Petroleum Development Oman L.L.C. Document title: Quality Management System for Project Delivery - Code of Practice. Document ID Document Type Security Discipline Owner Issue Date Version CP-190 Code of Practice Unrestricted Quality Management CFDH Quality Management 06 Aug 2014 2 Keywords: This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any part of this document may be disclosed to others or reproduced, stored in a retrieval system, or transmitted in any form by any means (electronic, mechanical, reprographic recording or otherwise) without prior written consent of the owner. Petroleum Development Oman LLC Version 2.0 Effective: Sep -14 This page was intentionally left blank Page 2 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC i Version 2.0 Effective: Sep -14 Document Authorisation Authorised For Issue – August 2014 Page 3 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Version 2.0 Effective: Sep -14 Petroleum Development Oman LLC ii Revision History The following table lists the four most recent revisions to this document. Details of all revisions prior to these are held on file by the issuing department. Version No. Date Author Checked Scope / Remarks 1.0 Sep. 09 UEQ UEOD First Issue 2.0 Aug. 14 UEQ UEOD Format revised, Quality Road Map added, FELT Review Comments incorporated. iii Related Business Processes Code Business Process ORP Opportunity Realisation Process iv Related Corporate Management Framework (CMF) Documents The related CMF Documents can be retrieved from the CMF Document Control. Doc. ID Document Title Policy PL-15 Quality Management Policy Code of Practice CP-117 Project Engineering Code of Practice CP-114 Maintenance & Integrity Management Code of Practice CP-180 Recruitment Code of Practice CP-131 Risk and Opportunity Management CP-129 Contracting and Procurement - CoP CP-142 Audits and Reviews Code of Practice Specification SP-2061 Engineering and Operations Technical Authority System SP-1122 Specification for Project Quality Plan SP-1171 Specification for Quality Management System for Product and Service SP-2065 Document Management for Projects Page 4 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC Version 2.0 Effective: Sep -14 Procedure PR-1247 Project Management of Change Procedure PR-1029 Competency Assessment and Assurance PR-1568 Corporate Document Management Procedure PR-1233 Contract & Procurement Procedure PR-1866 Quality Audit Procedure PR-2052 Project Quality Management system Review PR-2053 Control of Non-Conforming Product Procedure PR-2066 Managing Deviations from Standards and Procedures Guideline GU-611 PDO Guide to Engineering Standards and Procedures GU-711 Model Project Quality Plan v Related International Standards ISO9000 Quality Management System – Fundamentals and Vocabulary ISO9001 Quality Management System – Requirements ISO9004 Managing for the sustained success of an organization — A quality management approach ISO10005 Quality Management Systems – Guidelines for Quality Plans ISO10006 Quality Management Systems – Guidelines for quality management in projects ISO10015 Quality Management – Guidelines for Training ISO19011 Guidelines for Auditing Management Systems ISO/TS 29001 Quality Management Systems – requirements for the design, development, production, installation and service of products for the petroleum, petrochemical and natural gas industries ISO/TR 10013 Guideline for quality management system documentation Page 5 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC Version 2.0 Effective: Sep -14 TABLE OF CONTENTS i Document Authorisation ......................................................................................................... 3 ii Revision History...................................................................................................................... 4 iii Related Business Processes .................................................................................................. 4 iv Related Corporate Management Framework (CMF) Documents .......................................... 4 v Related International Standards ............................................................................................. 5 1 Introduction ............................................................................................................................. 8 1.1 Background ....................................................................................................................... 8 1.2 Purpose ............................................................................................................................. 8 1.3 Scope ................................................................................................................................ 9 1.4 Objective ........................................................................................................................... 9 1.5 Distribution/Target Audience ............................................................................................ 9 1.6 Review and Improvement ............................................................................................... 10 1.7 Step-out and Approval .................................................................................................... 10 1.8 Terminology, Definitions and Abbreviations ................................................................... 10 Term / Abbreviation ..................................................................................................................... 10 Definition (or meaning for the purpose of this document) ........................................................... 10 2 Managing Project Quality ..................................................................................................... 13 2.1 Quality Policy .................................................................................................................. 13 2.1.1 PDO Corporate Quality Management Policy PL-15 ................................................. 13 2.2 Management Responsibility ............................................................................................ 14 2.3 Roles and Responsibilities .............................................................................................. 15 2.3.1 Head of Quality UEQ ................................................................................................ 15 2.3.2 Business Opportunity Manager (BOM) / Project Manager or Engineer (PM / PE) .. 15 2.3.3 Project Quality Manager/Asset Lead Quality Engineer ............................................ 16 2.3.4 Senior Quality Assurance Engineer ......................................................................... 16 2.3.5 Quality Assurance Engineer .................................................................................... 17 2.3.6 QC Inspectors .......................................................................................................... 18 2.3.7 Disciplines ................................................................................................................ 18 2.4 Quality Management System Structure and Documentation Hierarchy ......................... 18 2.5 Quality Management Deployment Model ....................................................................... 19 2.6 Scaling / Application of a QMS ....................................................................................... 19 2.7 Quality Planning .............................................................................................................. 21 2.8 Resource Management .................................................................................................. 27 2.9 Quality Training ............................................................................................................... 28 2.10 3rd Party Inspection Agencies ........................................................................................ 28 2.11 Measurement, Analysis and Improvement ..................................................................... 29 2.12 Audits & Reviews ............................................................................................................ 29 Page 6 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC Version 2.0 Effective: Sep -14 2.13 Key Performance Indicators ............................................................................................29 2.14 Non-conformities .............................................................................................................30 2.15 Quality Improvement .......................................................................................................30 3 Appendices ...........................................................................................................................31 Appendix 1 Risk Form ..................................................................................................................32 Appendix 2 Quality Activities and Deliverable Guideline Road Map ..........................................33 Appendix 3 Project Quality Delivery Plan ...................................................................................35 Double click on the icon for opening the file. ...............................................................................35 Appendix 4 PQP Narrative Checklist ..........................................................................................36 Appendix 5 Quality Management Key Performance Indicators ..................................................37 Page 7 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Version 2.0 Effective: Sep -14 Petroleum Development Oman LLC 1 Introduction 1.1 Background In the majority of significant major incidents (irrespective of whether they are financial, safety or operational by nature), investigations conclude there were often inherent weaknesses in, and a lack of commitment to, the management of quality throughout the business processes. For any project to function effectively there must be a clear and well thought out framework of business controls applied - Opportunity Realisation process (ORP), Quality Management is one of those controls and is aimed at assuring compliance with requirements, however the existence of good management system does not in itself guarantee a quality product; this has to be accomplished via a combination of technical competence and, most importantly, adherence by all contributors to the system. 