lOMoARcPSD|13118480 Chapter 5 - Capacity Management Operations Management (The University of the South Pacific) StuDocu is not sponsored or endorsed by any college or university Downloaded by Quynh Anh Nguyen (quynhanhnguyenkris@gmail.com) lOMoARcPSD|13118480 CHAPTER 5 5.1. A work center consists of 4 machines each working a 16-hour day for 5 days a week. What is the weekly available time? Available time = 4 machines * 16 hour per day * 5 days a week = 320 hours per week 5.2. The work center in problem 5.1 is utilized 75% of the time. What are the hours per week actually worked? Rated capacity = 320 * 0.75 = 240 standard hours. We can expect to get 240 standard hours of work from that work center in an average week. 5.3. If the efficiency of the work center in problem 5.1 is 120%, what is the rated capacity of the work center? Rated capacity = 320 * 0.75 * 1.2 = 288 standard hours per week 5.4. A work center consisting of 7 machines is operated 16 hours a day for a 5-day week. Utilization is 80%, and efficiency is 110%. What is the rated weekly capacity in standard hours? Available time = 7 * 16 * 5 = 560 hours per week Rated capacity = 560 * 0.80 * 1.1 = 492.8 standard hours per week. 5.5. A work center consists of 3 machines working 8 hours a day for a 5-day week. If the utilization is 75% and the efficiency is 120%, what is the rated capacity of the work center? Available time = 3 * 8 * 5 = 120 hours per week Rated Capacity = 120 * -.75 * 1.2 = 108 standard hours per week. 5.6. Over a period of 4 weeks, a work center produced 50, 45, 40, and 55 standard hours of work. What is the demonstrated capacity of the work center? Demonstrated capacity = 50 + 45 + 40 + 55 / 4 = = 190 / 4 = 47.5 standard hours of work per week 5.7. In an 11-week period, a work center produces 1050 standard hours of work. What is the measured capacity of the work center? Measured capacity of the work center produces 1050 standard hours of work; = 1050 / 11 = 95.45 standard hours 5.8. In 1 week, a work center produces 85 standard hours of work. The hours scheduled are 80, and 75 hours are actually worked. Calculate the utilization and efficiency of the work center. Capacity required = 85 standard hours Efficiency = 85 / 75 = 1.133 * 100 = 113.33% Utilization = 75 / 80 * 100 = 93.75% Answer. Utilization is 93.75%; efficiency is 113.33% Downloaded by Quynh Anh Nguyen (quynhanhnguyenkris@gmail.com) lOMoARcPSD|13118480 5.9. A work center consisting of 3 machines operates 40 hours a week. In a 4-week period, it actually worked 355 hours and produced 475 standard hours of work. Calculate the utilization and efficiency of the work center. What is the demonstrated weekly capacity of the work center? Available time = 3 * 40 * 4 = 480 standard hours per week Demonstrated capacity = 355 + 475 / 2 = 830 / 2 = 415 standard hours 5.10. A firm wishes to determine the efficiency and utilization of a work center composed of 3 machines each working 16 hours per day for 5 days a week. A study undertaken by the materials management department found that over the past year the work center was available for work 12,000 hours, work was actually being done for 10,000 hours, and work was performed 11,480 standard hours. Calculate the utilization, efficiency, and demonstrated weekly capacity. Assume a 50-week year. Work center = 12,000 hours Hours actually worked = 10,000 hours Standard hours = 11,480 hours Available time = 3 * 16 * 5 = 240 Utilization = hours actually worked / available hours * 100% = 10,000 / 240 *100% = 41.67 *100% = 4,166.67 % Efficiency = standard hours produced / hours actually worked * 100 = 11,480 / 10,000 * 100% = 1.148 * 100% = 114.8% Rated Capacity = 240 * 41.67 * 1.15 = 11,500.92 Demonstrated Capacity = 12,000 + 10,000 + 11,480 / 3 = 33,480 / 3 = 11,160 standard hours 5.11. How many standard hours are needed to run an order of 200 pieces if the setup time is 1.3 hours and the run time 0.3 hours per piece? How many actual hours are needed at the work center if the efficiency is 130% and the utilization is 70%? Total standard time = set up time + run time = 1.3 + (200 * 0.3) = 1.3 + 60 = 61.3 standard hours (capacity required) Actual time = capacity required / (efficiency) (utilization) = 61.3 / (1.3) (0.7) = 61.3 / 0.91 = 67.36 ~ 67.4 actual hours Answer. 61.3 standard hours; 67.4 actual hours Downloaded by Quynh Anh Nguyen (quynhanhnguyenkris@gmail.com) lOMoARcPSD|13118480 5.12. How many standard hours are needed to run an order of 500 pieces if the setup time is 3.0 hours and the run time 0.2 hours per piece? How many actual hours are needed at the work center if the efficiency is 125% and the utilization is 85%? 