Gas Development Project for the Unitization of the Jambaran-Tiung Biru Field PROJECT EXECUTION PLAN Doc No. A Rev 28 Dec 15 Rev Date Issued For Bid Description DTS JY SS SS Prepared By Checked By Endorsed By Approved By JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 2 of 72 Document Information Revision History Revision Section A All Description Issued for Bidding Distribution List Master Controlled copy Honeywell Document Control Controlled Copy Customer Controlled Copy Honeywell Projects Copyright Statement This document contains information that is confidential and proprietary to Honeywell and may not be reproduced or given to third parties without the express written permission of Honeywell. Copyright 2022, Honeywell Source This document was developed and prepared by Honeywell. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 3 of 72 TABLE OF CONTENTS 1 REFERENCE DOCUMENTS.......................................................................................................8 1.1 1.2 2 Pertamina EP CEPU:...................................................................................................................... 8 Codes/Standards ............................................................................................................................. 8 ABBREVIATIONS, DEFINITIONS AND NOMENCLATURE ....................................9 2.1 2.2 3 Terms.............................................................................................................................................. 9 Abbreviations ................................................................................................................................. 9 INTRODUCTION ...............................................................................................................12 3.1 3.2 3.3 3.3. 3.4. 3.5. 3.7. 3.8. 4. Purpose of the Document ............................................................................................................. 12 Project Overview .......................................................................................................................... 12 HONEYWELL as a MAC............................................................................................................ 12 HONEYWELL Value Proportion .............................................................................................. 13 Honeywell Mission Statement ................................................................................................. 14 Quality Statement ...................................................................................................................... 15 Honeywell Executive sponsor .................................................................................................. 15 Confidentiality ............................................................................................................................. 15 PROJECT OVERVIEW .............................................................................................................16 4.1. 4.2. 4.3. 4.4. 5. Basis of the Execution Plan ..................................................................................................... 16 Key factors for Success of the Project ................................................................................... 16 MAC Scope of Work Overview ................................................................................................ 17 Project Locations and Sourcing............................................................................................... 19 PROJECT EXECUTION STRATEGY ..........................................................................................20 4.5. Project Execution Work Flow ................................................................................................... 20 4.5.1. 4.5.2. Manufacturing Process for ICSS - JTB MAC ............................................................ 20 Detailed Explanation on Implementation ................................................................... 23 4.6. 4.7. 4.8. 4.9. Manufacturing & Software development Process for IECS - JTB MAC............................ 23 Detailed design phase .............................................................................................................. 24 Project Implementation phase ................................................................................................. 24 Commissioning Phase .............................................................................................................. 24 4.9.1. Installation & Commissioning Support ....................................................................... 24 4.10. 4.11. 4.12. Post Commissioning / Long term Support ............................................................................. 24 Project Milestones ..................................................................................................................... 25 Proposed Project Schedule ..................................................................................................... 25 6. PROJECT ORGANIZATION ..............................................................................................26 4.13. Project Organization.................................................................................................................. 26 Project Members and Their Roles and Responsibilities. ...................................................................... 26 6.1. Honeywell Site Team ................................................................................................................ 31 6.2. Responsibilities Matrix (Between MAC and CONTRACTOR/Company) .......................... 31 7. PROJECT MANAGEMENT PLAN ...............................................................................33 6.3. 6.4. Global Project Management Methodology ............................................................................ 33 Global Project Engineering Methodology .............................................................................. 33 Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 4 of 72 6.4.1. Customer satisfaction survey ...................................................................................... 34 6.5. Project Communication Plan ................................................................................................... 34 6.5.1. 6.5.2. 6.5.3. 6.5.4. 6.5.5. 6.5.6. 6.5.7. 6.5.8. 6.5.9. Objectives ....................................................................................................................... 35 Project Correspondence .............................................................................................. 35 Communication links and channels ............................................................................ 35 Language ........................................................................................................................ 36 Contact Name(s) and Address of Client .................................................................... 36 Contact Name(s) and Address of Honeywell ............................................................ 37 Correspondence Identification .................................................................................... 37 Correspondence and Telephone/Facsimile Communication ................................. 37 Project authority............................................................................................................. 37 6.6. Project Controls ......................................................................................................................... 37 6.6.1. Project Cost Control ...................................................................................................... 38 6.6.1.1. Purpose....................................................................................................................... 38 6.6.1.2. Methodology............................................................................................................... 38 6.6.2. Project Schedule Control ............................................................................................. 38 6.6.2.1. Purpose....................................................................................................................... 39 6.6.2.2. Areas of Responsibility ............................................................................................. 39 6.6.2.3. Scheduling Criteria .................................................................................................... 39 6.6.2.4. Scheduling Technique .............................................................................................. 39 6.6.2.5. Progress Updating .................................................................................................... 39 6.6.2.6. Internal Planning Meetings ...................................................................................... 39 6.6.3. Reporting ........................................................................................................................ 39 6.7. Project Change Control ............................................................................................................ 40 6.7.1. 6.7.2. 6.7.3. 6.7.4. 6.7.5. 6.7.6. Change Management Plan .......................................................................................... 40 Change Management Flow Chart ............................................................................... 40 Change Management Plan Implementation ............................................................. 40 Change Verification and Approval .............................................................................. 41 Approval of PO amendment ........................................................................................ 41 Change Implementation ............................................................................................... 41 6.8. Customer Progress Reporting / Meetings ............................................................................. 43 6.8.1. 6.8.2. Progress Reports .......................................................................................................... 43 Customer Kick Off / Progress Meetings .................................................................... 43 6.9. Document Control...................................................................................................................... 43 6.9.1. 6.9.2. 6.9.3. 6.9.4. Document Handling Procedure ................................................................................... 43 Electronic Filing System ............................................................................................... 