Change Order Cover Letter

advertisement
October 6, 2020
Madeline McCormick
The Whiting Turner Contracting Company
6305 Ivy Lane, Suite 800
Greenbelt, MD 20770
Re: Capital One Block A -WEB CHANGE ORDER NO. 001
WEB JOB NO. 19032VF
Madeline:
Please see attached, our Change Order Proposal No. 001 for the above referenced project. This work will be
completed upon written directive from Whiting Turner.
Our Scope:
*Please be advised that pricing assumes all work can be performed during normal business hours. Night
work and or weekend premiums are not included.
Work requested by:
Contract Drawing Reference:
Total Cost for the above referenced work:
Time Extension required due to change
Whiting Turner
n/a
$
N/A
Quoted prices are good for 30 days. If pricing is not approved within 30 days we reserve the right to reevaluate and adjust as necessary. Change Order work that is not billable within 30 days of completion is
subject to finance charge of 1.5% per month.
Sincerely,
W. E. BOWERS & ASSOCIATES, INC.
Matt King
Matt King
Project Manager
This proposal is based solely on the usual cost elements such as labor, material and normal mark-ups. It does not include any
amount for additional changes in the sequence of work, delays, disruptions, rescheduling, extended overhead, overtime,
acceleration, effects of change orders on productivity and/or impact costs. We expressly reserve the right to address any and all of
these related items of impact costs, which affect W. E. Bowers, prior to the closeout of the contract.
cc:
File: PCO #001