1.2 Purpose The purpose of this Code of Practice is to ensure that quality is consistently applied and implemented in PDO projects by supporting the ORP to provide a standardised approach to Quality Management in projects and give direction to Project Management Teams. See Fig 1. Code of Practice -190 Project Quality Laws and Regulations Quality Risks SP-1122 SP-1171 Quality Management Activitites Front-end Development / Engineering (Quality Planning) Execution Detail Design Procurement Construction/ Commissioning and Hand-over Support Processes: Risk Mgt, HSE, Procurement, Cost & Planning, Finance etc. Related Assurance activities: FPD, DCAF, OR, AIPSM etc. Identify Assess Select Define Execute Fig 1 Interfaces with other PDO related assurance activities including Flawless Project Delivery (FPD), Operational Readiness (OR), Asset Integrity Process Safety Management (AIPSM) and the Discipline Controls and Assurance Framework (DCAF) have also been taken into account. Page 8 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Operate Petroleum Development Oman LLC Version 2.0 Effective: Sep -14 It is acknowledged that there is a degree of overlap between these activities: FPD / OR and DCAF apply a specific level of QA/QC to individual activities; A QMS provides the overall system framework within which all these activities are effectively managed and improved. It is therefore important that the boundaries and interfaces are clearly defined and agreed during the opportunity framing with the relevant accountabilities, responsibilities captured in the Project Quality Plan (PQP), See SP-1122 Specification for Project Quality Plan. 1.3 Scope This CoP shall be applicable to all phases of a project as defined in the ORP (ORS) and CP-117, up to and including the hand-over of the Asset. Plant changes during the operating phase are also included, irrespective of size. Subsurface and well engineering activities, as well as operations and maintenance activities after project handover are excluded. 1.4 Objective The primary objective is to set the recommended standard for project quality management related activities by; Providing a road map for project managers/engineers, quality managers, quality engineers and others in determining the right level of quality to suit their particular project. Providing direction and outline the quality management principles and practices; the implementation of which are important to, and have an impact on, the achievement of quality objectives in delivering projects In its simplest format, quality is delivered via the Deming PDCA cycle – See Fig 2. Plan: Design or revise business process components to improve results Do: Implement the plan and measure its performance Check: Assess the measurements and report the results to decision makers Act: Decide on changes needed to improve the process Fig 2 1.5 Distribution/Target Audience This Code of Practice is applicable to all PDO-staff and contractors who are involved in the processes and activities directly related, or in support, to the delivery of a project or modification to an existing Asset. Page 9 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC 1.6 Version 2.0 Effective: Sep -14 Review and Improvement CP-190 shall be reviewed every three (3) years. In case of change in company policies or long term directions, it may be necessary to update and re-issue at an appropriate time to ensure PDO’s current position is reflected. 1.7 Step-out and Approval Any changes that need to be made to this Code of Practice shall be forwarded to the Corporate Functional Discipline Head (CFDH) for Quality Management UEQ, See PR1247 Project Management of Change Procedure and PR-2066 Managing Deviations from Standards and Procedures. 1.8 Terminology, Definitions and Abbreviations Table 1 below lists the terminologies, definitions and abbreviations used throughout the text of this document, wherever the term ‘project’ occurs, it may also mean ‘opportunity’. Throughout this document the term Quality Management System (QMS) is used to describe the Quality System through which QM is implemented. This CoP uses “Shall” , “Should” and “May” in the following context: “Shall” indicates a mandatory requirement and dispensation can only be granted by the relevant authority. “Should” indicates a recommendation and “May” indicates a possible course of action and is optional. Table 1 Term / Abbreviation Definition (or meaning for the purpose of this document) Accountability Being liable for certain actions to be taken and results achieved. Accountability = Responsibility + Authority. AI-PSM Asset Integrity Process Safety Management. Audit Systematic, independent and documented process for obtaining audit evidence and evaluating it objectively to determine the extent to which audit criteria are fulfilled. BMS Business Management System. A set of policies, practices, processes & procedures used in developing strategies, their execution and all associated management activities. BOM Business Opportunity Manager. BFD Basis for Design. CFDH Corporate Functional Department Head. Change A planned action to revise: a rule, procedure, standard, process, hardware (including equipment and plant configuration) or organization. The approval of a change must be obtained in advance of its implementation. CMF Corporate Management Framework. Company Petroleum Development Oman. Contractor A third party (person, company, joint venture) employed to complete a specific task on behalf of the Company. CCMS Project Completions Management System. CoP Code of Practice. CQP Contract Quality Plan. CSR Company Site Representative. DCAF Discipline Control Assurance Framework. Page 10 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC Version 2.0 Effective: Sep -14 Term / Abbreviation Definition (or meaning for the purpose of this document) DE Decision Executive Deviation A proactive and planned intentional or approved non-compliance with mandatory requirements of a procedure, standard or specification. The justification shall be submitted for review and approval obtained from an appropriate technical authority prior to the deviation taking effect. A deviation can be temporary, but will often be permanent for a specific installation. DRB Decision Review Board, led by the Decision Executive EMC Engineering Maintenance Contract. EPC Engineering, Procurement, Construction. FAT Factory Acceptance Test. FEED Front End Engineering Design. FPD Flawless Project Delivery. Inspection Conformity evaluation by observation and judgement accompanied as appropriate by measurement, testing or gauging. ISO International Organisation for Standardisation. ITP Inspection and Test Plan. KPI Key Performance Indicator. Monitoring To check periodically and systematically. It does not imply that any action will be taken. MS Management System. System to establish policy and objectives and to achieve those objectives. NCR Non-Conformance Report. NDT Non-Destructive Testing. Nonconformity Non-fulfilment of a requirement. ODC Off-plot Development Contract. OR Operations Readiness ORM Opportunity Realisation Manual ORP Opportunity Realisation Process. ORS Opportunity Realisation Standard PAP Project Assurance Plan. PCAP Project Controls and Assurance Plan. PDO Petroleum Development Oman LLC. PE Project Engineer PEP Project Execution Plan. PM Project Manager PQP Project Quality Plan. Project Unique process, consisting of a set of coordinated and controlled activities with start and finish dates, undertaken to achieve an objective conforming to specific requirements, including the constraints of time, cost and resources. Quality Plan Document specifying which procedures and associated resources shall be applied by whom and when to a specific project (product, process or contract). Project Team Team involved in the project for the purpose of monitoring activities of the Contractor in all project phases. Procedure Specified way to carry out an activity or a process. Page 11 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC Version 2.0 Effective: Sep -14 Term / Abbreviation Definition (or meaning for the purpose of this document) PWR Practices Worth Replicating. QA Quality Assurance. Part of quality management focused on providing confidence that quality requirements will be fulfilled. QC Quality Control. Part of quality management focused on fulfilling quality requirements. QM Quality Management. Coordinated activities to direct and control an organisation with regard to quality. QMS Quality Management System. Management system to direct and control an organisation with regard to quality. RASCI Responsible, Accountable, Supporting, Consulted and Informed. Record Document stating results achieved or providing evidence of activities performed. Responsibility The execution of a delegated task, activity or process. Being required to undertake specific actions. Review Activity undertaken to determine the suitability, adequacy and effectiveness of the subject matter to achieve established objectives TA Technical Authority. TBC To be confirmed. TBD To be developed. TI Technical Integrity. TPI Third Party Inspection. VAR Value Assurance Review. Verification Confirmation through to the provision of objective evidence that specified requirements have been met. Page 12 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Version 2.0 