5.13. A work center has the following open and planned orders for week 4. Calculate the total standard time required (load). Order Setup Time (hrs) Run time (Hours / Total Time (Hours) Quantity piece) Released Orders 120 300 1.00 0.10 31 standard hours 340 200 2.50 0.30 62.5 standard hours Planned orders 560 300 3.00 0.25 78 standard hours 780 500 2.00 0.15 77 standard hours Total Time (Standard time) 248.5 standard hours Released orders – 120 Total time = 1.00 + (300 * 0.10) = 31 standard hours – 340 Total time = 2.50 + (200 * 0.30) = 62.5 standard hours Planned orders – 444 Total time = 3.00 + (300 * 0.25) = 78 standard hours – 555 Total time = 2.00 + (500 * 0.15) = 77 standard hours Total time = 31 + 62.5 + 78 + 77 = 248.5 standard hours 5.14. A work center has the following open and planned orders for week 4. Calculate the total standard time required (load). Order Setup Time (hrs) Run time (Hours / Total Time (Hours) Quantity piece) Released Orders 125 200 0.25 0.12 24.25 standard hours 345 70 0.70 0.05 4.2 standard hours Planned orders 565 80 1.00 0.25 21 standard hours 785 35 1.50 0.15 6.75 standard hours Total Time (Standard time) 56.2 standard hours Released orders Total time =0.25 + (200 * 0.12) = 24.25 standard hours Total time = 0.70 + (70 * 0.05) = 4.2 standard hours Planned Orders Total time = 1.00 + (80 * 0.25) = 21 standard hours Total time = 1.50 + (35 * 0.15) = 6.75 standard hours Total time = 24.25 + 4.2 + 21 + 6.75 = 56.2 standard hours 5.15. Using the information in the following route file, open order file, and MRP planned orders, calculate the load on the work center. Routing Part 123: Setup time = 2 standard hours Run time per piece = 3 standard hours per piece Part 456: Set up time = 3 standard hours Run time per piece = 1 standard hour per piece Downloaded by Quynh Anh Nguyen (quynhanhnguyenkris@gmail.com) lOMoARcPSD|13118480 Open orders for parts Week 1 123 12 456 15 Load Report Week Released load Planned Load 2 8 5 1 3 5 5 2 Planned orders for parts 1 2 3 0 5 10 0 10 15 3 123 456 123 456 Total Load Week 1: Released order 123 = 2 + (12 * 3) = 38 456 = 3 + (15 * 1) = 18 Planned order 123 = 2 (0 * 3) = 2 456 = 3 + (0 * 1) = 3 Total time = 38 + 18 + 2 + 3 = 61 standard hours Week 2: Released order 123 = 2 + (8 * 3) = 26 456 = 3 + (5 * 1) = 8 Planned order 123 = 2 + (5 * 3) = 17 456 = 3 + (10 * 1) = 13 Total time = 26 + 8 + 17 +13 = 64 standard hours Week 3: Released order 123 = 2 + (5 * 3) = 17 456 = 3 + (5 * 1) = 8 Planned order 123 = 2 + (10 * 3) = 32 456 = 3 + (15 * 1) = 18 Total time = 17 + 8 + 32 + 18 = 75 standard hours Load Report Week Released load Planned Load Total Load 123 456 123 456 1 3 8 18 2 3 61 2 26 3 17 8 17 13 6 4 8 32 18 75 5.16. Complete the following load report and suggest possible courses of action Downloaded by Quynh Anh Nguyen (quynhanhnguyenkris@gmail.com) lOMoARcPSD|13118480 Week 18 19 Released 150 155 Load Planned Load 0 0 Total Load 150 155 Rated 150 150 Capacity (Over) / 0 5 Under Total Load calculations as follows: Week 18 = 150 + 0 = 150 Week 19 = 155 + 0 = 155 Week 20 = 100 + 80 = 180 Week 21 = 70 + 80 = 150 Total load = 150 + 155 + 180 + 150 = 635 20 100 21 70 Total 475 80 180 150 80 150 150 160 635 600 30 0 35 Total calculation for over capacity: Total Load – Rated Capacity Week 18 = 150 – 150 = 0 Week 19 = 155 – 150 = 5 Week 20 = 180 – 150 = 30 Week 21 = 150 – 150 = 0 5.17. Back schedule the following shop order. All times are given in days. Move time between operations is 1 day, and wait time is 1 day. Due date is day 150. Assume orders start at the beginning of a day and finish at the end of a day. Operation Work Operation Queue Wait Move Arrival Finish Total Number Center Time Time time time date date (days) (days) (Days) (days) 10 111 2 4 1 1 126 132 377 20 130 4 5 1 1 134 143 418 30 155 1 2 1 1 145 148 453 Stores 150 Since the due date of 150 is given, we will start here. Finish date of operation number 30 = 150 – wait time – move time - 30 = 150 -1 -1 = 148 Arrival date of operation 30 = Finish date – operation time – queue time - 30 = 148 -1 -2 = 145 Finish date of operation number 20 = 145 – 1 – 1 = 143 Arrival date of operation number 20 = 143 – 4 – 5 = 134 Finish date of operation number 10 = 134 – 1 – 1 = 132 Arrival date of operation number 10 = 132 – 2 – 4 = 126 Answer: The order must arrive at work center 111 on day 126 Downloaded by Quynh Anh Nguyen (quynhanhnguyenkris@gmail.com) lOMoARcPSD|13118480 5.18. Back schedule the following shop order. All times are given in days. Move time between operations is 1 day, and wait time is 1 day. Due date is day 200. Assume orders start at the beginning of a day and finish at the end of a day. Operation Work Operation Queue Wait Move Arrival Finish Number Center Time (days) Time time time date date (days) (days) (days) 10 110 4 3 1 1 176 183 20 120 2 4 1 1 185 191 30 130 3 2 1 1 193 198 Stores 200 Since the due date of 200 is given, we will start here. Finish date of operation number 30 = 200 – wait time – move time - 30 = 200 -1 -1 = 198 Arrival date of operation 30 = Finish date – operation time – queue time - 30 = 198 -3 -2 = 193 Finish date of operation number 20 = 193 – 1 – 1 = 191 Arrival date of operation number 20 = 191 – 2 – 4 = 185 Finish date of operation number 10 = 185 – 1 – 1 = 183 Arrival date of operation number 10 = 183 – 4 – 3 = 176 Downloaded by Quynh Anh Nguyen (quynhanhnguyenkris@gmail.com)