44 Electronic Data Exchange ........................................................................................... 44 Document Transmittals ................................................................................................ 44 8. ENGINEERING PLAN ..............................................................................................................45 6.10. 6.11. General........................................................................................................................................ 45 Detailed design phase .............................................................................................................. 45 6.11.1. FEED verification........................................................................................................... 45 6.11.2. Detailed design .............................................................................................................. 46 6.12. Implementation Phase .............................................................................................................. 47 6.12.1. Engineering Work Packages ....................................................................................... 47 6.12.2. Use of Standard Builds (Toolkit) ................................................................................. 47 Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 5 of 72 6.12.3. 6.12.4. 6.12.5. 6.12.6. 6.12.7. 6.12.8. 6.12.9. PCS Hardware ............................................................................................................... 48 PCS Applications........................................................................................................... 48 ESD/FGS Hardware...................................................................................................... 48 ESD/FGS Applications ................................................................................................. 48 HMI .................................................................................................................................. 48 Third Party Interfaces ................................................................................................... 49 Network & High Level System Design ....................................................................... 49 6.13. Testing......................................................................................................................................... 49 6.13.1. Design Validation Tests ............................................................................................... 49 6.13.1.1. Software Prototype (Typical) test ........................................................................... 49 6.13.1.2. Hardware Prototype (Typical) Test......................................................................... 50 6.13.2. Communication Interface / Handshaking Test ......................................................... 50 6.13.3. Internal Testing .............................................................................................................. 50 6.13.4. System Readiness Review .......................................................................................... 50 6.13.5. Factory Acceptance Test ............................................................................................. 51 6.13.6. Third party interface testing ......................................................................................... 51 6.13.7. Integrated Factory Acceptance Test .......................................................................... 51 6.13.8. Certificate of Acceptance ............................................................................................. 51 6.13.9. Site Acceptance Test .................................................................................................... 52 6.13.10. Pre-Commissioning / Commissioning .................................................................... 52 6.14. Documentation ........................................................................................................................... 52 6.14.1. 6.14.2. 6.14.3. 6.14.4. 6.14.5. 6.14.6. INtools Instrument Database ....................................................................................... 52 Loop Schematics ........................................................................................................... 53 Bill Of Materials.............................................................................................................. 53 System Self Documentation ........................................................................................ 53 Technical Query Forms ................................................................................................ 53 Standard System Manuals........................................................................................... 53 6.15. Packing and Shipping ............................................................................................................... 53 6.15.1. Packing and Preparation for Shipment ...................................................................... 54 9. INTERFACE MANAGEMENT METHODOLOGY .....................................................56 9.2. 9.3. 9.4. 9.5. 9.6. 9.7. 9.8. Interface Management Plan .......................................................................................................... 56 Project Responsibilities for Interfaces .......................................................................................... 56 Client Responsibilities ................................................................................................................. 56 MAC Responsibilities .................................................................................................................. 56 CONTRACTOR or Third Party Responsibilities ......................................................................... 57 Potential Interfaces Issues ............................................................................................................ 57 Interface Procedures ..................................................................................................................... 58 9.8.1. 9.8.2. 9.8.3. 9.8.4. 9.8.5. 9.8.6. Defining ICSS Interfaces ................................................................................................. 58 MAC ICSS 3rd Party Interface ......................................................................................... 58 ICSS Interface Coordination ............................................................................................ 59 Interface Coordination Meetings ..................................................................................... 59 Interface Work Packages ................................................................................................. 59 Interface miles tones within Project Schedule ................................................................. 60 10. 10.2. QUALITY PLAN ...................................................................................................................61 Quality Plan.................................................................................................................................. 61 Project Execution Plan JIMBARAN TIUNG BIRU PROJECT 11. PROJECT EXECUTION PLAN Rev A Page 6 of 72 PROCUREMENT PLAN......................................................................................................64 11.2. 11.3. General ......................................................................................................................................... 64 Breakdown of Work activities...................................................................................................... 64 11.3.1. 11.3.2. 11.3.3. 11.3.4. 11.3.5. 6.15.2. 11.3.6. Engineering Phase ............................................................................................................ 64 System Integration Phase ................................................................................................. 64 Installation Phase ............................................................................................................. 64 Organisation and Staffing ................................................................................................ 65 Procurement Management ............................................................................................... 65 Subcontract Management ............................................................................................ 71 Materials Coordination .................................................................................................... 73 12. HEALTH SAFETY ENVIRONMENT (HSE) PLAN ...................................................................74 13. SITE EXECUTION PLAN .................................................................................................75 13.2. 13.3. 13.4. 13.5. 13.6. 13.7. 13.8. 13.9. 13.10. 13.11. 13.11.1. 13.12. 13.12.1. 14. 14.2. 14.3. 14.4. Site Scope ..................................................................................................................................... 75 Site Organization and Responsibilities ........................................................................................ 75 Pre-Commissioning Plan .............................................................................................................. 75 Pre-Commissioning Strategy........................................................................................................ 75 Pre-Commissioning Scope ........................................................................................................... 76 Permit to Work (PTW) ................................................................................................................. 76 Pre-Commissioning Responsibilities ........................................................................................... 77 Pre-Commissioning Activities ..................................................................................................... 77 HSE and QA................................................................................................................................. 78 Deficiency List Completion ......................................................................................................... 78 Site Changes and Control............................................................................................. 78 COMMISSIONING AND START-UP PLAN ............................................................................ 78 Commissioning and Start-up Scope ............................................................................. 