of the facility, e.g. Control Rooms and Electrical
substations
3.2.1.1 H2S Zones
H2S Zone
An area of the operational plant or pipeline, within a restricted area,
where there is, or there is potential for, high levels of H2S (>500ppm
mole) to be present in the process stream. Whenever work involves
breaking into the operating envelope in an H2S zone, then the area
measuring 10 to 15 metres, horizontal and vertical, shall be termed the
‘H2S Sterile Area’ and persons entering this H2S sterile area shall wear
a BA set and a personal monitor.
3.2.2 Unrestricted Areas
These are all other areas within the Plant or Pipeline perimeter fence, which have
not been defined as Restricted, and which do not normally require formal control
under the PTW System.
Unrestricted (Operational) Area
An area of the plant or pipeline, under control of the duty operations shift or
pipeline personnel, which does not normally require the application of the GASCO
PTW System, other than for specific, identified higher risk activities The appointed
Operations Asset Operator, where required, issues the Permit.
Unrestricted (Non-Operational) Area An area of the plant or pipeline, not under
the control of the duty operations shift or pipeline staff, which does not normally
require the application of the GASCO PTW System, other than for specific,
identified higher risk activities. The appointed Asset Operator, normally
Maintenance/ Engineering, where required, issues the Permit
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 4 of 42
3.3 CONTROL OF WORK WITHIN CLASSIFIED AREAS
3.3.1
Work in Restricted Areas not normally requiring a Permit
All work in a Restricted area is normally subject to full PTW System controls.
It is not, however, intended that the full PTW procedures be applied to all
activities.
It is, therefore, sensible and practicable that work activities, for which the
Activity
Risk Assessment process has shown to be of Low Risk, be permitted with a
minimum of controls. Examples of work in Restricted areas not normally
requiring a Permit are:
•
Normal routine activities, conducted by competent personnel, in
accordance with agreed operating procedures;
•
•
Visual inspection of areas and equipment, except for confined spaces;
•
•
Handling of non-hazardous materials;
•
Routine sampling of hydrocarbon products (excluding product streams
containing high levels of H2S) as per approved procedures by competent
laboratory staff.
Operation of equipment for approved operational training activities;
Routine housekeeping activities inside restricted operating areas, but
excepting electrical substations, where electrical engineering
authorisation is required for entry;
It is also permissible for Plant or Pipeline Vice-Presidents, to add to the list, for
their specific location, if a risk assessment of the work shows that a Permit
would not add value. The Plant or Pipeline Vice-President, must maintain a
register of ‘Work in Restricted Areas not normally requiring a Permit’.
A Permit is not needed when urgent action is required to prevent/minimise/limit
loss or damage of personnel or equipment, i.e. actions in emergency
situations;
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 5 of 42
3.3.1.1 Control of Work (not requiring a Permit) in Restricted Areas
In order that Operations staff may be aware of people visiting Restricted
Areas, or working in Restricted Areas without a Permit, a control
mechanism is required. Each site is to implement a ‘Restricted Area
Access and Work Register’. Suggested outline content for the register is:
•
•
•
•
•
Date / Time visit or work commenced;
•
Time visit or work completed.
Plant Area;
Purpose of visit / Work being undertaken;
Department / Name and signature of person(s) involved;
Approval signature of Operations Shift Controller, or Assistant Shift
Controller;
It is further recommended that the agreed list of work (as per 3.3.1),
which can be undertaken without a Permit, be appended to the
Restricted Area Access and Work Register, for reference purposes.
3.3.1.2 Control of Work in the Vicinity of Pipelines
In Pipeline Division, 30 metres either side of a designated pipeline, or
pipeline corridor, is defined as a Restricted Area. The intent is that no
work may take place within 30 metres of any Pipeline containing
hazardous material without GASCO PTW controls being applied.
In Pipeline Division, a specific form, the Authorisation to Work (ATW), is
provided (see Chapter 5, Section 5.9). The Purpose of an ATW is to
provide a process for the control of work being undertaken in the vicinity,
but not directly on, GASCO pipelines by GASCO, Third Parties or
Contractors, and to communicate this to other interested parties. A
flowchart is provided in Appendix G to aid the Permit Originator and
Permit Issuing Authorities in determining Pipeline Division PTW
requirements.
3.3.2 Control of Work (requiring a Permit) in Unrestricted Areas
In general, work in Unrestricted Areas is not required to be subject to the PTW
System. There will, however, be some work activities in Unrestricted Areas, which
are considered to be of a higher risk, which require further controls to be applied.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 6 of 42
Work in Unrestricted Areas requiring a Permit is
•
Work involving naked flame, grinding or welding (other than in defined,
approved areas e.g. Maintenance Workshops);
•
•
•
•
•
Confined Space Entry, e.g. sewers, pits or tanks;
Activities which introduce an electrical hazard;
Excavations, which are in proximity to underground services or pipelines.
Work involving a radiographic source
Any work where a hazard requiring controls is identified by the Originator,
e.g. working at heights on buildings or structures, and this list is not
exhaustive.
Depending on circumstances, Plant or Pipeline Vice-Presidents, may require
certain other work in Unrestricted areas to be subject to the PTW System. In
this case a Register of such work must be maintained. As with the 'Work in
Restricted Areas not normally requiring a Permit' (see 3.3.1) details are to be
maintained by the Plant or Pipeline Vice-President.
In Pipeline Division, where the distance from the pipeline exceeds 30 metres,
but is less than 200 metres, Third Parties and Contractors are required to
advise GASCO of proposed work activities and to obtain a No Objection
Certificate (NOC) prior to commencing work. After evaluating the risk, the Asset
Owner decides what PTW System controls (if any) are required.
3.3.2.1
Authorisation of Work in Unrestricted Areas
Where work in Unrestricted Areas is subject to the PTW System, the
authority for authorisation of work will normally be the Asset Holder of
that particular section of the site or facility.
Where there is potential to affect Plant Operations, the Operations
Shift Controller (the Asset Operator for Restricted Areas) should also
countersign the Permit.
The Plant/ Pipeline Vice-President, is responsible for authorisation of
the Asset Holders and Asset Operators, who will sign permity, for
defined areas of the site or facility.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 7 of 42
3.3.3 Work Requiring a Permit
All work to be done in a Restricted Area or H2S Zone, that is not included in
3.3.1, or is in an Unrestricted Area requiring controls, then the work is subject to
the PTW System.
3.3.4 Permits Covering more than one Work Activity
At the discretion of the Asset Holder, a Permit may be issued to cover more than
one simultaneous work activity within a designated area, subject to the following
criteria:
(i).
A Risk Assessment has shown the site conditions and hazards are of a
similar nature and can be covered on one Permit;
(ii).
There are clear isolation/ master isolation boundaries;
(iii). The same GASCO Maintenance/ Engineering discipline or Contractor is
involved, or, where considered appropriate, a lead Trade discipline has
been appointed with agreed responsibilities for overseeing the work
activities;
(iv). The jobs/ activities are all under the supervision of a single designated
PICWS (as per (iii) above) and there is no conflict with the PICWS role as
the ACCEPTOR of the Permit.
(v).
The area covered by the Permits is clearly defined on marked up drawings
(and attached to the Permit) and can be adequately supervised by one
person;
(vi). In general, the PICWS should have clear line of sight to all activities
undertaken under a single Permit, and have adequate access to, and
communication with all persons involved in the activities.
(vii). Gas tests, where required by the Permit, must be carried out as
appropriate to cover all activities within the designated area. The results
are to be recorded on the Gas Test Certificate (see Chapter 5, Section 5.2).
If any measurement is outside permissible levels, then the Permit must be
suspended and, if necessary, separate Permits issued.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 8 of 42
Typically, no more than four simultaneous activities, which meet the
aforementioned criteria, should be included on a Permit that is under the
supervision of a single PICWS. In special circumstances, the Asset Owner may
give dispensation to deviate from this standard, e.g. during major Plant
shutdowns, where the Plant is positively isolated and declared free of
hazardous and flammable materials, and it is deemed reasonable to expand
the work under the control of a single PICWS.
3.3.5
Work which requires Interface Procedures
Interface procedures apply whenever there is a risk of interference or mutual
risk between two parties working within close vicinity of each other. They exist
to ensure that all parties are aware of each others activities and that the risks
and potential hazardous interactions have been jointly identified and
communicated, and that satisfactory control measure have also been jointly
identified and implemented to allow the work activity to continue safely.
PTW Interface procedures (see 3.3.5.1 to 3.3.5.5) apply for all work being
undertaken within the following designated interface areas:
(i). Within 30m of the boundary between two different GASCO Area
Authorities who are responsible for a section of the plant within the
responsibility of the same Asset Operator;
(ii). Within 30m of the boundary between two different GASCO Asset
Operators, e.g. Habshan Plant/ Facility having different Shift Controllers;
(iii). Within 30m of an ADNOC Group Company administered area, facility or pipeline;
(iv). Where the work is conducted within the designated boundary of an
ADNOC Group Company facility, pipeline corridor or administered area by
GASCO or GASCO contractors;
(v). Where the work is conducted within the designated boundary of an
GASCO administered area, facility or pipeline corridor by an ADNOC
group company or their contractors;
(vi). Where the work is conducted within the designated boundary of a shared PTW
Interface Area by GASCO, or by GASCO contractors.
NB. A shared PTW interface area is one that is jointly administered by both GASCO
and another ADNOC Group Company (such as the Joint Pipeline Corridor).
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 9 of 42
3.3.5.1
Interface Procedures between Asset Operators/ Area Authorities
Any hot work being conducted within 30 metres of the boundary
between two separate Areas (Habshan) requires the countersignature of
the adjacent Asset Operator (the Area Shift Controller) as well as that
counter endorsement (initial) of the adjacent Area Authority.
For hot work being conducted within 30 metres of the boundary between
two distinct areas within a defined Plant or facility, having different Area
Authorities, e.g. between two separate Process Trains, the counter
endorsement (initial) of the adjacent Area Authority is required.
3.3.5.2
Interface Procedures for ADCO working within GASCO Controlled
Areas
Work by ADCO within GASCO controlled Areas, or within 30 metres of
GASCO Pipelines, requires the use of the GASCO PTW System.
The GASCO Asset Owner (the Plant or Pipeline Vice-President,) should
have an updated list, from the ADCO Division Manager, of ADCO
personnel who are Authorised signatories under the GASCO PTW
System having satisfied GASCO Competency requirements.
Prior to work commencing, the Issuing Authority (Asset Operator) is to
jointly visit and check the work site with the ADCO Authority to confirm
that all work site precautions required by both Authorities are in place.
The GASCO Permit must be referenced to any ADCO Permit which has
been issued, and which is related to the same work activity. In such
cases, the GASCO Authority is to countersign the Issue Section of the
ADCO Permit or Hot Permit.
The ADCO Authority is to countersign the Issue Section of the GASCO
Permit and any supporting Hot Work Permit(s).
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 10 of 42
3.3.5.3
Interface Procedures for GASCO working within ADCO Controlled
Areas
All personnel who have to enter areas under ADCO control for monitoring or
checking their equipment must obtain permission from the relevant ADCO
Area Authority. Where GASCO has to work in ADCO controlled areas, either
on their existing plant, on ADCO plant or new construction, they must first
obtain an ADCO PTW.
The ADCO Permit request must be signed and submitted by a GASCO
Permit Originator. The GASCO Permit Originator must meet the equivalent
job grade criteria (minimum supervisory Grade 11) as required by ADCO
PTW procedure. The GASCO Permit Originator must be authorised on a
written list submitted to the relevant ADCO Area Manager by the respective
GASCO Asset Owner (the Plant or Pipeline Vice President) to request work
to be undertaken within ADCO controlled areas.
Prior to work commencing, the ADCO PTW Procedure requires the ADCO
Issuing Authority to jointly visit and check the work site with the GASCO
Authority to confirm that all work site precautions required by both Authorities
are in place. The GASCO Authority (the Asset Operator) is to countersign the
Issue Section of the ADCO Permit or Hot Permit.
The ADCO Permit must be referenced to any GASCO Permit which has
been issued, and which is related to the same work activity. In such cases,
the ADCO Authority is to countersign the Issue Section of the Work Permit or
Hot Work Permit.
3.3.5.4
Interface Procedures for Working in Shared PTW Interface Areas
Shared PTW Interface Areas of GASCO and another ADNOC Group
Company, are those areas specifically designated on maps/ drawings where
both Companies have plant and/ or equipment and where neither Company
has overall responsibility. In general, these areas are commonly where
flowlines and pipeline are in close vicinity to each other or cross (see
Appendix A).
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 11 of 42
3.3.5.4
Interface Procedures for Working in Shared PTW Interface Areas
(Cont.)
Interface procedures also apply to the Joint Pipeline Corridors when
working in the vicinity of ADCO, GASCO or ADNOC pipelines. Joint
Pipeline Corridors will be bounded by an area 30m either side of the
outmost pipelines.
Within a Shared PTW Interface Areas, including the Joint Pipeline
Corridor, the PTW system of the Company undertaking the work will
apply, i.e. if GASCO, or GASCO contractors, are working a GASCO
PTW will be required; if another ADNOC Group Company is working
then their PTW will be required.
In all cases the work activity and PTW must be discussed with the Asset
Operator of the other ADNOC Company (in ADCO the Area Authority)
sharing the area before the work commences. The other ADNOC
company’s Asset Operator must countersign the PTW prior to issue. All
Permit Signatories authorised to sign/ countersign PTW, within Joint
PTW Interface Areas, must be authorised by the Asset Owner (the Plant
or Pipeline Vice-President,). This is to be on a written list submitted to
the other ADNOC company’s equivalent Asset Owner (in ADCO, the
Area Manager).
Work in the Ruwais Easement Areas is under the control of TAKREER
3.3.5.5
Requirements for Identification of PTW Interface Areas with ADCO
All areas within ADCO’s concession area are designated ADCO
administered areas, except for those areas specifically agreed and
marked up on approved drawings. ADCO PTW procedures and
requirements apply for all parties working within ADCO administered
areas.
Drawings clearly detailing the agreed designated boundaries of ADCO,
other ADNOC Group Company PTW administered areas, and agreed
PTW Interface Areas as specifically referred to in this section must be
available for all sites.
A simplified layout drawing, depicting GASCO/ ADCO PTW Interface
areas is included as a reference in Appendix A at the end of this Chapter.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 12 of 42
3.4 RISK MANAGEMENT PROCESS FOR WORK
There are, in general, three types of work activity:
•
Work activities that have had a Risk Assessment previously completed and
recorded in procedures or in Maximo;
•
Work activities that are new or have not been risk assessed, and
•
Work activities that can be covered by individual’s competence, skills and training.
In all cases, the initial Risk Assessment should be undertaken prior to the origination
of the Work Permit and any supporting Permits or Certificates (see Chapter 5). It is the
responsibility of the Maintenance/ Engineering Authority to initiate the process and
record the Risk Assessment
An overview of the risk assessment process for work activities, and its application
within the PTW System is provided in flowchart form in Appendix B at the end of this
section.
The following sections describe, for each of these types of activities, the steps that
must be taken in order to ensure the integrity of the risk assessment process.
3.4.1
Introduction to the Activity Risk Assessment (ARA) Process.
Whenever work has to be undertaken by GASCO, Third Parties or Contractors
on GASCO sites, or in the immediate vicinity of GASCO pipelines, it is
necessary to make a suitable and sufficient assessment of the risks to the
health and safety of employees and others, for the purpose of identifying the
necessary control measures. Practically this involves four basic steps, which
are to:
•
•
Identify the possible hazards associated with the work activity;
•
Introduce control measures (precautions) to prevent or reduce the risks to
a level ‘As Low As Reasonably Practicable’ (ALARP). See 3.4.1.3 for
further explanation and guidance on demonstrating ALARP;
•
Specify recovery measures in case the controls fail.
Assess the consequences of the hazardous event(s) and the likelihood of
their happening, i.e. evaluating the risks arising from them;
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 13 of 42
3.4.1 Introduction to the Activity Risk Assessment (ARA) Process. (Cont.)
The process of identifying the hazards, evaluating risks and applying controls
and specifying any recovery measures will be referred to as ‘Activity Risk
Assessment’ (ARA). This is shown diagrammatically in Fig. 3.4/1 below.
W hat are the hazards?
W hat could go wrong?
• List Hazards
IDENTIFY
What if it happens?
H o w t o re c o v e r ?
•Emergency Response
RECOVER
What could happen?
How serious will it be?
How likely is it?
ASSESS
CO NTRO L
• Escalation
•Lim it consequences
• Risk (Consequence x Probability)
•Reinstate to safe
•Eliminate
I s t h e re a b e t t e r w a y ?
H o w t o p re v e n t i t ?
•Prevent
•Reduce risk to ALARP
Figure 3.4/ 1 – The Activity Risk Assessment (ARA) Process
In practice, these steps are not always distinct and many decisions about the
overall process will be taken as part of the Activity Risk Assessment. Completing
the four steps of the ARA will produce risk reduction measures that both prevent
incidents, by reducing the probability of occurrence, and mitigate chronic and
acute effects by reducing the consequences.
3.4.1.1 Assessing the Risks
Assessing risk involves considering how likely it is that each hazard
could cause harm, by considering the threats which may lead to the
release of the hazard, what the consequences could be, and, in some
cases, the potential for the event to escalate.
The extent of any risk assessment will depend on the nature of the
risks, the complexity associated with the activity, and on whether the
risks are well understood. The ARA in the workplace can be as basic as
deciding how to go about doing a task safely for simple routine jobs.
GASCO has developed a Risk Assessment Matrix (RAM) as a tool to
help categorise the risk, based on its consequences and the probability
of the potential consequence occurring (see Appendix C).
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 14 of 42
3.4.1.2 Controlling the Risks
Controlling risk involves eliminating the hazard wherever possible, or
applying measures to prevent the hazardous event and/or the harm
from happening.
In all cases, the extent of any risk assessment and the controls arising
from it should be proportionate to the risks. The higher the risk, the
greater the degree of control required and the more senior the
management level required to approve the activity.
Figure 3.4/ 2 below illustrates that, as the risk increases, the necessary
level of control for the activity can be achieved by adding controls or by
strengthening existing ones.
Degrees
of
Control
Greater controls/
authority are
required as the risk
increases
Risk
Senior
Assessment Management
Authority
Risk
Assessment
Risk
Assessment
Risk
Awareness
Permit to Work
Standards, Procedures, etc.
Competency & Skills
LOW
MEDIUM
HIGH
Initial Risk
Figure 3.4/ 2 - Degree of Control versus Initial Risk
As the risk increases, a documented risk assessment is required and
the competency and skills may need to be strengthened and/or a
procedure implemented.
At higher levels of risk, Permit to Work Controls will be required.
Ultimately, Senior Management Authority will be necessary (see 3.4.5).
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 15 of 42
3.4.1.3 Demonstrating ALARP
ALARP means to reduce a risk to a level, which is as low as
reasonably practicable. This involves balancing reduction in risk
against the time, trouble, difficulty and cost of achieving it. This level
(ALARP) represents the point, objectively assessed, at which the time,
trouble, difficulty and cost of further reduction measures becomes
disproportionate to the additional risk reduction obtained.
A key concept in identifying the ALARP level is to ensure that all
possible options for risk reduction have been identified. It is often the
case that only the obvious or easy options are considered. It is
important, however, to look at all options even if at first they appear
difficult or costly.
The Risk Assessment Matrix (RAM), (see Appendix C) is a tool that
provides a standard approach to the qualitative assessment of risk. All
activities, which fall in the yellow (medium) or red (high) sectors of the
RAM, require documented evidence that they have been reduced to
ALARP. An Activity Risk Assessment (ARA) form is provided for this
purpose (see Appendix E).
Specific guidance on the completion of the ARA form is given in 3.4.3,
Stage 6, and Appendix D.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 16 of 42
3.4.2 Performing an ARA for Previously Assessed Activities
Most activities that are undertaken are not new, they are routine, or common
tasks that have previously been risk assessed and/ or are covered by existing
procedures. They have probably been developed through established good
practice and with due consideration for the hazards that may be present.
Such activities do not need a new risk assessment each time they are carried
out, but do require that the assessment is subject to periodic review, primarily
to identify if anything has changed that would affect the outcome of the
assessment.
Some questions, which should be asked, are, for example:
•
Have the persons doing the activity changed and are any new persons
competent?
•
•
Have new hazards been introduced?
Are new tools being used or new procedures introduced?
If new controls are identified then the Permit Originator should update the ARA
and the date of the review should be recorded.
3.4.3 Performing a New Activity Risk Assessment
This section describes the steps required to perform a risk assessment for an
activity, or combination of concurrent activities, which have not been previously
assessed. This process should also be used if a previously assessed routine or
common task has been reviewed and the risk assessment found to be not
appropriate for the particular job.
When a new risk assessment is performed, all hazards and threats should be
identified and the risk assessed such that controls can be identified to reduce
the risk to ALARP (see 3.4.1.3). If the risk cannot be reduced to ALARP, the
activity should be redefined or not undertaken.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 17 of 42
3.4.3
Performing a New Activity Risk Assessment (Cont.)
Figure 3.4/ 5 (below) sets out the main stages of this ARA process.
These stages are described in more detail in the remainder of this section.
3.4.3
PERFORM NEW ARA
Any task not previously performed or
assessed or reassessment of a task
Stage 1
Stage 2
IDENTIFY AND FORM ARA TEAM
IDENTIFY HAZARDS
Stage 3
INDENTIFY INITIAL RISK
Stage 4
IDENTIFY CONTROLS & RECOVERY
MEASURES
Stage 5
REVIEW RESIDUAL RISK
Does the Team agree that
Controls are adequate and
Residual Risk ALARP?
NO
YES
Stage 6
DOCUMENT AND RECORD
Figure 3.4/ 5 - Activity Risk Assessment Process
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 18 of 42
3.4.3 Performing a New Activity Risk Assessment (Cont.)
Stage 1:
The Originator will Identify and form the ARA Team.
The ARA is normally conducted within the Department responsible for doing
the activity and should include personnel who are:
•
•
Responsible for the task;
•
Have sufficient knowledge, expertise and competence in the activity to be
performed to have an understanding of the hazards it presents;
•
•
Knowledgeable about the location, and the hazards that are present;
Competent to conduct an ARA;
To be Involved in carrying out the task.
The ARA should be undertaken prior to origination of the permitry. Where
appropriate, the team should visit the worksite. The activity can be broken
down into a number of smaller tasks where it is considered necessary.
Stage 2.
Identify the Hazards and Effects.
Each task is to be studied to identify the hazards, hazardous events and
potential incidents whether they arise from the actions of people or from the
conditions surrounding the activity.
The assessment should identify who or what might be harmed and the findings
recorded.
Stage 3.
Identifying Risk Ratings for Initial Risks
Risk rating is a means whereby the risks associated with a particular hazard or
hazardous activity can be expressed as a value and compared with acceptable
limits.
The initial risk rating should be assessed on the situation that prevails before
any controls are implemented for each hazard. The Risk Assessment Matrix
(see Appendix C) should be used to calculate risk ratings.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 19 of 42
Stage 4.
Identify Control and Recovery Measures.
Taking each hazard in turn, the ARA team should develop ways to either,
eliminate the hazard or provide appropriate control and recovery measures to
mitigate them. In practice, a mixture of different controls often produces
effective control, e.g. engineering controls, personnel protective equipment
and procedures.
