Design Development Estimate Project: Building 2 - Student Success Center Owner: Tarrant County College Architect: Huckabee and Gensler Date: 18/Oct/21 Total SF: 153,000 Project Summary Sheet System Qnt 51,373 System UM A10 Foundations sf System U/P $24) B10 Superstructure 41,836 sf $146) B20 Exterior Enclosure 61,592 sf $199) B30 Roofing 51,373 sf $14) (702,926) Roof only SF 1.43% B31 Green Roof 51,373 sf $0) (22,568) Roof only SF 0.05% C10 Interior Construction 153,000 sf $15) C20 Stairs C30 Interior Finishes 12 flights $4,438) 296,000 sf $3) Project Totals (1,230,382) SF of foundation 2.49% (6,097,901) SF of floor and roof structures 12.36% (12,245,977) Face SF - from elevations (2,348,358) SF of finished area 24.83% 4.76% (53,254) total number of risers 0.11% (823,713) SF of finished area 1.67% D10 Conveying 4 stop $36,071) (144,283) total number of stops 0.29% D20 Plumbing 153,000 sf $2) (327,304) SF of building 0.66% D30 HVAC 153,000 sf $13) (2,016,270) SF of building 4.09% D40 Fire Protection 153,000 sf $1) D50 Electrical 153,000 sf $51) D51 Electrical Lighting 153,000 sf $8) E20 Furnishings 153,000 sf N/a Not Included F20 Selective Building Demolition 0 sf N/A Not Included G10 Site Preparation 3 acre $50,000) G20 Site Improvements 3 acre $100,000 G30 Utilities 3 acre $50,000 H10 General Conditions / Requirements 0 Months 10% Subtotal (207,060) SF of building 0.42% (7,817,004) SF of building 15.85% (1,164,212) SF of building 2.36% SF of building (172,000) Total project Acres (344,000) (172,000) (3,588,921) 10% of total costs $39,478,134) By Owner Utility Tap & Devel. Fees Plan Review Fees 2,410 Building Permit Fees 141,216 Use Tax (6.25% on Materials) 986,953 Street Closures/Parking Meters/Covered Walks Not Included Design Phase Contingency 3.00% (1,218,261) Construction Contingency 3.00% (1,254,809) Builders Risk Insurance 0.25% (107,704) Comprehensive General Liability Insurance 1.25% (539,869) Sub Bonding Subguard 1.25% (448,615) Perform., Labor & Material Bond 1.00% (477,122) Escalation Allowance - 12 months 6.20% (2,768,616) General Contractors Fee 3.50% (1,659,830) Preconstruction Services 0.50% (237,119) Initial Cost Model Total $49,320,659) $/sf: $322) Crew Daily Output Labor Hours Line Item QNTY A10 - Foundations Line Item U/M Labor U/P Total Labor Material U/P Total Material Equipment U/P Total Sub U/P Equipment Total Sub $1,230,382 A10203102400 - Special Foundations - Caissons Line Item 31 06 60 - Drill Rig Mobilization 310660150520 B43 Line Item 03 21 11 - Steel Reinforcement 4 Rodm 32111600200 0.5 $495,810 96 1.00 EA $4,825.00 $4,825.00 $0.00 $0.00 $1,575.00 $1,575.00 $6,400.00 $6,400.00 258 Caissons Mobilization, to 36" and remobe drill rig $8,684.33 $0 1.5 21.33 18.06 TN 0.07 TN/EA $653.90 $11,809.43 $1,454.35 $26,265.56 N/A N/A $2,108.25 $38,075.00 $46,469.82 $46,470 Line Item 31 63 26 - Fixed End Caisson Piles 316326130300 B43 150 Line