78 PROJECT COMPLETION PLAN ................................................................................................79 General ......................................................................................................................................... 79 Knowledge Transfer to Customer ................................................................................................ 79 Project Closeout Package ............................................................................................................. 79 Project Execution Plan JIMBARAN TIUNG BIRU PROJECT Project Execution Plan PROJECT EXECUTION PLAN Rev A Page 7 of 72 JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 8 of 72 1 REFERENCE DOCUMENTS 1.1 Pertamina EP CEPU: Document number JTB-SF-T-SPE-900-00006 JTB-SF-T-SPE-900-0005 JTB-SF-Z-DBS-900-0001 1.2 Document Description Main Automation Contractor Technical Proposal MAIN AUTOMATION CONTRACTOR (MAC) REQUIREMENT AND SCOPE OF WORK Project Design Basis Codes/Standards Term Name Acronym American National Standards Institute ANSI American Petroleum Institute API Institute of Electrical and Electronic Engineers IEEE International Electrotechnical Commission IEC The Instrument, Systems and Automation Society ISA International Standards Organisation ISO Technische Uberwachungs Verein TUV Underwriters Laboratories, Inc. UL Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 9 of 72 2 ABBREVIATIONS, DEFINITIONS AND NOMENCLATURE 2.1 Terms Context COMPANY CONTRACTOR SUB CONTRACTOR Project MAC VENDOR Meaning Pertamina EP CEPU Appointed by Company who shall be responsible for detail engineering design, material and equipment procurements and construction. Appointed by Contractor to provide services to Contractor Gas Development Project for Jambaran – Tiung Biru Field (JTB Project) Main Automation Contractor- Honeywell. Supplier of services, equipment fabrication or materials 2.2 Abbreviations Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 10 of 72 Acronyms Descriptions AMS Asset Management System AS Alarm System BMS Bypass Management System BOM Bill of Material C&E Cause and Effect CCR Central Control Room CCTV Closed Circuit Television CER Central Equipment Room CPF Central Processing Facilities DCC Document Control Centre DCS Distributed Control System DDS Detailed Design Specification ESD Emergency Shutdown System EPKS Experion PKS System FAT Factory Acceptance Test FDS Functional Design Specification FEED Front End Engineering Design FGS Fire and Gas System FTA Field Termination Assembly FSO Floating, Storage and Offloading vessel GPE Global Project Engineering (Honeywell) GPM Global Project Management (Honeywell) GPS HART Global Positioning System Highway-Addressable Remote Transmitter Communication Protocol HMI Human Machine Interface HSE Health, Safety and Environment HVAC Heating, Ventilation and Air Conditioning IAMS Instrument Asset Management System ICSS Integrated Control and Safety System IFAT Integrated Factory Acceptance Test IMS Information Management System ISA The Instrumentation, Systems and Automation Society LAN Local area Network LER Local Equipment Room LSS Load Shedding System MCC Motor Control Centers OLE Object Linking and Embedding OPC OLE for Process Control OTS Operator Training Simulator PAEAS Public Address / Emergency Alarm System Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 11 of 72 PCS Process Control System PDCS Power Distribution Control System P&ID Piping and Instrumentation Drawings PEP Project Execution Plan PFD Process Flow Diagram PLC Programmable Control System PMS Power Management System PPF Production Processing Facilities QA/QC Quality Control/Quality Assurance QMS Quality Management System RIETIS Remote Instrument Enclosure SAT Site Acceptance Test SIL Safety Integrity Level SIT Site Integration Test SM Safety Manager SUDS SPI Shared User Database Structure (data exchange) Smart Plant Implementation by Intools (instrument database) UCP Unit Control Panel TAT Typical Acceptance Test UPS Un-interruptible Power Supplier WBS Work Breakdown Structure WP Project Work Package Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 12 of 72 3 INTRODUCTION 3.1 Purpose of the Document The MAC Project Execution Plan document describes the Honeywell processes, activities and contractual arrangements associated with delivery of the JTB Project to achieve the project objectives. This document defines the plan, minimum administration requirements, project organization, project progress, roles and responsibilities. In addition, this document will define the execution of each phase of the project and each work package including engineering, assembly, sub-contracting, interface management, system integration, testing, construction, commissioning and start-up support and safety management. 3.2 Project Overview The JTB project is expected to produce 178 MMSCFD (169.1 MMSCFD annual average) of pipeline quality sales gas for export. Solid sulphur removed from the gas sweetening process is produced at rate of 60 to 120 metric tons/day for export. Condensate is recovered and pumped to ExxonMobil Cepu limited Banyu Urip Central Processing Facilities (EMCL BU CPF) at a rate of 3,750 bbls/day. Produced water is recovered and pumped to EMCL BU CPF at a rate of 8,253 bbls/day. 3.3 HONEYWELL as a MAC The MAC scope of work shall be consistent with the requirements described in COMPANY’s Instruction to Tenderness and Scope of Work for Main Automation Contractor (MAC) Technical Proposal, document no: JTB-SF-T-SPE-900-00006, Rev.1 date 14th July 2015. Honeywell as the MAC will work closely and directly with the CONTRACTOR and the COMPANY throughout the project from inception to commissioning. MAC will also provide the required interface to enable COMPANY/CONTRACTOR to liaise with other EPC’s (if Any), the EPC sub-contractors as needed and to ensure standardization objectives and overall ICSS integration objectives of the COMPANY are met with. As MAC, Honeywell will be required to design, engineer, supply, assemble, test and implement the Integrated Control and Safety System (ICSS) and Integrated Enterprise Control System (IECS) which includes supply of hardware and software for selected Manufacturing Operation Management System(MOMS). More detailed scope of work has been included in the Honeywell proposal document. The MAC concept will help in consistency and standardization of the hardware, software, integration, training and spare parts. The concept also ensure single point ownership for all ICSS & IECS related systems under MAC scope and ensure smooth integration and commissioning at site. The MAC anticipates and proposes the following phases during the project execution to meet the scope and objectives of this project: 3.2.1. Phase-1: Detailed Design Phase During this phase key team members of the MAC shall be mobilized and located in CONTRACTOR’s office in Jakarta or any other places. The team will be led by Project manager and engineering team which consist of lead engineer, and lead discipline engineers: ICSS and IECS system. During this phase MAC vendor will verify the FEED documents already developed by the COMPANY as part of a separate FEED contract. The MAC vendor shall also work with the CONTRACTOR to establish design basis and project fundamentals and agreed upon as possible. Those include compliance to scope, conformance/options/exceptions, Minimize customization/use of vendor standards, Document Deliverable List, functional design specifications (FDS), Graphic sketches basis, standard report format, data base format finalization (InTools) – if any, System Architecture review with L4/L5 interface requirements/security, project timeline, design freeze and project milestones, customer input design data, prototyping as applicable, package vendor schedule, project specifications, PEP approval etc. If any changes are required to the FEED documents the same will be discussed and agreed to ensure it is in line with the final ICSS & IECS system selected. Review and agree on the Project Execution Plan shall also be carried out during the FEED verification phase. Project manager shall be available in CONTRACTOR’s office as required Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 13 of 72 during the FEED verification phase and ensure it is executed as per plan. Project manager shall be mostly located at Honeywell office in Jakarta driving the project activities and interfacing with the CONTRACTOR and Company. An Overall lead engineer and other key engineers will be located at CONTRACTOR office full time during the detailed design phase will also provide necessary interface support to CONTRACTOR and Honeywell engineering team. 3.2.2. Phase-2: Implementation Phase Detailed engineering bulk drawings, Prototype (Typical) testing, Design Freeze, Approval, bulk building and generation, procurement, hardware manufacturing, CITs at vendor location, testing (FAT/IFAT). MAC will provide the office space, for COMPANY and CONTRACTOR personnel during FAT, IFAT and Review Sessions. This activity shall be done in Honeywell Jakarta office. MAC will deliver the cabinets to site after IFAT done and accepted by CONTRACTOR And COMPANY with receiving FAT/IFAT Acceptance report and Inspection Release Note, soon once Test completed. MAC will supervise the Cabinet Installation at COMPANY’s site if agreed by CONTRACTOR. 3.2.3. Phase-3: Commissioning Phase During this phase the system delivered to customer site will be verified and inspected upon receipt and stored at ware house of customer, installation by customer’s contractor, SAT, pre-commissioning and commissioning & start-up assistance. The following block diagram illustrates the various phases of the project. Phase-1 Detailed Design MAC Selectio n Phase-2 Phase-3 Implementation Procure, Build, Test Commissioning Install, SAT, Precommission & Commissioning - MAC Purchase Order issued End of Project Commencement of Life time support phase 3.3. HONEYWELL Value Proportion As experiences of MAC package, Honeywell has the following value proportion that will give advantages and meet the requirements of Contractor and COMPANY requirements: 3.3.1. Technology Proven-in-use ICSS Platform Universal I/O Technology to reduce field cabling, marshalling and accommodate late design inputs. Virtualisation Technology & Wireless for hardware platform optimisation. VEP engineering for accelerating schedule. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT 3.3.2. 3.3.3. 3.3.4. 