MEHRAN UNIVERSITY OF ENGINEERING & TECHNOLOGY JAMSHORO PERT ENGR. ANEES AHMED VIGHIO Lecturer, Department of Civil Engineering MUET, Jamshoro PERT • PERT stands for Program Evaluation and Review Technique. • PERT can be used to determine the earliest/latest start and finish times for each activity, the entire project completion time and the slack(FLOAT) time for each activity. • PERT and CPM are similar in their basic approach, they do differ in the way activity times are estimated. PERT PERT is an extension of CPM. In reality, activities are usually subjected to uncertainty which determine the actual durations of the activities. It incorporates variabilities in activity duration into project network analysis. The potential uncertainties in activity are accounted for by using three time estimates for each activity PERT • For each PERT activity three times (optimistic, pessimistic and most likely times) are combined to determine the expected activity completion time and its variance. Thus, PERT is a probabilistic technique: it allows us to find the probability of the entire project being completed by any given date. • CPM, on the other hand, is called a deterministic approach. It uses two time estimate, the normal time and the crash time, for each activity Program Evaluation & Review Technique a) Optimistic Time b) Most Likely Time c) Pessimistic Time PROJECT EVALUATION REVIEW TECHNIQUE, (PERT) In the critical path method, the time estimates are assumed to be known with certainty. In certain projects like research and development, new product introductions, it is difficult to estimate the time of various activities. Hence PERT is used in such projects with a probabilistic method using three time estimates for an activity, rather than a single estimate, as shown in Figure. Optimistic time tO: It is the shortest time taken to complete the activity. It means that if everything goes well then there is more chance of completing the activity within this time. Most likely time tm: It is the normal time taken to complete an activity, if the activity were frequently repeated under the same conditions. Pessimistic time tp: It is the longest time that an activity would take to complete. It is the worst time estimate that an activity would take if unexpected problems are faced. Taking all these time estimates into consideration, the expected time of an activity is arrived at. The average or mean (ta) value of the activity duration is given by, The variance of the activity time is calculated using the formula, Probability for Project Duration The probability of completing the project within the scheduled time (Ts) or contracted time may be obtained by using the standard normal deviate where Te is the expected time of project completion. Probability of completing the project within the scheduled time is, Example A R & D project has a list of tasks to be performed whose time estimates are given in the Table 8.11, as follows. Example A R & D project has a list of tasks to be performed whose time estimates are given in the Table 8.11, as follows. a.Draw the project network. b.Find the critical path. c.Find the probability that the project is completed in 19 days. Time expected for each activity is calculated using the formula (5): Similarly,the expected time is calculated for all the activities . The variance of activity time is calculated using the formula (6). Similarly, variances of all the activities are calculated. Solution: • Expected time of completion of the Project = 24 Days • Critical Path: B-E-G-J • Zo(19 Days)= -2.466 Probability= 0.69% Example no 2 Draw Arrow Network and perform the PERT calculations for the following schedule of the Project. Also determine the probability of completion of the project in 37,50 and 57 Days. Activity IPA Optimistic Pessimistic 5 Most Likely 6 A - B A 4 5 18 C A 4 15 20 D B 3 4 5 E B, C 5 16 21 F B, C 10 14 18 G D,E,F 11 15 19 7 Solution Activity IPA Optimistic Most Likely Pessimistic Expected Time Standard Deviation Variance A - 5 6 7 6 0.33 0.1089 B A 4 5 18 7 2.33 5.428 C A 4 15 20 14 2.67 7.1289 D B 3 4 5 4 0.33 0.1089 E B, C 5 16 21 15 2.67 7.1289 F C 10 14 18 14 1.33 1.7689 G D,E,F 11 15 19 15 1.33 1.7689 Solution: • Expected Project time = 50 Days • Critical Activities= A-C-E-G • Non-Critical Activities= B-D-F • Z0(37)=-3.23 0.062 % • Z0(20)=0 50 % • Zo(57)=1.742= 95.9% Example no 3 Draw Arrow Network and perform the PERT calculations for the following schedule of the Project. Determine probability at 50 days Activity IPA Optimistic Most Likely Pessimistic A - 1 2 3 B A 3 6 15 C A 4 10 16 D A 2 4 6 E B 4 7 10 F B,C 3 5 7 G C,D 1 3 11 H E,F 4 5 18 I G,H 1 2 9 Assignment Problems THANK YOU !