Effective: Sep -14 Petroleum Development Oman LLC 2 Managing Project Quality The commitment and active involvement of the project and functional leadership team(s) is essential for developing and maintaining an effective QMS. This CoP has been based on eight (8) management principles which underpin successful Quality Management: Principle 1 – Customer focus: Organizations depend on their customers and therefore should understand current and future customer needs, should meet customer requirements and strive to exceed customer expectations. Principle 2 – Leadership: Leaders establish unity of purpose and direction of the organization. They should create and maintain the internal environment in which people can become fully involved in achieving the organization’s objectives. Principle 3 – Involvement of people: People at all levels are the essence of an organization and their full involvement enables their abilities to be used for the organization’s benefit. Principle 4 – Process approach: A desired result is achieved more efficiently when activities and related resources are managed as a process. Principle 5 – System approach to management: Identifying, understanding and managing interrelated processes as a system contributes to the organization’s effectiveness and efficiency in achieving its objectives. Principle 6 – Continual improvement: Continual improvement of the organization’s overall performance should be a permanent objective of the organization. Principle 7 – Factual approach to decision making: Effective decisions are based on the analysis of data and information. Principle 8 – Mutually beneficial supplier relationships: An organization and its suppliers are interdependent and a mutually beneficial relationship enhances the ability of both to create value. 2.1 Quality Policy The project quality policy shall support the overall corporate and project objectives; It is a means by which PDO and/or a project organisation is able to channel its actions in meeting its specific objectives towards Quality. 2.1.1 PDO Corporate Quality Management Policy PL-15 It is PDO’s policy that working practices and a Quality Management System that aligns with the requirements of Code of Practice 190, shall be applied throughout our organization that: Page 13 Make Quality Management an integral part of normal business activities. Provides adequate resources throughout the organization, ensures competency of personnel by developing and maintaining a healthy Skillpool of Quality professionals and includes Quality performance as part of staff performance appraisal and reward. Ensure completed works and Assets comply with the requirements of Engineering Design, the laws of the Sultanate of Oman and Internal Standards. Establish Business Performance and Project Delivery quality objectives and targets; measure, appraise and report quality performance. Achieve continuous performance. improvements in Business and CP-190: Quality Management System for Project Delivery Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC Version 2.0 Effective: Sep -14 Engages future Asset-owners to align Project definitions and delivers Flawless start-up. The impact of this policy is that there is a Quality Management System established, maintained and continually improved that aligns with the requirements of PDO Code of Practice CoP-190. The Quality Management System includes key matrices, which will be used to monitor the effectiveness of the system in contributing to top quartile performance. The purpose of this policy is to: Ensure understanding of PDO’s commitment to Quality by recognizing Quality performance and accountability. Ensure Engineering Designs are clearly documented and agreed with the Business and Project owner that address specified Asset Integrity and Process Safety requirements. Ensure commitment to develop and allocate competent Quality resources within PDO Assets and Projects. Create a culture in which PDO and contractor employees are encouraged to share PDO’s commitment to QM principles. Promote best QM practices within the Oil and Gas industry of the Sultanate of Oman. Implement individual accountability to comply with QM requirements. NOTE: Any individual project Quality objectives shall as a minimum address and comply with PL - 15. 2.2 Management Responsibility The achievement of the quality objectives is a management responsibility, therefore the commitment and active involvement of PDO senior management and /or project organisations are essential for developing and maintaining an effective QMS. Typical actions required to demonstrate commitment: Applying PDO Corporate Quality Management Policy (PL-15) Providing the infrastructure and resources to ensure achievement of the project quality objectives; Making decisions based on data and factual information; Empowering and motivating all project personnel to improve the project processes and product; Planning for future preventive actions (continual improvement process) The project top management shall nominate a quality management representative who must have sufficient responsibility and authority for identifying and resolving quality issues and retain a high degree of independence and objectivity. Key performance indicators (KPI’s) should (dependant of size of Project and Risk) be developed and agreed for monitoring and steering quality performance throughout the project (See Section 2.13). Management shall ensure that Contractors also identify suitable quality resources which will be subject to acceptance by the project team and/or CFDH. Contractors management shall also define their commitment to execute the project in accordance with ISO/TS 29001 and SP-1171. Page 14 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC 2.3 Version 2.0 Effective: Sep -14 Roles and Responsibilities Quality related responsibilities in projects are described below (See also CP-117 Project Engineering CoP, CP-180 Recruitment Code of Practice and SP-1122 Specification for Project Quality Plan), specific project related responsibilities of individuals may be further described in individual project documents and/or procedures and specifications. 2.3.1 Head of Quality UEQ Head of Quality (UEQ) is the Management Representative who, irrespective of other responsibilities, shall have responsibility and authority that includes: Ensuring that processes needed for the QMS are established, implemented and maintained (PDO Quality Technical Authority TA1); Reporting to the Engineering & Operations Director UEOD on performance of the QMS and any need for improvement, and Providing support and guidance to all Project Teams on quality related matters and ensuring competent quality (QA/QC) resources are available within the Project Teams. UEQ is also responsible for the quality management system review: ensure its continuing suitability, adequacy and effectiveness. Key project personnel shall be invited to contribute to the reviews as appropriate. These reviews shall be formal, and recorded in detail, to monitor the effectiveness of the QMS. These reviews are described in the Project Quality Management System Review Procedure PR-2052 and compliment the ongoing feedback and continual improvement of the QMS in its day-today implementation. 2.3.2 Business Opportunity Manager (BOM) / Project Manager or Engineer (PM / PE) The BoM/PM/PE has overall responsibility for quality and its implementation at every stage of the project. The BOM/PM/PE should ensure that the project QMS is reviewed at regular intervals ensuring its continuing suitability, adequacy and effectiveness. Where repetitive projects (portfolio of projects) are covered within a single contract scope, a single QMS / PQP may be developed (see sections 2.4, 2.6, 2.7), underpinned by level 3, 4 documents / deliverables. Suitability is judged by its ability to sustain current performance; Adequacy is judged by its ability to deliver the project that satisfies requirements, standards and regulations; The review output should include decisions and actions related to the improvement of the effectiveness of the project QMS, its processes and related resource needs. Further responsibility and authority include; Page 15 Ensure that project quality requirements are addressed and included within the PEP. Establishing the budget and resource estimate for quality: ensuring that appropriate quality resources are available within their respective project team and contractors organisations in order to achieve PDO’s Quality Policy & Objectives; Establish, implement and maintain the project QMS including quality strategy and PQP; CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC 2.3.3 Version 2.0 Effective: Sep -14 Ensure that project quality requirements are included within contract documents and that contractors, subcontractors and vendors comply with project QMS requirements; Team development to ensure all project personnel are aware of quality responsibilities; Promoting a consistency of approach & sharing learning across projects and for promoting continual improvement within their project organisation; Taking the appropriate action necessary to address quality issues impacting project delivery including document reviews, and corrective and preventive actions are completed in a timely manner; Making use of available quality related information to evaluate options and make decisions; Identifying and implementing quality KPI’s and applying rewards/penalties as applicable under established contracts. Project Quality Manager/Asset Lead Quality Engineer The Project Quality Manager / Asset Lead Quality Engineer is the focal point for the project / asset for all quality aspects and is responsible for: Ensuring the project QMS strategy and processes/plans are established, implemented and maintained; Provide support in developing and implementing the PQP, Transition Plan and project specific procedures and/or work