Stage 5
Review Residual Risks.
The residual risk is any risk that remains after all the control measures are
applied.
The Risk Assessment Matrix (RAM) should again be used and the results
entered in the ARA Worksheet. The residual risk should be ALARP (see
3.4.1.3).
Stage 6
Document and Record.
The ARA should be recorded using the ARA Worksheet. A copy of the ARA
Worksheet is included in the Appendices (see Appendix E). An annotated
version of the ARA is also provided in Appendix D, which provides guidance on
its completion.
The ARA Worksheet can be used to:
•
Communicate the outcome and actions to those responsible for
implementing the control measures and performing the activity
•
Ensure the information is available to others who may have to perform the
activity.
3.4.4 Activities covered by Individuals Competence
It is recognised that some low risk activities are adequately covered by the
competency and skills of the individual. Therefore, where a formal risk
assessment would not produce any significant findings it is not necessary to
formally record the risk assessment.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 20 of 42
3.4.5 Responsibility for ARA process
The Plant and Pipeline Vice-Presidents are responsible in their respective
areas for the ARA process as described in 3.4.1. In addition, for certain
activities, they are personally responsible for approving the ARA where there is
a higher level of initial risk, such as, (though not exhaustive):
•
•
•
•
Hot tapping on live hydrocarbon process streams
Disjointing and/ or spading on live flare lines or lines containing H2S
Confined space entry in oxygen deficient or toxic atmospheres
Heavy lifting operations over live hydrocarbon process lines
It is the responsibility of the Area Superintendent to bring such high-risk
activities to the notice of the Plant/Pipeline Vice President
3.4.6 Linking the ARA and the Permit to Work
This section should be read in conjunction with the Work Permit (see Chapter
5, Section 5.1, Fig. 5.1).
A matrix diagram, which provides an overview of the Work Permit Lifecycle
versus Signatory Responsibilities, is provided in Appendix F.
Before work commences following the ARA, authorisation must be obtained
through the Permit to Work system by issuing a Work Permit together with any
necessary supporting documentation.
The Work Permit has a number of consecutive steps that are all part of the
overall Risk Management process and are in addition to the ARA. These steps
are as follows:
STEP 1 Work Description and Risk Assessment
Following completion of the ARA, the person who is requesting the work, the
Originator, has to describe what work is to be done and what equipment is to
be used. The work scope must be clearly defined in order that the persons
undertaking the worksite preparations are clear as to the intent.
The results of the ARA are also recorded on the Permit in terms of the hazards
associated with the work and the controls necessary during its execution.
Where the work activity covers several tasks, or is of a more complex nature
requiring sequential controls, with different persons responsible for individual
tasks, an Activity Sequence Control Sheet (ASC) should be completed (see
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 21 of 42
Chapter 6) and submitted with the permitry.
One of the controls to be specified is the requirement for the supervision of the
work, defined as the Person in Charge of the Worksite (PICWS). The level of
supervision (the category of worksite presence required) should be appropriate
to the risk of the job being undertaken.
The category of worksite presence is defined as follows:
Category A:
Continuous attendance of the PICWS, with signed transfer of
responsibility when one PICWS is replaced by another. Work MUST
stop when no PICWS is present. The PICWS is not to hold any other
Permit whilst nominated as a Category A, PICWS presence.
A Hot Work - Category 1, Permit and other designated high-risk jobs
(e.g. Vessel Entry) would normally require a Category A presence.
Category B:
As Category A, but work may continue during short (e.g. not more than
45 minutes) absence of the PICWS. One person cannot be responsible
for more than one Permit when nominated as a Category B, PICWS
presence, unless the other Permit is in close proximity to the first one
and can be safely supervised by one person.
Category C:
The PICWS is to make an initial visit, and is then required to make only
periodic visits to the worksite. The number of Permits, with a Category C
PICWS presence, which can be held by one PICWS, should be limited
to a maximum of six and is further dependent on the PICWS ability to
provide adequate supervision for all Permits under his control.
As a guideline, each worksite should be visited by the PICWS at least
three times during a shift/ normal work period.
The holding of several Category C Permits and one Category B Permit
is permissible providing the rules for Category B are satisfied
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 22 of 42
STEP 1 Work Description and Risk Assessment (Cont.)
Supporting documentation may also be originated at the same time as the
Permit because the Risk Assessment Process (ARA) may also have identified
particular hazards introduced by the work, which require further formal
controls. Examples are:
•
•
The introduction of risk due to hot work
•
Use of radioactive sources.
Confined space entry
Where such risks are identified, then Supporting Permits or Certificates are
needed. These are listed in Table 3.4/ 1 for specific activities and provide the
mechanism for defining the controls required.
Illustrations of all Permits and Supporting Certificates are given in Chapter 5,
Figure 5.1 to Figure 5.8.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 23 of 42
STEP 1 Work Description and Risk Assessment (Cont.)
TABLE 3.4/ 1 - WORK ACTIVITY Vs SUPPORTING PERMITS/ CERTIFICATE
REQUIREMENTS
WORK ACTIVITY
PERMITS/ CERTIFICATES
REQUIRED
Work which involves a continuous source of
ignition, i.e. naked flames, welding, grinding,
heat treatment, electric power tools, in a
Restricted Area, or, in an Unrestricted Area
for naked flame, welding or grinding
Hot Work Permit, Category 1
(Also see ATW for Pipelines
Appendix G)
Work which involves a potential source of
ignition, i.e. dry grit blasting, non-intrinsically
safe electrical equipment, opening live
junction boxes, hydraulic tools which may
generate a spark, inadequately protected
engines, cartridge operated tools all in
hazardous area (as per Electrical Zone Area
Classifications) within a Restricted Area
Hot Work Permit, Category 2
Work which involves entry to a confined
space
Confined Space Entry Certificate
Work which involves excavation
Excavation Permit
Work which involves a radio active source
Radiation Permit
Gas testing at worksite
Gas Test Certificate
Work which requires isolation of an energy
source to allow work to be done safely
Isolation Confirmation Certificate
Complex activities which require some
sequence controls
Activity Sequence Control Form
(ASC)
Low risk activities carried out by GASCO,
Third
Party or Contractors within 30 metres of
pipelines, or pipeline corridors
Pipeline Authorisation
(ATW)
(See appendix G)
NB. Not required in defined
pressurised Control Rooms and/ or
Sub-stations in Restricted
Areas.
(Also see ATW for Pipelines
Appendix G)
to
Work
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 24 of 42
3.4.6 Linking the ARA and the Permit to Work (Cont.)
STEP 2 Permit Review and Validation
Following the origination stage of the Permit, it is necessary to present the
Permit to Operations (the Asset Operator) so that agreement can be reached
with respect to the timing of the work. This is normally done at the daily Permit
to Work meeting.
This PTW meeting is the forum for Maintenance/ Engineering and Operations
to review all new permitry submitted for work that has been agreed as
necessary in the Maintenance/ Engineering Work Plan. It is here that any risk
assessment which has been previously undertaken (as described under 3.4.1)
and which requires submission of a formal Activity Risk Assessment sheet is
discussed, and further elements of the overall Risk Management process are
developed. Because of the importance of this daily PTW meeting it is described
here in more detail.
At weekends, or where permitry is not submitted via the daily PTW Meeting, the
Asset Operator and Authorised Maintenance/ Engineering Authority must
undertake the process of reviewing and validating of permitry.
DAILY PTW MEETING*
Objective:
(i)
To provide a daily overview of all ongoing and planned work under the
control of the Permit to Work System and to identify any potential
conflicting activities.
(ii)
For Operations to review and agree new Permits, including any Activity
Risk Assessments previously undertaken, time scales and resource
requirements.
Note that the daily PTW meeting is not the forum for undertaking the ARA.
(iii) To provide an effective handover mechanism to duty shift teams through
the recording of work that is to be undertaken in the Operations Area.
(iv) To provide a Maintenance/ Engineering and Operations interface for
Permit to Work requirements.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 25 of 42
3.4.6 Linking the ARA and the Permit to Work (Cont.)
DAILY PTW MEETING*
Attendees
As a minimum, the daily PTW Meeting will be attended, by the Operations
Coordinator, who will normally be the Chair Person, Shift Controller (as
available) and appointed Maintenance / Engineering staff.
Further attendees, for example Technical Support and/ or HSE, will be present if
requested by the Operations or Maintenance/ Engineering attendees, when it is
recognised that further expertise or advice is relevant.
Terms Of Reference
(i)
The meeting will be held daily, taking into account weekend working.
(ii)
Key input mechanisms to the daily PTW Meeting will be work details/ status
of ongoing work and any new activities. Any preparatory requirements for
new activities should be highlighted.
(iii) As far as is possible/ practicable, all new Permits should be processed
through the daily PTW meeting, unless it is HSE or production critical and
cannot wait. In such cases, Permits may be processed outside of the PTW
Meeting, but the Maintenance/ Engineering Authority and the Asset
Operator must still adhere to the same review and validation process.
(iv) Permitry must be submitted with adequate advance warning to allow
Operations the required timescale for detailing and recording of isolation
procedures and for equipment preparation.
A check must be made to ensure that there is no foreseen conflict, both
geographically (i.e. across other work boundaries) or on a time basis (activities
which may start later). This is to be done by the Asset Operator.
Once the permitry has been discussed at the daily PTW Meeting and controls
agreed, the Permit can be VALIDATED, that is, accepted by the Asset Operator
as an agreed piece of work that has been risk assessed and is to be undertaken
in an area controlled by Operations (or for Unrestricted Areas the appointed
Asset Operator).
* Pipelines Division may hold the meeting at a lesser frequency, as workload
requires but not less than weekly
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 26 of 42
3.4.6 Linking the ARA and the Permit to Work (Cont.)
STEP 3 Permit Issue
When the worksite preparations are complete, and any additional Permits/
Certificates prepared, the final stage of the authorisation process can take
place, that is, the ISSUING of the Permit.
It is important to note, however, that although the Permit is issued, work may
not start until all of the necessary Permits are accepted and endorsed (see
Steps 4 & 5).
STEP 4 Permit Acceptance
The person responsible for the work activity ACCEPTS the Permit. This is the
Person who will be, or will hand over to, the Person In Charge of the Work Site
(PICWS) and he must arrange any necessary Toolbox Talk(s).
The Toolbox Talk is the last step in the Risk Management process and is the
final opportunity to discuss the hazards and controls with the persons who will
execute the work. Generally speaking, a Toolbox Talk is required for all
activities undertaken under a Permit, although for routine, lower risk, activities
need not necessarily be formally recorded.
Guidance notes on undertaking Toolbox Talks is given in Chapter 7, which
includes an example of a Toolbox Talk record sheet.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 27 of 42
3.4.6 Linking the ARA and the Permit to Work (Cont.)
STEP 5 Worksite Responsibility
The PICWS must now sign the Permit to demonstrate that he understands the
hazards of the work and the controls necessary. He has the responsibility for
making sure everyone in the work party understands his particular role in the
work, and that they understand the relevant hazards and the required controls.
Should the PICWS change, or there be more than one PICWS, e.g. if there are
different shift teams, the same criteria of accepting responsibility apply.
STEP 6 Endorsements for the Continued Safety of the Worksite
6.1 Initial Endorsement
The Maintenance/ Engineering Authority, who has accepted the
Permit, must take it to the worksite and obtain the endorsement of the
Area Authority that it is safe for the work to start. This is a control as it
gives the Area Authority the opportunity for a further discussion of the
work and to identify any activities in the area, which may conflict with
the work.
The Permit is then endorsed by the PICWS, who accepts
responsibility for the worksite prior to work start, and is the final
opportunity to discuss the work prior to its commencing.
Once all parties have initialled for work start, the Permit is now
ENDORSED.
6.2 Recording of Work Stop
When work has stopped at the worksite, normally at the end of the
Maintenance/ Engineering work period, this is recorded on the Permit
by the PICWS. Once the PICWS has initialled for Work Stop, the
Permit is termed as SUSPENDED.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 28 of 42
STEP 6 Endorsements for the Continued Safety of the Worksite (Cont.)
6.3
Permit Re-endorsement
At the start of each new shift, a further re-endorsement is required by:
i)
The Asset Operator to confirm there is no conflict with any other
activity;
ii) The Area Authority to confirm that there is no change to worksite
conditions;
iii) The PICWS to accept responsibility for the continued safety of the
worksite.
STEP 7 Permit Closure
When work has been completed, or requires Permit renewal, the
CLOSURE portion of the Permit must be completed.
In particular, when work has been completed or will lapse for an
extended period, but isolations must remain in force, it is important
that the controls associated with the isolations remain valid. Such
controls must be visibly continued and displayed in the PCF.
Once the PICWS has initialled the Closure portion of the Permit it is
now termed as CLOSED.
3.4.7 Visibility of Permits
As part of the Risk Management process, Permits must be displayed in a
systematic arrangement, clearly showing work in progress or work suspended,
for each defined Operating Area. The display should be at a suitable Permit
Control Facility (PCF) (see Chapter 8). Management and Operations staff can
therefore readily see the activity status for all work subject to the PTW system.
Included in Chapter 8, Appendix A is a simplified flowchart showing the various
stages in the Permit lifecycle and how the continued safety of the worksite is
managed and administered.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 29 of 42
3.4.8 Layout and Colour of Permits
References should be made to Permit and Supporting Certificate examples,
Chapter 5, Figure 5.1 through to Figure 5.8.
The Work Permit is designed as a double A4 format to provide a sequencing of
signatures as the Permit passes through its various stages.
The Work Permit is the core the PTW System and is the only Permit which can
be 'stand-alone'.
Supporting Permits and Certificates are designed to identify specific hazards
and controls, additional to those recorded on the Work Permit. A Work Permit
MUST accompany all supporting Permits and Certificates.
For visibility purposes, and to aid identification of documents, different colours
are used on the border of Permits and Certificates as per Table 3.4/ 2 below.
Table 3.4/ 2 – Permit and Certificate Identification Colour Codes
DOCUMENT
BORDER COLOUR
Work Permit
Blue
Hot Work Permit Category 1
Red
Hot Work Permit Category 2
Pink
Confined Space Entry Permit
Dark Green
Excavation Permit
Brown
Radiation Permit
Yellow / Black
Isolation Confirmation Certificate
Yellow on left hand side
Gas Test Certificate
Buff
Pipeline ATW
Light Green
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 30 of 42
3.4.8 Layout and Colour of Permits (Cont.)
The Work Permit and the Supporting Permit or Certificates are printed to allow
2 copies for display purposes as follows:
•
The top (original) copy, which has a white background, is displayed at the
worksite.
•
The second copy, which has a yellow coloured background, is retained in
the Permit Control Facility.
3.4.9 Permit Signatories
3.4.9.1
Authorised Permit Signatories
The key steps of Validating, Issuing, Accepting and Endorsing of
Permits is done by Persons who have been assessed as competent
to execute the Risk Management Process associated with these
separate steps.
Certain activities, namely those that require supporting Permits, have
a higher level of risk and consequently higher levels of authorisation
exist.
Permit Signatories are those who have had sufficient training and
experience and have been duly authorised as those Permit
Signatories by Plant and Pipeline Vice-President.
The Authorised Signatories, who are responsible for signing the
various sections of the Work Permit and Supporting Permits or
Certificates, are tabulated in Table 3.4/ 3.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 31 of 42
TABLE 3.4/ 3 –PERMIT/ CERTIFICATE AUTHORISED SIGNATORIES
DOCUMENT
Work Permit
ACTION
Originating
Reviewing
Validating
Issuing
AUTHORISED SIGNATORY
Authorised Maintenance/ Engineering Authority
(minimum Senior Technician)
Authorised Maintenance/ Engineering Authority
(minimum Area Maintenance Supervisor)
The Asset Operator:
Restricted Areas: the Operations Co-ordinator or
Shift Controller (by exception)
Unrestricted Areas: the Senior Maintenance/ Engineering
Authority (Section Head level)
At Habshan, for work across Interface Areas (Restricted
or Unrestricted Areas), the Shift Superintendent
The Asset Operator: Restricted Areas: Shift Controller
Unrestricted Areas: Senior Maintenance/ Engineering
Authority (minimum Section Head Level)
Accepting
Authorised Maintenance/Engineering Authority
(Minimum Senior Technician)
Endorsing
Area Authority, PICWS
Asset Operator: - For Re-endorsement, it may be the
Assistant Shift Controller
- For common areas (e.g. MCR) and
Interface Areas it should be the Shift Controller
Closing
Authorised Maintenance/ Engineering Authority
(minimum Senior Technician) Asset Operator
Hot Work
Validating/
Permit -Cat.1
Issuing
The Asset Holder:
Restricted Area: Operations Superintendent or
Shift Superintendent, Habshan and Ruwais
Unrestricted Area: Asset Operator
Hot Work
Permit -Cat.2
Confined Space
Entry Certificate
Accepting
Authorised Maintenance/Engineering Authority
(Minimum Area Maintenance Supervisor)
Validating/
Issuing
Asset Operator
Accepting
Authorised Maintenance/Engineering Authority
(Minimum Senior Technician)
Asset Holder for oxygen deficient atmosphere.
Asset Operator (for normal atmosphere)
Asset Operator
Issuing
Excavation Permit
Endorsements
Review and Issue
Authorised Civil Signatory
Radiation Permit
Accepting
Approval
Validating/ Issuing
Asset Operator
Accepting
Radiography Company Representative
Authorisation
Asset Holder or Asset Operator
Accepting
Authorised Company, Third Party or Contractor representative
Pipeline AT W
Asset Operator
GASCO Inspection Authority
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 32 of 42
3.5 RULES GOVERNING PERMITRY
3.5.1 Permit and Certificate Validity Periods
To ensure that precautions required for tasks of a long duration are
reviewed regularly, limits are set on the validity periods that Authorised
Permit Signatories may set for Permits. These are:
Work Permits.....................................
7 consecutive (calendar) days.
Hot Work Permit, Category 1 & 2……
7 consecutive (calendar) days
Radiation Permits...............................
24 hours
Isolation Confirmation Certificate.......
No Validity period
Excavation Permit..............................
28 consecutive (calendar) days
Confined Space Entry Certificates…
28 consecutive (calendar) days
Gas Test Certificate…………………
No Validity period
Pipeline Authorisation to Work (ATW)… 28 consecutive (calendar) days
(max. extension of 3 x 28 days)
3.5.2 Permit Endorsement Periods
The maximum endorsement period for Permits, supporting Permits and
Certificates is 12 hours. An endorsement may not straddle an Operations
Shift change. Where a shorter endorsement period is required, a
statement in the 'Particular Hazards and Additional Precautions' section
of the Permit should indicate where this is required.
Pipeline ATW Forms have endorsement periods but are subject to
worksite checks by the Area Authority on a frequency defined by the Asset
Operator (see Chapter 5, Section 5.9.4).
3.5.3 Maximum Number of Permits
In normal circumstances, there should be a sensible limit on the
maximum number no of Permits to be administered and issued by the
Asset Operator and each Area Authority on a shift basis. Guidelines for
the maximum number of Permits are given in Table 3.5/ 1 below.
Preferably, the number of Permits should be managed below these
recommended figures.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 33 of 42
Table 3.5/ 1 – Guidelines for maximum number of Permits
Recommend Maximum Number per Authority
Permit Type
Area Authority
Asset Operator
Work Permit
15
40
Hot Work Permit Category 1
2
4
Hot Work Permit Category 2
5
10
The recommendation covers only the numbers of Work Permits and Hot Work
Permits to be managed, and does not take account of any other supporting
Permits or Certificates issued.
In other circumstances, e.g. during major shutdowns when Permit requirements
are greater, special arrangements for the control and administration of Permits
should be made and agreed with the Plant or Pipeline Division Manager.
At the daily PTW meeting, the Asset Operator should review the current number
of Permits per operational area prior to accepting new Permits. Any increase
beyond these criteria should first ensure that the quality control, safety and
individual responsibility is not compromised.
3.5.4 Stoppage of Work Following an Alarm
All work is to cease immediately on initiation of any Plant alarm or advised
change of Plant status away from normal by the Area Authority or Asset
Operator.
On the re-establishment of normal status, the PICWS is to obtain the verbal
authorisation of the Area Authority before restarting work except where there
has been an escape of H2S when the Permits issued in H2S zones must be
re-endorsed.
For Hot Work activities, or where there has been an escape of H2S, the PICWS
is to return the Hot Permit to the Permit Control Facility for subsequent
re-endorsement of the Asset Operator before restarting work.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 34 of 42
3.5.5 Changes to Work Details on a Permit
If changes are required to the work details on any Permit prior to the Work
Permit validation, the Originator must initial them. If changes are required
after the Work Permit validation, they are to be initialled by the Originator
and the Validating Authorities (the Asset Operator and Authorised
Maintenance/ Engineering Authority).
Precautions and controls may be added to, but not deleted from, a Permit.
These should be agreed with the Validating and Issuing Authorities prior
to making changes on the Permit details. All Permit signatories must then
initial against the agreed changes.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 35 of 42
APPENDIX A
Schematic depicting general principles of PTW requirements in GASCO/ ADCO Interface
Areas
GASCO/ADCO
PTW INTERFACE
ADCO PTW Area:- ADCO
PTW required everywhere
in ADCO concession area except
in areas otherwise designated
30m
(Joint pipeline
corridor)
GASCO
FENCED
AREA
ADCO
UNFENCED
PTW
CONCESSION
AREA
ADCO FENCED
PTW AREA
A
ARE
W
T
30m UNFENCEnDePcorridor)
peli
CO
GAS ASCO pi
(G
GASCO
FENCED
PTW AREA
GASCO PTW Area:GASCO PTW required
GASCO PTW Interface Area:GASCO PTW required,
countersigned by ADCO
Shared PTW Interface
Area:- PTW of party
undertaking activity
required, countersigned by
other party
ADCO PTW Interface Area:ADCO PTW required,
countersigned by GASCO
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 36 of 42
APPENDIX B
ACTIVITY RISK ASSESSMENT (ARA) PROCESS OVERVIEW
WORK AGREED TO BE
NECESSARY
3.3
Categorise the Activity
3.4
3.4.4
PREVIOUSLY ASSESSED
ACTIVITY
NEW ACTIVITY
Any activity not previously
performed or assessed or one
to be reassessed
3.4.2
3.4.3
LOW-RISK ACTIVITY
Performed by Competent
personnel
Review assessment
Form ARA Team
NO
No formal recorded ARA
required
Carry out ARA
Is ARA
still relevant?
Are Controls
adequate?
& Residual Risk
acceptable
(ALARP)?
YES
Additional specific controls
(as appropriate)
NO
YES
Document
& Record
Reassess
Risks
& Controls
3.4.6
Asset Operator & Authorised
Maintenance/ Engineering
Authority to review and validate if
outside of the PTW Meeting forum
Originate Permit Documentation
3.4.1.1
Submit to Daily PTW Meeting for
Review & Validation
STOP
Take
time out
Permit Issue after Worksite
Preparations complete
Permit Acceptance and Worksite
Endorsement
Change in Worksite
conditions or Plant
Status
Conduct Toolbox Talk
Reassess Risks
& Controls
(if necessary)
3.4.1.1
7.1
3.5.4
YES
Implement Controls & Start Work
(Monitor worksite for change)
NO
Agreement by
Work Party to
proceed?
