Concrete deck on Precast Beams Raw Risk Contingency Cost Estimate d cost of the event (£) £25,000 Time Estimate d time of the event (Days) 2 Severity (Quantitative Assessment of event severity) High Probability (Quantitative Assessment of event probability) Medium Risk Factor (Taken from risk matrix) 0.625 Cost of risk (£) Time of risk (Days) Comments or control measure puts in place £16,000 1.5 Extremely difficult to avoid use of crane to erect this scheme. Launching Jack or bearing failure Loss of stability during launching £125,000 12 Very high High 0.625 £78,125 7.5 Jacks and bearings under constant stress. Provide spares and standby fitting team. £650,000 90 Very high low 0.40 £260,00 0 36 Positioning and quantity of kentledge very important during movement of precast beams. Rehearsal of sequences and backup for computer controls essentials. Insufficient space on site to precast beams £150,000 60 High Low 0.50 £75.000 30 This construction technique requires previous sections to be used as a shutter (the surfaces will be matted later). A large space is required to undertake this operation. Investigate temporary used of adjacent waste land for this purpose. Event Crane Overturning Total Risk