instructions; Identifying quality shortfalls and creating training / coaching requirements; Managing the overall project assurance, surveillance, audit and review activities and executing project/contractor audits; Coordinating the timely closeout of audit actions as applicable to their project; Compile relevant quality statistics/KPI’s and implementing lateral quality learning’s; Monitoring the performance of the EP, C, EPC/ODC/EMC and/or major contractors against contract requirements; Reporting to the project manager/engineer and the quality CFDH on the performance of the QMS, including needs for improvement; 2.3.4 Review and approval of the contractors QA / QC personnel. Liaising with supply chain management and function to: Confirm supplier’s capability/approved vendor list; Agree surveillance plans as applicable; Act on surveillance reports as necessary. Assist PM / PE in the identification / compilation of quality documents subjected to review and approval by project team. Senior Quality Assurance Engineer Sr. QA Engineer is responsible for day to day management of quality for a given project / asset area under supervision of the Project Quality Manager / Asset Lead Quality Engineer. He is responsible for: Page 16 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Version 2.0 Effective: Sep -14 Petroleum Development Oman LLC 2.3.5 Provide support in developing and implementing the PQP, Transition Plan and project specific procedures and/or work instructions; Identifying quality shortfalls and creating training / coaching requirements; Managing the overall project assurance, surveillance, audit and review activities and executing project/contractor audits; Coordinating the timely closeout of audit actions as applicable to their project; Compile relevant quality statistics/KPI’s and implementing lateral quality learning’s; Providing early contribution to the contractor's ITP/QCP to identify critical hold, witness, monitor and review points including PDO’s activities; Reviewing contractor and manufacturer contract quality plan and relevant procedures as per SP-1171 Specification for Quality Assurance Requirements for Product and Service) Ensuring the quality requirements manufacturer's ITP/QCP are followed; Conducting surveillance of contractor's activities in the procurement, fabrication, construction and installation of a facility or product by: Reporting problem areas to the quality manager (lead project engineer if project does not have a designated quality manager) and raising non-conformance reports (NCR’s) or Product NCR’s to document work that fails to meet the specified quality requirements so that remedial action can be taken; Verifying that all NCR’s and Product NCRs have been satisfactorily resolved; Reviewing the contractor's submission of the QC data package at completion of the work. It is the PM’s/PE's job to see that the quality related requirements are adhered to and that competent resources are available, in time, to assist in achieving same (see BOM/PM/PE responsibility requirements). identified in the contractor's or Quality Assurance Engineer Is responsible for ensuring the quality requirements identified in the contractor's or manufacturer's ITP/QCP are followed; conducting surveillance of contractor's activities in the procurement, fabrication, construction and installation of a facility or product by: Page 17 Providing early contribution to the contractor's ITP/QCP to identify critical hold, witness, monitor and review points including PDO’s activities; Reviewing contractor and manufacturer contract quality plan and relevant procedures as per SP-1171 Specification for Quality Assurance Requirements for Product and Service) Reporting problem areas to the quality manager (lead project engineer if project does not have a designated quality manager) and raising non-conformance reports (NCR’s) or Product NCR’s to document work that fails to meet the specified quality requirements so that remedial action can be taken; Verifying that all NCR’s and Product NCRs have been satisfactorily resolved; Reviewing the contractor's submission of the QC data package at completion of the work. It is the PM’s/PE's job to see that the quality related requirements are adhered to and that competent resources are available, in time, to assist in achieving same (see BOM/PM/PE responsibility requirements). CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Version 2.0 Effective: Sep -14 Petroleum Development Oman LLC 2.3.6 QC Inspectors Provide early contribution to a project in order to ensure: 2.3.7 Adequate inspection during fabrication / construction; Inclusion of the asset holder requirements; Records and evaluates the findings of manufacturer and contractor QC activities so as to recommend improvements; Assist in evaluating the impact of new fabrications on existing facilities and provides recommendations on best options; maintains records of repairs and changes in the maintenance administration and information. Disciplines Ensure the effectiveness and efficiency of processes under their control. NOTE: Specific requirements should be detailed in individual job descriptions. 2.4 Quality Management Hierarchy System Structure and Documentation Project QMS documentation is firmed up post DG3 space as illustrated in Figure 3. Fig 3 Page 18 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC Version 2.0 Effective: Sep -14 Principal contractors / sub-contractors selected to execute the work, shall (dependant on work to be executed) develop and implement specific quality plans, associated procedures, work instructions, and inspection and test plans. The PM/PE shall identify which documents are subject to review by the Project Team and shall form an integral part of the overall Project QMS. 2.5 Quality Management Deployment Model The quality management deployment model is illustrated in Fig 4 below. This model is common to both ISO10006 & ISO9001, and shall be used as the basis for developing the project QMS. Fig 4 To facilitate deployment, the elements of the model should be grouped according to their affinity to one another: 2.6 Managing the Project - Management Responsibility / Resource Management / Measurement, Analysis & Improvement. Realising Project Quality - Comprise the demand fulfilment processes, e.g. Design / Construction / Commissioning together with the interdependent processes, e.g. HSE, Risk Management, Work Planning & Scheduling, Contracting & Procurement, etc. Scaling / Application of a QMS Scaling/tailoring the QMS for each project shall be defined by the opportunity project team and agreed with the Business Opportunity Manager (BOM), project manager and/or project engineer / CSR as applicable at the outset, recorded in the PEP and implemented via the PQP and reviewed at each decision gate. This decision should be based on the interfaces with other business processes, the intent of each activity, identified risks and lessons learned from other projects. Table 2 below shows the recommended application of a quality management system by ORP phase and project value. Page 19 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Version 2.0 Effective: Sep -14 Petroleum Development Oman LLC Table 2 Project size (millions) Identify & Assess Select Define Execute >$ 1000 <$ 1000 <$ 200 <$ 50 <$20 (EMC/ODC) Recommended. Mandatory Table 2 above is only indicative as Projects differ in terms of complexity and uniqueness, reflected in their risk exposure and applied mitigation actions. The QMS is also unique and may differ in terms of structure, complexity and application based on the identified Risk and cost, Table 3 (example of Risk Form is provided in Appendix 1). Facility / Capital Intensity (in Million USD) Table 3 >$ 1000 QMS Level 3 QMS Level 4 QMS Level 4 <$ 1000 QMS Level 2 QMS Level 3 QMS Level 4 <$ 200 QMS Level 1 QMS Level 2 QMS Level 3 <$ 50 QMS Level 1 QMS Level 1 QMS Level 2 <$20 (EMC/ODC) QMS Level A1 QMS Level A1 QMS Level A2 Risk Category: Low Medium High Risk category explanation: Page 20 Low Risk: Conventional projects that involve limited engineering scope and only few vendor interfaces, typically single discipline such as pipeline and overhead line projects, or single vendor package, standard materials, no prototype, low risk impact, limited brown field scope. Medium Risk: projects with considerable engineering scope, many discipline interfaces, multiple vendors, various high grade material types, and /or medium risk impact. (gas compression/ production facilities steam projects, polymer projects, water-floods, some prototypes, brownfield projects) High Risk: projects involving extensive multidiscipline engineering, many different vendors, typically sour, high pressure projects such as miscible gas, exotic materials, many prototypes, many discipline interfaces, high brownfield content, high risk impact. CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC Version 2.0 Effective: Sep -14 Table 4 identifies the minimum quality management system(s) assurance and control requirements based on Value and/or Risk See also CP-131. Table 4 Quality Management System requirements QMS Level 3 &4 a. The QMS / PQP should be specifically developed for the Project, including a Quality Strategy/objectives, supporting procedures and work instructions. PDO Corporate Quality Policy, management system and procedures shall be used as a main reference. b. Quality Resources, including a Quality Manager and QA Engineer(s) should be dedicated to the project and should be progressively deployed during the Identify & Assess phases of the ORP. QMS Level 2 a. The Project’s QMS may be a combination of the PDO Corporate management system and procedures and project specific procedures. The level of documentation is to be assessed on an as-needed basis. b. A dedicated Quality Lead should be deployed as a minimum during the Select phases of the ORP. QA/QC resources can be shared with other projects on an as-needed basis. QMS Level 1 a. The Project Quality System should basically consist of a PQP that makes reference to, and is supported by, applicable PDO standards and processes; i.e. normally there will be no need for the Project to develop its own specific procedures. b. More reliance should be placed on Line Management to practice their own responsibilities towards QA/QC activities at early phases; i.e. generally, a dedicated quality resource will be mobilized at the Define Phase of the ORP. c. Minimum one dedicated QA Lead Engineer, additional QA/QC resources may be shared between more than one project through a matrix organization or skill pool. EMC/ODC QMS Level A2, dedicated Quality Lead full time to the project. QMS level For QMS Level A1, QA/QC resources may be shared between more than one A1 & A2 project through a matrix organization or skill pool. Supply Chain Quality Lead/Engineer, position may be covered by corporate Function. Execution QA/QC Engineers and Inspectors, The number will vary per project and may include both full time and call-off arrangements. The roles may also be filled by 3rd. Party inspection agencies. 