DO NOT
START
JOB
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 37 of 42
APPENDIX C
GASCO RISK ASSESSMENT MATRIX (RAM)
PROBABILITY
POTENTIAL CONSEQUENCES
A
Loss or Damage to Effect on the
Assets
Environment
Impact on
Reputation
RATING
Harm to People
1
Slight injury or
health effects
Slight
<US$ 10,000
Slight
Slight
2
Minor injury or
health effects
Minor
<US$ 100,000
Minor
Minor
3
Major injury or
health effects
Major
<US$ 500,000
Major
Major
Severe
National
Catastrophic
International
4
5
1 - 3 fatalities or
Severe
permanent total
<US$ 10,000,000
disability
>3 fatalities
Catastrophic
>US$ 10,000,000
B
C
D
E
Has occurred in Has occurred in Has occurred in Occurs several Occurs several times
worldwide industry another ADNOC
GASCO
times per year in per year in the same
but not in ADNOC Group Company
GASCO
location or operation
LOW
MEDIUM
HIGH
HOW TO USE THE RISK ASSESSMENT MATRIX (RAM)
1.
2.
3.
4.
5.
Assess the POTENTIAL CONSEQUENCES of the hazard for each of the four categories (People, Assets, Environment, Reputation)
Assess the PROBABILITY of these POTENTIAL CONSEQUENCES occurring for each of the four categories (People, Assets, Environment,
Reputation)
Classify the risk on the matrix for each of the four categories (People, Assets, Environment, Reputation) from the intersection of the chosen row
(POTENTIAL CONSEQUENCES) with the chosen column ( PROBABILITY)
In order to document the risk classification, first record the PROBABILITY (A - E), then the POTENTIAL CONSEQUENCES (1 - 5), and finally the
category to which the classification applies (People = P, Assets = A, Environment = E, Reputation = R ), for example C3P.
Based on the risk classification, identify and implement appropriate remedial action for each of the four categories (People, Assets, Environment,
Reputation) as indicated below:
•
LOW risk – manage for continuous improvement
•
MEDIUM risk – demonstrate that the risk is at a level that is as low as reasonably practicable (ALARP)
•
HIGH risk – take action to reduce the risk to a level that is as low as reasonably practicable (ALARP)
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 38 of 42
APPENDIX D
ACTIVITY RISK ASSESSMENT WORKSHEET GUIDELINES
Ref. No:
Date:
ACTIVITY RISK ASSESSMENT WORKSHEET
Work Activity:
Location:
Assessment Team
Approved by:
Position:
Separate the Work Activity
into individual tasks and
record in step sequence
Describe all hazards
identified and their
effects for each task.
Note: Additional
hazards may be caused
by interaction with other
work
Describe fully all controls applicable for
each hazard, e.g. if PPE is used as a
control, it must be specifically described.
List what might be
affected, i.e. People;
Assets; Environment;
Re putation
If a control can only be verified by
documentation then it must be available.
From * RAM, identify
the potential
consequence without
controls in place for
each hazard
Classify risk rating
from * RAM for
each hazard
From * RAM, identify
the potential
consequence with
controls in place for
eachhazard
*Residual
Risk Level
Low
Medium
High
Classify risk
rating from *RAM
for each hazard
All controls must be valid in that they
reduce consequence, probability or both.
From * RAM, identify
the probability, without
controls in place, for
each hazard
Risk Rating
Controls Measures and/or Recovery
Measures
Probability
Who or
What
might be
Harmed?
RESIDUAL RISK
Consequence
Hazard Description & Effect
CONTROLS
Risk Rating
Description of
Task Step
Probability
Step
No:
INITIAL
RISK
HAZARD
Consequence
TASK
From *RAM, identify
the probability, with
controls in place, for
each hazard
* From the RAM, record
the overall band for the
residual risk, i.e. Low.
Medium or High
This should be ALARP
* RAM = Risk Assessment Matri
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 39 of 42
APPENDIX E
Ref. No:
Date:
ACTIVITY RISK ASSESSMENT WORKSHEET
Work Activity:
Assessment Team
Location:
Approved by:
Position:
Risk Rating
Controls Measures and/or Recovery
Measures
Probability
Who or
What
might be
Harmed?
RESIDUAL RISK
Consequence
Hazard Description & Effect
CONTROLS
Risk Rating
Description of
Task Step
Probability
Step
No:
INITIAL
RISK
HAZARD
Consequence
TASK
Residual
Risk
Level
Low
Medium
High
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 40 of 42
APPENDIX F
KEY
RESPONSIBILITY
Step
1
2
3
ACTIVITY
Work Description and
Risk Assessment
2
3
4
5
Work Permit Lifecycle and Signatory Responsibilities
PICWS
Permit
Originator
1
End of Process
GASCO Permit to Work System
Authorised
Maint/ Eng.
Authority
Area Authority
Decision
Asset Operator
Activity/ Responsibility
Asset Holder
Preparation/ Start of Process
Asset Owner
Data Input
6
7
(see PTW System Manual, Chapter 3, Section 3.4.2)
LIFECYCLE STEPS AND ACTIVITY DESCRIPTION
Step No
1.
High
Risk?
Risk
ALARP
1.1
1.2
1.3
Permit Review and
Validation
ACTIVITY DESCRIPTION
On instruction of Maintenance/ Engineering Authority, Originator
prepares the Work Permit, describes work to be done and what
equipment is to be used
The Activity Risk Assessment (ARA) is reviewed and requirements
agreed with the appropriate authority (higher risks require higher
authority).
Supporting Permits and/ or Certificates originated if required
2.1
Maintenance/ Engineering Authority submits Work Permit to PTW
Meeting for review and agreement with the Asset Operator
2.2
Unplanned Work Permits submitted directly to Asset Operator for
review and agreement
3.
3.1
Asset Operator issues Work Permit to the Maintenance/ Engineering
Authority when worksite preparations are completed
2.
Permit Issue
4
Permit Acceptance
4.
4.1
Maintenance/ Engineering Authority accepts the Work Permit and
takes to Worksite for PICWS acceptance and signature
5
Worksite
Responsibility
5.
5.1
PICWS signs acceptance for Worksite Responsibility
6.
6.1
Asset Operator and Area Authority Endorse the Work Permit
6
Endorsements
Work
Complete?
Yes
7
Permit Closure
No
7.
6.2
PICWS initials ‘Work Start’ box in Endorsement section
6.3
When work stops, PICWS initials ‘Work Stop’ box of Endorsement
section and returns Work Permit to Maintenance/ Engineering Authority
6.4
At start of each new shift, further re-endorsement is required by the
Asset Operator, Area Authority and PICWS
7
When work is completed, or requires a new Work Permit, the Closure
box is completed. The Asset Operator authorises any equipment reinstatement and archives closed Work Permits
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 41 of 42
APPENDIX G
Work Control by Pipeline Division
Is work located
within 200m
NO
No Objection Certificate
(NOC) Issued by OPL
NO
Follow NOC Procedure
YES
Agree with other OPC Os the
Permit requirements
YES
Is work located
within 30m
YES
Is work in a
shared Pipelings
area?
NO
Is the work on
Pipeline itself?
YES
Is the Risk
Potential H or
M?
YES
Issue Permit to work
NO
Is there a
physical Risk
to the pipeline? e.g.
Digger, Drilling or
Bridging?
NO
YES
Issue ATW
Fix the position
and type of
barrier
NO
Does work
invole naked
flame?
NO
YES
Is work in a
Manifold or CRS
or SV?
NO
Is work in an area
Classifield as
Hazardous?
YES
NO
Does Risk
Assessment
indicate H or M?
YES
Issue ATW
Issue permit to work
NO
YES
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 3
Page 42 of 42
WORKSITE PREPARATIONS
CHAPTER 4
WORKSITE PREPARATIONS
CONTENTS
Section
Page
4.1 INTRODUCTION
2
4.2 STANDARD OF ISOLATION
2
4.2.1 Isolation Requirements
2
4.2.2 Establishment of Isolation Boundaries
3
4.2.3 Control of Equipment Preparation
3
4.2.4 Master Isolations
4
4.2.5 Minor Mechanical Isolations
5
4.3 PHYSICAL SECURING AND TAGGING OF ISOLATIONS
4.3.1 Requirements for Securing Valve Isolations
6
6
4.3.1.1 Immobilising Devices
6
4.3.1.2 Securing, Locking and Tagging
6
4.3.1.3 Common Isolations
4.4 LOSS OF ISOLATION RECORDS
7
4.5 EXTENDED PERIOD ISOLATIONS (EPI’s)
10
4.5.1 Documenting of EPI’s
10
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 4
Page 1 of 10
CHAPTER 4
WORKSITE PREPARATIONS
4.1 INTRODUCTION
Once the hazards associated with a particular job have been identified, it will be
necessary to consider how they can be separated or isolated from the equipment or
plant to be worked on. Flammable, toxic, pressurised, high temperature, or low
temperature fluids will normally have to be removed from the isolated plant before
working on it.
An essential ingredient of any Safe System of Work is the integrity of the isolation
procedure. Whilst the Work Permit identifies the isolation requirements it does not
provide the specific isolation details. These are to be documented and appended to
Permits as per existing, Plant specific, Isolation and re-instatement procedures.
All sites must ensure that the latter are controlled in accordance with specified
standards. These should be in compliance with the following.
4.2 STANDARD OF ISOLATION
4.2.1 Isolation Requirements
In general, Plants are built with isolation provisions an integral part of the design
(for example, DGS-0000-020) with the basic premise that the isolations prevent
leakage. In case this premise in practice is not confirmed additional controls are
required to manage risk to As Low As Reasonably Practicable
There are two main methods of isolation:
a) Positive isolation.
There are specific situations where positive isolation is required such as
Confined Space Entry and Hot Work with a Naked Flame. This means
incorporating the use of spades, spectacle blinds, or removable spools and
blind flanges. Spades and blinds must be fully rated; use of thin blinds must
be with site management approval. Positive isolations must be at the closest
point possible to the work.
b) Valved isolation
Under less hazardous situations a valved isolation may be applied:
i)
Double Block and Bleed.
•
Breaking of the hydrocarbon or toxic gas envelope should be against a
double block and bleed with the tightness of the isolation confirmed by
testing. Residual pressure must be zero at the work location.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 4
Page 2 of 10
•
If the breaking of the hydrocarbon or toxic gas envelope has to be done
against a single isolation valve a risk assessment is required involving as a
minimum Superintendent level. Tightness of the isolation must be confirmed by
testing and if not 100% tight, additional barriers are required.
ii) Single valve isolations
Single valve isolations may be used for less hazardous materials e.g. water and nitrogen.
•
When work is to be undertaken which requires isolation of equipment a formal
written scheme of isolation must be prepared with isolations documented on the
Isolation Confirmation Certificate The isolations must provide control of all
hazardous energy sources within the defined system and/or equipment isolation
boundaries including electrical power, process fluids, hydraulic, pneumatic,
thermal, chemical and mechanical systems. Where appropriate (e.g. where there
are no tag numbers or where the isolation is complex), a P&ID showing the
isolations must accompany the isolation procedure.
4.2.2 Establishment of Isolation Boundaries
The Operations Superintendent is responsible for ensuring that a comprehensive
suite of documented procedures is in place, which define the mechanical
(process) system isolations for all plant and equipment.
The Maintenance Superintendent is responsible for ensuring a comprehensive
suite of documented procedures is in place, which define the electrical and
instrument Isolation boundaries for plant equipment.
The Shift Controller is responsible for the authorisation of the isolation of
equipment to be worked on, and any action necessary to prepare the equipment
for safe working, such as de-pressurising or purging. He is also responsible for
the authorisation of de-isolations on completion of work.
4.2.3 Control of Equipment Preparation
The preparation and isolation / de-isolation of equipment can introduce particular
hazards. The Shift Controller must ensure that controls are in place to manage the
risks associated with these hazards at each step of the preparation, isolation and
de-isolation process.
4.2.4 Documentation of Isolations
4.2.4.1 Mechanical and Instrument Isolations
Where isolations form part of the preparations for work, there must be a clear
description of the isolation procedure, including a detailed list of all items (e.g.
valves, spades, blinds, pipework removed, blank flanges fitted, vents and
drains opened, breakers racked out, etc.), utilised in the isolation. These are
to be documented on the Isolation Confirmation Certificate
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 4
Page 3 of 10
Where appropriate (e.g. where there are no tag numbers or where the
isolation is complex), a P&ID showing the isolations must accompany the
isolation procedure.
The Isolation Confirmation Certificate together with any P&IDs used to
show isolations, must be kept in the PCF with the copies of the relevant
Work Permits.
Any changes to the isolation procedure or isolation boundaries are to be
approved and initialled, after the relevant section of the procedure, by the
Maintenance/ Engineering Authority and the Shift Controller. This should
be done prior to making any change in the isolation.
4.2.4.2 Electrical Isolations
The document for recording electrical isolation and de-isolation
operations, for the purpose of the PTW System, shall be the Isolation
Confirmation Certificate. (See Chapter 5, Section 5.7) The use of any
Sub-Station/ Switching Logs and Switching Programmes required for by
the Electrical Safety Rules, to record isolations and de-isolations, are
additional to the PTW System requirement.
The only exception to the rule that specifies the need for an Electrical
Isolation on an Isolation Confirmation Certificate to be raised is when an
electrical isolation is required for low voltage (<50 volts) electrical work.
An Electrical Person, having the required level of competence, may carry
this out providing he has been duly authorized by the Senior Electrical
Engineer to undertake this type of work.
4.2.5 Master Isolations
A Master Isolation may be used to establish isolation boundaries for major
tasks, which encompass more than one process system and/or piece of
equipment. This is so that a number of tasks can be undertaken within a
single boundary. Recommended standards for controlling work under A
Master Isolations are as follows:
(i) Each Master Isolation Boundary should be clearly defined in a written
procedure. The specific isolation details covered in the procedure should
indicate the isolated and de-isolated position of each isolation device and
the equipment and/ or system affected.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 4
Page 4 of 10
The Operations Co-ordinator has the responsibility for approving this procedure.
Final authorisation for its use rests with the Operations Superintendent.
(ii) Control of the Permits in use within the boundary is to be maintained by the
Shift Controller.
(iii) When a Master Isolation is in place, the Shift Controller is to ensure that all
Permits in use within the boundary have been closed out before the Master
Isolation integrity is compromised, i.e. prior to allowing any de-isolations to be
undertaken.
4.2.6 Minor Mechanical Isolations
The recording of isolation details is not mandatory for Small Bore Instrument
Mechanical Isolations carried out by an Instrument Person, assessed to the
required level of competence, provided ALL the following conditions are met:
(i) The work is minor routine maintenance work, i.e. work that is considered to
present no more risk than that associated with achieving a physical
isolation;
(ii) A Work Permit exists to cover the work, endorsed by the Shift Controller and
Area Operator;
(iii) The isolations are listed on a suitable document to the satisfaction of the
Shift Controller;
(iv) The isolations are of such a minor nature that they will not degrade the
integrity of any Safety/ Emergency System;
(v) The work to be done under the isolation will be undertaken by the person
who applied the isolation, who will not leave the worksite whilst the isolation
is in place. If the isolation is to remain in place beyond a single shift, then the
isolation details must be recorded and the isolation points secured and
labelled.
(vi) The isolation does not form part of an isolation boundary for other work;
4.3 PHYSICAL SECURING AND TAGGING OF ISOLATIONS
4.3.1 Requirements for Securing Valve Isolations
Valves require to be immobilised in such a manner that they cannot be
inadvertently operated. In this case the interference with the isolation will be
immediately obvious.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 4
Page 5 of 10
4.3.1.1 Immobilising Devices
The range of valves fitted on GASCO facilities would require a number of
different methods of Immobilisation. Some valves may already have fixed,
immobilising devices fitted, e.g. Castell Locks, Ellis Locks, etc. As it is not
practical to provide such devices for all valves, the recommended method is to
use simple securing mechanisms with locking and tagging.
4.3.1.2 Securing, Locking and Tagging
Multi part labels, as shown below, are to be utilized to identify isolation and
break points. Each Vice President for Plant and Pipelines is responsible for
developing detailed procedures for the labels.
a) Securing
Valves and other isolation devices required to be physically secured in such a
manner that they cannot be inadvertently operated without destroying the
securing mechanisms (e.g. chain and lock arrangements). The preferred
method is to use Red and white high strength polycarbonate chain. This has
good visibility, is easily handled and secured, and is sufficiently strong to provide
adequate integrity of the isolation.
b) Locking
A tamper-proof seal to be used to lock the securing mechanism or where
appropriate to directly lock the immobilizing device in position is the nylon Grip
Rip seal
c) Isolation Tagging
A visible Isolation Tag (see Fig.1) is to be used for valve isolations which is:
a)
Made up of material which cannot be torn off easily.
b)
Red in colour printed with a unique number on each of 3 parts part so that
the stubs and counterfoils can be kept with isolation details in the PCF
when the label is attached to the isolation point.
c)
Capable of being written on with a permanent marker.
d)
Fitted with large secure eyelet to enable the sealing device to fit through
it, thus making it an integral part of the securing arrangement.
e)
Identified with the Work Permit number related to the isolation, and the
Labels own unique serial number on all the three parts of the label.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 4
Page 6 of 10
!
Figure: 1
Spades, spectacle blinds and blanks will be identified by a similar design label,
but Yellow in colour (see Fig.2).
!
Figure: 2
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 4
Page 7 of 10
Spade and Blank insertion is generally the preparatory activity for other work
and is identified in the approved Method Statement supporting a Work Permit
and Isolation Confirmation Certificate
To assist in the identification of spading points, and to identify the spacers that
may be removed when a spade is fitted; a blue spade location tag is attached to
the spading point at the planning stage (see FIG.3). When the spade is fitted,
the Blue tag is attached to the removed spacer. This ensures the spacer is
refitted into correct location. Spade location tags do not have stub and
counterfoil portions.
!
Figure: 3
d)
Re-instatement of Process Line-Breaks
All flanges/joints above 10” that have been ‘broken’ by Maintenance Department
are required to be torqued /tensioned. These are to be positively identified in order
to record the location, re-instatement and final pressure testing of the joint.
Operations will maintain a ‘Joint Broken’ register in the to control room and record
compliance to these requirements. A unique 3-part, multi-colored, Joint Assembly
Tag, is to be utilized for this purpose (see Fig.4)
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 4
Page 8 of 10
!
Figure: 4
4.3.1.3 Common Isolations
Where a single valve is used as isolation for more than one isolation boundary,
a tag label relating to each Work Permit is to be applied to the device. In this
situation the securing device fitted SHALL NOT be removed until the last
isolation label applicable to the valve or spade is removed.
4.4 LOSS OF ISOLATION RECORDS
Where isolation is found with some, or all, of its documentation missing, an
investigation will be required before the isolation can be removed. The following
procedure should be followed:
(i) The Shift Controller is to double-check the Permit, in the PCF and the archive
for the relevant documentation;
(ii) The Area Authority is to carry out an onsite check of the system against a P&ID
for any other isolations, for valves not in their normal operating position, or
breaks/open ends in the system;
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 4
Page 9 of 10
4.5 EXTENDED PERIOD ISOLATIONS
Extended Period Isolations (EPI's) are isolations, which are required to remain in
place although no work is being carried out within their boundary. They may be
required for two main reasons
(i) Where work has commenced but is, or is likely to be, suspended for a period
exceeding the validity period of the Work Permit, for example, when awaiting
spares for a repair;
(ii) Where an item of equipment becomes redundant and is to be isolated pending
a Plant Change Proposal to remove it or provide a more permanent means of
isolation.
4.5.1 Documenting of EPI's
The procedure for the documenting of EPI’s is as follows:
(i) The Shift Controller is to record the EPI in an EPI Register in the PCF. The
white copies of the Work Permit and the Electrical Isolation Certificate and/
or other isolation details are to be retained in the EPI section of the Permit
Rack in the PCF.
(ii) When it becomes possible for work to restart within the EPI boundary the
Originator is to raise a new Work Permit. The isolation details are then to be
attached to the new Work Permit, and handled by the Originator in the
normal manner.
(iii) The Shift Controller will record the fact that the EPI has been cancelled in
the EPI Register.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 4
Page 10 of 10
COMPLETION OF THE WORK PERMIT,
SUPPORTING PERMITS,
CERTIFICATES AND PIPELINE
AUTHORISATION TO WORK
CHAPTER 5
COMPLETION OF THE WORK PERMIT, SUPPORTING PERMITS,
CERTIFICATES AND PIPELINE AUTHORISATION TO WORK
CONTENTS
Section
Page
5.1 COMPLETION OF THE WORK PERMIT
2
5.2 COMPLETION OF GAS TEST CERTIFICATE
9
5.3 COMPLETION OF HOT WORK PERMIT, CATEGORY 1
10
5.4 COMPLETION OF HOT WORK PERMIT, CATEGORY 2
14
5.5 COMPLETION OF CONFINED SPACE ENTRY CERTIFICATE
18
5.6 COMPLETION OF EXCAVATION PERMIT
22
5.7 COMPLETION OF AN ISOLATION CONFIRMATION CERTIFICATE
26
5.8 COMPLETION OF RADIOGRAPHY PERMIT
29
5.9 COMPLETION OF PIPELINE AUTHORISATION TO WORK (ATW)
32
ILLUSTRATIONS
Figure
Page
5.1 Work Permit
37
5.2 Gas Test Certificate
38
5.3 Hot Work Permit, Category 1
39
5.4 Hot Work Permit, Category 2
40
5.5 Confined Space Entry Certificate
41
5.6 Excavation Permit
42
5.7 Isolation Confirmation Certificate
43
5.8 Radiography Permit
44
5.9 Pipeline Authorisation to Work (ATW)
45
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 1 of 45
CHAPTER 5
COMPLETION OF THE WORK PERMIT, SUPPORTING PERMITS AND
CERTIFICATES
5.1 COMPLETION OF THE WORK PERMIT
This procedure should be read whilst referring to the Work Permit (see Chapter 5,
Figure 5.1). The responsibilities of the Permit of Work Signatories are explained in
Chapter 2, Section 2.2.
5.1.1 Work Description and Risk Assessment
The work order number should be entered into the space provided
Box 1a. Identification of the Task and its location
Permit Originator is to enter:
•
An overview of the task so that is easily visible from the Work
Permit’s slot position in the Permit display rack, and the date that the
Work Permit is required;
Box 1b. The Originator enters the Location/ Tag number and Area/ Worksite in
order to clearly identify the equipment and area where the work is to
take place. The Originator ticks the Boxes relevant for the Area (and if
he does not know, then the Asset operator will tick the boxes).
Box 2
Work Description and Equipment
The Originator is to describe the work in summary form but containing
sufficient detail so that appropriate worksite preparations can be made.
Any special equipment to be used, especially where it may introduce a
threat or hazard, is to be entered. Reference may be made to
engineering method statements and if this is the case the engineering
method statement should be attached to the Permit.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 2 of 45
Box 3
Particular Hazards and Special Precautions
When the Originator undertakes the Activity Risk Assessment (ARA)
process and subsequently the review with the Validator, hazards may
be identified that require to be highlighted on the Work Permit.
Provision is made for this in Box 3.
Whenever a protective function is being disabled or a Safety/
Emergency system being isolated, it is mandatory to enter in Box 3 the
controls necessary to prevent escalation should a hazard be released.
The Originator will also enter the category of worksite presence by the
PICWS, after agreement with the Asset Operator during the PTW
Planning Meeting. This is a worksite control.