3.4. PROJECT EXECUTION PLAN Rev A Page 14 of 72 Seamless Integration with existing Banyu Urip ICSS system. Experiences/Capability Leverage on MAC project capabilities in Indonesia (BU MICC, Jangkrik FPU ICSS) Familiarity with Banyu Fields (EPF, MICC) Experienced resources in global and SEA for support Large staging area available in Jakarta Extensive ICSS and 3rd Party system Integration/non-DCS scope Vast Upstream Installed Base Worldwide Proven methodology, tools and global Lesson Learn Values Experience from Banyu Urip ICSS design(typical/HMI)for optimizing repeat functions for JTB MAC Project Single window integrated MAC approach Backup by Regional and Global MAC experience and resources GPM 2012 Best Practices, Standard Builds and Integrated Tools Global Quality and HSE policies enforced Financially Strong & Sound Minimize Risk Regional & Global Management commitment – Executive sposorship Proven track record in meeting delivery schedule Experienced Project Management & engineering team members Familiar with multiple EPCs engagement and MAC delivery Honeywell Mission Statement To achieve recognition as the best Automation Systems Integrator that pro-actively attains the project goals for the Customer through: On-schedule and on-budget delivery of the project within scope and Quality requirements. Implementation to ensure standardization throughout the project, as possible. An Integrated Control and Safety System (ICSS) which is engineered, manufactured and tested to the highest standards and fully meeting the functional requirements of the project Trouble free and safe start up by seamless provision of skilled resources for each location and phase of the project The Vision is to provide an integrated Control and Safety System (ICSS) that is best in class for: SAFETY: Confident operators guided by the best system, to recognize, understand and respond to process upsets in a safe manner. OPERABILITY: Design strategies shall achieve for the operators, the best integration of process safety, marine and package systems to a single Human-Machine Interface. MAINTAINABILITY: Maintenance technicians shall regard the system’s engineering tools, its access, its redundancy and its commonality as an asset for reliable and safe facilities. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PERFORMANCE: 3.5. PROJECT EXECUTION PLAN Rev A Page 15 of 72 All systems and equipment designed, manufactured, supplied and commissioned under Honeywell scope will perform to the highest level of system availability and reliability throughout the life of the project. Quality Statement It is the intention of Honeywell to deliver defect-free competitive products and services, on time, to both internal and external customers by performing exactly to requirements. Our name must represent excellence to our customers, our vendors and ourselves. It is the policy of Honeywell to achieve continual improvement by: 3.6. Identifying improvement possibilities Setting appropriate objectives and targets Implementing programs to meet the objectives and targets Supplying appropriate QMS training and guidance Seeking ways to improve the Quality Management System Quality management shall be consistent with requirements of Project Quality Plan of CONTRACTOR and COMPANY. Health Safety & Environment Statement Honeywell policies, commitments and responsibilities to Health Safety and the Environment are stated in Doc Health Safety Environment (HSE) Plan. 3.7. Honeywell Executive sponsor In recognition of the importance of the JTB project to both CONTRACTOR and COMPANY, Honeywell will nominate an Executive Sponsors for the project. The Executive Sponsors will act as Champion within Honeywell for this critical project, and facilitate resolution of issues that might require their attention. 3.8. Confidentiality Honeywell will ensure that all project team members are familiar with the Confidentiality requirements contained within the contract and that all project team members comply with the procedure as detailed in document Honeywell Project Quality Plan. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 16 of 72 4. PROJECT OVERVIEW This section specifies the Project Execution Model that will be adopted for the Integrated Control and Safety System (ICSS) and Integrated Enterprise Control System (IECS) for Jambaran Tiung Biru Project, Indonesia. Honeywell believes that the proposed execution model will be most suited to this project scope and location as well as to deliver the best commitment to our customer. The Project Execution Plan (PEP) describes project methodologies, project organization, roles and responsibilities, change management, resource loading, locations of manufacturing, communication channel, procurement management, system integration and site commissioning activities in order to achieve on-time delivery of the project. The PEP also provides an overview of the quality controls and administration planned for the project including engineering and design audits, manufacturing audits, etc. The PEP is a live document and will be updated as required during project execution to reflect any changes in implementation methodology and philosophy as mutually agreed between MAC,CONTRACTOR and COMPANY. 4.1. Basis of the Execution Plan The Project Execution Plan is developed based on the Jambaran Tiung Biru project specification documents listing out the requirements and furnishing basis for developing applications and hardware engineering for ICSS and IECS system. 4.2. Key factors for Success of the Project Experienced Project Manager providing single window contact to CONTRACTOR for managing all the contractual requirements of scope, schedule, resources and quality Program management approach to guide close coordination with COMPANY, CONTRACTOR, EPCs, Project team and other Stake holders. Ensure standardization amongst all systems supplied by different parties. Dedicated EPKS and SIS engineers from local affiliate to be full time with CONTRACTOR to verify FEED and involvement of MAC lead engineer to ensure proper coordination amongst all EPC’s and COMPANY. Continuity of Key personnel from start to finish. Engaging experienced consultant with domain knowledge during key phases of the project. Effective management of all interfaces achieved through key personnel engagement Honeywell will adopt a Program management approach to ensure close coordination between Honeywell and other stakeholders of the project for achieving standardization of all systems integrated in the ICSS and IECS. This approach provides strength to the Honeywell project team and comes as a benefit to the COMPANY. A Project Director will be driving the approach and provide the necessary guidance to the MAC Project manager, and the team, taking the overall stewardship of the project. He will be based at the Singapore project centre and be available for all key meetings during the project life cycle. He will also coordinate with the Honeywell Global Program Management team as necessary to cover the overall expectations on the Jambaran Tiung Biru Project. Honeywell understand that the success of the Jambaran Tiung Biru project depends very much on an experienced team of Project Management, Engineering and Consultant resources to be deployed in the project. Key resources are critical for the success factor of the project and Honeywell will assure the availability of such resources from project start to commissioning and handover to COMPANY. Honeywell also plans to ensure participation of resources from local affiliate service organization who will later be involved in site commissioning and long term support to COMPANY. Even though Honeywell has a rich history of project execution and engineering for such projects, we plan to engage an experienced engineering consultant with rich background in upstream oil and gas facilities, during the key design phases and preparation of functional design specification documents till freeze. Such consultant support is Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 17 of 72 expected to pay rich dividends in the success of the project. Honeywell also plan to engage experts in review and validation of network architecture and setup in line with Honeywell’s global best practices and design guidelines which is another critical factor in the success of implementation. 4.3. MAC Scope of Work Overview Detailed Engineering Services: Review and finalization of preliminary controls engineering specifications provided in Instructn to Bidder (ITB) package for all instrumentation, control and safety systems on the Project. Design of Integrated Control and Safety System (ICSS) and its interfaces. Supply of Goods and Services: supply of goods for specified instrumentation and control systems during Detailed Engineering design. Provide construction support, commissioning support, startup support and after market training and on-site assistance. The MAC's responsibilities include the following and as per mutually agreed contract scope and proposal/costing basis: Resulting automation deliverables, participation in review meetings, and collaboration via comments and/or input into the development of other automation CONTRACTOR deliverables. Supply the hardware and software components for Integrated Control And Safety Systems (ICSS) and all related services. Supply the hardware and software component for selected Manufacturing Operation Management System (MOMS) as part of IECS and all related services. Provide the PROJECT management, procurement, cost and schedule control, engineering, services as described in this document associated with the systems supplied by the MAC. Provide services related to automation and resolve interface issues between MAC supplied systems and other instrumentation and control systems, including package system supplied by others. MAC will be acted as automation system interfaces leader. Work closely with the CONTRACTOR, equipment package VENDORs, and COMPANY to reduce duplicated activities and to compress schedule. Produce as-built instrumentation and control systems documentation, drawings and data bases for use by COMPANY. Develop TAT, FAT and integrated FAT (IFAT) plan, stage equipment, and perform prototype/typical test, FATs and IFAT MAC will provide training to COMPANY personnel as defined in contract. Provide spare parts for start up, commissioning and two-year (optional) operations. Provide certain inspection, construction support, and commissioning services as defined in Project Specifications. The MAC scope of work shall be performed by Honeywell Process Solutions (HPS), Jakarta office and includes Design, Implementation and Test of ICSS and IECS System Infrastructure facilities as spelt out in our proposal. MAC Scope of Work – By Honeywell The following is brief description on ICSS/IECS system that will be provided by Honeywell as a MAC: Process Control System (PCS) : Experion PKS C‐300 Series ‐ Universal IO SIS : Safety Manager ‐ Remote Universal Safety IO F&G : Safety Manager ‐ Remote Universal Safety IO RTU : Safety Manager ‐ Remote Universal Safety IO Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 18 of 72 OTS : Honeywell Unisim or