2.7 Quality Planning In order to achieve project quality objectives, it is necessary to manage and control the project processes and activities by means of Project Quality Plan (PQP). Where relevant, the PQP should be supported by lower tier quality plans, procedures and/or work instructions specific to discrete parts of the project, see SP-1122 and SP-1171 for specific details. Quality Planning should commence at the Identify / Asses phase of the ORP (Fig 5) and be continually updated as and when project requirements become more clearly defined until final project delivery and hand-over to Operation. To guide development of the PQP the primary quality activities and quality deliverables associated with each ORP phase, ‘What you do,’ are illustrated in the Quality Activity and Deliverable Roadmap, see section 3 Appendix 2. An outline of project QA/QC activities and deliverables in various ORP-phases of Identify/Assess, Select, Define, and Execute respectively is provided in the Project Quality Delivery Plan (PQDP), see section 3 Appendix 3. Page 21 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC Version 2.0 Effective: Sep -14 The PQP should indicate how the required activities will be carried out, either directly or by reference to appropriate documented procedures, or other documents (e.g. project plan, work instruction, checklist, etc, see also Appendix 4 – PQP Narrative Checklist Inputs that need to be considered include: The project classification by Cost and Risk; The requirements of stakeholders and any statutory, regulatory and industry specifications; The capability / experience of the project organisation and maturity of the QMS. The Quality Characteristics that need to be controlled, assured, improved, managed & demonstrated. Quality Resources (both availability and capability) If a requirement results in a deviation from the QMS, this deviation should be justified and authorised. Page 22 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC Version 2.0 Effective: Sep -14 The depth and breadth of the PQP should be determined by the overall project / quality characteristics and associated risks to be mitigated (RE: Section 2.6). Fig 5 Page 23 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC Version 2.0 Effective: Sep -14 Table 5 identifies the minimum quality activities and controls that should be addressed within the PQP, irrespective of the QMS scaling (details of corporate Codes of Practice, Specifications, Procedures and Guidelines are provided for reference, refer to LiveLink for latest copy). Table 5 QMS Requirement Design & Development Quality Management (Front-end Engineering & Detailed) including Technical Integrity. (CP-117, CP-185, SP1122, SP-1134, SP11-71, SP-2061, PR-1232, PR1247, PR-1358, PR-1151, PR-1561, PR-1729, PR1741, PR1727, PR1734, PR-1735, PR-1761, PR1768, GU-603, PR1772, PR-1759). PQP Activity The design quality assurance process is key in enabling the project to achieve its objectives and therefore must be effectively controlled. The following steps should to be addressed and reviewed: Setting Quality objectives for the design process; Submission of a Design Quality Plan (which should include requirements for assuring technical integrity. Quality measures for indicating achievement of these design quality objectives; A defined sequence of design processes, procedures, or tasks that transform the design inputs into design outputs; Essential QA/QC requirements set out in project specifications; Checking, verification and approval procedures for establishing that the process is achieving its objectives (internal and external); Design change control is properly managed (internal external); Processes for improving the effectiveness of the design process. Auditing effectiveness of the Competence Assurance process Drawing Office quality controls and associated procedures should be available. All work should also be undertaken in accordance with the relevant Technical Integrity Framework and/or DCAF and other applicable Project Standards / Guides. Where an Independent Verification Body is required to verify a design in order to comply with any prevailing regulations and legislation (e.g., Pressure Vessel Directive, Lifting Reg’s, etc), the requirement should be specified in the PQP and should identify both the internal Technical Authorities (TA) and 3rd parties required to review and approve the relevant documentation. Interface Control (Project specific document) (CP-162, CP-111, PL-13, GU-435) The project should have and implement an interface control procedure. Establish and implement an effective communication system / process that address all project interfaces including internal/external Meetings, communications, reporting, correspondence etc. This should be subject to audit and included in the Audit plan. Alternative arrangements to manage interfaces should also be addressed as a scope item in the Audit plan. Change and Deviation Controls (PR-1247, SP-2061, PR1001x, PR-1029, PR-2066) Page 24 Management of Change and the Deviation processes should be subject to audit and included in the Audit plan. The audit scope should assure all technical deviations are approved by designated Technical Authorities, and that deviations are managed and controlled. The deviation register should be audited. CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC QMS Requirement Risk Management Control. Version 2.0 Effective: Sep -14 PQP Activity The projects should have a risk management procedure: (CP-131) Develop project risk management procedure and establish risk register including mitigation measures and time frames. System should be subject to audit and included in the Quality Audit plan. Alternative arrangements to manage risk should also be addressed as a scope item in the Audit plan. Information Management / Document Control. (PL-06, CP-102, CP-139, SP-1003, SP-2047, SP2065, SP-2066, SP-2067, SP2079, PR-1009, PR1561, PR-1568, PR1692, PR1772, GU-453, GU-493, GU-556, GU-582) Project Controls (CP-131, CP-142, CP-185, GU-484, GU-569, GU-117, GU-521, GU-569, GU-611, GU-711) Quality in Contracting and Procurement. (CP-129, SP-1122, SP1171, PR-1233, PR-1279, GU-115, GU-556, GU-586, GU-598) The document control system should be audited to assure achievement of information quality, and that changes/revisions, are approved, retained on file and issued in a controlled and systematic manner. Quality record requirements should be set out in the IM plan. The IM process should be part of the audit plan. The use of the project suite of project controls and procedures should be audited and included in the Audit plan. The audit of project control effectiveness should also extend to contractors and key subcontractors. Robust and effective methods should be established to assess, monitor and control contractors, sub-contractor, suppliers and service providers at a very early stage in the project life. The focus should be determined by the quality risks to the project and measures established to ensure effective delivery of all products, services and materials. Key quality inputs should include: Determining the level of quality management intervention through a risk based assessment of contracted and supplied services, equipment materials, and goods (e.g. criticality process). Design Contractor Quality Appraisal and Evaluation Contractors/Supplier Quality Appraisal and performance monitoring Contract and Procurement Quality Control The requirement for a Contractor/Supplier Quality Plan should be embodied in each major contract, or purchase order The QA and QC inspection requirements (level of Quality Intervention) should be incorporated in purchase orders in order to reduce the risk of non-conformance to specification and late delivery. Key quality inputs should include: Page 25 Quality Intervention Strategy and Plans Quality Control/Inspection, Testing and Quality Surveillance plans Material Quality Control and Traceability (Procurement) Appraisal and Use of Inspection Contractors (Execution Phase) Supply Chain Quality Assurance Plans CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC QMS Requirement Construction Quality Assurance and Control. (SP-1122, SP-1171, PR1483, PR-1561) Version 2.0 Effective: Sep -14 PQP Activity The PDO project team should ensure that a Construction Quality Plan and Quality Audit plan is available. It should cover the construction and installation quality activities and that any audits and reviews are planned in a methodical manner to assure that the construction work meets the requirements of the contract and project specifications. Participation in contractor quality audit plans is an effective way to monitor implementation and effectiveness of construction and