Box 4
Worksite Supporting Documents
Box 4a The Originator enters the reference number of any supporting Permits
or Certificates required as a result of the ARA process These
supporting documents will accompany the Work Permit when
presented to the daily PTW meeting, or, where the work is of an urgent
unplanned nature, directly to the Asset Operator.
Box 4b The Originator enters the reference number of any related Work
Permits including the Trade that the related Work Permit has been
issued to. Where the Work Permit is a continuation then the previous
Work Permit reference number is also entered.
Box 4c The Originator is to tick the relevant Boxes for any other supporting
documentation that is to be submitted with the Permit.
Box 5
Specific HSE Requirements
The Originator will tick the relevant Boxes in the ‘required’ column of
Box 5 thus indicating the HSE equipment/ resources necessary as
precautions for the work. These will have been identified during the
Activity Risk Assessment step
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 3 of 45
Box 6 Work Permit Originator
The Originator completes Box to signify the end of the origination steps.
It should be noted, however, that the subsequent Permit review,
Validation and Issue steps might identify a need to add to Boxes 3, 4 or 5.
If this is the case, the Originator must initial any such change to signify
that he is aware of them and accepts them.
5.1.2 Permit Review and Validation
Box 7 Worksite Preparations
When the Work Permit is presented to Operations, the Asset Operator
(Operations Co ordinator or his deputy) will decide what preparation and
isolations are to be made on the equipment (refer to Chapter 4, Worksite
Preparations) and tick the required Box.
When the preparation is complete the Area Operator or Assistant Shift
controller will initial the check Box.
In the case of Protective Function Disable or Safety Systems isolations,
the Asset Operator ticks the requirement in Box 7. The Shift Controller
records the detail in the Trip and Safety System Defeat Register, which is
held in the Main Control Room, when the protective function is disabled.
Box 8 The Maintenance/ Engineering Authority completes Box 8. When more
than one Maintenance/ Engineering Authority is involved, the
Maintenance/ Engineering Authority who signs does so on behalf of the
others and assumes overall responsibility for the permitry aspects.
Box 9 The Asset Operator (the Operations Co-ordinator or Shift Controller)
completes Box 9. This validation step is normally completed at the Permit
Planning Meeting when the Activity Risk Assessment (ARA) is reviewed.
The Asset Operator then sends the Validated Work Permits to the PCF for
display in the Validation slot of the display rack.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 4 of 45
5.1.3 Permit Issue by Operations
Box 10 Once it is confirmed that:
(i). The worksite preparations are complete, and
(ii). There is no conflict with any other Work Permit or work activity.
The Shift Controller completes Box 10.
(If the work requires any type of isolations, then ICC certificate must be
completed prior permit issue).
When the work involves an interface activity (defined in Chapter 3,
Section 3.3.5) or the work involves a higher degree of risk (see
Chapter 3, Section 3.4.3) then a countersignature is required, by the
other Asset Operator or the Asset Holder, in the space provided in Box
10.
5.1.4 Permit Acceptance by Maintenance/Engineering Authority
Box 11 The Maintenance/ Engineering Authority accepts the Permit from the
Shift Controller and completes Box 11.
5.1.5 Worksite Responsibility
Box 12 The Maintenance/ Engineering Authority will enter the name of the
Person in Charge of the Worksite (PICWS) in Box 12(a). The PICWS
will sign to acknowledge he understands his responsibilities after Area
Authority endorsement at the worksite.
Normally the PICWS will remain in charge for the duration of the job,
but to cater for a change in the designated PICWS, extra spaces are
provided in Box 12(b). Also if there is more than one designated
PICWS, e.g. to cater for shift working, then the name of the additional
PICWS should be entered in Box 12(b). In both cases the PICWS must
sign Box 12(b).
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 5 of 45
5.1.6 Endorsement for the Continued Safety of the worksite
Box 13 The Maintenance/ Engineering Authority will take the top (white) copy to
the worksite for endorsements in Box 13 by the Area Operator and
PICWS. The PICWS will display the Permit at the worksite. (Note for
Pipelines the endorsement may take place in the PCF)
The 2nd (yellow) copy is retained in the Permit Control Facility and
visibly displayed by the Shift Controller, or Assistant Shift Controller, in a
slot in the Endorsed section of the display rack.
At the end of the Engineering work period, the PICWS initials the space
in Box 13 (Work Stop) on the top (white) copy displayed at the worksite
to state that work has stopped. The PICWS takes the top (white) copy to
the Maintenance/ Engineering Authority for return to the Permit Control
Facility.
The original and the copy are now brought together by the Operations
Shift Co-ordinator and placed in a slot in the Suspended section of the
PCF display rack, with the white top (white) copy uppermost. This allows
Operations Department to gain an overview of Suspended Permits and
the following days commitments.
Box 13 Shift Handovers:
When a shift change occurs within an Engineering work period (e.g. 8
hour shifts) the work must stop until both the oncoming Asset Operator
and Area Authority have endorsed the Work Permit prior to endorsement
of the PICWS
Further Endorsements:
Where work has to continue on the following day the Asset Operator will
again check for conflict and approve the work continuation by initialing
Box 13. The top (white) copy is then issued at the Permit Control Facility
to the Maintenance/ Engineering Authority, who again takes it to the
worksite for endorsements as described above
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 6 of 45
5.1.7 Permit Closure
Box 14a When the work is completed, the PICWS will initial the space
provided in Box 14a and take the copy to the Maintenance/
Engineering Authority. The Maintenance/ Engineering Authority takes
the copy to the Permit Control Facility and completes Box 14a.
Box 14b The Area Authority will confirm the worksite conditions and initial the
space in Box 14b for the worksite.
The Asset Operator completes Box 14b, including the statements on
isolations.
Box 15a If the work is not completed, the PICWS will initial the space provided
in Box 15a and take the top copy to the Maintenance/ Engineering
Authority. The Maintenance/Engineering Authority takes the copy to
the PCF and completes Box 15a indicating the work status.
Box 15b If the Maintenance/ Engineering authority has indicated in Box 15a
that the worksite has been cleared the Area authority will confirm the
fact and sign Box 15b. The Asset Operator then completes Box 15b.
5.1.8 Archiving
After close-out, the Asset Operator is to file the original (white) copy of all
Permits, together with the top copies of any supporting Permits or Certificates,
as per archiving requirements (see Chapter 8).
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 7 of 45
5.2
COMPLETION OF THE GAS TEST CERTIFICATE
This Section should be read whilst referring to the Gas Test Certificate (See
Chapter 5, Figure 5.2).
If not specified by the Operations Co-ordinator at the Daily PTW meeting, the Shift
Controller should complete the Gas Test Certificate sections, relating to:
•
•
The Gas Testing Requirements;
•
The gas or gases to be tested for Worksite Certification.
The Test Frequency;
The results of the gas test will be entered on to the Gas Test Certificate which is
on the backside of the Work Permit, at the worksite, by the Authorised Gas Tester,
and (if the Area Operator is not undertaking the gas test) advise the Area Authority
of the result.
If the Area Authority is not undertaking the gas testing, then he must initial the
Certificate in the space provided to show he is aware of the test result(s).
For higher risk activities, such as Confined Space Entry and Hot Work-Category
1, the Issuing Authority is to witness the initial gas test prior to the issue of the
supporting Permit or Certificate.
Subsequent gas test results, as stipulated in the Test Frequency requirements
section, are to be recorded in the Additional Gas Test Record Section.
5.2.1 Archiving
After close out the Gas Test Certificate will be automatically archived with the
Work Permit
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 8 of 45
5.3
COMPLETION OF HOT WORK PERMIT, CATEGORY 1
This Section should be read whilst referring to the Hot Work Permit, Category 1
(See Chapter 5, Figure 5.3)
5.3.1 Work Description and Risk Assessment
Any previous Hot Work Permit, Category 1, is to be entered
in the space provided.
Box 1a Identification of Task and its Location
The Originator will enter in Box 1a a description of the work for which
the Hot Work Permit is raised. It will be more specific than the
associated task description on the Work Permit and it will be the
description visible in the Permit display rack in the PCF.
The date that the Hot Work Permit is required is entered. This allows
planning of the preparatory work by Operations.
Box1b The Originator completes Box 1b, specifically referring to the location,
worksite and Area Classification in which the Hot Work is taking place.
Box 2
Work Description
The Originator completes Box 2, describing only the Hot Work aspects
in the Work Description. The sources of ignition that are being
introduced (e.g. welding) should be stated.
The associated Work Permit number should be referenced in the space
provided.
Box 3
Worksite Preparations
The Hot Work Permit, along with its associated Work Permit, is taken to
the daily PTW Meeting, where the Maintenance/Engineering Authority
and Operations Co-ordinator review Boxes 1 and 2, and agree what
worksite preparations are appropriate and tick the first column in Box 3.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 9 of 45
Box 4 Specific HSE Requirements
At the PTW Review Meeting the Maintenance/ Engineering Authority and
Operations Co-ordinator also agree the specific HSE equipment requirements
and tick the first column in Box 4a. Further, they will agree the PPE requirements
and tick the first column in Box 4b.
Box 5 Particular Hazards and Special Precautions
The Operations Issuing Authority completes Box 5, if any requirements are
identified over and above those already stated in Boxes 3 and 4.
The Issuing Authority must enter the category of PICWS presence. In Restricted
Areas, after agreement with the Asset Holder. The normal category of worksite
presence will be ‘A’ for Restricted Areas but in Unrestricted Areas will be
dependent on the risk.
The Hot Work Permit remains with Operations in the Permit Control Facility,
along with (but behind) its associated Work Permit, until it is ready for issue.
5.3.2 Permit Review and Issue
Box 6 In a Restricted Area, when the worksite preparations are complete, and the work
is ready to start, the Asset Holder will visit the workplace to personally confirm
that the requirements of Boxes 3, 4 and 5 are complete and initial the
appropriate spaces in Boxes 3 and 4. He will then sign Box 6.
If the Area is classified as Unrestricted then the Asset Operator for that area will
carry out the confirmation checks and sign Box 6.
If an interface activity is identified (see Chapter 3, Section 3.3.5) then a counter
signature is required from the Asset Operator of the other area.
For Pipelines only, because of the geographical practicality, the Asset Operator
may sign box 6 providing the Asset Holder has reviewed the Hot Work Permit
and authorized the Asset Operator to sign on his behalf
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 10 of 45
5.3.3 Permit Acceptance by Maintenance/Engineering
This Section should be read whilst referring to the Hot Work Permit, Category 1
(See Chapter 5, Figure 5.3)
Box 7
The Maintenance/ Engineering Authority now completes Box 7 and
accepts the Hot Work Permit, Category 1
5.3.4 Endorsement for Continued Safety of the Worksite
Box 8
The Maintenance/ Engineering Authority will take the top (white) copy to
the worksite for endorsements in Box 8 by the Area Operator and
PICWS. The PICWS will display the Hot Work Permit at the worksite, on
top of the worksite copy of the Work Permit, in the plastic folder
provided for this purpose.
The 2nd (yellow) copy is retained in the Permit Control Facility and
visibly displayed in front of the associated copy of the Work Permit by
the Shift Controller.
At the end of the Engineering work period, or when the hot work has
been completed, the PICWS initials the space in Box 8 on the top copy
displayed at the worksite to state that the Hot Work has stopped. The
PICWS takes the top (white) copy and the Associated Work Permit
(white) copy to the Maintenance/Engineering Authority for return to the
Permit Control Facility.
The Shift Controller (or Assistant Shift Controller) now assembles the
original plus copy with the white copy on top, behind the copies of the
Work Permit. This allows Operations Department to gain an overview of
the Permit Status.
Shift Handovers: When a shift change occurs within an Engineering
work period (e.g. 8 hour shifts), the Hot Work must stop until both the
oncoming Shift Controller and Area Operator have endorsed the Hot
Work Permit and its associated Work Permit (See also Chapter 2,
Section 2.4).
Where work has to continue next day, the Shift Controller will check for
conflict and approve the work continuation by initialing Box 8. The top
(white) copy is then issued at the Permit Control Facility to the
Maintenance/ Engineering Authority, who again takes it to the worksite
for endorsements as described above.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 11 of 45
5.3.5 Closure of the Permit
Box 9a When the work is completed, or the endorsement boxes full, the PICWS
initials the space provided in Box 9a and takes the top (white) copy to the
Maintenance/ Engineering Authority.
The Maintenance/ Engineering Authority takes the top (white) copy to the
Permit Control Facility. The Shift Controller assembles the original and copy
of the Hot Work Permit and the Maintenance/Engineering Authority
completes Box 9a.
Box 9b The Area Authority initials space in Box 9b. The Shift Controller completes
Box 9b, including the continuation (if necessary).
5.3.6 Archiving
After close-out, the Shift Controller files the original (white) copy of the Hot Work
Permit, together with the copy of the Associated Work Permit and any other
supporting Permits or Certificates, as per archiving requirements (see Chapter 8,).
Should work be continuing under the associated Work Permit, the top (white) copy of
the (now closed) Hot Work Permit should remain with (but behind) the copies of the
Work Permit, in the PCF display rack, until it too is closed out and requires to be
archived.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 12 of 45
5.4 COMPLETION OF HOT WORK PERMIT, CATEGORY 2
This Section should be read whilst referring to the Hot Work Permit, Category 2
(See Chapter 5, Figure 5.4).
5.4.1 Work Description and Risk Assessment
The unique number of any previous Hot Work Permit, Category 2 is
to be entered in the space provided.
Box 1a Identification of Task and its Location
The Originator will enter in Box 1(a) a description of the work for which the
Hot Work Permit is raised. It will be more specific than the associated task
description on the Work Permit and it will be the description visible in the
Permit display rack in the PCF.
The date that the Hot Work Permit is required is entered. This allows
planning of the preparatory work by Operations.
Box1b The Originator completes 1b, specifically referring to the location,
worksite and Area Classification in which the Hot Work is taking
place.
Box 2
Work Description
The Originator completes Box 2, describing only the Hot Work
aspects in the Work Description. The sources of ignition that are
being introduced (e.g. diesel engine) should be stated.
The associated Work Permit number should be referenced in the
space provided.
Box 3
Worksite Preparations
The Hot Work Permit, along with its associated Work Permit, is
taken to the daily PTW review meeting, where the Maintenance/
Engineering Authority and Operations Co-ordinator review Boxes
1 and 2, and agree what worksite preparations are appropriate and
tick the first column in Box 3.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 13 of 45
Box 4 Specific HSE Requirements
At the PTW review meeting the Maintenance/ Engineering Authority and
Operations Co-ordinator will agree the specific HSE equipment requirements
and tick the first column in Box 4a. Further they will agree the PPE
requirements and tick the first column in Box 4b.
Box 5 Particular Hazards and Special Precautions
The Issuing Authority completes Box 5, if any requirements are identified over
and above those already stated in Boxes 3 and 4.
The Issuing Authority must enter the category of PICWS presence after
agreement with the Maintenance/ Engineering Authority. The category will be
dependent on the risk.
The Hot Work Permit remains with Operations in the Permit Control Facility,
along with (but behind) its associated Work Permit, until it is ready for issue
5.4.2 Permit Review and Issuing by Operations
Box 6 When satisfied that the worksite preparations are complete, and the work is
ready to start, the Shift Controller can complete Box 6.
If an interface activity is identified (see Chapter 3, Section 3.3.5) then a
counter signature is required from the Asset Operator of the other area.
5.4.3 Permit Acceptance by Maintenance/ Engineering
Box 7 The Maintenance/Engineering Authority now completes Box 7 and accepts
the Hot Work Permit, Category 2
5.4.4 Endorsements for Continued Safety of the Worksite
Box 8 The Maintenance/ Engineering Authority will take the top (white) copy to the
worksite for endorsements in Box 8 by the Area Operator and PICWS. The
PICWS will display the Hot Work Permit at the worksite, on top of the worksite
copy of the Work Permit, in the plastic folder provided for this purpose.
The 2nd (yellow) copy is retained in the Permit Control Facility and visibly
displayed in front of the associated (yellow) copy of the Work Permit. The Shift
Controller must arrange this step.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 14 of 45
At the end of the Engineering work period, or when the hot work has been
completed, the PICWS initials the space in Box 8 on the top (white) copy
displayed at the worksite to state that the Hot Work has stopped. The
PICWS takes the top copy and the Associated Work Permit (white) copy to
the Maintenance/ Engineering Authority for return to the Permit Control
Facility.
The Shift Controller (or Assistant Shift Controller) now assembles the
original plus copy, with the white copy on top behind the copies of the Work
Permit. This allows Operations Department to gain an overview of the
Permit Status.
Shift Handovers: When a shift change occurs within an Engineering work
period (e.g. 8 hour shifts) the Hot Work must stop until both the oncoming
Shift Controller and Area Operator have endorsed the Permit.
Where work has to continue next day, the Shift Controller will check for
conflict and approve the work continuation by initialing Box 8. The top copy
is then issued at the Permit Control Facility to the Maintenance/ Engineering
Authority, who again takes the top copy to the worksite for endorsement by
the Area Operator, display and instruction to the PICWS.
5.4.5 Closure of the Permit
Box 9a When the work is completed, or the endorsement boxes full, the
PICWS initials the space provided in Box 9a and takes the top
(white) copy to the Maintenance/ Engineering Authority.
The Maintenance/ Engineering Authority takes the top (white) copy
to the Permit Control Facility. The Shift Controller assembles the
original plus copy of the Hot Work Permit and the Maintenance/
Engineering Authority completes Box 9a.
Box 9b The Area Authority initials the space in Box 9b. The Shift Controller
completes Box 9b, including the continuation (if necessary).
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 15 of 45
5.4.6 Archiving
After close-out, the Shift Controller files the original (white) copy of the Hot Work
Permit, together with the top copies of the Associated Work Permit and any other
supporting Permits or Certificates, as per archiving requirements (see Chapter
8,).
Should work be continuing under the associated Work Permit, the top (white)
copy of the (now closed) Hot Work Permit should remain with (but behind) the
copies of the Work Permit, in the PCF display rack, until it too is closed out and
requires to be archived.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 16 of 45
5.5 COMPLETION OF CONFINED SPACE ENTRY CERTIFICATE
This Section should be read whilst referring to the Confined Space Entry
Certificate (See Chapter 5, Figure 5.5).
5.5.1 Entry Description and Risk Assessment
The originator enters the number of any previous entry certificate.
Box 1a The Originator enters in Box 1a the exact description of the
Confined Space to be entered.
Box 1b The Originator describes in summary form in Box 1b the reason
for the confined space entry.
Box 2
The Originator enters into Box 2 the details of any associated
Work Permits. Note that the issue date and closure date can only
be entered by the Asset Operator, as operations are responsible
for issuing and closing Permits.
Box 3
The Originator signs and dates Box 3.
Following origination of the Certificate, the Engineering/
Maintenance Authority will present it at the PTW Review Meeting
for discussion, specifically Boxes 1 to 6.
Box 4
The Asset Operator initials the applicable worksite preparations
as complete.
Box 5
The Asset Operator initials the specific HSE requirements as
complete.
Box 6
The Asset Operator completes Box 6 by recording any particular
hazards and special precautions not already covered in previous
Boxes. The category of worksite presence agreed at the PTW
Review Meeting is entered.
Note that category C is not an option for Confined Space
Entry.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 17 of 45
5.5.2 Certificate Review and Issue
Box 7
Where the confined space is safe for entry without breathing apparatus
then the Asset Operator may issue the Confined Space Entry Certificate.
Where the confined space is not safe for entry and requires breathing
apparatus to be worn the Asset Holder will issue the Certificate.
The Maintenance/ Engineering Authority will take the top (white) copy to
the worksite for display and instruction of the PICWS. The PICWS will
display the Confined Space Entry Certificate at the worksite (at the point
of entry to the confined space), on top of the worksite copy of the Work
Permit, in the plastic folder provided for this purpose.
The 2nd (yellow) copy is retained in the Permit Control Facility and
visibly displayed in front of the associated (yellow) copy of the Work
Permit. The Shift Controller must arrange this step.
5.5.3 Controlling Entry to the Confined Space
The number of persons permitted to enter the confined space will be dependent
on the nature of the enclosed space and the degree of risk associated with the
entry activity. It should however be kept to the minimum required to execute the
task. The Risk Assessment should determine what restrictions on personnel entry
are to be imposed and include precautions and controls for entry under the
specific HSE requirements detailed in Box 5 of the Confined Space Entry
Certificate.
Trained and competent stand-by personnel must be in attendance outside the
confined space entry point, to control and record the numbers of people entering
the confined space and to initiate a first response in the event of an emergency.
The back of the top (white) copy of the Confined Space Entry Certificate has a
table to record personnel in and out of the confined space. It is the responsibility
of the nominated Stand-by Person to maintain this record. It is permissible to
attach additional copies of the record sheet to the Confined Space Entry
Certificate should more spaces be required.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 18 of 45
If the Stand-by Person is required to leave the worksite, all personnel are to be
withdrawn from the confined space and “DO NOT ENTER” warning notices
posted and a physical barrier placed, at the point of entry.
Shift Handovers: When a shift change occurs within a Maintenance/
Engineering work period (e.g. 8 hour shifts) the oncoming Shift Controller (the
Asset Operator) is to endorse the Confined Space Entry Certificate to confirm
that there has been no change to the confined space entry conditions (see also
Chapter 2, Section 2.4).
At the end of the Maintenance or Engineering work period, the PICWS takes the
top copy to the Maintenance/ Engineering Authority who returns the top copy to
the Permit Control Facility along with its associated Work Permit. This allows
Operations Department to gain an overview of the following days commitments.
5.5.4 Endorsements for Continued Entry to the Confined Space
Where work has to continue into another shift, or the next day, the
Asset Operator checks for conflict and approves the work continuation
by endorsing Box 8 of the Confined Space Entry Certificate.
Box 8
NB. Endorsement is only permitted once the gas testing
requirements, as stated in the accompanying Gas Test Certificate,
have been fulfilled.
He then hands the Certificate to the Maintenance/ Engineering
Authority, along with the associated Work Permit, who again takes the
top copy to the worksite for display and instruction to the PICWS.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 19 of 45
5.5.5 Closure of the Certificate
Box 9a When the work is completed, or the Confined Space Entry Certificate
requires renewal, the PICWS initials the space provided in Box 9a and
take the top copy to the Maintenance/ Engineering Authority. The
Maintenance/ Engineering Authority takes the top copy to the Permit
Control Facility, assembles the original and copy and completes Box 9a.
Box 9b The Asset Operator completes Box 9b, including the continuation (if
necessary).
5.5.6 Archiving
After close-out, the Shift Controller files the original (white) copy of the Confined
Space Entry Certificate, together with the top copies of the associated Work
Permit and any other supporting Permits or Certificates, as per archiving
requirements (see Chapter 8, Section 8.1.5.2).
Should work be continuing under the associated Work Permit, the top (white)
copy of the (now closed) Confined Space Entry Certificate should remain with (but
behind) the copies of the Work Permit, in the Permit Control Facility display rack,
until it too is closed out and requires to be archived.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 20 of 45
5.6
COMPLETION OF EXCAVATION PERMIT
This procedure should be read whilst referring to the Excavation Permit (See
Chapter 5, Figure 5.6).
5.6.1 Safe Work Practices in Excavations
Confined Spaces: Due to the potential presence of heavier than air,
Hydrogen Sulphide or hydrocarbons a Confined Space Entry Certificate
must be issued for all excavations over 1.5 metres deep, irrespective of
depth to width ratio, within Restricted Areas where these gases are
present, or are likely to be present.