equal Alarm Management : Honeywell Dynamo Alarm Manager or equal APMS : Honeywell Asset Management or Equal EPMS : Honeywell Uniformance Process or Equal CMMS : Honeywell FMEA Tools or Equal E‐LOG BOOK : Honeywell E‐Log Book or Equal IMS : Honeywell Inspection Management RTIS : Honeywell PHD Futuristic Operator Workstation : TBA ESD and F&G Matrix Console : Local Made Engineering Workstation : Dell or Equal. MAC Scope of Work – By NON- Honeywell MMS : Bruel Kjaer Vibro or Equal or Equal Weather Monitoring System : Climatronic or equal EDMS : Integraph or Equal LIMS : LabMate Enterprise or Equal Project Execution Plan JIMBARAN TIUNG BIRU PROJECT 4.4. PROJECT EXECUTION PLAN Rev A Page 19 of 72 Project Locations and Sourcing Honeywell will control the execution of this project from the central location of MAC Front office (FO) in Jakarta, Indonesia for the smoother implementation of the project and based on past experience. The Project Manager, who is based in MAC Front Office (FO), is the single point of contact with responsibility for the execution of the project. The core engineering team will be based at the MAC FO implementation Centre. During Detailed design phase a team of key team engineers (for ICSS and IECS) will be co-located with CONTRACTOR in his office. In addition a team of project engineers will be located at Honeywell’s front office (FO) to provide necessary FEED support. This in line with the MAC capacity and to leverage expertise and ensure cost effectiveness. The Key engineers located at CONTRACTOR office will be led by the Project Manager (PM) to establish a minimum team at CONTRACTOR office. The PM will provide leadership and carry out interface responsibilities (with support by MAC lead Engineer as required). The need for a dedicated interface Lead engineer will be determined with the COTRACTOR. Interface role will be primarily acting as coordinator and interface with COMPANY, CONTRACTOR other EPC contractors, vendors, 3rd party suppliers of EPC’s etc .required at CONTRACTOR office. This role along with the MAC Lead Engineer will also attempt to achieve consistency in design across the plant systems under MAC responsibility. After detailed design phase the key engineers located at CONTRACTOR office will move to MAC FO for implementation and testing phase. PCS/ESD/FGS hardware will be supplied through Honeywell’s Global Customer Solution Centre (CSC). The factory allocated for this project shall be Tianjin Factory, China. Network equipment/Components for ICSS and IECS shall be sourced as per Honeywell Factory Approved manufacturers. All 3rd party hardware, software, cabinets, consoles etc in MAC scope shall be sourced as per Honeywell approved vendors per Honeywell global supply chain sourcing guidelines as well as meeting Customer specifications and Approved Vendor List. All marshalling, power distribution, auxiliary cabinets, console furniture will be assembled, wired and tested in Jakarta. DCS/ESD/FGS systems shall be assembled and wired in Honeywell Factory and shipped to Jakarta for integration and testing. In the capacity of MAC and to leverage expertise and cost effectiveness, Honeywell plans to utilize Honeywell Graphics Development Centre (GDC), Indonesia for the implementation of graphics generation work packages. Design, Integration and testing of these packages will remain the responsibility of MAC FO Engineering Team. All project integration testing, staging and prototype/typical test, Factory Acceptance Tests (FAT/IFAT) will be carried out at the Jakarta staging facilities. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT 5. PROJECT EXECUTION PLAN Rev A Page 20 of 72 PROJECT EXECUTION STRATEGY 5.1. Project Execution Work Flow 5.1.1. Manufacturing Process for ICSS - JTB MAC The Honeywell factories are ISO 9001 certified and covers the complete range of HPS (Honeywell Process Solutions) offerings, including the Series C standard build, integration of Experion® Process Knowledge System (PKS), safety systems and Total Plant Solution systems. Honeywell executes to a global policy where we only build Safety Manager SIS cabinets at certified locations. These locations are certified by TUV and use the same processes and materials in all locations to ensure global consistency. So, there would be no difference in the specification and certification of an SM built in any of the certified locations including Honeywell’s Tianjin factory in China. We will provide TUV certificate copies for the factory used to support IEC61508 and SIL compliance . For successful strategy for MAC, the execution for ICSS and IECS-MOMs will: 1) Closely follow the EPC’s master schedule milestones for close alignment and establishing of Common Objectives. As such the MAC project schedule milestones shall complement the overall schedule the EPC is looking for starting from KOM, Design Freeze, Manufacturing, Testing, delivery and post delivery site support up to start up and warranty period. 2) Design documentation schedule, format, numbering philosophy, review cycles etc will take into account EPC and COMPANY requirements and aligned to milestones 3) Identification of testing philosophy, interface design strategy and prototype testing upfront to avoid risks and delays 4) Strong scope change management to contain cost and productivity 5) Use of Robust Methodology, Lessons Learned, Proven Technology and Tools available (LEAP concepts) to extend flexibility during execution. This is to accommodate late design inputs in some cases and to perform system configuration where possible without target hardware being available, quicker recovery for slippage etc 6) Staggered delivery of equipment to meet construction schedule as priority during execution 7) Proactive planning and mobilisation of resources throughout the project to ensure timely support. Full time Resident Engineers at EPC office from KOM up to start of FAT will be deployed as needed to enhance coordination and accelerate work 8) Regular reviews of Risks and opportunities and involve customer team members as needed to identify and mitigate risks that will impact progress 9) Reporting accuracy and avoidance of gaps in progress measurement 10) Safety and Quality as top priority throughout the MAC life cycle The following diagram illustrates the overall project execution work flow. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 21 of 72 ICSS/IECS System Hardware Design Spec MAC Contract Award FEED verification Kickoff Meeting ICSS/IECS System Software Design Spec Detail Design Freeze ICSS/IECS Define System Interfaces IECS/MOMS/LDS Procurement, Design, Manufacture PCS System cabinet assembly and factory quality checks @ Tianjin, China factory. PCS System cabinet Order Global Order Process SIS System cabinet OrderGlobal Order Process Marshalling/Aux Cabinet Prototype mfg& Approve @Jakarta Detailed cabinet drawings Internal FAT @ Jakarta staging @Jakarta staging Manufacturing Marshall/Aux Cabinets @Jakarta SW Prototype Develop/Test and approve Perform FAT/IFAT @Jakarta System Staging for FAT/IFAT SIS System cabinet Assembly and validation checks (Waterford, Ireland for SM boards & Tianjin factory, China. S/W Bulk Generation Receive the System at Site * Packing & Shipping Site Supervise Installation * As-Built Prep and submit Detailed design Phase Implementation Phase Perform SAT * Project Execution Plan Plant Start-up * Supervision Project * Close-out After market Service * Commissioning Phase * By Honeywell, Indonesia # By Contractor JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 22 of 72 Below are the steps involved in PCS/SIS/Marshalling cabinet manufacturing and testing processes and the relevant locations where they will happen. PCS System cabinets 1. Upon completion of approval of I/O list and BOM (Bill of Material) for construction, the factory order is placed for system cabinets through global factory order process using TPC (Total Plant Configuration) software tool for build quality and consistency. 2. Upon receipt of order, the order processing will review the order for correctness and look at the region where supply to be delivered and allocate order to Honeywell factory. 3. Tianjin Factory, China will be receiving order and will determine delivery time as per order request and confirm order receipt and delivery. 4. Tianjin Factory, China assembles the system inside the cabinet and carries out quality checks as per mandatory internal factory procedure (Steps 1 to 4 belong to Honeywell internal process) 5. Tianjin Factory, China ships system to project execution location in Jakarta, Indonesia for staging and IAT, FAT/IFAT. SIS System cabinets 1. After having drawings approved for construction, the factory order is placed for system cabinets through global factory order process using SM tool for build quality and consistency. 2. Upon receipt of order, the order processing will review the order for correctness and look at the region where supply to be delivered and allocate order to Honeywell factory. 3. Tianjin Factory, China will be receiving order and will determine delivery time as requested and confirm order receipt and delivery. 4. Tianjin factory, China will obtain the required critical SM boards/components of the order from Honeywell’s Waterford, Ireland factory 5. Tianjin Factory, China assembles the system inside the cabinet and carries out quality checks as per mandatory internal factory procedure. 6. Tianjin factory, China ships the assembled system to Singapore Factory for validation checks as per Solution Binder. 7. Singapore Factory carries out the required validation checks as per Honeywell Solution Binder procedure. (Customer will be informed of this test schedule but witness is not mandatory as, the activities from steps 1 to 7 belongs to the Honeywell internal process). 8. Singapore Factory ships system to project execution location in Jakarta, Indonesia for staging and IAT, FAT/IFAT. Marshalling cabinets 1. After design freeze order is placed on Local Indonesian suppliers for marshalling cabinets, terminals, other accessories that go into marshalling cabinets. 2. Upon receipt of materials the same is issued to qualified cabinet assembly vendor factory in Jakarta, Indonesia selected as per supply chain procurement procedures. 3. Cabinets are assembled and wired with all components by qualified cabinet assembly vendor factory in Jakarta, Indonesia. 4. Cabinets are tested by cabinet assembly vendor factory in Jakarta, Indonesia for continuity checks and layout checks as per approved drawings. 5. Cabinets are checked for internal quality control by project team. 6. Cabinets are delivered to Honeywell staging area in Jakarta, Indonesia 7. Cabinets are hooked up to System cabinets using pre-fabricated cables and tested as per IAT, FAT/IFAT. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 23 of 72 5.1.2. Detailed Explanation on Implementation Honeywell would like to furnish further explanation on the Project Execution plan regarding manufacturing and testing of SIS and DCS systems. Honeywell complies with the TUV requirements on functional safety management for SIS system as follows: Engineering and design - Honeywell adopts engineering and design according to IEC61508/11 requirement and the work is performed by competent engineers (whom TUV FS certified perform the work). Honeywell standard Safety Binder is used for SIS implementation which consists of all documentations to support verifications and validation activities. SIS system assembly - Honeywell approved factory is TUV approved for SM assembly. Technicians assemble the system according to the approved engineering drawings provided by project team (using standard drawings configuration). The system is then internally tested in Singapore against the approved engineering drawings and configuration as part of the verification and validation process. This is to ensure when the cabinets arrive in Jakarta for FAT/IFAT testing with customer, the SIS has passed the stringent internal processes. Below are the validation checks done in Singapore factory as part of validation process: 1. Layout & Mechanical Check 2. Tagging Checks 3. Wiring checks 4. Power distribution Checks 5. Earth connection checks 6. Dielectric & resistance test 7. Redundancy Checks 8. Simulation Input & Output Signal Test Testing (FAT, IFAT) - This is performed by TUV certified engineers to verify the SIS system against the customer approved design drawings, logic configuration, specifications for JTB MAC project. Management of changes, checklists and testing records are managed by the project team thorough out the whole FAT/IFAT process. If critical hardware rectifications are required during FAT/IFAT, qualified SM technician from Singapore will be dispatched to Jakarta as required to perform the required changes under the coordination Lead SM. This support is similar to critical rectifications carried out for RIE and site location faults. Staging Facilities- The staging facilities established in Jakarta follow Honeywell global staging management system in goods receiving, HSE, tools, power distribution, HAVC, cable railings, facilities maintenance, defects rectification, meeting rooms, rest rooms and shipment procedure. All testing tools will be properly calibrated as per ISO requirement. The staging area provides space, basic utilities and staging management support while the actual testing is handled by qualified and experienced project team engineers. 5.2. Manufacturing & Software development Process for IECS - JTB MAC After kick off meeting, MAC will appoint one lead IECS/MOMS that will be acting as interface with customer to define the requirements of IECS/MOMS together with CONTRACTOR and COMPANY. The outcome of defining the requirements of MOMS are: selecting the hardware and software that will be implemented as MOMS applications that defined on the project specification. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 24 of 72 IECS/MOMS hardware that will provide by MAC mostly are ONLY server/PC that already recommended by HONEYWELL or other 3rd party vendors; So that hardware purchase will be part of vendor MOMS software that NOT Honeywell’s supply. Meanwhile for software side, once the FDS of IECS approved by CONTRACTOR/COMPANY; Lead IECS/MAC will monitor the software implementation as per schedule agreed; A detailed implementation plan for MOMS packages will be determined and reviewed for further execution at this early stage when the right stake holders are established. 5.3. Detailed design phase During Detailed Engineering phase of the Project, the MAC will be required to work closely with the Detailed Engineering Services Contractor(s). As such, the MAC’s objective will be to build upon the specifications provided in the ITB package and refine the design of the Integrated Control and Safety System (ICSS) and Integrated Enterprise Control System (IECS) which the MAC will in turn procure, build, install and commission. The MAC will provide input concerning the control, monitoring and safety systems for the basic facilities design as well as the interfaces to all packaged equipment. Some salient features of Implementation phase include (more details in section 6): 5.4. Key team members from MAC are mobilized and collocated in CONTRACTOR office Finalize project execution plan and schedule. FEED verification and necessary updates. Develop and finalize Functional design specifications. Define and finalize interface issues with other EPC contractors Define and finalize design basis for bulk drawing generations and detailed engineering drawings. Project Implementation phase Some salient features of Implementation phase include (more details in section 6): 5.5. Key team members of MAC Jakarta office continue with the implementation and testing phase of the project. Develop detailed project drawings, cabinet layouts, wiring schedules, databases and other detailed engineering drawings. Use of appropriate methodologies, tools, standards (GPM) and ‘Honeywell standard build’ – building blocks ready for use – for consistency, standardisation, maintainability and optimal quality. Honeywell will execute the project utilizing its local competences and global resource pools. The use of Web-based Intranet Project Work spaces to support proper communications between teams in various locations. Commissioning Phase 5.5.1. Installation & Commissioning Support Installation and commissioning support will be provided in accordance with the provisions in the CONTRACTOR contract. This support will be generally provided on a time and material basis. 5.6. Post Commissioning / Long term Support Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 25 of 72 Long-term technical support will be provided in accordance with the provisions in the contract and will be covered under a separate agreement with Honeywell local affiliate in Indonesia. 5.7. Parts Management Program Software Support Program Optional Support Services including Training Project Milestones The following table highlights the project milestone assumed in the RFQ response. MAC Contract Award KOM with selected CONTRACTOR FEED Verification &detail design Detail Design Freeze Manufacturing / Bulk generation Internal Test FAT IFAT Shipment SAT Commissioning / Project Closure The tentative duration for the above milestone activities will be updated upon receiving the integrated project schedule from CONTRACTOR. 5.8. Proposed Project Schedule Please refer to document Project schedule. The detail schedule will be prepared upon confirmation of project milestone dates during Kick-Off meeting, Customer input design data, Hardware Design Freeze, Prototyping, Software Design Freeze milestones, System Readiness Review, FAT/IFAT start, SAT and Commissioning. Honeywell will develop a Level 3 Project Schedule, then updated at the end of the KOM and thereafter on a monthly basis. The progress updated schedule will be issued with the monthly report and discussed during regular coordination meetings. The MAC schedule shall comply the overall project schedule of the contractor for the timeline of overall installation. The schedule will identify any deliverables required from Owner/CONTRACTOR for Honeywell to complete the System design and configuration. In addition, any design interface required or provided by Honeywell will be identified. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 26 of 72 6. PROJECT ORGANIZATION 6.1. Project Organization The key considerations in developing the organization structure for the Implementation phase of the Jambaran Tiung Biru project include: Program management approach to ensure close coordination and manage interfaces between Honeywell and COMPANY, CONTRACTOR and other EPC’s, sub-system suppliers and other stakeholders. The key objective is to ensure use of vendor standards and best practices and minimize customization as applicable. This will drive consistency in design between different honeywell systems supplied and interfaces with other 3rd party sub-systems supplied by others so that operator has a standard view of all systems and displays, consistent implementation method, consistency in documentation, ease of long term maintenance etc. A Project Director located at the Singapore project centre will oversee and drive this approach and providing necessary guidance to the MAC Project manager and Lead Engineer. Main MAC execution centre located in Jakarta with core project team resources, engineering execution and implementation in Jakarta. Location of Key team members of the project at CONTRACTOR office for the detailed design phase. Involvement of Specialist consultant with extensive experience in upstream oil and gas facilities. Involvement of local affiliate resources during project implementation phase to provide seamless support during commissioning and post commissioning support. Objective and efficient use of experienced pool of resources in Global Engineering Services centre. Honeywell’s prior experience in similar MAC projects Mobilization of Subject Matter Experts within Honeywell and from relevant Third Party Systems/ Interface Vendors to support the design/detailed engineering Interface management to ensure smooth information exchange and resolution of issues between all parties and strict adherence to work processes so as to provide consistency and to avoid delays due to re-work Refer to document of project organization chart. The Project Team will be responsible for the timely delivery of all project deliverables and for ensuring customer satisfaction. Technical design of the ICSS and IECS. Implementation of control strategies as defined by the process unit designers Implementation of Project and operations requirements (e.g. operator interface) Consulting to CONTRACTOR on other design criteria as required Execution of the Project, including focus on the following: o Schedule, cost, deliverables, documentation, Quality and Safety o Integration across the EPC’s and the other participants in the Project o Completion and stewarding of Project design standards o Procurement, work releases for ICSS equipment and services Integration and interface management with the CONTRACTOR Teams which will: o be resident, or have sufficient assignment at CONTRACTOR office, o have tight integration with the CONTRACTOR workflow, Project Members and Their Roles and Responsibilities. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 27 of 72 Function Primary role Support role 1. Project Director Overall stewardship of the project Interact with Honeywell Global Program Management team Based in Project centre in Singapore Guidance and mentoring of Project Manager. Coordination with executive sponsors as required Attends all key meetings with CONTRACTOR, COMPANY As an escalation path for the project team and customers alike. 