site QA/QC activities. The extent of quality monitoring should be dependent upon the technical criticality of the work and contractor/subcontractor work scopes. Key areas to check are Systems Handover Quality Control. (SP-1131, PR-1000, PR1150, PR-1612) Project specific Inspection and Test Plans have been prepared that define critical fabrication steps, the acceptance criteria, and the specific methods and procedures to be used to ensure that all Contract requirements are met Construction quality team is notified and involved in the review and sign off on inspection release notes, or Inspection and Test Plan hold points. Inspection and Test plan actions are monitored to closure. This should also include supplied equipment and material. Monitoring and measuring devices, applicable to inspecting construction work scope of work, is available and calibrated and is the proper instrument for inspecting the work. On handover of each completed system or subsystem to commissioning, a construction dossier shall be compiled that includes all quality information on that system (e.g. as-built drawings, test results, factory acceptance test outcomes, mechanical completion, vendor documents and data etc.). Project Completions Management System (CCMS) shall be used for systematic approach. The site quality team should assure collection of these quality records is both effective and complete. The process should be audited as part for the construction audit plan. Contractor and subcontractor handover controls should be included. Commissioning Quality Control & tools Project Completions Management System (CCMS). (PR-1159, PR-1172, PR1561, PR-1612) Quality activities to verify that the Installation: has been constructed as designed; meets its performance specification; is safe and reliable for operation; and design limits have not been violated. This is particularly important when items are constructed at a number of locations are brought together on site. Mechanical completion of systems should be confirmed by the completion of quality checklists prior to handing the system over for commissioning. Incomplete minor items should be recorded on punch-lists. Commissioning should be executed using pre-agreed procedures and checklists. On handover to Operations for start-up, the package of information transferred into the operations records should include: Page 26 Quality records and handover certificates and completed check sheets; CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Version 2.0 Effective: Sep -14 Petroleum Development Oman LLC QMS Requirement PQP Activity agreed punch lists of minor items to be completed after handover; and outstanding inspection activity. Quality records of equipment and running trials. Readiness Review/Start-up (OR) The methodology of the Flawless Project Delivery (FPD) should be applied on all PDO projects in accordance with the Operational Readiness and Assurance Plan (OR). This will generally be co-ordinated by a dedicated OR Team with close liaison/tie-in with the site Quality team. 2.8 Resource Management Within the QMS attention shall be given to the activities in the personnel-related processes to assure the competence of suitable resources to manage quality. The processes should ensure: The establishment of the project quality organisation structure (both for the project and principle contractors) The allocation of quality resources, and Team development to ensure all project personnel are aware of quality responsibilities A summary of key quality related responsibilities is provided in section 2.3 and shall be reflected in the tasks and targets of the project team roles. The Quality Manager/Engineer should report direct to the PM / PE or most senior individual who has been given responsibility of assuring that quality and technical integrity requirements are compliant. Quality functionality remains with UEQ. It is recommended that RASCI Charts (Responsible, Accountable, Support, Consult and Inform) are used to define who should do what quality activities on the project. An indicative QA/QC resources required across projects is shown in Table 6: Table 6 Position Page 27 EPC Project QMS Level Comment 1 2 3 4 Quality Manager 0 0 1 1 Level 3 - 4 project, dedicated full time to the project. Project Quality Assurance Lead/Engineer 1 1 1 2 On a Level 4 project, will be progressively involved from Identify & Assess phase through to Execution. Supply Chain Quality Lead/Engineer 1 1 1 1 Construction Quality Lead/Engineer 1 1 1 1 For level 2 or 3 projects, will become involved from Select phase and may be full time (Level 3) or support several projects (Level 2). Execution QA/QC Engineers and Inspectors As reqd Note: the actual numbers depending on Project portfolio. As reqd. As reqd. As reqd. will vary The number will vary per project and may include both full time and call-off arrangements. The roles may also be filled by 3rd. Party inspection agencies. CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Version 2.0 Effective: Sep -14 Petroleum Development Oman LLC Position South / North Asset Quality Assurance Lead / Engineer ODC/EMC Project QMS Level A1 A2 1 1 Comment Level A2 project, dedicated full time to the project. For Level A1 project, generally provide support to all projects. Supply Chain Quality 1 Lead/Engineer 1 May be covered by corporate Function. Execution QA/QC Engineers and Inspectors As reqd. The number will vary per project and may include both full time and call-off arrangements. The roles may also be filled by 3rd. Party inspection agencies. As reqd. The above table is indicative, should the project involve a shift rotation, the quality resources may increase significantly. The number of quality resources may also be influenced by the type of contractual arrangements and the role of the Principle contractor. These resources should be planned across the ORP, ideally with the Quality Manager/Lead identified at the end of the Select / start of Define phase. 2.9 Quality Training Project personnel should be adequately familiar with project quality system requirements and their specific role in the system for the performance of their assigned tasks. Initial quality system induction training is therefore required at the start of each (phase of a) project, followed by sustained training e.g. covering specific quality topics. Specifically for the construction and commissioning phase QMS training is important as usually a large part of the supervisory staff are hired-in on short-term contracts and may not be familiar with PDO’s, Contractor/Subcontractor standard procedures and systems. See also PR-1029 Competence Assessment & Assurance. 2.10 3rd Party Inspection Agencies To help monitor the performance of its contractor and the supply chain (including expediting and inspection related activities), projects may employ the services of a 3rd Party Inspection Agency or utilise services through an EPC type contract. Where such organisations are used, it is important they are able to demonstrate the necessary competency requirements. In addition performance of each individual inspectors shall be monitorerd for key factors of their performance such as competency, availablility, timeliness, documentation and accuracy. Page 28 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC 2.11 Version 2.0 Effective: Sep -14 Measurement, Analysis and Improvement The project organisation shall ensure that measurement, collection and validation of data is effective and efficient, to improve the organisations performance and enable continual improvement in both current and future projects. Examples: 2.12 Evaluation of individual activities and processes; Auditing; Evaluation of supplier performance; Evaluation of actual resources (cost/time) compared to original estimates. Audits & Reviews A Project Quality Audit and Review plan shall be developed and maintained for the whole project lifecycle SP-1866 Quality Audit procedure . Its purpose is to: Provide documentary evidence to stakeholders of the effectiveness of the project assurance process, the project management/quality management systems and business controls; Demonstrate that compliance to Project specified requirements have been achieved; Identify areas for continual improvement. The Project Quality Audit and Review plan shall include audits of all key project controls, prime contractors and areas identified as at risk that may require a certain level of Quality intervention to assure compliance to project requirements. The Quality Audit and Review Schedule shall detail the outline scope and frequency of all audit /reviews against each project control, contractor, sub contractor, supplier. The status of audits/reviews and associated findings should be summarized and included in Project Reports issued to the PM Team. The review of Quality Audit /Review reports should be the primary method used in measuring achievement of the stated Project Quality Objectives. 2.13 Key Performance Indicators Key performance indicators should be both ‘leading’ and ‘lagging’: Leading are used to signal ‘possible’ future events Lagging follows the event. The importance of a lagging indicator is its ability to confirm that a pattern is occurring or is about to occur. The leading indicators should focus on the effectiveness and efficiency of the QMS from a system, organisational, and process viewpoint. This should apply both internally (within the project team) and externally (critical contractors and suppliers). The lagging indicators should be QA/QC focused, and aligned with Flawless Project Delivery objectives to avoid duplication. Examples of both Leading & Lagging Indications are shown in Section 3 Appendix 5. Page 29 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC 2.14 Version 2.0 Effective: Sep -14 Non-conformities Projects shall ensure the control of all nonconformities by one or more of the following ways: By taking action to eliminate the detected nonconformity; By authorising its use, release or acceptance under concession by a relevant authority; By taking action to preclude its original intended use or application. Records of the nature of nonconformities (NCR) and any subsequent action taken, including concessions obtained, shall be maintained by the project. See also PR-2053 Control of Non-Conforming Product Procedure. 