A Confined Space Entry Certificate is also required for excavations over
1.5 metres deep, irrespective of depth to width ratio, in Unrestricted
Areas, where buried hydrocarbon pipelines are exposed.
In both cases, Oxygen, Hydrogen Sulphide and combustible gas testing
must be conducted as part of the Confined Space Entry Certificate
conditions.
In addition, a Confined Space Entry Certificate is required in all areas for
excavations over 1.5 metres, having an excavation depth to excavation
width ratio of more than 2.0 or when the access and egress are limited
requiring further controls.
Road Excavations: Traffic flow for emergency access shall be
maintained at all times (alternative arrangements may be required).
During road crossing excavations, a responsible person shall be
delegated to control traffic. In the case of road blocking, the Asset
Operator should be consulted as to possible alternative access routes.
Use of Mechanical Excavators: Mechanical excavators shall not be
used when the presence of underground pipes, cables, vessels or
structures are known, or expected within 3 metres of the excavation,
where the risks have been adequately assessed, mechanical excavations
can be undertaken to a distance of 1 metre from pipework/ structures.
In addition, Risk management must include marking and exposing the
pipework/ structure to be excavated, suitably protecting it from damage
where appropriate and providing close and competent supervision. The
identified risks and action to be taken must be discussed and
communicated during the Toolbox Talk.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 21 of 45
5.6.2 Excavation Details and Risk Assessment
The serial number of the Excavation Permit is a unique pre-printed number
allocated to the Permit form. The Originator should enter the number of any
previous Excavation Permit issued for the same work activity.
Box 1 Location and Worksite Details
The Originator completes Box 1, specifically referring to the location,
worksite and area where the Excavation is taking place.
Box 2 Excavation Details
Where a pilot excavation is necessary then the Originator must enter
these details into Box 2a
The Originator will outline in Box 2b the detail of the work for which the
Excavation Permit is raised. It will be more specific than the associated
task description on the Work Permit. It will be visible in the PCF.
The approximate dimensions of the excavation should be entered
together with the equipment to be used.
Box 3 Associated Work Permits
The Originator should enter the Work Permit details of any associated
Work Permits.
It is the responsibility of the Asset Operator to update details and status
of these Work Permits and any subsequent Work Permits.
Box 4 Worksite Preparations and Precautions
The Originator, or the Maintenance/ Engineering Authority, is to agree the
requirements with the Asset Operator who will tick the preparations and
precautions that are applicable.
Box 5 Service in Worksite Area
The Originator is responsible for obtaining the required signatures of all
the Authorised Maintenance/ Engineering Authorities as to whether
services are present in the vicinity of the excavation and this must include
telecommunications under the responsible trade.
The Authorised Maintenance/ Engineering Authority should enter any
specific conditions in the space provided.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 22 of 45
Box 6 Particular Hazards and Special Precautions
The Originator should specify any particular hazards identified together
with any additional precautions. These are in addition to those in Box 4 or
those stated in the associated Work Permit and may include, for example,
the requirement for a Confined Space Entry Certificate.
The Asset Operator, in conjunction with the Authorised Maintenance/
Engineering Authority is to review and agree these aspects prior to issue.
The Permit is taken to the PTW Review Meeting, where the Authorised
Maintenance/ Engineering Authority and Asset Operator review and
agree Boxes 1 through to 6.
The Permit remains with Operations in the Permit Control Facility, along
with its associated Work Permit until it is required.
5.6.3 Permit Review and Issue
Box 7 When the work is ready to start, the Asset Operator confirms the
requirements of the Excavation Permit have been met and completes
Box 7.
5.6.4 Permit Acceptance
Box 8 The Authorised Civil Maintenance/ Engineering Authority completes Box
8 and takes the top (white) copy to the worksite for display and
instruction of the PICWS.
The 2nd (yellow) copy is retained in the Permit Control Facility and
visibly displayed in front of the associated (yellow) copy of the Work
Permit. The Shift Controller must arrange this step.
At the end of the Engineering work period the PICWS takes the top
(white) copy to the Authorised Civil Signatory who returns it to the Permit
Control Facility. The original and copy are assembled together and
retained with the associated Work Permit. This allows Operations
Department to gain an overview of the following days commitments.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 23 of 45
No subsequent endorsements of the Excavation Permit are required. The
Excavation Permit may remain valid for a maximum of 28 consecutive days
(providing it is accompanied by a valid Work Permit).
Where work has to continue next day, the top (white) copy is handed over to
Authorised Civil Signatory, who again takes the top copy to the worksite for
display and instruction to the PICWS along with the associated Work Permit.
5.6.5 Closure of the Permit
When the work is completed, or a new Excavation Permit is needed, the
Authorised Civil Signatory completes Box 9a
The Asset Operator completes Box 9b, including the continuation (if necessary).
5.6.6 Archiving
After close-out, the Asset Operator files the original (white) copy of the Excavation
Permit, together with the top copies of the Associated Work Permit and any other
supporting Permits or Certificates, as per archiving requirements (see Chapter
8,).
Should work be continuing under the associated Work Permit, the top (white)
copy of the (now closed) Excavation Permit should remain with (but behind) them
copies of the Work Permit, in the PCF display rack, until it too is closed out and
requires to be archived.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 24 of 45
5.7 COMPLETION OF AN ISOLATION CONFIRMATION CERTIFICATE
This Section should be read whilst referring to the Isolation Confirmation
Certificate (See Chapter 5, Figure 5.7).
5.7.1 Equipment Isolation Requirements
Box A1 Equipment to be Isolated
The Originator of the associated Work Permit is the person who
will normally originate the Isolation Confirmation Certificate.
Details of the equipment to be isolated are entered into Box A1a.
The Originator should also provide a brief outline of the purpose of
the isolation in Box A1b and indicate when the isolation is
required.
Box A2 Associated Work Permits
The Originator should enter details of the associated Work
Permit(s) to which the isolation is to be cross-referenced.
It is the responsibility of the Asset Operator to update these details
to reflect the status of all associated Work Permits.
Box A3 Certificate Originator
The Certificate Originator signs Box 3 and submits the Isolation
Confirmation Certificate to the daily PTW Review Meeting, along
with the associated Work Permit in order to allow the isolation to
be planned.
5.7.2 Completion of Section B Electrical Isolation/Deisolation
Section B is required to be completed when it is necessary to work on Plant
or equipment connected to a source of electrical power.
Section B does NOT permit any work of an electrical nature (other than the
isolation itself) to be undertaken. Work on electrical equipment, or work in
the vicinity of live electrical conductors, is subject to additional controls as
required by the GASCO Standing Instructions and Procedures Electrical
(SIPE)
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 25 of 45
Section B has no validity period. It is valid until the associated work has been
completed, and when the associated work permit closed it must be considered
as EPI)
Box B1 The Asset Operator certifies that the equipment has been taken out of service
and is ready for Electrical Isolation by signing Box B1.
Box B2 The Authorised Electrical Person is to detail the specific isolation reference
points, tick against the isolation requirements (Items1-16) and sign Box B2. He
is also to indicate which Trade Padlocks will be required by placing a tick in the
space against the designated Trade.
Box B3 Confirmation of Isolation
The appointed Isolator (the Certified Person, Electrical) is to confirm the
isolation requirements have been completed, by initialing against the ticked
requirements in Box B3. He then completes and signs Box B3.
The Isolator (the Certified Person, Electrical) should then place a multi-hasp
on the local isolation point and place his own (Electrical) Trade padlock on it,
recording the details in Box B2.
The Operations Appointed Person (the Area Authority), on being advised of
the completed isolation, is to install his own (Operations) padlock on the
multihasp in addition to Electrical padlock and record the details in Box B2.
Where indicated in Box B2, the other Trades should also fit their Trade padlock
on the multi-hasp at the local isolation point and record the details in Box B2.
Box B4 Equipment Release for Restoration of Electrical Supply
The Asset Operator, after completion of work and closure of all associated
Work Permits (as detailed in Box 2), will complete and sign Box B4 and
request the Certified Person, Electrical, to restore electrical power to the
equipment.
Box B5 Restoration of Electrical Supply
The Certified Person, Electrical, will complete and sign Section B5 when the
electrical supply to the equipment has been restored.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 26 of 45
5.7.3. Completion of Section C Mechanical Isolation / Deisolation Isolation/Deisolation
Box C1
The Asset Operator certifies that the equipment has been taken out
of service and is ready for Mechanical/Instrument Isolation by
signing Box C1.
Box C2/C3 The Authorised Mechanical and Instrument Persons are to detail
the specific isolation reference points, record the isolations and sign
in Box C2 and C3 that the isolation is complete and proven. He is
also to indicate which Trade Padlocks will be required by placing a
tick in the space against the designated Trade
Box C4
The Asset Operator, after completion of work and closure of all
associated Work Permits (as detailed in Box 2), will complete and
sign Box B4 and request the Authorised Mechanical/Instrument
persons to de-isolate. The Authorised Persons Mechanical and
Instrument will then sign the relevant de-isolations in Box C2 and C3
Box D1
When the ICC is to remain in force without an associated Work
Permit; the Issuing Authority must complete the details in Box D1
Box D2
When the EPI is cancelled the Issuing Authority will complete Box D2
5.7.4 Distribution of Copies of the Isolation Confirmation Certificate
Where the isolation is only associated with one Work Permit, the normal
distribution of copies apply, i.e. top (white) copy to the worksite; 2nd (yellow)
copy to the PCF; Where an isolation is associated with more than one Work
Permit, photocopies of the top (white) copy of the Isolation Confirmation
Certificate should be made and distributed with the other associated Work
Permits for display at the worksite and the PCF Display Rack. In such
circumstances, it is the responsibility of the Asset Operator to ensure these
photocopies are updated to reflect the current status of all associated Permits.
NO DE-ISOLATION IS PERMITTED UNTIL CLOSURE OF ALL ASSOCIATED
WORK PERMITS IS COMPLETED.
5.7.5 Archiving
After close-out, the Asset Operator files the original (white) copy of the Isolation
Confirmation Certificate, together with the copy of the Associated Work Permit
and any other supporting Permits or Certificates, as per archiving requirements
(see Chapter 8,).
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 27 of 45
5.8
COMPLETION OF RADIOGRAPHY PERMIT
This Section should be read whilst referring to the Radiography Permit (See
Chapter 5, Figure 5.8).
5.8.1 Radiation Source and Risk Assessment
Box 1 Location and Boundaries of Area/ Worksite
A unique pre-printed number is allocated to the Radiation Permit.
The Originator (in this case the Authorised Inspection Authority)
completes Box
1, specifically referring to the location and providing information as to
the boundaries of the Area/ Worksite and where/ when the
Radiography is to be undertaken.
Box 2 Associated Permits
The Originator enters the details of the associated Work Permit(s).
Box 3 Radiation Source
The Originator completes Box 3, describing the type of radioactive
source that will be used and its strength. The Contractor who will be
undertaking the work is recorded also.
Box 4 Worksite Preparations
The Originator completes Box 4, ticking those precautions that are
required.
Box 5 Specific HSE Requirements
The Originator completes Box 5a and 5b, ticking against the
equipment and P.P.E. that is required.
Box 6 Particular Hazards and Special Precautions
The Originator completes Box 6 and records any particular hazards
identified (additional to those pre-printed) together with any
additional precautions.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 28 of 45
5.8.2 Technical Approval
Box 7 Inspection Authority Approval
The Authorised Gasco Inspection Signatory completes Box 7 and takes
the Radiography Permit to the daily PTW Review Meeting for review
with the Asset Operator, as part of the Risk Management Process.
The Radiography Permit remains with Operations in the Permit Control
Facility until it is required.
5.8.3 Permit Issue
Box 8 Permit Issue by the Asset Operator
The Asset Operator confirms the Worksite preparations are complete
and that the specific HSE requirements for equipment are in place. He
then initials check Boxes in Box 4 and Box 5.
The Asset Operator then formally issues the Permit to the Authorised
Gasco Inspection Authority by completing Box 8, stipulating also the
maximum validity period allowed. This may be for the same duration as
the associated Work Permit.
5.8.4 Permit Acceptance
Box 9 Permit Acceptance by Nominated Company Representative
TThe Authorised Gasco Inspection Authority will take the top (white)
copy of the Radiography Permit to the worksite, together with the copy
of the associated Work Permit. The nominated Contract Company
representative accepts the Permit by signing in Box 9, arranges for its
display and instruction of the PICWS.
The second (yellow) is retained in the Permit Control Facility and visibly
displayed (in front of the associated Work Permit) by the Asset Operator
in the Permit Display rack.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 29 of 45
5.8.5 Permit Closure
Box 10a Closure by Authorised Inspection Authority/ Contract Company
At the end of the Radiography work the PICWS takes the top copy to
the Authorised Gasco Inspection Signatory who returns the top copy to
the Permit Control Facility.
The Gasco Authorised Inspection Signatory or Contract Company
Representative then completes Box 10a.
Box 10b Closure by the Asset Operator
The Asset Operator cancels the Radiography Permit by signing in Box
10b.
5.8.6 Archiving
After close-out, the Asset Operator files the original (white) copy of the
Radiography Permit, together with the top copy of the Associated Work Permit
and any other supporting Permits or Certificates, as per archiving requirements
(see Chapter 8,).
Should the associated Work Permit still remain open, the top (white) copy of the
(now closed) Excavation Permit should remain with (but behind) the copies of the
Work Permit, in the PCF display rack, until it too is closed out and requires to be
archived.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 30 of 45
5.9 COMPLETION OF PIPELINE AUTHORISATION TO WORK
This Section should be read whilst referring to the Pipeline Authorisation to Work
(See Chapter 5, Figure 5.9).
5.9.1 Originating the ATW, Work Description and Risk Assessment
GASCO, Third Party or Contractor may originate an ATW. In the case of a
Third Party or Contractor the ATW may originated in direct consultation with
the Pipeline Asset Holder/ Asset Operator.
5.9.2 The Pipeline Asset Owner will have undertaken a preliminary evaluation of
the work activity and methods of work proposed, to determine the initial risk
and what levels of controls are required. Where there is a requirement for
a formal risk assessment, this is to be undertaken by the ATW Originator in
conjunction with the asset operation. Holder and any of the concerned
disciplies and is to be recorded on the Activity Risk Assessment Form (see
Chapter 3, Appendix E), which should accompany the ATW.
Box 1a The Company or Contractor name shall be printed. In the case of a
contractor then the Mobile number shall be entered.
Box 1 b Task Outline.
The GASCO, Contractor or Third Party representative, in consultation
with the Pipeline Asset Holder or Asset Operator will enter the Task
Outline, Pipeline Location and Specific Work Site, in boxes 1(b) and 1(c)
respectively, in order to clearly detail the boundaries of the work area.
This should be visible from the Permit Display Rack Slot
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 31 of 45
Box 2 Description of Work
A synopsis of the intended work is to be entered in sufficient detail to
clearly describe the overall work activity. Where supplied, reference is to
be made to supporting sketches or drawings and detailed Engineering
Procedures or Method Statements. The closest distance of the worksite
from the edge of the pipeline corridor is to be entered in the box provided.
Box 3 Supporting Documentation
Where supporting sketches/ drawings or detailed Engineering Procedures
or Method Statements have been provided these should be noted by
ticking the boxes provided. A space is provided for entering any other
additional information regarding supporting documentation.
The number of any No Objection Certificate should be entered in the
space provided.
Box 4 Equipment to be Used
The equipment that is to be used should be discussed and agreed with
Operations or the concerned discipline and then the relevant check boxes
ticked.
Box 5 Precautions Required
Any specific precautions required are to be discussed and agreed with the
Asset Holder/ Asset Operator subsequent to ticking the relevant check
boxes.
Where a formal risk assessment has been undertaken the risk
assessment should accompany the ATW.
Box 6 Signature of Originator
The Originator of the ATW will complete this box
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 32 of 45
5.9.2 Notification of Others
The Pipeline Asset Holder, or Asset Operator, will identify who needs to be
notified of the work. Where the Police Authority has been identified, it is
normal practice to obtain the Police Stamp of Approval prior to authorising
the work to commence.
It is the responsibility of the Third Party or Contractor to obtain this Police
Stamp of approval.
The Police Stamp of approval is not normally required for work activities
undertaken by GASCO.
5.9.3 Review of workscope, HSE requirements and precations
The Maintenance/Engineering/Project Authorized Person will review the
workscope and the requirements of boxes 1 to 6 and when satisfied he will
complete box 8
5.9.4 ATW Issuer
Once the workscope, equipment to be used and precautions have been
agreed, the Pipeline Asset Holder, or Asset Operator, is to enter the validity
period for the ATW. This may be for a maximum of 28 continuous days
from the date of issue.
The nature of the risk will determine what frequency of worksite visit by the
Area Authority is required. A tick should be placed in the appropriate box.
The Asset Operator then signs and dates the ATW and issues it to the
nominated Gasco Representative or third party Representative.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 33 of 45
5.9.5. Acceptance
Box 10 Acceptance on behalf of the Contractor Work Party
The nominated GASCO, Contractor or Third Party representative
acknowledges the conditions and accepts the ATW by signing Box 10. He
takes the original (white) copy of the ATW for display at the worksite. The
second yellow copy is displayed in the PCF
5.9.6 Extension to the Validity Period
Box 11 Providing there has been no change to the defined workscope,
equipment, or precautions required, the Asset Holder may authorise an
extension of the original validity period, for a further period of 28 days.
Provision is made for a maximum of 3 such extensions.
When obtaining an extension to the validity period, all copies of the ATW
must be matched for completion and signature of the Asset Operator.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 34 of 45
5.9.7
Closure of Authorisation to Work (ATW)
Box 12(a) Work Completion
When the job has been completed, the nominated GASCO,
Contractor or Third Party representative completes Box 12(a) and
returns the ATW to the Pipeline Asset Operator.
Box 12(b) Acknowledgement by GASCO
The Pipeline Asset Operator acknowledges the completion of the
work and formally closes the ATW by signing Box 12(b).
5.9.8
Endorsements
Box 13 Worksite endorsement
Where work is to continue after the first day then the Acceptor (in box
10) shall record the work start and stop time up to a maximum of 28
days, in box 13
Box 14 Operations endorsement
Where work is to continue after the first day then the Area Authority (in
box 9) is to confirm continued safety at the worksite at the frequency
specified in Box 9 by completing box 14.
5.9.9
Archiving
After close out, the Asset Operator is to file the original (white) copy of
the ATW as per archiving requirements (see Chapter 8, Section
8.1.5.2 of the PTW System Manual).
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 35 of 45
PERMIT ISSUE
Work Order No:
Work Permit No:
WORK PERMIT
Counter Signature (as required) for Interface/ High Risk Activity
10. Permit Issue by Asset Operator
Worksite Preparations, as listed in Section 7, are complete.
There is no geographic or timing conflict with any other Work Permit or activity.
Work may proceed after Maintenance/ Engineering Acceptance and Area Endorsement.
WORK DESCRIPTION AND RISK ASSESSMENT
Name:
Date Work Permit
Required:
1 (a) TASK:
Signed:
Name:
Signed:
Date:
Position:
Time:
Date:
Position:
PERMIT ACCEPTANCE
1 (b) LOCATION/ TAG NO.
AREA/ WORK SITE:
Restricted Area
H2S Zone: Yes
11. Permit Acceptance by Maintenance/ Engineering Authority
I understand the workscope and precautions to be taken.
I will explain them to the person in Charge of the Worksite (PICWS), as given in Section 12, to ensure they are adhered to.
I will ensure a toolbox talk is conducted and, where considered appropriate for higher risks, that it is recorded.
Unrestricted Area
No
2. WORK DESCRIPTION
Name:
Signed:
Time:
Date:
Position:
WORKSITE RESPONSIBILITY
12. Acceptance by the Person in Charge of the Worksite (PICWS)
12 (a) I will endeavour to ensure the work party abide the conditions stated in this Work Permit.
ENGINEERING EQUIPMENT TO BE USED:
Hand Tools Only will be used
I will ensure attendance at any Toolbox Talk at the commencement of each stated work period, or, as stated otherwise in the Risk Assessment or Activity
Sequence Control Form, to ensure the hazards and precautions are known and understood by the work party.
SPECIAL PRECAUTIONS
3. PARTICULAR HAZARDS
Name:
Signed:
12 (b) Additional PICWS (or change of PICWS)
Name
Date:
Time:
I acknowledge, understand, and will comply with the statements in Section 12(a)
Signed
Date
Time
* Additional PICWS?
* Change of PICWS?
* Yes/ No is to be entered
in each column to
Category of Worksite Presence Required:
A
B
indicate whether the
C
PICWS is an addition to,
4. WORKSITE SUPPORTING DOCUMENTS
4(a) Supporting Permits or Certificates
or in place of, the original
4(b) Associated Work Permits
Ref. No.
Hot Work Permit, Category 1
Work Permit Details
4(c) Other Supporting Documentation
Trade
Ref. No.
Details
PICWS.
*Tick
Hot Work Permit, Category 2
Activity Risk Assessment Form
ENDORSEMENTS FOR THE CONTINUED SAFETY OF THE WORKSITE
Confined Space Entry Certificate.
Activity Sequence Control Form
13. Worksite Endorsement
Excavation Permit
Maint/ Eng. Method Statement
Radiography Permit
Toolbox Talk Record Form
Isolation Confirmation Certificate
Gas Test Certificate
6. WORK PERMIT ORIGINATOR
Name:
MUST comply with specific
members of the work party
Site Rules for the wearing of
PPE in Restricted Areas.
Asset Operator [1]
PICWS (Work Start) [3]
PICWS (Work Stop) [4]
Area Authority [2]
PICWS (Work Start) [3]
PICWS (Work Stop) [4]
Asset Operator [1]
To the best of my knowledge, the information given in Section 1, through to Section 5, is correct and addresses the risks invol ved in undertaking the work.
Signed:
Morning Shift
Ear Protection
Disposable Coveralls
Lifejacket
Other:
Afternoon Shift
Fire Hose Branch / Portable Monitor
Portable Gas Detectors
requirements listed, all
Position:
Company:
Data Originated
PERMIT REVIEW AND VALIDATION
Night Shift
Rubber boots
Chemical Suit
H2S Personal Monitor
Portable Radio
Area Authority [2]
Area Authority [2]
PICWS (Work Start) [3]
PICWS (Work Stop) [4]
7. WORKSITE PREPARATIONS
Req’d
Initial
Time
Initial
Time
Initial
Time
Initial
Time
Initial
................................................................................................
Dust Mask
Safety Harness / Lifeline
Warning Beacons
NB. Irrespective of the PPE
Time
................................................................................................
BA Escape Set
Self Contained BA/Airline
Req’d
Stand-by Person
Initial
................................................................................................
Req’d Type
Face / Eye Protection
Gloves
Time
................................................................................................
Equipment/ Resources and Personal Protective Equipment (P.P.E.)
Req’d
Safety Barriers / Warning Signs
Asset Operator [1]
................................................................................................
5. SPECIFIC HSE REQUIREMENTS
* Tick if included in Permitry package
................................................................................................
Initial
Other:
................................................................................................
Day/ Date
Drawing
Any Previous Work Permit Ref. No.
[1] Asset Operator confirms no conflict with other Permit or activity prior to worksite endorsement
[2] Area Authority acknowledges and confirms continued safety of the work site for work to start.