2. MAC Project Manager Project Manager shall be responsible for the entire project execution and control. He holds overall project management responsibilities Assigned at Contractor’s office during detailed design phase(FEED review) Overall responsible for Project HSE planning and management Responsible for development, update and adherence to the Project Execution Plan Responsible for overall project success criteria (schedule, budget, quality, customer satisfaction) Focal point for interface to CONTRACTOR and COMPANY. Responsible for effective coordination amongst multiple teams and EPC’s located in different geographies. Selection and staffing of the Project team with quality resources Guidance and mentoring of Engineering Team. Team Building activities Arrange logistics Arrange and lead regular internal review meetings. Procurement of hardware and software Internal/ external audits Quality assurance to ensure all deliverables are consistent. Sets targets for project members and ensure they are met. Raising invoices, payments etc.. Setting up internal project cost monitoring systems and tracking. Issue resolution Risk monitoring and mitigation Based in Honeywell Project office in Jakarta Attend all meetings with customers. Tracks progress and reports progress on agreed time line to CONTRACTOR and COMPANY. Work closely with Project Director and project team. 3. MAC Lead Engineer MAC Lead engineer holds technical responsibility for all ICSS scope Reports to the Project Manager Responsible for HSE Development, maintenance and adherence to project engineering standards and procedures Project Execution Plan Supports the PM and Engineers in Contractor’s office during Detailed Design Training and mentoring engineers. Adopting new tools available with Honeywell development centres. Adopting best engineering practices. JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 28 of 72 Responsible for engineering consistency across different contracts Technical roles and responsibility definition Overall technical accountability and control of design and implementation activities Technical risk identification, assessment and control Based in Honeywell Project office but will be located in Contractor office during key periods of detailed design phase. Develop and maintain check sheets to be used during implementation and testing phase to ensure quality. Technical audits. Assist PM to track progress. Assist PM in procurement activities. Set target to engineers and ensure they are met with. Arrange regular internal review meetings between different engineering teams and subcontractors. Coordinates with CONTRACTOR and other EPC’s on all technical issues. Coordinates with Engineering consultants and design specialists. Coordinates with Technical assistance centres. Leads and Drives the Testing phase. 4. Specialist Consultant Specialist consultant will support the project team during key design phase to develop and review functional design specifications which will form the back bone of design and development Specialized background experience in upstream oil and gas facilities Design engineering support to MAC Lead engineer and his team which needs specific domain knowledge, experience and background Attend critical Design review meetings with customer 5. Project Controls Development of project schedule and tracking of project tasks Set up and manage costing system Progress collection and reporting within Honeywell Help prepare monthly progress report to customer Handle scope changes and change management. Update and monitor regularly the Deliverable Control Index tool Update and monitor customer input data Project Execution Plan Coordination with CONTRACTOR and COMPANY during design reviews. JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 29 of 72 Schedule and flag delays immediately. Reports to Project manager. 6. EPKS Engineers/ SIS Engineers Other engineers Assigned at Contractor’s office as required during detailed design phase(FEED review) Attending training and obtaining certification in EPKS and SIS modules. Report to MAC Lead engineer Checking engineering inputs for quality. Develop design documents and drawings. Follow and adopt engineering standards developed for the project and Honeywell best practices. Check for standardization anomalies and advise MAC Lead engineer. Responsible for coming out with design deliverables in assigned time in line with overall schedule requirements. Implementation using tools developed by Honeywell. 7. Specialist Engineers Responsible for providing specialist support to the team in areas such as network, IAMS, ALMS etc,, on as required basis. Consultation role to customers as required. Support MAC Lead engineer during design, implementation and testing of these specialist items. Report on progress to MAC Lead engineer. Ensure adherence to best practices of honeywell design processes 7. Lead IECS Responsible for interface with customer for defining the requirements of IECS Report to MAC Lead engineer and Support the MAC Lead Engineer to deliver the IECS items delivery Coordinate with all vendors that part of IECS supply Checking engineering inputs for quality. Develop design documents and drawings. 8. Lead Interface Engineer Responsible for interface with customer for defining the requirements of interface with 3rd party package Attend/arrange the schedule testing with 3rd party package Responsible for coordination/implementation of 3rd party Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 30 of 72 package into the ICSS system and IECS system Checking engineering inputs for quality. Develop design documents and drawings. 8. Project Admin A key role supporting Project Team as a whole. Provides logistic support, arranging travel, visa, shipment etc.. Provide for stationery and other office materials. Provide logistic support to customers as required. Other support as needed to customers and Honeywell team. Arrange and book meeting rooms etc.. Arranging team building activities. Arranging support services such as meals during meetings Assist in order processing tasks and raising purchase requisitions. 9. Supporting staff Project Manager will be ably supported by Supply chain and Procurement staff, Logistics staff, Health, Safety and Environment staff, QA/QC staff. All the project personnel identified above, including the Core Team, will be drawn mainly from Honeywell’s vast engineering resources in South East Asian region. To ensure smooth hand-over of ICSS system to the Site support team based in Indonesia, special efforts will be made to get the relevant personnel involved during project detailed design and testing phases. Specialized engineering skills e.g., Networking will be provided from Honeywell’s engineering resources in the Asia Pacific region as required and supported corporate personnel from Phoenix as required. HSE representative based in SEA will guide the Project manager and Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 31 of 72 team to implement Honeywell’s HSE policies and guidelines. He will also do necessary audits of the site for HSE adherence. QA/QC representative will be responsible for internal QC audits and provide the team support and help to develop and maintain Project Quality Plan specific to the project. Procurement team will assist Project Manager in selecting vendors and ordering materials as well as processing invoices etc.. Document control staff will help in maintaining and tracking incoming documents and deliverable documents and report any delays to Project manager. Storage of documents in electronic format. 3.4 Honeywell Site Team Honeywell will form a site team led by Site Manager/Leader to support Site Installation, Power-on Support and Pre-commissioning. Engineers from Honeywell, Indonesia office shall be included in the project implementation team to ensure project background and continuity of experience needed for smooth site activities. 8.1. Responsibilities Matrix (Between MAC and CONTRACTOR/Company) This paragraph refers to the responsibilities of the Project Team versus the Customer in terms of simple table showing different activities and the responsible party. A more detailed scope responsibility matrix would be prepared and finalized during the detailed design phase in accordance with scope of work Post Feed Responsibility Matrix Activity Company CONTRACTOR MAC Input design data - Primary - Design freeze Support Primary Primary Implementation - Support Primary Standardization drive amongst different EPC’s Primary Support Support Getting design detail inputs from other EPC’s Primary Support Support Engineering Change Control Support Primary Primary Schedule control Support Support Primary Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 32 of 72 Testing Support Support Primary Interface Management Support Primary Support Project reporting to COMPANY/CONTRACTOR - - Primary Site services Support Primary Support Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 33 of 72 7. PROJECT MANAGEMENT PLAN Honeywell shall assign a single Project Manager (PM) responsible for all aspects of this project including, engineering, design, procurement, integration, testing and installation. The PM shall be empowered to marshal all necessary Honeywell resources for the successful completion of the project. The Honeywell PM shall be the single point of contact for all formal communications, either verbal or written. The execution of the project will be in compliance with Honeywell Jakarta quality processes and procedures, which are fully aligned with Honeywell GPM (Global Project Management) and Honeywell GPE (Global Project Engineering) methodologies. 