2.15 Quality Improvement Projects shall continually seek to improve the effectiveness of its QMS through the use of the quality policy (quality objectives), audit results (incl. PEER reviews, etc), analysis of data (e. g. training records, deviation control, change control, process monitoring measures etc.), Risk matrix/mitigating, corrective and preventative actions and management reviews. This information should be captured in an appropriate database, to enable learning (both good and bad) to be assessed by other similar projects. A “Quality Alert” process shall also be used to communicate specific quality issues with other projects and UEQ. The PM / PE should review the effectiveness of this process and take the necessary steps to continually improve the project organisation and the processes used to support effective project delivery. Where necessary, this may include working with the supply chain to ensure similar objectives are achieved. Prior to closing a project it is recommended that the project team carry out a documented review of the project performance, highlighting experience from the project that can be used by other projects. Page 30 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC 3 Version 2.0 Effective: Sep -14 Appendices Page 31 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC Version 2.0 Effective: Sep -14 Appendix 1 Risk Form Risk Type Risk Rated Justification for Risk selection Rating definition Individual Rating: H = 15, M = 10 & L = 5 Technical Risk Subsurface Uncertainty Risk H Surface Complecity Risk M Project Execution Risk H L: Development in a well-developed, mature area. M: Development in a relatively new area / location. H: Development in a new area in a particularly unusual setting. L: Straight-forward repeat execution of a typical production system. M: Unsual development configuration, non-traditional facilities integration into existing system, brownfield development. H: Mid steam integration 9LNG/GTL). L: Single well developed location, low likelyhood of late changes, C&P straight forward. M: Single location, manageable logistical challenges, low likelyhood post DG-3 changes, some C&P issues. H: Multi locations, cross business, logistical challenges, potential for late changes to concept, C&P vhallenges. Novel Technology Risk L L: No novel technology, all technology applied within PDO. M: New Technology, not applied in PDO, considerable experience outside PDO. H: New technology, not applied in PDO, limited experience outside PDO. Ecomonic Risk L L: Well predicable economics (wages, currency), margin predicable. M: Limited economic risks (wages, currency), larger variation in margin possible. H: High economic risks (high impact currency fluctuations, wide variation in margin possible. Commercial Risk L L: Commercial and JV contracts in place, no problems expected, partners with long standing relationship. M: Expect some problems completing commercial and JV contracts, partners with no clear alignment. H: No clear commercial and JV contracts in place, access to goods and services is limited by local environment, or dealing with partners known to be out of alignment or adversarial. Organisational Risk Business Environment Risk L L: Well established line of business and relationships with government/regulators/venture partners well understood. M: Unusual business conditions or relationships challenges in a region that is otherwise well understood. H: New country entry. New venture, new line of business, area with known issues / relationship challenges Risk of Team Capability to Deliver M Quality System/ DCAF Maturity Risk M Environmental / Social Perfromance Risk H Risk Summary Page 32 L: Expert team in place and available. M: More-experience Team in place and available. H: Less-experience Team in place. L: Very mature QMS / DCAF in place. M: QMS / DCAF practices embedded in projects. H: Only QMS / DCAF basic framework exists. L: No reputational issues, no community issues, no permit issues expected. M: Some reputational issues, limited community issues, manageable permit uncertainties. M H: High reputational issues, serious community issues, major permit uncertainties. Risk Summary Rating: L< 75 M = 75 to 125 H>125 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Appendix 2 Quality Activities and Deliverable Guideline Road Map Identify Assess Select Define Pre-FEED DG /VAR Key Activities 1 Provide outline strategy for Quality Assurance against identified opportunity risks. 2 Frame strategy for Quality Assurance against identified risks and QA resource need. Establish Policy / Goals / Objectives / KPI’s / Procedures. Determine level of Quality monitoring / surveillance / manpower / competency shortfalls / Risks. Initiate Quality Audit plan and improvements. Establish and maintain action tracking system. Confirm applicable QMS and work within it. Populate DCAF for the project, monitor and measure implementation Establish and follow-up Lessons learned 3 Refine strategy for Quality Assurance against identified risks and QA resource need. Appoint Quality lead, determine Quality resource requirements, conduct quality training. Draft Preliminary Project Quality Plan. Provide Quality inputs into Job descriptions Updated strategy for field/site Quality Assurance against identified risks. Finalise Project Quality Plan. Update and set equipment and material criticality ratings and quality intervention levels critically rating. Establish QA resource need. Populate DCAF for the project, monitor and measure implementation. Periodic quality management review of the project within the defined QMS. Periodic quality management review of the project within the defined QMS/PQP. Provide Quality Assurance input to project execution strategy including contracting strategies 4 Updated strategy for Quality Assurance against identified risks. Establish and set equipment and material criticality ratings and quality intervention levels. Conduct quality audits and peer reviews. Continual improvement, nonconformance reporting, corrective & preventative action, and trend analysis. Surveillance of LL contractors & suppliers QA/QC systems and performance. Operate FEED (opt)3a Populate DCAF for the project, monitor and measure implementation. Conduct quality audits and peer reviews. Execute Update QA and QC resource need. Determine special skills and/or training requirements. Implement project specific PQP, and review periodically. Align and approve QMS for FEED contractor. Establish/implement Change management. Populate DCAF for the project monitor and measure implementation. Conduct quality audits and peer reviews. Continual Improvement, Nonconformance reporting, Corrective & Preventative Action, and trend analysis, 5 Approved strategy for Construction/Commissioning Quality, Technical Integrity and Flawless delivery against identified risks. Update critically rating. Finalise QA/QC resource and rd 3 party inspection need. Implement project specific PQP procedures and review periodically. Conduct Quality awareness and training sessions. Align and approve QMS and PQP for EPC contractor. Populate DCAF for the project, monitor and measure implementation. Conduct Quality Audits and Peer Assist. Maintain action tracking. Continual Improvement, Nonconformance reporting, Corrective & Preventative Action, and trend analysis. Surveillance of contractors PQP, and performance & suppliers QA/QC systems, ITP’s and performance. Prepare monthly QA reports and analysis. Conduct quality Health-check. Provide input into Closeout report and Lessons Learned. Version 2.0 Effective: Sep -14 Petroleum Development Oman LLC Identify Assess Select Define Pre-FEED DG /VAR 1 2 3 Execute Operate FEED (opt)3a 4 5 implement KPI’s, Surveillance of contractors PQP & suppliers QA/QC systems and performance. Key Deliverables Strategies. Aligned Quality Policy and Objectives. Identified resource requirements. Draft Audit plan / PAP Preliminary Project Quality Plan. Project Audit & Review Plan + tracking register. Project Team Audit & Review reports. DCAF MOX Risk Register Project Quality Plan. Updated Project Audit & Review Plan + tracking register. Quality Criticality Rating and Quality Intervention schedule. Project Team and Contractor Audit & Review and Surveillance reports / trend analysis. QA/QC Resource Plan. Updated Project Quality Plan. Agreed FEED contractor quality plans. Updated Quality Criticality Rating and Quality Intervention schedule. Updated Project Audit & Review Plan + tracking register. Quality learning, measurement and trend analysis report. Project Team and Contractor Audit & Review and Surveillance reports. Change registers. Page 34 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Final Project Quality Plan. Agreed (EPC) contractor Project Quality Plan. QA/QC Resource Plan. Updated Quality Criticality Rating and Quality Intervention schedule for construction. Third party inspection reports. Quality learning, measurement and trend analysis report. Project and Contractor Quality Audit & Review and Surveillance reports. Quality certification records and hand-over documentation. Quality health-check report. Appendix 3 Project Quality Delivery Plan PDO_Project Quality Delivery Plan-TEMPLATE_R02.xlsx Double click on the icon for opening the file. Version 2.0 Effective: Sep -14 Petroleum Development Oman LLC Appendix 4 PQP Narrative Checklist Manage Project Quality Source: based on ISO9001, ISO10005 & ISO10006 (Guidance notes provided in Shell PS and PG’s). PQP Part 1 Content Guidance 1. Introduction: Purpose & Scope Opportunity Statement Governance & Assurance 2. Project QMS 3. Resource Management Quality Objectives & Strategy Quality Policy QMS System Framework & Document Hierarchy/Procedure Summary Quality Management Review Project Organisation (by ORP phase) Quality Accountabilities & Responsibilities Competencies for Quality and Inspection. Quality Audits & Reviews + Project QMS Health Check Nonconformities & Corrective Action Quality Performance Measurement / KPI’s Quality Improvement PS00 Project Development and Implementation + PS06 Project Controls + PS 07 Opportunity Framing / Project Premises + PS10 Project Execution Planning. PS13 Quality in Projects + Quality Toolkit. 