[3] PICWS accepts responsibility for worksite at workstart
[4] PICWS confirms worksite left safe at work stop.
Required every shift/ work period.
Time
PERMIT CLOSURE
*Initial
Equipment De-pressurised
14. WORK COMPLETED
Equipment Drained
PICWS initial:
15. WORK NOT COMPLETED
PICWS initial:
Equipment Nitrogen Inerted
14 (a) Permit Return by Maintenance/ Engineering Authority
Equipment Ventilated / Flushed
Equipment Free from Chemicals
15 (a) Permit Return by Maintenance/ Engineering Authority
Worksite is clear & equipment affected left in safe condition
Worksite clear & equipment affected left in safe condition
Instrument Protective Function Disable Required
Housekeeping is Satisfactory
Housekeeping is Satisfactory
Safety System Isolation Required
* Work is continuing under Work Permit No.
Operations is authorised to return equipment to service
* Isolations retained under isolation Certificate * Delete as appropriate
Other:
* Delete where not applicable
Date:
Name:
Signed:
Time:
Signed:
Date:
* Initial to confirm PRIOR to Permit Issue.
8. MAINTENANCE / ENGINEERING REVIEW
I have reviewed and approved the workscope, HSE Requirements and Precautions as detailed in Section 1 to 5 (inclusive) and agree with the Risk Assessment (where included).
I certify that the equipment to be used for this work, as stated in Section 2, has been inspected and is suitable for use on the worksite as described.
I agree with the Worksite preparation requirements detailed in Section 7.
Name:
Signed:
Position:
Date:
9. ASSET OPERATOR REVIEW AND VALIDATION
I have reviewed Sections 1 through to 7 with the Maintenance / Engineering Authority and concur with the requirements.
The Worksite Preparation requirements, as listed in Section 7, must be confirmed prior to Permit Issue and Worksite Endorsement
Days
The Work Permit is valid for: * the maximum 7 day validity Period/
from the date of issue. * Delete if reduced number of days is specified
Name:
Name:
Signed:
Distribution: White Original - Worksite; Yellow - PCF Copy
Position:
Date:
14 (b) Permit Closure by Asset Operator
Area Authority initial:
Time:
15 (b) Permit Closure by Asset Operator
Worksite is confirmed clear.
Equipment affected is in a safe condition
Housekeeping is confirmed as satisfactory
Supporting documents closed
* Reinstatements / De-isolations complete * Delete as appropriate
* Isolations retained and displayed in PCF
WORK PERMIT IS NOW CLOSED
Area Authority initial:
Worksite is confirmed as clear
Equipment is in a safe condition
Housekeeping is confirmed as satisfactory
THIS WORK PERMIT IS NOW CLOSED
Name:
Date:
Name:
Date:
Signed:
Time:
Signed:
Time:
Rev 2.0, April 2009
Rev 2.0, April 2009
FIGURE 5.1 Work Permit
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 36 of 42
TOOLBOX TALK RECORD FORM
GAS TEST CERTIFICATE
All personnel involved in the work activity must be participate in the Toolbox Talk and sign below as being present.
Gas Test Requirements (Permit Originator and Asset Operator to agree)
Checklist / Prompt for Discussions (Tick where applicable)
Area / Location / Equipment to be Tested
Types of Operation to be executed
Crane / Lifting requirements
Methods/ Procedures to be adopted
Supplementary Permit / Certificate Requirements
PTW / ARA Precautions & Controls
Hazards & Hazardous substances used / present
Safety Equipment and Location
Isolation Requirements
Yes
No
Each Work Period?
Individual Responsibilities
Conficting Activities
Continuous gas monitoring equipment required?
Yes
(Portable)
No
Access / Egress
Work in adjacent areas
Worksite Certification (by Authorised Gas Tester)
Tests / Monitoring
Environmental considerations
Work Equipment
Waste Management
Oxygen (O2):
Production / Operational Constraints
Site Rules
Hydrocarbons:
< 5% LEL
% LEL
Hydrogen Sulphide (H2S):
< 10 ppm
ppm
Attach drawing or sketch if required:
Yes
No
Yes
No
Continuous gas monitoring equipment operating?
Yes
(Fixed)
No
Test Frequency
Prior to work commencing?
Threshold Values
Gases to be Tested
General Comments / Observations Identified during Toolbox
Tick as Required
Results of the Initial Gas Test
> 19.5%; < 22.5% by Volume
% Volume
Others (specify):
Remarks:
Name:
Signed:
Position:
AGT
Date:
Time:
Date:
Time:
Area Authority Counter Signature (if not the AGT)
Name:
Action required?
Yes
No
Details of persons attending Toolbox Talk
Name
Signed:
Position:
Additional Gas Test Record
Trade / Discipline
Signature
Date
Oxygen
(% Vol)
Hydrocarbons
(% LEL)
H2S
(ppm)
Others (Specify: %; ppm; etc.)
Authorised Gas Tester
Name
Signature
Date
Time
Area Authority
Counter Signature
(If not the AGT)
Toolbox Talk conducted by:
Name:
Signed:
Date:
FIGURE 5.2 Work Permit
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 37 of 45
Previous Permit No:
Permit No:
HOT WORK PERMIT
Category 1
WORK DESCRIPTION AND RISK ASSESSMENT
Date Hot Work Permit
Required:
1. (a) TASK:
1. (b) LOCATION/TAG No:
AREA/WORK SITE:
Restricted Area
H2S Zone: Yes
Unrestricted Area
No
2. WORK DESCRIPTION
Associated Work Permit No.
Source(s) of Ignition:
3. WORKSITE PREPARATIONS:
4. SPECIFIC HSE REQUIREMENTS:
Req’d *Initial
Shielding / Screening to be provided
4(a) Equipment
Sewers & drains covered
Area free from combustibles
Portable Gas Detector
Safe Access / Egress provided
System Isolations / Preparations confirmed
Protective system inhibit
Gas Test Certificate requirements
Fire Stand-by Man
* Initial to confirm PRIOR to Permit Issue
Req’d *Initial 4(b) P.P.E. (specify type)
Req’d
Safety Barriers / Signs
Fire Extinquishers
Face / Eyes
Fire Blanket
Fire Hose (charged)
Portable Fire Monitor
Protective
Clothing
Type
Gloves
* Initial to confirm PRIOR to Permit Issue
5. PARTICULAR HAZARDS AND SPECIAL PRECAUTIONS
A
CATEGORY OF PICWS PRESENCE
B
PERMIT REVIEW AND ISSUE
by Asset Holder (Restricted Area); Asset Operator (Unrestricted Area)
6. PERMIT REVIEW & ISSUE
I have examined the worksite and I am satisfied that the Worksite Preparations are complete.
I confirm that the requirements, as listed in boxes 3, 4 and 5 above have been met. Work may commence after Worksite endorseme nt.
Name:
Signed:
Date:
Time:
Signed:
Date:
Time:
Counter Signature for Interface Area:
Name:
PERMIT ACCEPTANCE
7. PERMIT ACCEPTANCE
I understand the workscope and precautions to be taken. I will explain them to the Person in Charge of
by Maintenance /Engineering Authority the Worksite (PICWS) to ensure they are adhered to.
I will ensure a Toolbox Talk is given.
Name:
Signed:
Date:
Time:
ENDORSEMENTS FOR CONTINUED SAFETY OF THE WORKSITE
8. WORKSITE ENDORSEMENTS
..................................................
..................................................
..................................................
..................................................
..................................................
..................................................
..................................................
..................................................
PICWS
(Work Start)
PICWS
(Work Stop)
..................................................
Area Authority
..................................................
Asset Operator
Permit Validity Period may NOT extend beyond that of the associated Work Permit.
Signatories responsibilities are as defined in Endorsement section of the Work Permit.
Date:
Date:
Date:
Date:
Date:
Date:
Date:
Date:
Date:
Date:
Initial Time
Initial Time
Initial Time
Initial Time
Initial Time
Initial Time
Initial Time
Initial Time
Initial Time
Initial Time
PERMIT CLOSURE
9(a) Declaration by Maintenance /Engineering Authority
Work Complete
Not Complete
Worksite clear & equipment left in safe condition
Housekeeping is satisfactory
9(b) Permit Closure by Asset Operator
Area Authority initial:
Worksite confirmed clear and equipment in safe condition
Housekeeping is confirmed as satisfactory
THIS HOT WORK PERMIT IS NOW CLOSED
PICWS initial:
Name:
Date:
Signed:
Time:
Work continues under Hotwork Permit No.:
Name:
Date:
Signed:
Time:
Distribution: White Original - Worksite; Yellow - PCF Copy
Rev 2.0, April 2009
FIGURE 5.3 Hot Work Permit, Category 1
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 38 of 45
Previous Permit No:
Permit No:
HOT WORK PERMIT
Category 2
WORK DESCRIPTION AND RISK ASSESSMENT
Date Hot Work Permit
Required:
1. (a) TASK:
1. (b) LOCATION/TAG No:
AREA/WORK SITE:
Restricted Area
H2S Zone: Yes
Unrestricted Area
No
2. WORK DESCRIPTION
Associated Work Permit No.
Source(s) of Ignition:
3. WORKSITE PREPARATIONS:
4. SPECIFIC HSE REQUIREMENTS:
Req’d *Initial
System Isolations / Preparations confirmed
Gas Test Certificate requirements
4(a) Equipment
Req’d *Initial 4(b) P.P.E. (specify type)
Non Spark / Air Operated Tools to be used
Contact point of Drill / Tool to be kept wetted
HSE Stand-by
Safety Barriers / Signs
Fire Extinquishers
Face / Eyes
Fire Blanket
Protective
Clothing
Portable Gas Detector
Req’d
Type
Gloves
Banksman for vehicular movements
* Initial to confirm PRIOR to Permit Issue
* Initial to confirm PRIOR to Permit Issue
5. PARTICULAR HAZARDS AND SPECIAL PRECAUTIONS
A
CATEGORY OF PICWS PRESENCE
B
C
PERMIT REVIEW AND ISSUE
6. PERMIT REVIEW & ISSUE by Asset Operator
I am satisfied that the Worksite Preparations are complete
I confirm the requirements, as listed in boxes 3, 4 and 5 above have been met. Work may commence after Worksite Endorsement.
Name:
Signed:
Date:
Time:
Signed:
Date:
Time:
Counter signature for Interface Area:
Name:
PERMIT ACCEPTANCE
7. PERMIT ACCEPTANCE
I understand the workscope and precautions to be taken. I will explain them to the Person in Charge of
by Maintenance /Engineering Authority the Worksite (PICWS) to ensure they are adhered to.
I will ensure a Toolbox Talk is given.
Name:
Signed:
Date:
Time:
ENDORSEMENTS FOR CONTINUED SAFETY OF THE WORKSITE
8. WORKSITE ENDORSEMENTS
..................................................
..................................................
..................................................
..................................................
..................................................
..................................................
..................................................
..................................................
PICWS
(Work Start)
PICWS
(Work Stop)
..................................................
Area Authority
..................................................
Asset Operator
Permit Validity Period may NOT extend beyond that of the associated Work Permit.
Signatories responsibilities are as defined in Endorsement section of the Work Permit.
Date:
Date:
Date:
Date:
Date:
Date:
Date:
Date:
Date:
Date:
Initial Time
Initial Time
Initial Time
Initial Time
Initial Time
Initial Time
Initial Time
Initial Time
Initial Time
Initial Time
PERMIT CLOSURE
9(a) Declaration by Maintenance /Engineering Authority
Work Complete
Not Complete
Worksite clear & equipment left in safe condition
Housekeeping is satisfactory
9(b) Permit Closure by Asset Operator
Area Authority initial:
Worksite confirmed clear and equipment in safe condition
Housekeeping is confirmed as satisfactory
THIS HOT WORK PERMIT IS NOW CLOSED
PICWS initial:
Name:
Date:
Signed:
Time:
Work continues under Hotwork Permit No.:
Name:
Date:
Signed:
Time:
Distribution: White Original - Worksite; Yellow - PCF Copy
Rev 2.0, April 2009
FIGURE 5.4 Hot Work Permit, Category 2
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 39 of 45
Previous Cert. No.
Certificate No.
CONFINED SPACE
ENTRY CERTIFICATE
ENTRY DESCRIPTION AND RISK ASSESSMENT:
2. Associated Work Permits
1. DETAILS OF CONFINED SPACE
Work Permit Details
1(a) WORK SITE / VESSEL:
Trade
Permit No.
Issue Date
Closure Date
LOCATION:
1(b) Reason for Confined Space Entry:
Status to be updated by the Asset Operator.
3. Signature of Certificate Originator
Name:
Signed:
4. WORKSITE PREPARATIONS:
Position
* Initial to confirm PRIOR to certificate issue
Delete but do NOT initial non-applicable items
Date:
5. SPECIFIC HSE REQUIREMENTS:
* Req’d * Initial
* Req’d * Initial
The above Plant / Equipment has been removed from service
Lifelines / harnesses provided
The above Plant / Equipment has been isolated from all sources of dangerous liquids,
gases, chemicals and fumes
Breathing apparatus available
The above Plant / Equipment has been isolated from all energy sources
Resuscitation equipment available
All drains, sewers or vents within 25 metres are covered or closed
Safe for Entry / Entry Prohibited Notices
have been posted
The Plant / Equipment is sufficiently cool
Stand-by personnel have been detailed
Adequate Access / Egrees is provided
A Rescue Plan has been formulated and
personnel briefed accordingly
Natural Ventilation is adequate
Communication means provided
Air moving equipment has been installed
Temporary lighting, where installed, is of low voltage (<50V) supply.
There are no hazards that could arise from concurrent operations or work activities
Confined Space atmosphere checked; Results recorded on Gas Test Certificate
Other:
* Initial to confirm PRIOR to certificate issue
Delete but do NOT initial non-applicable items
6. PARTICULAR HAZARDS AND SPECIAL PRECAUTIONS The above Plant / Equipment *has been/* requires to be freed from all dangerous materials (incl. Pyrophoric Scale)
* Delete as appropriate
CERTIFICATE REVIEW AND ISSUE
7. CERTIFICATE ISSUE by *Asset Holder/ * Asset Operator
*Delete as appropriate
I certify that I have personally examined the plant/ equipment detailed above and confirm that the worksite preparations, and requirements as listed in Section 4,
5 and 6 above are complete.
The Confined Space is safe for entry without breathing apparatus
Tick as applicable
The Confined Space is NOT safe for entry. Breathing apparatus MUST be worn
(Asset Holder must sign for entry with BA)
Name:
Signed:
Date:
Time:
ENDORSEMENTS FOR CONTINUED ENTRIES TO CONFINED SPACE
Asset Operator to date, time and initial each work period to confirm that there has been no change to the Confined Space Entry conditions
8. WORKSITE ENDORSEMENTS
Date
...............................
Time Initial
...............................
Date
...............................
Time Initial
...............................
Date
...............................
Time Initial
...............................
Date
...............................
Time Initial
...............................
Date
...............................
Time Initial
...............................
Date
...............................
Time Initial
...............................
...............................
...............................
Date
Time Initial
CERTIFICATE CLOSURE
9. CLOSURE
9(a) Declaration by Permit Originator
Work Complete
Not Complete
I have confirmed Worksite/ Vessel to be clear and left in safe condition
All equipment and materials have been removed from the Confined Space
9(b) Certificate Closure by Asset Operator
Name:
Date:
Signed:
Time:
Work continues under Confined Space Entry Certificate.
Confirmed Worksite/ Vessel clear and left in safe condition
All equipment and materials removed from the confined space
THIS CONFINED SPACE ENTRY CERTIFICATE IS NOW CLOSED:
Name:
Date:
Signed:
Time:
Distribution: White Original - Worksite; Yellow - PCF Copy
Rev 2.0, April 2009
FIGURE 5.5 Confined Space Entry Certificate
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 40 of 45
Confined Space Entry Certificate
Register of Persons Entering the Confined Space Defined on this Certificate
Name
Company
Time in
Time Out
FIGURE 5.6 Confined Space Entry Certificate
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 41 of 45
Previous Excavation
Permit No:
Excavation
Permit No:
EXCAVATION
PERMIT
EXCAVATION DETAILS AND RISK ASSESSMENT
1. LOCATION:
3. Associated Work Permits
* Work Permit Details
Trade
Permit No.
Issue Date
Closure Date
AREA/ WORK SITE:
2. (a) PILOT EXCAVATION DETAILS:
Pilot trenches to be hand dug
metre
2. (b) MAIN EXCAVATION DETAILS:
Approximate Dimensions:
Length (m)
Breadth (m)
Depth (m)*
Equipment to be Used:
* Details & Status to be updated by the Asset Operator.
Hand Tools Only:
4. WORKSITE PREPARATIONS AND PRECAUTIONS:
Tick if required
5. SERVICES IN WORKSITE AREA
Appropriate Area Authority to be notified
Services Present in Area?
Trade
All Services to be located/marked
Pilot trenches to be hand dug
Authorised Maintenance /Engineer Authority
Name:
Yes
metre
Signed:
Date
No
Electrical
Machine use allowed after Pilot trenching
Mechanical
Service trenching equipment to be used
Instrument
* Shoring/ Battering/ Benching to be applied
Inspection
Detailed Drawing to be provided
Any Specific Conditions :
Situation Sketch to be provided
Other:
* Delete as appropriate
6. PARTICULAR HAZARDS AND SPECIAL PRECAUTIONS:
*Confined Space Entry Certificate is required where depth of excavation > 1.5 metres, and
where the ratio of excavation width to excavation depth (width/ depth) <2.0.
PERMIT REVIEW AND ISSUE
7. PERMIT REVIEW & ISSUE by Asset Operator
Excavation Permit is valid until:
I confirm the requirements, as listed in boxes 4, 5 & 6 above have been met.
Day:
Date
Name:
Month:
Signed:
Year
20
(maximum 1 month validity period)
Date:
Time:
PERMIT ACCEPTANCE
8. ACCEPTANCE by Authorised Civil Signatory
I have read and understood this Permit
I will undertake to work in accordance with the Precautions/ Conditions defined in this Permit and in Associated Work Permits.
I will undertake to brief all those in the excavation work party to ensure compliance.
Name:
Signed:
Date:
Time:
PERMIT CLOSURE
9. CLOSURE
9(a) Declaration by Authorised Civil Signatory
Work Complete
Not Complete
Worksite clear and equipment left in safe condition
Housekeeping is satisfactory
Excavation has been back filled
9(b) Permit Closure by Asset Operator
Name:
Date:
Signed:
Time:
Work continues under new Excavation Permit No.:
I Confirm Worksite has been left in Safe Condition
Housekeeping is confimed as satisfactory
Name:
Date:
THIS EXCAVATION PERMIT IS NOW CLOSED
Signed:
Time:
Distribution: White Original - Worksite; Yellow - PCF Copy
Rev 2.0, April 2009
FIGURE 5.7 Excavation Permit
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 42 of 45
Certificate No.
C. Mechanical/Instrument Isolation / De-Isolation
1.
A. Workscope Details
1 (a) Equipment Tag No:
Equipment Description:
Work Permit No:
Work Permit Date:
Worksite:
Work continuing on Permit:
Isolation Detail Sheet attached : Yes / No
No. of
P & ID's attached :Yes / No No. of
Is this isolation being used as a Master Isolation? Yes
2 (b) Associated Permits / Certificates
Details
1 (b) Purpose of Isolation:
Trade
Number
The equipment is out of service and is released for Mechanical / Instrument Isolation
Date:
Signed:
Isolation
Position
Tag No.
Mechanical / Instrument Isolation Details
No
Issue Date
Closure Date
Time:
Asset Operator
2.
System
Asset Operator Approval for Isolation
Name:
2 (a) Work Permits Details
1. EQUIPMENT TO BE ISOLATED
Item
Valve / Line No. / Instrument System
Open
Close
Temporary Motive
Power Supply
Isolation Confirmation Certificate
Motive Power
Supply Disconnected
Certificate No.
GASCO - Abu Dhabi Gas Industries Ltd.
Lock
No.
Isolation Complete
& Proven
(Signature)
De-Isolation
Complete
(Signature)
Isolation Complete
& Proven
(Signature)
De-Isolation
Complete
(Signature)
1
2
3
* Details & Status to be updated by the Asset Operator
De-isolation may NOT take place until ALL Associated Permits are Closed
Date that the Equipment Requires to be isolated:
4
3. CERTIFICATE ORIGINATOR
5
Name:
Signed:
Date:
Time:
6
B. Electrical Isolation / De-isolation
7
The equipment is out of service and is released for Electrical Isolation
Asset Operator Approval for Isolation
1.
8
Name:
Date:
Signed:
Time:
9
Asset Operator
2.
10
Electrical Isolation Details
Sub Station No:
Switchboard No:
Tick as Required
Tick
1. Field Control Switch Off & Locked
1.
2. Switch Main Isolator to Off Position
2.
3. Racking Out - Check Finger Contacts
3.
4. Shutter Locked - Mechanism Check
4.
5. Removal of Contractor Carriage
5.
6. Removal of Control Fuses / MCB Switched Off
6.
7. Main Fuses Removed and Kept in Safe Custody
7.
8. Main Isolator - Locked Off
8.
9. No Voltage Checking & Testing
9.
10. Earthing at Cubicle
10.
11. Earthing Switch Breaker Closed
11.
12. Earthing Through External Earths
12.
13. Anti Condensation Heater Isolated
13.
14. Warning Notice(s) Posted
14.
15. Padlock Applied
15.
16. Isolation Details Recorded in Isolation Register
16.
3.
12
Isolation Detail Sheet Attached:
Yes / No No. of:
I have checked that the equipment cannot be started from the Sub-Station or Motor
Control Centre (MCS)
Positive Isolation Details
Spade
Tag No.
Isolation Padlocks
Trade Padlock
Tick
*Initial
Serial No.
1
2
Electrical Padlock
Operations Padlock
3
Mechanical Padlock
4
Instrument Padlock
5
6
Authorised Electrical Person
The Electrical Isolation requirements are as detailed, Isolations may proceed
7
8
Name:
Date:
Signed:
Time:
Name:
Date:
9
10
11
Signed:
12
4.
Time:
Authorisation to De-Isolate
Name:
Certified Person Electrical
I confirm all associated work has been completed and that Mechanical/Instrument De-Isolation may proceed.
Date:
Signed:
All Trade padlocks have been removed
Operations padlock has been removed
Name:
Date:
Signed:
Time:
There is no conflict with any other activity: Equipment De-Isolation may proceed
D 1 This section to be completed by the Issuing Authority when this ICC remains in force without an associated Work Permit Tick box as appropriate to indicate
systems remaining isolated.
EPI recorded
in the Register: EPI No:
Reason for EPI:
Padlocks returned to racks
Any additional Earthing has been removed
Electrical Supply has been restored
Finger contacts checked when racking in
Isolation Register completed
Warning notices have been removed
D. Extended Period Isolation (EPI) / EPI Cancellation
Asset Operator
Restoration of Electrical Supply
Confirmed all padlocks removed
Time:
Asset Operator
Equipment Release for Restoration of Electrical Supply
Work has been confirmed as completed and all associated Work Permits are closed
Disconnected Spectacle Blind
& Blanked
(Position)
Tag No.
Tag No.
Location of Isolation
Item
* Indicate where required and initial when in place
I have checked that the equipment cannot be started locally
5.
3.
Ref No:
Confirmation of Isolation by Certified Person(s)
I have completed the Electrical Isolation of the above equipment
4.