Item 31 63 26 - Bell Excavation Add 316326131040 B43 Line Item 31 63 26 - Load and Haul Soil 316326134500 B34B 0.32 5,676.00 VLF 22.00 VLF/EA $14.39 $81,677.64 $5.25 $29,799.00 $31.13 $176,693.88 $50.61 $287,262.36 $347,541.48 $394,011 5.7 8.421 258.00 EA $379.95 $98,027.10 $219.25 $56,566.50 $133.72 $34,499.76 $732.92 $189,093.36 $245,536.02 $0 178 0.045 7,120.80 LCY 27.60 LCY/EA $2.13 $15,167.30 $0.00 $0.00 $4.18 $29,764.94 $6.31 $44,932.25 $55,329 A10301206800 - Slab on Void Line Item $734,572 03 11 13 - C.I.P. concrete forms 31113653050 0.03 C1 435.00 51373 SF 0.07 1541.19 SFCA 0.03 SFCA/SF $2.41 $3,714.27 $1.21 $1,864.84 $0.00 $0.00 $3.62 $5,579.11 $7,551.83 $7,552 Total Line Item 03 15 16 - Expansion Joint 0.22 1 Carp 31516302000 375 0.021 11302.06 LF 0.22 LF/SF $0.73 $8,250.50 $0.41 $4,633.84 $0.00 $0.00 $1.14 $12,884.35 $17,405.17 $17,405 Total Line Item 03 22 11 - Welded Wire Fabric 32211100400 0.01 2 Rodm 27 0.593 513.73 CSF 0.01 CSF/SF $18.11 $9,303.65 $52.16 $26,796.16 $0.00 $0.00 $70.27 $36,099.81 $43,194.42 $60,600 Total Line Item 03 31 13 - Structrual Concrete Mix 33113350350 0.025 1284.325 CY 0.025 CY/SF $0.00 $0.00 $117.18 $150,497.20 $0.00 $0.00 $117.18 $150,497.20 $164,984.39 $164,984 Total Line Item 03 31 13 - Structural Concrete Placing 33113704600 0.025 C6 165 0.291 1284.325 CY 0.025 CY/SF $9.21 $11,828.63 $0.00 $0.00 $0.33 $423.83 $9.54 $12,252.46 $18,108.98 $18,109 Total Line Item Line Item 03 35 13 - Concrete Finishing 33513300250 1 C10C 33516302100 1715 03 35 16 - Concrete Floor Hardener , Dry Shake 1 Cefi 650 0.014 0.012 51373 SF 1 SF/SF $0.48 51373 SF 1 SF/SF $0.44 $24,659.04 $0.00 $0.00 $0.05 $2,568.65 $0.53 $27,227.69 $39,043.48 $39,043 $22,604.12 $1.44 $73,977.12 $0.00 $0.00 $1.88 $96,581.24 $114,048.06 $114,048 Total Line Item 03 39 23 - Concrete Cure, Sprayed Membrane 33923130300 1 2 Clab 95 0.168 513.73 CSF 0.01 CSF/SF $5.16 $2,650.85 $11.76 $6,041.46 $0.00 $0.00 $16.92 $8,692.31 $10,582.84 $10,583 Total Line Item 03 53 16 - Granolithic topping , Trowel Finish 35316500850 1 C10B 575 0.07 51373 SF 1 SF/SF $2.10 $107,883.30 $0.68 $34,933.64 $0.53 $27,227.69 $3.31 $170,044.63 $227,068.66 $227,069 Total Line Item Line Item 07 26 13 - Vapor Retarder 72613100900 0.01 1 Carp 312216100012 31 22 16 - Fine Grading 0.11 B11L 37 400 0.216 0.04 513.73 SQ 0.01 SQ/SF $7.85 5651.03 SY 0.11 SY/SF $2.08 $4,032.78 $5.56 $2,856.34 $0.00 $0.00 $13.41 $6,889.12 $9,144.39 $9,144 $11,754.14 $0.00 $0.00 $1.87 $10,567.43 $3.95 $22,321.57 $29,046.29 $29,046 Total Line Item 31 22 16 - Fill, Gravel 312323170500 1 B37 Total Volume Caisson * 1.2 Swell / 27 $55,328.62 10000 0.005 51373 SF 1 $0.23 $11,815.79 $0.33 $16,953.09 $0.03 $1,541.19 $0.59 $30,310.07 $36,988.56 $36,989 Crew Daily Output Labor Hours B10 - Superstructure Line Item QNTY Line Item U/M Labor U/P Total Labor Material U/P Total Material Equipment U/P Total Sub U/P Equipment Total Sub Total