One-day workshop on Transfer capabilities studies (TTC/ATC) by NRLDC Case study for Punjab and Delhi 14.03.2022 Methodology to assess TTC/ATC • Generation of a control area kept fixed and demand increases up to the limit where the congestion in network/Constraint observed. • For a certain Demand, Import capability is assessed for different generation scenario. Detailed Procedure for relieving congestion in real time operation under Regulation 4 (2) of the Central Electricity Regulatory Commission (Measures to relieve congestion in real time operation) Regulations, 2009 3.10.2 states that while assessing TTC limits there should not be violation of transmission element loading limit in n-1 contingency case. Change in Demand Change in generation Punjab TTC/ATC Punjab TTC/ATC Generation Considered State own generation = 6100MW (excluding Intrastate Solar Gen) N-1 Non-Compliance ICTs at Nakodar and Rajpura, With high generation at Rajpura TPS (>1300MW), the loading of 400kV Rajpura TPS-Rajpura D/C is observed to be N-1 non-compliant TTC/ATC of Punjab for Solar and Non-Solar hours (*TTC/ATC has been assessed considering frequent outages of TSPL units for different cases) Punjab Demand, Import and N-1 Non-Compliance of ICTs N-1 Loading limit: 710MW Punjab ATC: 7100MW N-1 Loading limit: 1110MW N-1 Loading limit: 460MW N-1 Loading limit: 1220MW Delhi TTC/ATC Delhi Power transmission Network Transmission Network Transmissi on line 400kV 220kV Intra OH UG state (CKMs) (CKMs) (nos) 10 246 3 108 ~1108 ~174 108 nos of line 10 nos of line Nodes 400/220kV 220/132or 66 kV Transformatio Nos n capacity (MVA) 7 11040 49 ~11590 New 400kv S/s Delhi TTC/ATC Generation Considered State own generation = 600MW N-1 Non-Compliance N-1 non-compliance issue at 400/220kV Bamnauli and Mundka ICTs. After commissioning of 400kV Dwarka(PG) S/s N-1 issue at Bamnoli got relived however Mundka would still be N-1 non-compliant with 2*315MVA ICTs. TTC/ATC of Delhi TTC= 6800 MW ATC= 6500 MW (Considering RM as 300 MW) 400/220kV, 1500 MVA, Dwarka-I GIS commissioned on Feb’22 (LILO of One Ckt of Bamnauli Jhattikara at 400kV Dwarka (PG) S/s. After commissioning of S/s and 400/220kV, 500MVA ICT-1,2&3, loading on Bamnoli ICTs reduced significantly. 220kV Dwarka-Papankalan-1 ckt-1&2 is newly commissioned line and significant load of Papankalan-1 is being fed by Dawarka S/s through this D/C line, earlier it was fed by Bamnoli. 220kV Narain400kV Dwarka a-Papankalan-3 ckt-1&2 LILOed at 220kV Dawarka. Relief on Mundka ICTs is only around 50MW, loading is still closed to N-1 loading limit, Hence shift of 400/220kV, 315MVA ICT-1 from Bamnoli to Mundka was recommended. Delhi Demand, Import and N-1 Non-Compliance of ICTs Delhi ATC: 6500MW 3 N-1 Loading limit: 1150MW N-1 Loading limit: 650MW Monitoring of Import, ATC violation of each states along with critical ICTs loading and ICTs N-1 Non-Compliance in a Single SCADA display at NRLDC Thank You