11
Cubicle No:
Initial
Name:
Signed:
Certified Person Electrical
Date:
Name:
Time:
D 2 EPI is cancelled and this ICC associated with new permit.
Name:
Signed:
Signed:
Mech
Date:
Date:
Inst
Time:
Distribution:
C7032_07 ICC, 05/12/08, Rev Pre HIRA
Elec
Time:
White Original - Worksite
Yellow - PCF Copy
FIGURE 5.8 Isolation Confirmation Certificate
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 43 of 45
RADIOGRAPHY
Radiography Permit No:
PERMIT
RADIATION SOURCE AND RISK ASSESSMENT:
1. LOCATION/TAG No:
2. ASSOCIATED WORK PERMITS
Permit Details
Serial Number
BOUNDARIES OF AREA/ WORKSITE:
Date Radiography will be undertaken:
3. RADIATION SOURCE
X-Ray apparatus
Maximum tube voltage (Kv)
! -Ray sealed source type:
Strength/Activity (Curies)
Identification Data:
Contractor:
5. SPECIFIC HSE REQUIREMENTS:
5(a) Equipment
Req’d
4. WORKSITE PREPARATIONS:
Req’d *Initial
* Initial to confirm prior to permit issue
5(b) P.P.E.
Type
UV Detectors within affected area to be isolated
Portable Gas Detector
Ear
Gas Test in vicinity of equipment
Safety Barriers/Signs
Face/Eyes
One sounding radiation detector to be provided
Fire Extinguishers
Gloves
Warning Beacons
Protective
Clothing
Portable Radio
6. PARTICULAR HAZARDS AND SPECIAL PRECAUTIONS
CATEGORY OF PICWS PRESENCE
✁ A
1. Only authorised personnel wearing film badges and dosimeters will be permitted within the restricted area
2. Red flashing lights to be sited at source
3. Amber flashing lights to be sited at barriers
4. Exposure limits outside the barriers MUST be below 7.5 u Sv/hr
5. A Stand by Person must be assigned to patrol outside the boundaries of the worksite, to prevent unauthorised admittance, whi lst the source is in place.
Others:
TECHNICAL APPROVAL
7. INSPECTION AUTHORITY APPROVAL
I have reviewed and approved the radiography work and Risk Assessment as detailed in sections 1 to 6 inclusive.
I certify that the radiography equipment to be used on this job has been checked and is suitable for use on the worksite as described.
Name:
Signed:
Date:
Time:
PERMIT ISSUE
8. PERMIT ISSUE by Asset Operator
I agree with the Requirements, as listed in boxes 4, 5 and 6 above
This Radiography Permit is issued subject to these requirements being in place.
Radiography may be undertaken for the undernoted validity period.
From:
hrs on
Date:
To:
Name:
hrs on
Signed:
Date:
Date:
Time:
PERMIT ACCEPTANCE
9. ACCEPTANCE by nominated Company Representative
Name:
I agree with the worksite preparations and controls as stated in this Permit. I will check that
these are in place prior to commencement of, and during, the radiography work.
I will ensure that the Person in Charge of the Worksite (PICWS) is aware of the requirements
Signed:
Date:
Time:
PERMIT CLOSURE
10. CLOSURE
10 (a) Declaration by authorised *Inspection Signatory / *Contract Company Representative
I declare that the work is complete.
The radioactive source has been removed from the Worksite and stored
safely in the designated area.
10 (b) Permit Closure by Asset Operator
I acknowledge that the work is complete and the area is now
safe to enter.
THIS RADIOGRAPHY PERMIT IS NOW CLOSED
* Delete as appropriate
Name:
Date:
Signed:
Time:
Name:
Date:
Signed:
Time:
Distribution: White Original - Worksite; Yellow - PCF Copy
Rev 2.0, April 2009
FIGURE 5.9 Radiograpy Permit
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 44 of 45
ENDORSEMENTS FOR THE CONTINUED SAFETY OF THE WORKSITE
PIPELINES DIVISION Ö«HÉfC’G •ƒ£N IôFGO
ATW No.
AUTHORISATION TO WORK π`ªY íjöüJ
WORK DESCRIPTION AND RISK ASSESSMENT :
1(a) COMPANY/CONTRACTOR :
1(b) TASK OUT LINE:
13. WORKSITE ENDORSEMENT :
ôWÉîŸG º««≤Jh πª©dG ∞°Uh
∫hÉ≤ŸG / ácöûdG
á©fɪŸG ΩóY ádÉ°SQ ºbQ
Other Suppoting Documents: iôNCG äÉ≤ë∏e
πª©dG á≤jôW ∞°Uh hCG á«°Sóæ¡dG äGAGôL’G
áeóîà°ùŸG Iõ¡LC’G
Tick as appropriate
5. PRECAUTIONS REQUIRED :
á«FÉbƒdG äGAGôLE’G
Yes No N/A
§≤a ájhój äGhOCG
á«FÉHô¡c äGhOCG
ábÉW ó«dƒJ äGhOCG / ΩÉ◊
»μ«fÉμ«ŸG ôØ◊G
√É«e Öë°S áî°†e
á«ëFÉØ°U OÉæ°SEG õFÉcQ
•ƒ£ÿG â– »≤aC’G ôØ◊G ∫ɪYCG
iô`NCG
Temp. Crossing Reqd.
Temp. Fence Reqd.
Shoring/ Barriers Reqd.
Monitor Ground Settlement
Monitor water accumulations
Warning Signs.
Other (Specify)
âbDƒe QƒÑY
âbDƒe êÉ«°S
õLGƒM / OÉæ°SEG
¢VQC’G •ƒÑg iƒà°ùe áÑbGôe
√É«ŸG ™ªŒ áÑbGôe
ájôjò– äÉMƒd
iô`NCG
1st Week
Time
initial
Tuesday:
Time
initial
Thursday:
Wednesday:
Time
initial
Time
initial
Friday:
Time
initial
Time
Authorized
work start
Authorized
work start
Authorized
work start
Authorized
work stop
Authorized
work stop
Authorized
work stop
™¡©gEG
Name : º°S’G
Position : áØ«XƒdG
Signed : ™«bƒàdG
Date : ïjQÉàdG
NOTIFICATION
7. NOTIFICATION OF OTHERS :
iôNC’G äÉ¡÷G ÆÓHEG
(Details to be entered where applicable)
GASCO Site:
Other OPCO:
ADCO Site:
Third Party
OPERATIONS SITE ENDORSEMENT
Police Approval (Stamp)
14. OPERATIONS SITE ENDORSEMENT:
Assest Operator / Area Authority acknowledges and conf irms continued safety of the work during site visit.
Other
MAINTENANCE / ENGINEERING / PROJECT REVIEW
8. MAINTENANCE / ENGINEERING / PROJECT REVIEW :
(This section is applicable for Gasco Activities).
™jQÉ°ûŸG / á°Sóæ¡dG / áfÉ«°üdG º°ùb ≥«bóJ
Saturday:
I have reviewed the workscope. HSE Requirements and Precautions as detailed in Section 1 to 5 inclusive:
Name : º°S’G
Position : áØ«XƒdG
Sunday:
Monday:
Tuesday:
Wednesday:
Thursday:
Friday:
Day / Date
Signed : ™«bƒàdG
initial
Date : ïjQÉàdG
ATW ISSUER
Time
initial
Time
initial
Time
initial
Time
initial
Time
initial
Time
initial
Time
1st Week
9. PIPELINES OPERATIONS SUPERVISOR : äÉ«∏ª©dG ±öûe
I have reviewed the proposed workscope, equipment to be used and precautions detailed in Section 1 to 6 inclusive. Work may proceed for the undernoted
period (maximum 28 continuous days)
Date: From:
To:
From:
Area Authority to visit worksite (Tick as applicable) Daily:
Weekly:
To:
Operations
Operations
2nd Week
No objection Certif icate Ref.:
Engineering Procedure or Method Statement:
6. ATW ORIGINATOR :
Operations
Yes No
initial
Authorized
work stop
3rd Week
܃ÑfC’G §N øe áaÉ°ùŸG
Time
Authorized
work start
4th Week
DISTANCE FROM PIPELINE
Hand Tool Only
Powered Tools
Welding/ Generating Sets
Mechanical Digger
De-watering Pump
Sheet Piling
NDRC
Other (Specify)
Maint /Eng / Project
Activity Performer
Activity Performer
2. DESCRIPTION OF WORK: πª©∏d »∏«°üØJ ∞°Uh The permitted scope of work, which may be undertaken within the specified location is as outlined below.
á«aÉ°VG iôNCG äÉeƒ∏©e
á≤ë∏e äÉeƒ°SQ
Monday:
Day / Date
initial
4. EQUIPMENT TO BE USED :
Conf irms worksite left safe when work stops.
Sunday:
Saturday:
1(C) PIPELINES SPECIFIC LOCATION:
Ö«HÉfC’G •ƒ£N ™bƒe
3. OTHER SUPPORTING DOCUMENTS:
ATW Acceptor conf irms no conf l ict with other Permit or activity prior to worksite endorsement
and accepts responsibility for worksite.
2.
Mobile No.
πª©∏d ΩÉY ∞°Uh
Supporting sketches/ drawings Attached:
1.
2nd Week
3rd Week
N/A
Activity Performer
4th Week
Name : º°S’G
Position : áØ«XƒdG
Signed : ™«bƒàdG
Date : ïjQÉàdG
ATW ACCEPTOR
10. ACCEPTOR : íjöüà∏d
on behalf of Work Party
º∏à°ùŸG
Name : º°S’G
I have read and understood the stated precautions and agree to observe them.
Position : áØ«XƒdG
Signed : ™«bƒàdG
Date : ïjQÉàdG
Activity Performer /
Operations
Operations
EXTENSION TO VALIDITY PERIOD
11. EXTENSION TO VALIDITY PERIOD : íjöüàdG IÎa ójó“
Pipelines Operations Supervisor
(Maximum of 28 continuous days for each extension)
There has bee no change to the original workscope, equipment to be used or precautions required. Work may continue until the undernoted date.
To: Date:
Name:
Position:
Signed:
Date:
To: Date:
Name:
Position:
Signed:
Date:
To: Date:
Name:
Position:
Signed:
Date:
CLOSURE OF AUTHORISATION TO WORK
12(a) WORK COMPLETION :
πª©dG AÉ¡àfEG
(Activity Performer)
The job has been completed
The Work Site is clear and safe
Housekeeping is satisfactory
Name:
Signed:
Date:
Position:
12(b) WORK COMPLETION: πª©dG
AÉ¡àfEG
I acknowledge that work is complete.
This Authorisation to Work is Withdrawn
(Operations Supervisor)
Area Authority
Initial
Name:
Position:
Signed:
Date:
Distribution: White Original - Worksite; Yellow - PCF Copy; Pink - Contractor/ Eng Copy
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 5
Page 45 of 45
ACTIVITY SEQUENCE
CONTROL FORM
CHAPTER 6
ACTIVITY SEQUENCE CONTROL FORM
CONTENTS
Section
Page
6.1
OBJECTIVE
2
6.2
Use of Activity Sequence Control (ASC) forms
2
6.2.1
Identifying the Need for an ASC
2
6.2.2
Use of ASC forms in the Permit to Work System
2
ILLUSTRATIONS
Figure 6.1
COMPLETING AN ASC FORM
3
Figure 6.2
ASC CONTROL FORM
4
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 6
Page 1 of 4
CHAPTER 6
ACTIVITY SEQUENCE CONTROL FORM
6.1 OBJECTIVE
The Activity Sequence Control (ASC) form provides a useful tool in the PTW
System for work that involves several stages, or is complex, by allowing the work
to be described in a stepwise sequence, whereby:
•
the hazards are identified for each work activity
•
the controls to mitigate the associated risks are defined
•
the responsible parties at each stage are identified
The use of an ASC is recommended whenever a Work Permit covers more than
one work activity (see Chapter 3, Section 3.3.4), which requires clear identification
of boundaries of responsibility, e.g. more than one Trade discipline is involved.
6.2 Use of ASC in the Permit to Work System
The ASC is not intended to be a substitute for a Maintenance/ Engineering Method
Statement, but more a sequential listing of tasks so that hazard identification and
application of controls is structured. In particular, it provides a control mechanism
should any stage of the work require a signature of approval before proceeding to
the next stage.
An annotated version of the ASC, which provides guidelines for its completion, is
given in Figure 6.1.
A blank copy of the ASC Form is provided in Figure 6.2.
6.2.1 Responsibility for Identifying the Need for an ASC
The Activity Risk Assessment (ARA) team will normally be responsible for
identifying the need for, and the writing of an ASC (see Chapter 3, Section
3.4.2). An ASC will normally be presented with the Permit at the PTW
planning meeting for review and discussion, and is to be cross-referenced
in Box 4c of the Work Permit. Where incorporated, it is to be included in the
Toolbox Talks associated with the work.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 6
Page 2 of 4
* An asterisk next to an activity number
denotes a hold point beyond which
further approval is required.
ASC No.
*
Activity
No
SubActivity
No.
1. Provide a unique
reference number on the
ASC for record purposes
ACTIVITY SEQUENCE CONTROL FORM
TASK:
Sequential Activity Description
6. Provide a brief
description of the critical
activities and associated
sub-activities
4. Identify any critical activity
requiring a control.
Mark with an asterisk (*) to
indicate where an
approval signature of the
Responsible Person is
required to confirm the
ste has been com leted
2. Enter details of main
Task (as detailed on
the Work Permit)
Hazards Identified
7. List the Hazards
associated with the
critical activity (from
the ARA)
Associated
Work Permit:
Controls Required
* Responsible
Person
8. List the Controls
required to mitigate
the risks associated
with the hazards
3. Enter the unique number of
the Associated Work Permit
Step
Complete
Remarks
11. Provide
explanatory
notes where
considered
necessary
5. Identify any key
sub-activity
associated with
the main activity
9. Nominate the Responsible
Person, who is to confirm that
the required controls are in
place, and the critical step or
sequence in the activity is
completed
10. Box for the Signature of
the Responsible Person
(where indicated with an
asterisk)
Signature confirms the
critical step is complete
and provides the approval
to proceed to the next
step in the sequence
Figure 6.1 – COMPLETING AN ACTIVITY SEQUENCE CONTROL (ASC) FORM
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 6
Page 3 of 4
* An asterisk next to an activity number
denotes a hold point beyond which further
approval is required to proceed to next step.
ASC No.
*
Activity
No
SubActivity
No.
ACTIVITY SEQUENCE CONTROL FORM
TASK:
Sequential Activity Description
Associated
Work Permit:
Hazards Identified
Controls Required
Responsible
Person
* Step
Complete
Remarks
Figure 6.2 – ACTIVITY SEQUENCE CONTROL (ASC) FORM
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 6
Page 4 of 4
TOOLBOX TALKS
CHAPTER 7
TOOLBOX TALKS
CONTENTS
Section
7.1
Page
INTRODUCTION
7.1.1 Deciding on the need for a Toolbox Talk
7.1.1.1 Checklist for identifying need for Toolbox Talk
2
3
3
7.1.2 Format of the Toolbox Talk
4
7.1.3 The Presenter of the Toolbox Talk
5
7.1.4 Checklist for Toolbox Talk Presenter
6
APPENDICES
APPENDIX 1
TOOLBOX TALK RECORD FORM
7
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 7
Page 1 of 7
CHAPTER 7
TOOLBOX TALKS
7.1 INTRODUCTION
This Section supports the Activity Risk Assessment Process described in Chapter 3,
Section 3.4 and should be read whilst referring to the Work Permit (Chapter 5,
Figure 5.1).
One of the last steps in the Activity Risk Assessment (ARA) Process is to discuss
the Work Permit, and any supporting Permits or Certificates, with the persons who
will actually be carrying out the work, and therefore be directly exposed to possible
release of hazards. This is achieved by holding a 'Toolbox Talk '.
Toolbox Talks are an essential element of safe working practices in GASCO’s sites
for both GASCO and contractor staff. The purpose of the talk is to discuss with the
working party:
• What the work activities will be;
• What hazards have been identified that will require controls during the course of
the work;
• What those controls are and how the work party will be affected.
The work party may, by virtue of their experience identify further hazards or may be
able to suggest alternative, or improved, controls. Where this is the case, the
hazards and additional precautions section of the Permit should, if necessary, be
modified and initialled after consultation and agreement with the validating and
issuing authorities.
The Originator of the Permit should formally capture this feedback by updating the
ARA, which can then be utilised the next time the work is undertaken.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 7
Page 2 of 7
7.1.1 Deciding on the need for a Toolbox Talk
The requirement for a Toolbox Talk will be decided by the Permit Originator,
based on his judgement of the risks involved and the work party’s experience
and familiarity with the task.
A formal Toolbox Talk is not normally required for routine jobs, covered by
maintenance procedures, which are carried out by competent staff and
which are undertaken frequently.
If the job is unusual, complex, is done infrequently, or, is being done by new
persons then a formal Toolbox Talk is required. The Toolbox Talk need not
cover all of the work at the same time. The Toolbox Talks may be given at
different stages of the job and should, where applicable, be linked to the Activity Sequence Control Form (ASC).
7.1.1.1 Checklist for identifying the need for a Toolbox Talk
To help the Originator decide if a formal Toolbox Talk is required
guidance is given in the matrix below
Work Aspect
Yes
No
Are there any Inexperienced (work experienced) Members
in the Work Party?
Is the Task unfamiliar to the Work Party?
Is the Work Site unfamiliar to the Work Party?
Is the Work Scope of a complex nature?
Is Multi-Trade Co-ordination required?
Is the Task HSE Critical?
Is the Task Operationally Critical?
Are hazards, or potential hazards, present?
Has there been any change to Work Scope?
Can Adverse Weather Conditions affect the Task?
Are Operations or Specialist Personnel to be
present?
If the answer to all questions is NO, a formal Tool Box talk is not required.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 7
Page 3 of 7
7.1.2 Format of the Toolbox Talk
Where there is a perceived higher risk, the Permit Originator should stipulate the
requirement for a formal record of the Toolbox Talk. In such cases, the Toolbox
Talk is to be recorded on the Toolbox Talk Record Form on the back of the PTW
The Toolbox Talk Record Form provides an effective communication means for
ensuring the work party are:
•
•
•
•
•
•
•
•
•
Aware of the work scope;
Aware of the hazards;
Knowledgeable as to the methods/ procedures to be adopted;
Aware of the PTW precautions/ controls;
Aware of any constraints;
Aware of what tools and equipment are to be used;
Aware of Environmental considerations;
Aware of any potentially conflicting activities;
Able to clarify any issues and provide comments.
Where included, the Toolbox Talk Record Form should be cross-referenced by
ticking the box in Section 4c of the Work Permit.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 7
Page 4 of 7
7.1.3 The Presenter of the Toolbox Talk
The presenter of the Toolbox Talk(s) is to be agreed at the Daily PTW Meeting.
It is normally the person who knows most about the job. Depending on the
circumstances, it may be more than one person. For example, an Operations
person rather than an Engineering member of staff can better describe hazards
that may arise from Operations.
All members of the work party must indicate that they understand the Toolbox
Talk. Where different nationalities are involved, it may be necessary to appoint
an additional person who is conversant in that language, to assist the presenter
in the talk, in order to overcome any language barriers or literacy issues.
The Toolbox Talk should be repeated if:
(i).
The work party changes or new personnel are assigned to the work party;
(ii).
Circumstances, or conditions, relating to the work activity change;
(iii).
The work enters a different phase.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 7
Page 5 of 7
7.1.4 Checklist for the Toolbox Talk Presenter
After giving the Toolbox Talk, the Presenter should confirm the understanding of
the Work Party by using the following checklist as an aide-memoir:
Can all the personnel in the Work Group answer YES to the following questions?
Are all members of the work party aware of the hazards involved with the
work activity?
Are all members of the work party aware of the control measures required
to mitigate the risks associated with the hazards?
Are those people in the work party who are responsible for implementing
these control measures aware of their responsibilities?
Are these control measures in place?
Is everyone aware of what is being done at the worksite?
Is the work party aware of what everyone else is doing at the worksite?
Is there other work ongoing in close vicinity to the worksite, which the work
party need to be aware of?
Does the Person in Charge of the Worksite (PICWS) know an additional
Toolbox Talk is required should there be any significant change to the work
scope?
Does the PICWS understand the requirement to provide a Toolbox Talk to
any new people joining the work party?
Are there any Language/ Literacy Issues?
Does everyone know what to do in the event of a site alarm or
emergency?
If the answer to any of these questions is NO, then the safety of
people is at risk and must be addressed.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 7
Page 6 of 7
TOOLBOX TALK RECORD FORM
All personnel involved in the work activity must be participate in the Toolbox Talk and sign below as being present.
Checklist / Prompt for Discussions (Tick where applicable)
Types of Operation to be executed
Crane / Lifting requirements
Methods/ Procedures to be adopted
Supplementary Permit / Certificate Requirements
PTW / ARA Precautions & Controls
Hazards & Hazardous substances used / present
Safety Equipment and Location
Isolation Requirements
Individual Responsibilities
Conficting Activities
Access / Egress
Work in adjacent areas
Tests / Monitoring
Environmental considerations
Work Equipment
Waste Management
Production / Operational Constraints
Site Rules
General Comments / Observations Identified during Toolbox
Action required?
Yes
No
Details of persons attending Toolbox Talk
Name
Trade / Discipline
Signature
Date
Toolbox Talk conducted by:
Name:
Signed:
Date:
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 7
Page 7 of 7
PERMIT CONTROL FACILITY
AND ADMINISTRATION OF PTW
CHAPTER 8
TOOLBOX TALKS
CONTENTS
Section
8.1
Page
OBJECTIVE
2
8.1.1
PCF Requirements
2
8.1.1.1
Purpose of PCF
3
8.1.1.2
Layout and Location of PCF
3
8.1.1.3
Facilities within PCF
4
8.1.2
PCF- Principles of Operation
5
8.1.3
PCF- Operating Rules
5
8.1.4
Segregation of Permits in Display Racks
6
8.1.5
PTW Administration and Document Control
8
8.1.5.1
Permit Return
8
8.1.5.2
Archiving of Permits
9
ILLUSTRATIONS
Figure 8.1
Representation of Permit Lifecycle with PCF Display
10
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 8
Page 1 of 10
CHAPTER 8
PERMIT CONTROL FACILITY AND ADMINISTRATION OF THE PTW SYSTEM
8.1 OBJECTIVE
A fundamental requirement of any PTW System is that it provides a suitable
display of permitry on the facility, in a central location, to allow staff an overview of
current status. It is also required that all closed out permitry be archived in a
systematic fashion for easy reference and follow-up auditing purposes.
This section contains the detailed procedure for the handling of Work Permits,
supporting Permits and Certificates, and other related documents as they pass
between signatories and are administered through the Permit Control Facility
(PCF).
8.1.1 Permit Control Facility Requirements
8.1.1.1 Purpose of the Permit Control Facility
The Permit Control Facility (PCF) will be provided in a central point
of the Plant or Pipeline facility through which all Permits pass each
time their status changes, i.e. when Authorised, Endorsed,
Suspended or Closed.
This enables a check to be made that the work specified does not
conflict with any ongoing Permit work. It also allows a continuous
display of work in progress to be maintained.
