Ruci Construction LTD
Provisional Plan for 2 Norfolk Close , TW1 1RT
On behalf of Clients Louise and Ben Dunster
All plans are subject to change depending on findings during the process.
Stage 1
Support the kitchen wall with needles and props and expose the longitudinal
beam separating the kitchen and living area. Confirm with structural engineer if
any extra support is required
Kitchen/Living room partition wall complete removal and make good corners and
edges, ready for decorating.
Removal of kitchen door and frame, blocking up opening, hardwall and plaster
ready for decorating.
Stripping old floor tiles, clear floor from adhesive. Self leveling floor, to bring it up
to desired level, ready for flooring to be laid.
Reducing outside storage in the right corner of the kitchen. Plaster whole ceiling
to cover existing features.
Remove the old kitchen .
Stage 2
Removal of living room flooring and skirting, removal of skirting in hallway and
two rooms.
Self leveling Living room floor to hallway and room floor level.
Removal of section of wall, built in wardrobe and chimney in small bedroom.
Build a steel plate to top of the existing chimney using props to support the load
(as per engineers directions). Fit new boxing-in to cover steel plate with mdf
board/plaster board.
Block up the fireplace opening and make a good living room/bedroom wall with
hardwall and plaster, ready for decoration.
Inspect and remove the hollow part of the large bedroom wall next to the
door/window. Build the wall back to exact size with blocks, make a good wall,
ready for decoration.
Move existing ceiling light to center/requested position.
Complete removal of 5 doors and door frames.
Fit new kitchen
Stage 3
Lay new underlay/laminate flooring in kitchen, living room, hallway and bedrooms.
Fit new skirting in all round and all rooms.
Fit 5 new door frames and hang new doors.
Stage 4
Remove the existing bathroom floor, toilet and bathroom basin, shower unit.
Tiling the whole bathroom floor and replacing 4 cracked wall tile.
Fit new toilet, basin and shower unit.
Plaster bathroom ceiling.
Fit new doors to bathroom storage on wall above toilet.
Painting and decorating.