4. Measurement Analysis & Improvement Realise Project Quality PQP Part 2 Contents 5. Design & Engineering Co-ordination (incl. DCAF/TQAF) 6. Risk Management 7. Cost Estimating, Cost Control and Planning Contracting and Procurement 8. 9. 10. 11. Page 36 Information Management & Document Control Construction & Installation, Commissioning Start-up Technical Integrity Verification plan Interface Performance Standards & Verification Schemes Interface Change & Deviation Control Interface Control Constructability Equipment/Material Quality Intervention Strategy Reference to procedures, process and risk registers. Reference to procedures, process and, plans and reports. Quality Assessment of Contractors / Suppliers Inspection Test & Surveillance Plan Co-ordination of Inspection Agencies Quality Records, Certification Hand-over dossiers Construction Site Quality Activities. Inspection and Test Plans Flawless Delivery Interface PS11 Project Organisation + Quality Toolkit. PS12 Lessons Learned + Quality Toolkit. PS 08 Defining the Technical Scope + DCAF / TQAF + Quality Toolkit PS20 Risk Management PS03 Capital Cost Estimating + PS04 Scheduling PS05 Contracting & Procurement Strategy Realisation + Quality Toolkit PS15 Information Quality Toolkit Management + PS17 Construction + FPD/OR + Quality Toolkit CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Petroleum Development Oman LLC Version 2.0 Effective: Sep -14 Appendix 5 Quality Management Key Performance Indicators Leading Quality Indicators - Project Quality Management System Health-Check Tool (See Shell Quality health check tool) The tool is intended to be used when assessing the capabilities of a project and/or 3 rd parties Quality Management System (QMS) to meet PDO’s requirements. The questionnaire is aimed at projects categorised ‘business critical’ although it can be tailored to suit other situations. Its primary purpose is to benchmark how mature an organisation’s processes are, how well they are embedded in their culture and to identify where the gaps are so that action can be identified to improve. The questionnaire is not a replacement for independent third party certification, nor does it address all aspects of ISO9001: 2008. Its focus is on those elements of a QMS viewed by PDO as essential to successful project delivery. The questionnaire has been divided into 5 elements which align with ISO9000 and ISO10006: 1. Quality Management System, 2. Management Responsibility, 3. Resource Management, 4. Product (Project) Realisation and Measurement, 5. Analysis and Improvement, These are further broken down into sub-elements (example for Quality Management system sub-element 1, is shown below). For each sub element there are statements that characterise different levels of maturity. The five levels range from the most elementary stage (level 1) that indicates that the arrangements are under development and incomplete through to level 5 where systems are fully implemented, checked and personnel are constantly looking for ways to improve the system and performance. Page 37 CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Version 2.0 Effective: Sep -14 Petroleum Development Oman LLC Lagging Quality Indicators A lagging indication, by definition, is one that follows an event. The importance of a lagging indicator is its ability to confirm that a pattern is occurring or about to occur. Lagging indicators are by far the most widely used in industry, in particular, those associated with measuring defects, e.g. % weld repair; % non-conformities; % waste. Others take into account customer satisfaction – Totally satisfied / Fairly satisfied / Neither satisfied nor dissatisfied / Fairly dissatisfied and Totally dissatisfied. It is suggested that a 4-stage process is followed: Stage Objective/activity 1 Agree on the objectives and scope of the activity to develop performance indicators 2 Development of a deeper understanding by workshop attendees of the main stakeholders in the activity and their concerns. 3 Exploration of the evidence the main stakeholders require to address their concerns, i.e. appropriate and useful indicators. Selection of relevant stakeholders, concerns and indicators 4 Exploration of how the results of the performance measurement against the chosen indicators are going to be used for improving performance, and by whom Exploration of the data required, the practicalities associated with collecting it and using the output, e.g. how this activity may link with the other measurement or monitoring activities taking place Good practice examples of key performance indicators are shown below. They should be used across each ORP phase, reported using existing project management tools, and adjusted to meet the needs of an individual project. Quality Management KPI’s: Quality Indicator Measure Audits and reviews planned, actioned, outstanding Total No. overdue Vs Total planned for period Quality Resources No. of resources Vs No. of positions established No. raised Vs No. closed No. of documents delivered late Vs No. required by schedule / MDR Total No. overdue Vs Total planned for period QKPI 01 – QMS Effectiveness Closure of NCR’s Management system Procedures per function/discipline Management review meetings Page 38 ORP Phase All Threshold >90% Review Frequency Quarterly All >90% Quarterly Statistic / Trend All > 90% Quarterly Statistic / Trend All < 5% Monthly Statistic / Trend All >90% Yearly Statistic / Trend CP-190: Quality Management System for Project Delivery Report Format Statistic / Trend Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Version 2.0 Effective: Sep -14 QKPI 02 – Quality in Design Petroleum Development Oman LLC Quality Indicator Measure HAZOP actions outstanding No. cleared Vs Targeted Holds outstanding No. design issues / queries closed Vs Targeted No. raised Vs No. cleared Design Changes and/or Deviations Design deliverables Closure of Supply Chain NCR’s Holds outstanding Correctness and completeness of the procurement documents QKPI 03 – Quality in Supply Chain Document turnaround compliance (vendor/contractor/PDO) PGSC compliance ITP witness & hold points Page 39 No. of document delivered late Vs No. required by schedule / MDR No. raised Vs No. closed No. of Holds cleared Vs Targeted Correct TA level Approval for Material Requisitions Vs Technical Specifications of POs (along with respective PE Signature) issued for criticality level CR1 & CR2 Items. Material Requisitions / Technical Specifications, Drawings & ITPs approved in ten (10 Working days) for criticality level CR1 & CR2 Items. Vendor / Subvendors selected from the AVME List or approved by CFDH (prior to award) for criticality level CR1 & CR2 Items. No. of witness & hold points missed Vs No. required ORP Phase Select, Define and Execute Select, Define and Execute Select, Define and Execute Select, Define and Execute Threshold > 90% Review Frequency Monthly Report Format Statistic / Trend > 90% Monthly Statistic / Trend > 90% Monthly Statistic / Trend < 5% Monthly Statistic / Trend Execute > 90% Monthly Statistic / Trend Execute > 90% Monthly Statistic / Trend Execute 100 % Monthly Statistic / Trend Execute > 95 Monthly Statistic / Trend (An auditable Spread sheet shall be developed and implemented) Execute 100 % Monthly Statistic / Trend Monthly Statistic / Trend Execute < 5% CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. Version 2.0 Effective: Sep -14 Petroleum Development Oman LLC Quality Indicator Measure CR/ITP compliance (approval and H/W points) Inspection visit performed for Hold or Witness points as per ITP for criticality level CR1 & CR2 Items. Material / Equipment inspected and accepted prior to dispatch to sites for criticality level CR1 & CR2 Items. No. of documents delivered late Vs No. required by schedule / MDR Material delivery compliance (documentation & Technical) Vendor Quality Records & Data outstanding Vendor / supplier materials / equipment QKPI 04 – Quality in Fabrication, Construction & Installation ITP witness & hold points Field Trouble Reports NCR’s Deviations / Concessions Weld repair rate (Piping) Weld repair rate (Pipeline) Hand-over documentation Page 40 No.of recorded material / equipment traceability / identification issues. Vs No of materials / equipment items received No. of witness & hold points missed Vs No. required No. cleared Vs No. raised No. closed Vs No. raised No. cleared Vs No. raise No of joints rejected Vs No of joints tested No of joints rejected Vs No of joints tested No. of documents delivered late Vs No. required by schedule / MDR ORP Phase Execute Threshold Execute 100 % 100% for H & 95%for W Review Frequency Monthly Report Format Statistic / Trend Monthly Statistic / Trend Execute < 5% Monthly Statistic / Trend Execute < 5% Monthly Statistic / Trend Execute < 5% Monthly Statistic / Trend Execute > 90% Monthly Statistic Execute > 90% Quarterly Statistic / Trend Execute > 90% Monthly Statistic / Trend Execute < 3% Weekly Statistic / Trend Execute < 5% Weekly Statistic / Trend Execute < 5% Monthly Statistic / Trend CP-190: Quality Management System for Project Delivery Printed 13/04/22 The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.