It can, in addition, provide the venue for the daily Permit-to-Work
(PTW) meeting whereby all work requirements will be discussed
and agreed.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 8
Page 2 of 10
8.1.1.2
Layout and Location of the PCF
The size and layout of the PCF will depend upon the complexity and
configuration of the facility. For a small and less complex facility it may be a
section of the Control Room, whilst for a more complex facility, if space
permits, it may merit a separate room.
The PCF should ideally be located in, or in close proximity to, the Control
Room or other central facility. Where this is impractical, the location should
be selected carefully to ensure that it is readily accessible to users, and will
not cause excessive additional journeys for personnel obtaining signatures.
A PCF has to be of sufficient size to house, in one location, all the
information displays boards, permit racks, and all the relevant files and data
that are required to be stored, for the Asset under the authority and control
of the Asset Operator. Where there is more than one Asset, with several
Asset Operators (e.g. Habshan), it is permissible to have separate PCF
facilities, providing the Shift Superintendent (the Asset Holder) can maintain
an overview.
Within the PCF, there should be physical separation between the occupants
and the customers so that only nominated personnel can alter the displayed
data.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 8
Page 3 of 10
8.1.1.3 Facilities Within the PCF
Permit Rack: As a minimum, there are to be conventional racks for the display
of paper copies of all Permits from all departments on the Plant or Pipeline.
It is to be arranged in such a way that Permit location and status are readily
visible. This enables staff to readily check which equipment is under
maintenance and is not available for operation.
Permit Location Board: Ideally, there should be a plan of all areas and units
of the facility showing, as appropriate, the Hazardous Areas in correct
geographical orientation. The location of all Permit work in progress can be
indicated with suitable markers, together with safety system inhibits and the
position of barriers and scaffolding work.
Firemain and Fire & Gas System Schematic Diagrams: It is useful for
schematic diagrams of the Firemain and Fire & Gas System network to be
displayed in the PCF. These can be arranged in such a way that equipment for
maintenance or repair can be indicated in a highly visible manner. This
provides an indication of fire and safety systems not available for operation.
Desk and Counter Arrangement: This should be arranged to suit the
configuration of the PCF. It is recommended that it provide physical separation
between the customers and the Issuing Authority. This will allow the customers
visibility of the information displayed whilst ensuring that only authorised
personnel can alter the displayed data.
The Shift Controller, who is the Asset Operator responsible for shift operations,
will manage the PCF. The Assistant Shift Controller may assist him but there
must be clear understanding as to their individual roles and responsibilities,
when changing Permit status and updating displays, to avoid potential conflict
situations arising.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 8
Page 4 of 10
8.1.2 PCF - Principles of Operation
In the PCF, for each asset under the control of the Asset Operator (Shift
Controller), all Permits and systems isolation boundaries will be systematically
displayed in one location, so that operators can readily see and check which
equipment is isolated for maintenance and not available for operation.
At the PCF, staff will be able to obtain key information to aid their decisions with
respect to Permits and the isolating and de-isolations of equipment. Data
displayed will cover the whole facility.
The facilities of the PCF are to be available throughout periods when work is in
progress on the Plant. When unattended, the PCF should be secured to
maintain the integrity of the information it contains.
8.1.3 Review and Control of Work under PTW
No work under a Permit is to be commenced until that Permit has been reviewed
by the Asset Operator (Shift Controller) to give confirmation that:
(1) The work does not clash with that being undertaken under the authority of
any other Permit or isolation.
(2) The Authorised Signatory is correct for the category of work and that the
Permit is correctly filled in.
No isolation or De-isolation is to be started until the appropriate
isolation/deisolation details are documented and agreed by the Shift Controller.
The Shift Controller should confirm that the proposed isolation boundary is
compatible with any other isolation boundaries in force under the PTW System.
Only when the above has been properly completed may the Permit be issued.
All Suspended and Closed Permits are to be displayed separately from those
Endorsed and Validated in the PCF Permit Display Racks.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 8
Page 5 of 10
8.1.4
Segregation of Permits in Permit Display Racks
The Permit Control Facility (PCF) is to provide a Permit Rack system, suitable
for the display of permitry, sub-divided by Area of the Plant or Pipeline facility.
The Permit Rack arrangement should allow for the further segregation and
visual presentation of permitry status within the following sections (see also
diagrammatic representation, Figure 8.1):
VALIDATED Section
After validation, by the Maintenance/ Engineering Authority and the Asset
Operator (normally the Operations Co-ordinator), the Work Permit, together
with its additional supporting certificates are placed in the 'VALIDATED'
section of the Permit Display Rack.
Operations staff is now aware that planned work in the Operations area
has been approved but has not yet started.
The Shift Controller shall, prior to arranging for any worksite preparations,
check the Permit against other Permits displayed in the PCF for conflicting
activities. If any conflicts are identified, he is to advise the Originator and
Operations Co-ordinator who will agree either to:
a) Withdraw the new Work Permit, or,
b) Arrange for other Permits to be Suspended or Cancelled, dependent upon
relative priorities.
Once this step is completed the Shift Controller may authorise Worksite
preparations to proceed. He is to ensure that any other supporting documentation
(e.g. isolation/ blind lists) is retained in the Permit Rack along with the
associated permitry.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 8
Page 6 of 10
8.1.4 Segregation of Permits in Permit Display Racks (cont.)
ENDORSED Section
When the worksite preparations and checks for conflict are complete, the permit
is issued by the Asset Operator (Shift Controller) and accepted by the
Maintenance/Engineering Authority who then takes the top, original (white) copy
to the worksite for Area Endorsement.
The 2nd (yellow) is transferred to the 'ENDORSED' section of the Permit
Display Rack
Operations staff is now aware that the planned work is actually proceeding
in the Operations Area.
At the start of each new shift period, prior to each subsequent endorsement of
the Work Permit, the Asset Operator will again check for conflict with any other
Work Permit or ongoing activity prior to releasing the Permit.
NB. It is permissible for the Assistant Shift Controller to carry out subsequent
endorsements of permitry on the agreement of the Shift Controller who is the
principle Asset Operator.
SUSPENDED Section
At the end of the Maintenance/ Engineering work period the original top copy, is
returned to the PCF and, together with the other copy, is transferred to the
'SUSPENDED' section of the Permit Display Rack. The permitry is to be
arranged with the top original (white) copy on top.
Operations staff are now aware that work which was in progress will/ has
been suspended but is to continue and isolations will/may be in place.
In the event of the Maintenance/Engineering Authority not returning permitry for
re-endorsement at the end of a shift period, the Asset Operator (Shift Controller
or Assistant Shift Controller) should change the display to SUSPENDED. As the
yellow copy will be displayed (instead of the white), it will be evident to the
incoming Asset Operator that action must be taken to follow-up with the
responsible Maintenance/Engineering Authority.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 8
Page 7 of 10
CLOSED Section
When work has been completed, or a new permit is required, all the permitry
is transferred to the ‘CLOSED’ section of the Permit Display Rack.
Operations staff is now aware that the work is completed or requires
new permitry.
Prior to arranging for any de-isolations of equipment, the Shift Controller is to
check that de-isolations will not conflict with any other Work Permit or work
activity in progress.
NB. The permitry can be archived only once it is confirmed that all
de-isolations are complete.
8.1.5
PTW Administration and Document Control
8.1.5.1
Permit Return
The persons working under the PTW (the Accepting Authorities)
should have no direct access to Permit Display Racks. Only the Shift
Controller (or his nominated Assistant) may alter permit displays.
To provide a workable system for the return of completed, or
suspended, permits at the end of the working period, or on completion
of the job, it is recommended to provide a tray system in the PCF.
The tray system should have (as a minimum) two trays to accept the
return of all original permitry:
•
One for CLOSED - for completed and/or expired Permits out with
validity periods.
•
One for SUSPENDED - where work is to continue.
The Shift Controller (or his assistant) will then transfer them to, and
update, the Permit Display racks.
Closed permitry is to remain in the CLOSED section of the rack until
it is confirmed that the worksite conditions are as stated and, where
applicable, de-isolations have been completed and equipment
returned to normal status.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 8
Page 8 of 10
8.1.5.2 Archiving of Permitry
All permitry is to be archived, by Area, in the PCF, or other adjoining facility,
which has a controlled access. The retention period for all permitry is 6 months
from the date of closure.
The recommended method of filing is to have a short term (monthly) archive
and long term (6-monthly) archive system. Closed out Permits are placed by
the dayshift Shift Controller into the short-term archive for later filing in the
long-term archive.
The long-term archive will have all Permits archived by month and area. Each
month the short-term archive contents will be transferred to the long-term
archive, replacing all permitry from the first month of the preceding 6-month
period. Such permitry removed from the Archive is to be destroyed.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 8
Page 9 of 10
P e rm itry
origination
P e rm itry
rev ie w
W o rk s ite
E n d o rse m e n t
YES
W o rk
sto p o r
c o m p le te
J o b c o m p le te ?
P E R M ITR Y
TO P C F
P C F D IS P L AY R A C K S
VA L ID AT E D
NO
W o rks ite
P re p a ra tio n s
Is th e re
any
c o n flic t?
NO
YES
S h ift Issue,
Acceptance &
E n do rs e m e n t
SU SPEN D ED
CLOSED
W o rk s ite re in s ta te m e n t
P e rm itry
a rc h iv ed
Figure 8.1: Graphical Representation of Permit Lifecycle with PCF Status Display
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 8
Page 10 of 10
PERMIT TO WORK SYSTEM
AUDITING AND REVIEW
CHAPTER 9
PTW SYSTEM AUDITING AND REVIEW
CONTENTS
Section
Page
9.1
OBJECTIVE
3
9.2
FREQUENCY OF AUDITS
3
9.3
TYPES OF AUDITS
3
9.3.1 Level 1 Compliance checks
3
9.3.2 Level 1 System checks
4
9.3.3 Level 2 System Operation checks.
5
AUDITING OF PTW TRAINING COURSES
6
9.4.1 Types of PTW Training Course Audits
6
9.4.2 Scope of PTW Training Course Audits
6
PTW SYSTEM REVIEW PROCEDURE
6
9.5.1 Introduction
6
9.5.2 Contributing Sources for Review Mechanisms
7
9.5.3 Annual Review of GASCO PTW System
7
PROPOSALS FOR CHANGE TO PTW SYSTEM
8
9.4
9.5
9.6
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 9
Page 1 of 13
CHAPTER 9
PTW SYSTEM AUDITING AND REVIEW
CONTENTS
ILLUSTRATIONS
FIGURE 9.1
PROFORMA - PTW SYSTEM CHANGE PROPOSAL
9
APPENDICES
APPENDIX 1
PTW AUDIT FORM – LEVEL 1, DOCUMENTATION
10
Form W: Weekly Permit to Work Checks
APPENDIX 2
PTW AUDIT FORM – LEVEL 1, SYSTEM CHECKS
12
Form M: Management and Administration of PTW System
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 9
Page 2 of 13
CHAPTER 9
PTW SYSTEM AUDITING AND REVIEW
9.1 OBJECTIVE
To periodically review and monitor the effectiveness and the application of the
GASCO PTW System.
9.2 FREQUENCY OF AUDITS
Auditing of the PTW system (including the ATW) will take place at Level 1 and
Level 2 as described below.
Type of audit
Frequency
Level 1 Compliance Check
Level 1 System Check
Lead Auditor
Weekly using Form W
(Monthly for Pipelines)
Monthly using Form M
(Quarterly for Pipelines)
Plant and Pipeline
Vice-President
Annually
HSE Vice-President
Level 2 System Operation
Site to nominate
9.3 TYPES OF AUDITS
9.3.1 Level 1 Compliance checks
The sites will prepare an annual programme of Level-1 Compliance checks.
The programme will:
• Identify those who will participate as Lead Auditors and Audit Team
Members, including Contractors;
• Have a minimum of one audit of a live Permit, each week, (monthly in the
case of Pipelines)
• Include all types of supporting Permits and Certificates;
• Include all areas of the site where the PTW system applies;
• Include work by both Site Personnel and Contractor staff.
• The audit will use the standard audit checklist Form W (see APPENDIX 1)
which has Guidance Notes included on the reverse side
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 9
Page 3 of 13
9.3.2 Level 1 System checks
The Sites will prepare an annual programme of Level-1 Monthly System checks
to be carried out by the Plant or Pipeline Vice-President, or his delegate. The
programme will:
•
Confirm the standards of the Daily PTW meeting are maintained
(see Chapter 3,Section 3.5.2) by attending one of the meetings;
•
Confirm that the process of Risk Assessment is being correctly followed
• Check that Permits are being displayed correctly in the Permit Control Facility
(see Chapter 8, Section 8.1.4);
•
Confirm that the process for PTW issuing and handover to the acceptor in the
PCF is adequate
•
•
Confirm that the PTW Authorisation Register is up to date (See Chapter 2)
Check that PTW archiving is being done according to procedures (see Chapter 8,
Section 8.1.5.2)
•
Check, by reviewing previous Incident Report statistics, that any incidents
involving Permits have been reviewed for potential impact on the PTW System;
•
•
Check the status of the RAP's from the Level-1 Compliance checks;
Include a review of the Register of Work Activities for Work Undertaken not
requiring a Permit (see Chapter 3, Section 3.3.1);
•
Confirm that the Trip and Alarm Defeat register in the MCR is being operated
correctly;
•
Confirm that Shift Handover Logs contain written information on ongoing
Permits, particularly those that have an impact on safety systems.
The audit will use the standard audit checklist Form M (see APPENDIX 2) which
has Guidance Notes included on the reverse side. The Plant Division Vice President
(or his delegate) is responsible for producing the Remedial Action plan (RAP)
resulting from the audit. The documented actions are to be entered into the HSE
Tracking System, by the HSE Superintendent, for subsequent review by HSE.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 9
Page 4 of 13
9.3.3 Level 2 System Operation checks.
HSE Division will prepare an Annual Programme of PTW System operation
checks (one per site). The programme will:
• Confirm that the level 1 audit programmes are being maintained;
• Confirm lateral learning is being maximised between sites in the review of
RAP's;
• Identify areas for improvement on sites and/ or the PTW System arising from
RAP's.
HSE is responsible for:
•
Preparing an overview report at the end of the Level-2 programme and
submitting to SVP (O)
•
Producing any Remedial Action Plan resulting from the Level 2 audit.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 9
Page 5 of 13
9.4
AUDITING OF PTW TRAINING COURSES
9.4.1 Types of PTW Training Course Audits
There are to be three PTW courses:
(1) User.
(2) Permit Signatories.
(3) PICWS
The Plant or Pipeline Vice-President is responsible for ensuring a
comprehensive training programme is in place (see Chapter 2)
9.4.2 Scope of PTW Training Course Audits
The audit provides a mechanism for ensuring that the Training Standards
are maintained across all courses. At least one audit of each course
should be conducted every year. The Plant or Pipeline Vice President has
the responsibility for ensuring the Audit of Training is carried out.
9.5
PTW SYSTEM REVIEW PROCEDURE
9.5.1 Introduction
The PTW System is subject to continuous reassessment and regular
review.
Though there will be information collated throughout the year, it is required
that no more than one amendment is issued per year (unless operational
reasons demand otherwise). The amendment needs to obtain the same
authorisation/approval level as the original PTW System Manual.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 9
Page 6 of 13
9.5.2 Contributing Sources for the Review Mechanism
Information for incorporation in the review will come from the following
sources:
(1) Proposals for Change.
(2) Audit Reports.
(3) Incident Reports.
(4) PTW training course feedback.
(5) Feedback from GASCO and Contractor Personnel.
All information from whatever source must be submitted in the form of a
Change Proposal (see 9.8) to enable it to be incorporated in the review
mechanism.
When the VP-HSE believes that sufficient changes to the PTW System
have been agreed to warrant it, he will request SVP (O) to authorise the
issue of an amendment to all controlled copies of the PTW System manuals.
9.5.3 Annual Review of Gasco PTW System
Proposals for changes to the PTW System Manual and/or procedures
therein should be submitted, in writing, by the respective Plant or Pipeline
Vice President, to the HSE custodian for initial review and approval. Any
subsequent amendments may then be authorised for issue by SVP (O),
if urgent, or, where not urgent, incorporated as part of the annual review
process.
There will be a formal annual review of the PTW System, and its operation,
led by the HSE Vice President. This review will encompass but will not
necessarily be limited to:
•
•
•
•
•
Incidents relating to PTW violations and non-compliances;
Level 1 and Level 2 Audit results;
The review of proposals for change to the PTW System;
All deviations applied for;
Lateral learning opportunities from the Industry and sharing of Best
Practice.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 9
Page 7 of 13
9.6
PROPOSALS FOR CHANGE TO THE PTW SYSTEM
Proposals for change or improvement to the PTW System and/or Manual can be
made at any time. The proposal should be raised and documented on the
standard PTW
System Change Proposal Form (see Fig. 9.1). This is to be discussed, agreed
and countersigned by the Plant or Pipeline Vice-President before being
forwarded to the HSE Vice-President. The HSE Superintendent will keep a copy
of the Change Proposal on location for reference purposes
The HSE Vice-President will review such proposals on a regular basis. Approved
proposals will be incorporated in the Annual review of the PTW System Manual.
Originators will receive notification of the action taken on their proposal or
reasons for rejection.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 9
Page 8 of 13
PTW SYSTEM CHANGE PROPOSAL
PLANT OR PIPELINE
DIVISION
CHANGE PROPOSED BY:
POSITION:
SIGNED:
DATE:
COUNTERSIGNED:
(Plant or Pipeline Division
Manager)
DATE:
PROPOSAL FOR
CHANGE:
SECTION:
PARAGRAPH:
REASON FOR CHANGE:
COMMENTS BY HSE DIVISION:
SIGNED:
DATE:
Fig 9.1 - Proforma for Proposal for Change to the PTW System/Manual
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 9
Page 9 of 13
Weekly Permit To Work Audits
Form W
Audit Date:
Audit Reference No.
Auditor
Signature
Work Permit No
Supporting Permit
/ Certificate
Sr.
No
01
02
03
04
05
06
07
08
09
10
11
Task
Type
Number
Description
Yes
Remarks
No
Is the Work Permit displayed at the work site?
Is the Work description, Location and Area
Classification correctly described on the Work Permit?
Is the work being undertaken the same as described
in Section 2?
Is the presence of the PICWS same as stated in Section 3?
Are all supporting Permits or Certificates, as listed in
Section 4, available at the work site?
Are all specific Precautions / HSE Requirements
listed in Sections 3 and 5, or required by the Risk
Assessment, in place?
Are all required signatures in place with dates and
times?
Is equipment tagged and locked as required by the
Isolation Confirmation Certificate?
Do members of the work party understand the
hazards and controls related to their work?
Are members of the work party complying with the PPE
requirements?
Is the permit copy displayed in PCF display rack
together with any supporting permits or certificates?
Immediate Remedial Action Taken:
Status
Further Remedial Action Required:
Action By
Audit Reviewed and Remedial Actions Approved (HSE Superintendent)
Name:
Signature:
Signature of Ops.
Superintendent
Target Date
Date:
Comments:
See notes on Reverse
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 9
Page 10 of 13
Weekly Permit To Work Audits
Form W
Notes
1. One PTW Auditor can conduct this PTW audit.
2. The PTW Auditor must be an approved Level 1 HSE Auditor
3. Audits will be conducted on Endorsed Work Permit at the work site
and in the PCF.
4. The PTW Auditor will take immediate corrective action when
required and advise Operations Supervision.
5. If any further action is required this must be discussed and agreed
by the Area Superintendent and the PTW Auditor
6. The HSE Superintendent will review the Audit and when proposed
remedial actions have been agreed with the Action Party he will
sign off the Audit Form
7. The Remedial Actions will be entered into a database and progress
will be monitored by HSE Department.
8. HSE Department will archive completed Audit Reports with a copy
of the permit.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 9
Page 11 of 13
Monthly Permit To Work System Audits
Form M
Plant or Pipeline
Division:
Audit
Date:
Audit Team
Members:
Audit Team
Leader :
Sr.
No
01
02
03
04
05
06
07
08
09
10
11
12
13
14
15
16
Audit Reference No.
Description
Yes
No
Remarks
Are the standards of the daily permit to work planning
meeting being maintained?
Are risk assessments being conducted in an adequate
manner?
Are members of the risk assessment team aware of
which activities require the Risk Assessment to be
signed by the Plant Vice-President?
Are permits and certificates correctly displayed in the
PCF?
Is the process for Issuing and Handover of the Permit to
the Acceptor adequate?
Is the total number of endorsed permits per area at a
manageable level?
Are drawings available which show Restricted Areas,
Unrestricted Areas and H2S zones?
Is the PTW Authorisation Register up to date ?
Are Permits being closed when work complete and
correctly archived ?
Is the Level 1 PTW Audit Programme complied with,
and are Level-1 PTW Audit reports correctly
completed?
Are remedial actions identified during Level -1 PTW
Audits being entered into the Remedial Action Tracking
System?
Is the Register of Work Not Requiring a Permit up to
date?
Is the Trip and Alarm Defeat Register being operated
correctly?
Is the Shift Handover Log being used to record ongoing
PTW activities?
Are any PTW Deviations in place correctly recorded in
the PTW Deviation register?
Is there a record maintained for EPI’s in the PCF?
Remedial Action Required:
Lead Auditor
Action By
Target Date
Date:
See notes on reverse
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 9
Page 13 of 13
Monthly Permit To Work System Audits
Form M
Notes
1.
The Plant Vice-President/ or his delegate will lead this Audit. Team
Members should include a representative of the HSE Department.
2.
The Lead Auditor will identify any Action Parties and advise them
of the required Remedial Action.
3.
This completed Audit Form will be sent to the HSE Superintendent
who will ensure any Remedial Actions are entered into the
Remedial Action Plan.
4.
HSE Department will archive completed Audit Forms
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 9
Page 12 of 13
AUTHORIZED DEVIATIONS
FROM PERMIT TO WORK SYSTEM
CHAPTER 10
AUTHORISED DEVIATIONS FROM PTW SYSTEM
CONTENTS
Section
Page
10.1 DEVIATION REGISTER
2
10.2 AUTHORISED SUPPLEMENTARY PROCEDURES (DEROGATIONS)
3
10.2.1 Token Header for the Derogation
3
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 10
Page 1 of 3
10.1
SITE DEVIATION REGISTER
Any planned deviations (see Chapter 1, Section 1.6) from the PTW System
must be requested by the Plant or Pipeline Vice-President, in writing, to the
Senior Vice-President Operations (SVP (O)).
Approved derogations are to be issued as a Supplementary PTW procedure,
authorised by SVP (O) and approved for issue by the Plant or Pipeline
Vice-President for subsequent inclusion in all site copies of the PTW System
Manual. The Plant or Pipeline Vice-President may cancel derogations when no
longer required.
The approved derogations are to be detailed in the Deviation Register, Table
10.1 below, and the approved Supplementary Procedures appended to each
controlled copy of the PTW System Manual (of that site) in Section10.2.
Table 10.1 – PTW System Site Deviation Register
Derogation
No.
Date
submitted
Derogation Details
Date
Approved
Date
Rescinded
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 10
Page 2 of 3
10.2 AUTHORISED SUPPLEMENTARY PTW PROCEDURES (DEROGATIONS)
10.2.1 Token Header for the Derogation
Each of the controlled copies of the PTW System Manual (as issued to
that site where the derogation is to exist) should have the approved
derogation appended in this section as a Supplementary Procedure.
GASCO Permit to Work Standard
Rev 2.0 2009
CHAPTER 10
Page 3 of 3
Download