O&P $6,097,901 B10102087800 - Steel Columns Line Item $1,454,843.12 05 22 37 - Steel Columns w/ Labor and Equipment 51223770800 E6 14.40 8.89 311.808 TN 162.40 LB/VLF $375.51 $117,087.02 $3,530.90 $1,100,962.87 $197.68 $61,638.21 $4,104.09 $1,279,688.09 $1,454,843.12 80 Col 48' EA $1,454,843 B10102417750- Steel W Beams Line Item 05 22 37 - Steel Beams w/ Labor and Equipment 51223770800 E6 Line Item 07 81 16 - Spray Fireproofing Beams G2 78116100400 $2,105,231 102746 SF 14.40 8.89 431.5332 TN 8.40 LB/SF $375.51 $162,045.03 $3,530.90 $1,523,700.58 $197.68 $85,305.48 $4,104.09 $1,771,051.09 $2,013,460.55 $2,013,461 1,500.00 0.016 64627.234 SF 0.63 SF/SF $0.49 $31,667.34 $0.55 $35,544.98 $0.09 $5,816.45 $1.13 $73,028.77 $91,770.67 $91,771 B10102542400- CLT Deck Line Item 32211100100 03 22 11 - Welded Wire Fabric 2 Rodm $2,537,826 102746 SF 35.00 0.457 1130.206 CSF 0.011 CSF/SF $14.08 $15,913.30 $22.07 $24,943.65 $0.00 $0.00 $36.15 $40,856.95 $51,356.56 $51,357 03 31 13 - Structural Concrete Line Item 33113350150 Line Item 03 31 13 - Elevated Slab, Placing, Pumped C20 33113701400 Line Item 03 35 13 - Concrete Finishing C10C 33513300250 Line Item 03 39 23 - Concrete Curing Finish 2 Clab 33923130300 Line Item 05 31 13 - CLT Decking E4 53113505800 Line Item 05 31 33CLT - Metal Decking Decking edge edge E14 53133507100 Line Item 07 81 16 - Spray Fireproofing - Deck G2 78116100500 1130.206 CY 0.011 CY/SF $0.00 $0.00 $138.01 $155,979.73 $0.00 $0.00 $138.01 $155,979.73 $171,678.29 $171,678 140.00 0.457 1130.206 CY 0.011 CY/SF $14.74 $16,659.24 $0.00 $0.00 $5.62 $6,351.76 $20.36 $23,010.99 $31,939.62 $31,940 1,715.00 0.014 102746 SF 1.000 SF/SF $0.48 $49,318.08 $0.00 $0.00 $0.05 $5,137.30 $0.53 $54,455.38 $78,086.96 $78,087 95.00 1.68 1027.46 CSF 0.010 CSF/SF $5.16 $5,301.69 $11.76 $12,082.93 $0.00 $0.00 $1.13 $16.92 $21,165.68 $21,166 3000 0.011 107883.3 SF 1.050 SF/SF $0.47 $50,705.15 $3.39 $365,724.39 $0.05 $5,394.17 $3.91 $421,823.70 $483,317.18 $483,317 360.00 0.022 3390.618 LF 0.033 LF/SF $1.42 $4,814.68 $4.96 $16,817.47 $0.41 $1,390.15 $6.79 $23,022.30 $27,430.10 $27,430 1,250.00 0.019 102746 SF 1.000 SF/SF $0.59 $60,620.14 $0.81 $83,224.26 $0.11 $11,302.06 $1.51 $155,146.46 $195,217.40 $195,217 3840 Crew Daily Output B20 - Superstructure Labor Hours Line Item QNTY Line Item U/M Labor U/P Total Labor Material U/P Total Material Equipment U/P Total Sub U/P Equipment Total Sub Total O&P $12,245,977 B20202202650 - Enclosure - Curtain Wall Curtain Wall Line Item 84413100200 61592.5 SF $5,550,520.76 26084.5 SF H1 160.00 0.20 26084.5 SF $6.84 $178,417.98 $184.12 $4,802,678.14 $0.00 $0.00 $190.96 $4,981,096.12 $5,550,520.76 0.423501238 $5,550,521 Total B20202202650 - Enclosure - Brick Cladding Line Item $325,513 04 27 10 - Brick Walls, Face Brick, 4" Thick, includes mortar, waster, vertical reinforcement, grout 42710301200 D8 210.00 0.19 14178 SF 1.0000 SF/SF $5.74 $81,381.72 $10.66 $151,137.48 $0.00 $0.00 $10.66 $151,137.48 $198,775.56 14178 sf $198,776 Line Item 72116201320 07 21 16 - Mineral Wool, 2", R15 1 Carp 1,600.00 0.005 8101.7 SF 0.5714 SF/SF $0.18 $1,458.31 $0.96 $7,777.65 $0.00 $0.00 $1.14 $9,235.95 $10,775.28 $10,775 Line Item 06 16 43 - Glass Matt Gyp, 5/8" 61643100040 2 Carp includes interior and exterior 1,100.00 0.015 35445 SF $0.52 $18,431.40 $0.63 $22,330.35 $0.00 $0.00 $1.15 $40,761.75 0.2301903641 $51,749.70 2.5000 SF/SF $51,750 Line Item 07 25 10 - Weather Barrier 7251010048 1 Carp 4,000.00 0.002 14178 SF 1.0000 SF/SF $0.07 $992.46 $0.06 $850.68 $0.00 $0.00 $0.13 $1,843.14 $2,410.26 $27,080 Line Item 09 22 16 - Cold Formed Metal Stud (16' x 6" x 20 Gauge) 16" OC 92216133430 1 Carp 400.00 Line Item 07 65 10 - Sheet Metal Flashing 76510100060 1 Rofc 0.02 14178 SF 1.0000 SF/SF $0.70 $9,924.60 $0.63 $8,932.14 $0.00 $0.00 $1.33 $18,856.74 $24,669.72 $24,670 145.00 0.055 1417.8 SF 0.1000 SF/SF $1.86 $2,637.11 $5.22 $7,400.92 $0.00 $0.00 $7.08 $10,038.02 $12,462.46 $12,462 B20101545800 - Enclosure - Metal Cladding Aluminum Siding, .125" Thick G3 Line Item 74213200100 Line Item 07 21 16 - Mineral Wool, 2", R15 72116201320 1 Carp $191,018 775.00 0.04 13002 SF 1.00 SF/SF $1.55 $20,153.10 $1.73 $22,493.46 $962.64 $12,516,245.28 $3.22 $41,866.44 $64,749.96 $64,750 13002 SF 1,600.00 0.005 7429.71 SF 0.5714 SF/SF $0.18 $1,337.35 $0.96 $7,132.53 $0.00 $0.00 $3.28 $24,369.46 $31,353.39 0.2110971303 $31,353 Line Item 61643100040 includes interior and exterior 06 16 43 - Glass Matt Gyp, 5/8" 2 Carp 1,100.00 0.015 32505 SF $0.52 $16,902.60 $0.63 $20,478.15 $0.00 $0.00 $1.15 $37,380.75 $47,457.30 2.5000 SF/SF $47,457 Line Item 07 25 10 - Weather Barrier 7251010048 1 Carp 4,000.00 0.002 13002 SF 1.0000 SF/SF $0.07 $910.14 $0.06 $780.12 $0.00 $0.00 $0.13 $1,690.26 $2,210.34 $24,834 Line Item 09 22 16 - Cold Formed Metal Stud (16' x 6" x 20 Gauge) 16" OC 92216133430 1 Carp 400.00 0.02 13002 SF 1.0000 SF/SF $0.70 $9,101.40 $0.63 $8,191.26 $0.00 $0.00 $1.33 $17,292.66 $22,623.48 $22,623 C10101403030 - Enclosure - Plaster Cladding Line Item 92320101200 92236233000 $111,874 Gypsum Plaster 3 Coats, Metal Lath, On Studs J2 86.00 8328 SF 0.56 924.4 SY 0.11 SF/SY $17.44 $0.00 $16,120.75 $0.00 $12.72 $2.26 $11,758.47 $2,089.16 $1.28 $0.00 $1,183.24 $0.00 $29.13 $0.00 $26,928.01 $0.00 $35,756.10 $0.00 $35,756 Line Item 07 21 16 - Mineral Wool, 2", R15 72116201320 1 Carp 8328 SF 1,600.00 0.005 4758.9 SF 0.5714 SF/SF $0.18 $856.59 $0.96 $4,568.50 $0.00 $0.00 $1.14 $5,425.10 $6,329.28 $6,329 Line Item 06 16 43 - Glass Matt Gyp, 5/8" 61643100040 2 Carp includes interior and exterior 1,100.00 0.015 20820.0 SF $0.52 $10,826.40 $0.63 $13,116.60 $0.00 $0.00 $1.15 $23,943.00 $30,397.20 2.5000 SF/SF $30,397 Line Item 07 25 10 - Weather Barrier 7251010048 1 Carp 4,000.00 0.002 8328.0 SF 1.0000 SF/SF $0.07 $582.96 $0.06 $499.68 $0.00 $0.00 $0.13 $1,082.64 $1,415.76 $15,906 Line Item 09 22 16 - Cold Formed Metal Stud (16' x 6" x 20 Gauge) 16" OC 92216133430 1 Carp 400.00 Line Item 09 96 53 - Elastomeric Coatings, One Coat, Spray, Stucco 1 Pord 99653100320 1,500.00 0.02 8328.0 SF 1.0000 SF/SF $0.70 $5,829.60 $0.63 $5,246.64 $0.00 $0.00 $1.33 $11,076.24 $14,490.72 $14,491 0.80 8328.0 SF 1.0000 SF/SF $0.13 $1,082.64 $0.80 $6,662.40 $0.00 $0.00 $0.93 $7,745.04 $8,994.24 $8,994 Type Mark Manufacturer Model Lamp Line Item U/M Line Item U/P Labor U/P Total Labor Total Material Material U/P Sub U/P Total O&P D51 - Electrical Lighting $1,164,212 $159,746.73 Type Mark Manufacturer Model Lamp XA1 XB1 XD1 XL1 XL2 XM1 XP1 iGuzzini BEGA USAI Lighting iGuzzini iGuzzini WAC Lighting Lithonia Trick 360 77 221 4.5" BeveLED Linealuce Compact Linealuce Compact Accent 120V Radean Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Count Count Count Count Count Count Count XW1 WAC Lighting CUBE Architectural Integrated LED Count Type Mark Manufacturer Model Lamp C1 D1 L1 M1 P1 P1A P1B P1C P1D P1E P1F P1G P1H P1I P2A P2B P2C P2D P2E P2F P2G P3 P4 P5 R1 R2 S1 T1 Prudential P59 USAI Lighting 4.5" BeveLED Tivoli Flexile LG WAC Lighting Paloma OCL Tubie 7 OCL Tubie 7 OCL Tubie 7 OCL Tubie 7 OCL Tubie 7 OCL Tubie 7 OCL Tubie 7 OCL Tubie 7 OCL Tubie 7 OCL Tubie 7 Beta-Calco Ring 3 Beta-Calco Ring 3 Beta-Calco Ring 3 Beta-Calco Ring 3 Beta-Calco Ring 3 Beta-Calco Ring 3 Beta-Calco Ring 3 USAI Lighting CNRD WAC Lighting Tube Architectural Mark Architectural Lighting SLOT1 Mark Architectural Lighting Whisper Lumenwerx VIA4R Lithonia CSS WAC Lighting W Track System 24 11 39 182 64 33 4 2,311 $125.00 $300.00 $62.50 $62.50 $62.50 $37.50 $500.00 $3,000.00 $3,300.00 $2,437.50 $11,375.00 $4,000.00 $1,237.50 $2,000.00 $0.25 $577.75 $500.00 $1,200.00 $250.00 $250.00 $250.00 $150.00 $2,000.00 $12,000.00 $13,200.00 $9,750.00 $45,500.00 $16,000.00 $4,950.00 $8,000.00 $2,160.00 $2,376.00 $1,755.00 $8,190.00 $2,880.00 $891.00 $1,440.00 $17,160.00 $18,876.00 $13,942.50 $65,065.00 $22,880.00 $7,078.50 $11,440.00 $1.00 $2,311.00 $415.98 $3,304.73 $959,465.65 Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Integrated LED Count Count Count Count Count Count Count Count Count Count Count Count Count Count Count Count Count Count Count Count Count Count Count Count Count Count Count Count 100 250 60 350 600 600 600 800 800 1000 1000 1200 1200 1200 750 1500 2250 3000 4500 6000 9000 500 400 800 125 540 60 271.25 $70.25 $34.75 $0.25 $6.00 $1.00 $2.75 $2.50 $2.75 $1.50 $2.25 $2.25 $1.25 $0.50 $1.00 $0.50 $1.50 $4.00 $5.00 $5.00 $0.75 $0.50 $53.75 $6.00 $15.00 $227.00 $9.00 $34.25 $1.00 $7,025.00 $8,687.50 $15.00 $2,100.00 $600.00 $1,650.00 $1,500.00 $2,200.00 $1,200.00 $2,250.00 $2,250.00 $1,500.00 $600.00 $1,200.00 $375.00 $2,250.00 $9,000.00 $15,000.00 $22,500.00 $4,500.00 $4,500.00 $26,875.00 $2,400.00 $12,000.00 $28,375.00 $4,860.00 $2,055.00 $271.25 $281 $139 $1 24 $4 $11 $10 11 $6 $9 $9 5 $2 $4 $2 6 $16 $20 $20 $3.00 2 $215 $24 $60 908 $36 $137 $4 $28,100.00 $34,750.00 $60.00 $8,400.00 $2,400.00 $6,600.00 $6,000.00 $8,800.00 $4,800.00 $9,000.00 $9,000.00 $6,000.00 $2,400.00 $4,800.00 $1,500.00 $9,000.00 $36,000.00 $60,000.00 $90,000.00 $18,000.00 $18,000.00 $107,500.00 $9,600.00 $48,000.00 $113,500.00 $19,440.00 $8,220.00 $1,085.00 $5,058.00 $6,255.00 $10.80 $1,512.00 $432.00 $1,188.00 $1,080.00 $1,584.00 $864.00 $1,620.00 $1,620.00 $1,080.00 $432.00 $864.00 $270.00 $1,620.00 $6,480.00 $10,800.00 $16,200.00 $3,240.00 $3,240.00 $19,350.00 $1,728.00 $8,640.00 $20,430.00 $3,499.20 $1,479.60 $195.30 $40,183.00 $49,692.50 $85.80 $12,012.00 $3,432.00 $9,438.00 $8,580.00 $12,584.00 $6,864.00 $12,870.00 $12,870.00 $8,580.00 $3,432.00 $6,864.00 $2,145.00 $12,870.00 $51,480.00 $85,800.00 $128,700.00 $25,740.00 $25,740.00 $153,725.00 $13,728.00 $68,640.00 $162,305.00 $27,799.20 $11,754.60 $1,551.55 $45,000.00 Motorized Window Shades Count 1 $45,000.00 TCC Schematic Design Classic WBS Layout Qtr 3, 2021 Jul Aug Qtr 4, 2021 Sep Oct Nov Qtr 1, 2022 Dec Jan Feb Qtr 2, 2022 Mar Apr May Qtr 3, 2022 Jun Jul Aug Qtr 4, 2022 Sep Oct Nov 03-Dec-21 13:32 Qtr 1, 2023 Dec Jan Feb Qtr 2, 2023 Mar Apr May Qtr 3, 2023 Jun Jul Aug Qtr 4, 2023 Sep Oct Nov Qtr 1, 2024 Dec Jan Feb Qtr 2, 2024 Mar Apr May Qtr 3, 2024 Jun Jul Aug Sep 05-Jun-24, TCC Schematic Design Design Start 27-Jul-22, 1: Pre-Construction / Planning 13-Aug-21, Introduction Team Discussion Team Introduction Interviews 27-Jul-22, Design Phases Notice to Proceed OwnerApproval on Schematic Design OwnerApproval to DD OwnerApproval to 50% CD OwnerApproval Full CD DD SD and CD Full CD 50% CD 13-Jul-22, Scheudling Preliminary Schedule Detailed Schedule Final Schedule Schematic Design Schedule 21-Jul-22, Permits Grading and Erosion Permit Utilities Permit Building Permit 08-Jun-22, Submittals Rebar Submittal Steel Submittal Curtain Wall Submittals Mechanical Submittals Elevator Submittals Electrical Submittals Fire Submittal 02-Dec-22, 2: Building Sitework 21-Sep-22, Cut and Fill Construction Start Staking and Survey Cut and Fill 02-Dec-22, Utilities Sewer Storm Water 04-Jan-23, 3: Substructure 14-Dec-22, Caissons Caissons Area A Caissons Area B Actual Work Critical Remaining Work Remaining Work Milestone Summary Page 1 of 3 TASK filter: All Activities © Oracle Corporation XC045 TCC Schematic Design Classic WBS Layout Qtr 3, 2021 Jul Aug Qtr 4, 2021 Sep Oct Nov Qtr 1, 2022 Dec Jan Feb Qtr 2, 2022 Mar Apr May Qtr 3, 2022 Jun Jul Aug Qtr 4, 2022 Sep Oct Nov 03-Dec-21 13:32 Qtr 1, 2023 Dec Jan Feb Qtr 2, 2023 Mar Apr May Qtr 3, 2023 Jun Jul Aug Qtr 4, 2023 Sep Oct Nov Qtr 1, 2024 Dec Jan Feb Qtr 2, 2024 Mar Apr May Qtr 3, 2024 Jun Jul Aug Sep 04-Jan-23, Slab on Void SOV Area A SOV Area B 08-Mar-23, 4: Superstructure 08-Feb-23, Steel Columns Steel Columns First Floor