INSPECTION DATA SHEET FOR HOT INDUCTION BENDS

advertisement
Berkine South Area A
Oil Wells Development
INSPECTION DATA SHEET FOR
HOT INDUCTION BENDS
M. Shankar E
Morgante
EX-DE
01
07/02/2022
Final Issue
M Shankar E Morgante
M Sala
EX-DE
00
30/11/21
Issued for Comment
M Shankar E Morgante
M Sala
Validity
Status
Revision
Number
Date
Description
Validity
Status
Company logo and business name
Prepared
Checked
Project name:
Contractor
Approval
Approved
Company
Document ID:
BERKINE South Area A
Oil Wells Development
Contractor logo and business name
Contractor Identification
141204DLGB15710
Vendor logo and business name
Contract N. Job N. JA0702
Vendor Identification
Facility and Sub Facility Name:
Scale:
Order N
CAFC-BERKINE SOUTH
Location
Algeria
Sheet of Sheets
na
1/6
Supersedes N.
INSPECTION DATA SHEET FOR
HOT INDUCTION BENDS
Software: Microsoft Excel
Superaseded N.
Plant Area:
Plant Unit
n.a.
n.a.
File Name; 141204DLGB15710_EXDE01_06.xls
Contractor Document ID
141204DLGB15710
REVISION LIST
EXDE-00
EXDE-01
Issued for comment
Final Issue
HOLD RECORD
GENERAL NOTES
This document is property of Eni S.p.a.
It shall neither be shown to Third Parties nor used for purposes other those for which it has been sent
Sheet of Sheets
2/6
Validity
Revision
Status
Number
EX-DE
01
Contractor Document ID
141204DLGB15710
Sheet of Sheets
3/6
Validity
Revision
Status
Number
EX-DE
01
INSPECTION DATA SHEET FOR HOT INDUCTION BENDS
TABLE OF CONTENTS
Sheet
1
2
3
4
5
6
Cover
Revision
Index
Datasheet 1/3
Datasheet 2/3
Datasheet 3/3
References:
Project
1
141204DLST15708
2
141204DLGA15709
3
141204DLGC15711
141204BXSG04812
4
5
141204DLEB15707
141204DGSG03422
6
Supply Specification for Hot Induction Bends
Technical Datasheet for Hot Induction Bends
Required Document Datasheet for Hot Induction Bends
Specification for Pipeline Bend Coating
MTO for Onshore Pipeline System
Vendor’s Follow-up and ARH Requirements
COMPANY
7
03529.ENG.PLI.STD
8
28907.ENG.PLI.STD
Onshore Pipeline Transportation Systems for Hydrocarbons-Hot Induction Bends
Made from Pipe for Pipelines
Carbon Steel Line Pipe for Onshore and Offshore Pipelines
9
29001.ENG.CPI.STD
Painting and Coatings for Onshore Facilities
10
29006.ENG.CPI.STD
Painting System Sheets
11
12
20185.COS.GEN.STD
23005.ENG.PLI.STD
Handling and Protection of Materials and Equipment
Stacking of Pipes
International
13
ISO 15590-1
Petroleum and natural gas industries — Induction bends, fittings and flanges for
pipeline transportation systems —Part 1: Induction Bends
14
15
16
ASME B31.4
API 5L (46th Edition)
IOGP Spec. S-616
Pipeline Transportation Systems for Liquid Hydrocarbons and OtherLiquids
Specification for Line Pipe
Supplementary Specification to API Specification 5L and ISO 3183 Line Pipe
This document is property of Eni S.p.a.
It shall neither be shown to Third Parties nor used for purposes other those for which it has been sent
Sheet of Sheets
4/6
Contractor Document ID
141204DLGB15710
Validity Status
Revision Number
EX-DE
01
INSPECTION DATA SHEET FOR HOT INDUCTION BENDS
This data sheet specifies tha minimum inspection requirements to be met for the Supply of Induction to Company.
This document shall not relieve Supplier to prepare and issue for Company approval a supply-dedicated Inspection and Test Plan, in accordance with the requirements of
technical specification and Technical Data Sheet.
ITEMS:
Induction Bends
CONCERNED PARTIES:
C= COMPANY (2)
A= ARH (1)
E= CONTRACTOR
S= SUPPLIER
OFFICIAL AUTHORITY:
N/A
CERTIFYING AUTHORITIES:
OTHER:
N/A
TYPE OF INTERVENTION:
H
BINDING PRESENCE. The cycle continuationis bound to the presence
P
BINDING PRESENCE FOR THE % INDICATED IN THE NOTES
W
NOT BINDING PRESENCE. In case of unwitnessed test the Supplier is authorized to continues
the production cycle supplying the appropriate documents.
M
MONITORING
R
CHECK CARRIED OUT WITH RELEASE OF CERTIFICATE.
N
CHECK CARRIED OUT WITHOUT RELEASE OF CERTIFICATE.
C
CHECK HAS BEEN PERFORMED AND CERTIFICATE ISSUED.
D
SIMPLE DOCUMENTATION.
NOTES :
1
ARH
2
Company is: SH-FCP ENI (The Contracting Authority)
Autorité de Régulation des Hydrocarbures
3
Supplier shall follow the requirements of project specification 141204DLST15708
This document is property of Eni S.p.a. It shall neither be shown to Third Parties nor used for purposes other those for which it has been sent
Sheet of Sheets
5/6
Contractor Document ID
141204DLGB15710
Validity Status
Revision Number
EX-DE
01
INSPECTION DATA SHEET FOR HOT INDUCTION BENDS
POS.
C
A
Pre Inspection / Pre Production Meeting
H
W
Manufacturing procedure qualification tests
H
1
1.1
1.2
1.3
1.4
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3.2
3.3
3.4
3.5
3.6
Notes
S
H
H/R
Preliminary ARH Dossier
H
NDT Personnel and Procedures
H
R
H/R See Ref. 6
H/R
Material Certificates
W/R
N
Heat Treatment Tests
IN-PROCESS INSPECTION & TEST REQUIREMENT
W/R
H/R
Production Mechanical test- Tensile tests
W
H/R
Production Mechanical tests- Charpy V-natch
W
H/R
Hardness test -on body & hard spot
W
H/R
Non Destructive Examinations after heat treatment (UT on welding ends and MPI on whole external/internal surface)
W
H/R
Visual Examination
H
H/R
Dimensional testing (outside & inside diameter, OOR, wall thickness at intrados & extrados, & according to construction
drawings)
H
H/R
Residual Magnetism
W
H/R
FINAL INSPECTION & TEST REQUIREMENTS
3
3.1
E
PRE FABRICATION & PRODUCTION REQUIREMENTS
2
2.1
CODE OF
INTERVENTION
DESCRIPTION OF INSPECTIONS AND TESTS
Temporary Protection
N
H
Marking and packing
W
H
Final inspection for compliance with P.O Requirement
H
H/R
Review of Manufacturing Record Book
H
H
Final Inspectionfor acceptabce by Company
H
Final ARH Dossier
H
R
NOTES :
This document is property of Eni S.p.a.
It shall neither be shown to Third Parties nor used for purposes other those for which it has been sent
See Ref. 6
Sheet of Sheets
6/6
Contractor Document ID
141204DLGB15710
Validity Status
Revision Number
EX-DE
01
INSPECTION DATA SHEET FOR COATING OF HOT INDUCTION BENDS
POS.
CODE OF
INTERVENTION
DESCRIPTION OF INSPECTIONS AND TESTS
C
1
FOR INSPECTION of COATING OF BENDS, REFER to PROJECT SPECIFICATION 141204BXSG04812
NOTES :