METHOD STATEMENT BRIDGE #13 CONSTRUCTION Saturday, December 04, 2010 v1 No RESOURCES STEP OF CONSTRUCTION MANPOWER Labor 1 Preparation of site location: A) clearing, stock pile yard, temporary shelter, delivery all materials. B) Armco Bridge works: Assemble wooden mat as raft foundation and cilindrical armco C) Construct temporary dock for pedestrian and motorcycle to pass over the river while bridge will be demolish 2 Constructing ramp on Bridge #11: Labor A) Dumping fill material (laterit soil) ± 30 m3 on one side of bridge #11 (side that facing Desa Cinta Puri). B) Levelling and compacting ramp TOOL Hand Tools Hand Tools 3 Dumping fill material to rise up river bed elevation, near by bridge # 13, ± 100 m3 or less. (dump trucks do not pass bridge #13) LOCATION EQUIPMENT MATERIAL Excavator, Dozer & Tarpaulin, Galams, Bridge #13 Nails. small boat. Light truck, Dozer/Grader & Vibro Roller. Laterit Soil Bridge #11 Light truck, Excavator Boulder and Stone Bridge #13 (Base coarse) Labor, Operator 4 Demolishing exisiting bridge : A) Remove Realling and wooden deck (upper Structure) B )Pulling out existing bridge's beam and pile using excavator. Beam or pile that cannot reach by hydraulic boom will be pulled out with assist of Steel Wire. Steel Wire Excavator Bridge #13 Labor, Operator, 5 Rise up middle section of river bed elevation : A) Filling middle section of river bed with boulder Surveyor and stone until achieved 1.3 m height from existing level. The dimension of filled area 1) 7.5 m long regarding Armco length 2) 5 m width regarding Armco Dia. 4500 mm 3) 1.3 m height to rise up armco elevation up to 1.3 m or less B) Measure/Check river bed after filled to confirm the elevation 7 Wooden mat/raft foundation: Labor, Operator putting down wooden mat at the river bed and piling array galam timber to fix the position of armco Pole Stick Excavator Boulder and Stone Bridge #13 (Base coarse) Steel Wire Excavator Galam Steel Wire Excavator 2 x Armco Dia. 3600 Bridge #13 mm, Dia. 4500 mm, galam pile Labor, Operator 8 Armco bridge works: A) rolling Armco #1 Dia. 3600 mm to move the precised position using Excavator #1, while the Excavator #2 that stand on the other side pulling it using steel cable to stabilize the position. B) Rolling Armco #2 Dia. 4500 mm using Excavator #1 , while Excavator #1 pulling it the oposite. C) rolling Armco #3 Dia. 3000 mm using Excavator #1. D) Pilling galam to hold the armco on the required position. 9 Back Filling work : Labor, Operator A) Install soil bag to divert water flow & protect backfill area between armco. B) Back fill the space between armco using sirtu up to require elevation 10 Compacting and levelling : Grading & Levelling pavement structure over the bridge surface to design elevation including compaction Labor, Operator Bridge #13 Galam, Sirtu, Excavator, Pontoon, Bulldozer, Sand/soil bags, & Dump Truck Manila Rope. Bridge #13 Vibratory Roller, Bulldozer Bridge #13 Gravel and base coarse