Steel Columns Second Floor 15-Feb-23, Concrete Shear Walls Shear Walls First Floor Shear Walls Second Floor Shear Walls Third Floor 01-Mar-23, Steel Beams Steel Beams Second Floor Steel Beams Third Floor 08-Mar-23, Wooden Deck Wooden Deck Second Floor Wooden Deck Third Floor 03-Jan-24, 5: Exterior Enclosure 23-Nov-23, Exterior Walls Finish Core and Shell Brick Walls Area A Brick Walls Area B Curtain Walls Area A Curtain Walls Area B Plaster Walls Area A Plaster Walls Area B 03-Jan-24, Exterior Doors Exterior Doors 19-Apr-23, Roof Coverings Roof 14-Feb-24, 6: Interior Construction 10-May-23, Interior Metal Studs Interior Studs 14-Feb-24, Interior Partitions Interior Partitions 20-Mar-24, 7: Interior Finishes 20-Mar-24, Wall Finishes Wall Finishes 20-Dec-23, Floor Finishes Carpet 12-Jul-23, Ceiling Finishes Acoustical Ceiling 02-Aug-23, 8: Conveying 02-Aug-23, Elevator Elevator 23-Aug-23, 9: Plumbing Actual Work Critical Remaining Work Remaining Work Milestone Summary Page 2 of 3 TASK filter: All Activities © Oracle Corporation XC046 TCC Schematic Design Classic WBS Layout Qtr 3, 2021 Jul Aug Qtr 4, 2021 Sep Oct Nov Qtr 1, 2022 Dec Jan Feb Qtr 2, 2022 Mar Apr May Qtr 3, 2022 Jun Jul Aug Qtr 4, 2022 Sep Oct Nov 03-Dec-21 13:32 Qtr 1, 2023 Dec Jan Feb Qtr 2, 2023 Mar Apr May Qtr 3, 2023 Jun Jul Aug Qtr 4, 2023 Sep Oct Nov Qtr 1, 2024 Dec Jan Feb Qtr 2, 2024 Mar Apr Qtr 3, 2024 May Jun Jul Aug Sep 23-Aug-23, Plumbing Fixtures Plumbing Fixtures 22-Mar-23, Interior Water Supply Interior Water 14-Feb-24, 10: HVAC 12-Jul-23, MEP Rough MEP Rough 03-Jan-24, MEP Finished MEP Finished 07-Feb-24, Heat Generation System Heat System 14-Feb-24, Cooling Generation System Cooling System 14-Jun-23, 11: Fire Protection 14-Jun-23, Sprinklers Sprinklers 14-Jun-23, Standpipes Standpipes 07-Feb-24, 12: Electrical 14-Jun-23, Interior Electrical Rough Interior Electrical Rough 27-Dec-23, Inteior Electrical Finish Interior Electrical Finish 07-Feb-24, Communication Systems Communication System 25-Apr-24, 13: Electrical Lighting 07-Feb-24, Interior Lighting Interior Lighting 25-Apr-24, Exterior Lighting Exterior 24-Apr-24, 14: Furnishings 24-Apr-24, Install Furnishings Furnishing 29-May-24, 15: Landscaping 29-May-24, Landscaping Landscaping 05-Jun-24, 16: Site Improvements 05-Jun-24, Site Improvements Project Finish Site Improvements Actual Work Critical Remaining Work Remaining Work Milestone Summary Page 3 of 3 TASK filter: All Activities © Oracle Corporation XC047 Legend Parking Signs Fence Jobsite Trailer Crane location Concrete Pump Concrete Washout Material Laydown Utilities Equipment Storage Pedestrian Path Jobsite Sanitation Proposed Building Construction Equipment Path XE-048 Orange path shows the path in which material will be delivered to the site. The orange path has a highway entrance and exit nearby. The green path shows how the other part of campus can remain in use. XE-049