8.2. Global Project Management Methodology The project will be executed in alignment with Honeywell’s Global Project Management (GPM) methodology. GPM provides the Honeywell Project Manager with a methodology to ensure consistency in project execution regardless of the geographical location of the project offices. The methodology and tools are accessed through the Honeywell intranet and provide guidelines, standard templates, checklists and other tools for managing a global project. GPM includes the best of Honeywell's established procedures from past project efforts and experiences, combining them with advanced concepts and state-of-the-art practices that places Honeywell into the domain of best-in-class companies in project management. The Gartner Group has consistently ranked Honeywell as first among its peers in ability to execute automation projects. Strong project management has long been an essential Honeywell strategy, to ensure on-time delivery and minimise project risk. GPM is a worldwide program, based on the Project Management Institute standards, and includes the provision of consistent training to all Honeywell project management personnel. This ensures consistent standards on a worldwide basis, and allows deployment of project management and engineering resources on a global basis. Further, Honeywell’s Six Sigma Plus programme and ISO9001 quality standards ensure that consistent quality processes are employed in all phases of the project. The GPM approach to project management addresses the following aspects of project management: 8.3. Developing and assigning professional project managers Establishing and using a consistent process and a common approach to project management for all Honeywell project managers Providing effective project management tools and techniques Aligning Honeywell project management services to provide oversight and ongoing support for Honeywell project managers and maintenance of the GPM methodology Global Project Engineering Methodology The Global Project Engineering (GPE) Methodology provides a framework for the successful execution of Jambaran Tiung Biru Project engineering, including a well-defined process that delineates what the required tasks are and how they are performed. Within the scope for the Jambaran Tiung Biru Project, the GPE process definition includes all aspects of project engineering disciplines including basic engineering, application development, detail systems engineering and testing. GPE also defines interfaces to other essential processes such as packaged systems interfaces, and communication systems. Honeywell will deploy methods to satisfy industry standard quality conditions that correspond to the required level of techniques specified in the PO. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 34 of 72 8.3.1. Customer satisfaction survey During the course of the project, customer satisfaction survey will take place to obtain information about the performance of the Honeywell project team. The survey will be conducted by a different Honeywell team with the nominated CONTRACTOR representative and it is expected that their input will include the views of the Company related to the project’s implementation by Honeywell. The results of the survey and any necessary actions will be reviewed with the Honeywell project team for corrective actions and closure with the customer. 8.4. Project Communication Plan This will define the information requirements of the key stakeholders. It will also address how changes in communication requirements will be handled and authorized. The communication plan will be finalized upon award of the contract, and agreed with CONTRACTOR and Company. The format will be as detailed in the following sub-sections. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 35 of 72 8.4.1. Objectives To define the types of project correspondence. To identify the communication protocol. To define the format of the correspondence identification codes. 8.4.2. Project Correspondence All formal communication will be in one of the following written formats: Letters Transmittals Facsimiles Electronic Mail Honeywell shall distribute all correspondence in accordance with a Communication Plan (see section 7.6) to be finalised shortly after contract award. All formal transmitted documentation will be signed. Every formal communication will have a unique document reference number for tracking and recording purposes. 8.4.3. Communication links and channels All official contacts with the CONTRACTOR will be via the MAC Project Manager for all matters. However, for technical matters, the MAC Lead engineer will co-ordinate with CONTRACTOR counterpart as required. Interface issues and coordination amongst different EPC’s will be handled by the Project Manager and MAC Lead engineer. Project Director will guide and ensure smooth communications amongst COMPANY, CONTRACTOR and Honeywell team takes place at all times. The communication management will be consistent with Exhibit C Coordination procedure Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 36 of 72 COMPANY CONTRACTOR Project Director MAC MAC Lead Engineer MAC Project Manager Project Team Sub-vendors Site team Legend Technical Commercial Stewardship 8.4.4. Language All correspondence and Project documents shall be in the English Language 8.4.5. Contact Name(s) and Address of Client Technical correspondence to Company Name Email END USER (COMPANY) TBA TBA EPC (CONTRACTOR) TBA TBA Commercial correspondence to Company Name Email END USER (COMPANY) TBA TBA EPC (CONTRACTOR) TBA TBA Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 37 of 72 Formal correspondence to Jambaran Tiung Biru Project office Address PT. TBA XXXX 8.4.6. Contact Name(s) and Address of Honeywell Commercial and Technical correspondence to Company: Honeywell Name Email Commercial Sofia Subur Sofia.subur@Honeywell.com Commercial & Technical Dwi Trisno Susanto Dwi.susanto@honeywell.com Technical Krisna Danurdono krisna.darundono@hwl-pas.com Document Control Sri Wulansari wulansari.sri@hwl-pas.com Formal correspondence to MAC Jambaran Tiung Biru Project office Address PT. Honeywell Indonesia Graha Muncul Mekar, 1st floor Jl Panjang No 27 – Kelapa Dua Jakarta 11550 Indonesia 8.4.7. Correspondence Identification For identification of correspondence, minutes of meetings, etc., the following is applicable and this shall is maintained by the Document Controller: Each correspondence shall be limited to one subject only. All correspondences to CONTRACTOR whether by letter, facsimile or transmittal shall be dated and shall have the reference defined by MAC Document Controller. 8.4.8. Correspondence and Telephone/Facsimile Communication The Project Manager or his deputy will distribute incoming correspondence via the project document controller to project team members as appropriate. The Project Manager or his deputy will indicate who has to take action and which persons will receive the documents for info. All outgoing correspondence will be reviewed, approved and signed by the Project Manager or his deputy. Telephone conversations and informal email correspondence with technical or commercial impact shall be formally confirmed prior to any related action(s) being taken. 8.4.9. Project authority The Honeywell Project Manager has the sole authority for all commercial matters related to the Jambaran Tiung Biru project under his control. The MAC Lead engineer has authority on technical matters with no commercial impact – those with commercial impact will additionally be referred to the Project Manager. CONTRACTOR authority to be defined 8.5. Project Controls Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 38 of 72 Honeywell will implement cost control, planning, scheduling, and internal reporting mechanisms as necessary to control the project scope and execution. Honeywell will develop a detailed Level 3 Project Schedule, which will be agreed during the project “kick-off” meeting and then updated on a monthly basis. The schedule will identify any deliverables required from others (CONTRACTOR or 3rd party) to allow Honeywell to complete the system design and configuration. Where practical, and if required by the CONTRACTOR, deliverable dates will be phased to allow issue of initial date to allow design / manufacture to proceed, with a later final freeze date. Formal design review meetings will also be identified on the schedule. The updated schedule will be issued to the CONTRACTOR with the monthly report and reviewed during the monthly progress meetings. 8.5.1. Project Cost Control 8.5.1.1. Purpose To ensure that timely and accurate cost information is provided to the project team in accordance with their requirements. 8.5.1.2. Methodology The Honeywell cost management system is specifically designed as a source of control serving both Honeywell and the CONTRACTOR. Best practices are employed in accordance with industry standards. Earned value progress is based on engineering deliverables and milestones. Fundamental goals are as follows: Increase cost awareness of all members of the project team Collect expenditures, progress, and productivity data Report man-hour, cost, and progress information relative to budgets and forecasts to project management. Ensure that invoicing is accurate and in accordance with terms and conditions of the contract. Implement a project variance system to pinpoint budget deviations and potential productivity issues. Final “close out” to ensure and agree that all invoices have been issued and payments received. 8.5.2. Project Schedule Control Assessment of schedule performance will be made against plan to identify key activities or deliverables that may need corrective action. The schedule will be in overall project schedule that issued by CONTRACTOR. The aim will be to prevent schedule delay by clearly identifying key input data that may affect the critical path and to work with the CONTRACTOR to ensure that this data is provided complete and on time. Honeywell will use tools such as MS Project planning package to monitor deviation from plan. In order to prevent delays on the project, following methods will be used: Regular progress reviews Risk analysis, Resource requirements Baseline deviations reviews Any deviations will be assessed to determine corrective action(s) required and whether the change control procedure should be implemented. Ways to mitigate any schedule impact will be assessed and if necessary a recovery plan will be produced. Under certain circumstances and upon approval the project may need to be re-base lined. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT 8.5.2.1. PROJECT EXECUTION PLAN Rev A Page 39 of 72 Purpose This section describes Honeywell procedures and techniques to be used for project scheduling. The basis for schedule control and for management status reporting is also presented. 8.5.2.2. Areas of Responsibility Honeywell will be responsible for developing and maintaining their project schedule for the agreed scope of work. If required, this schedule will be identical at the upper level to the CONTRACTOR Master Schedule, such that only one schedule is being used by the overall project team. 8.5.2.3. Scheduling Criteria Honeywell will base the schedule on the following criteria: 8.5.2.4. Required milestone dates / site need dates Honeywell manpower levelling Cost effectiveness CONTRACTOR required milestones and deliverables required from Honeywell. Engineering contractors schedule of deliverables, including issues of preliminary and final data where relevant Construction requirements Scheduling Technique Critical path scheduling technique will be utilized on the project, utilizing MS Project software. The schedule will be base-lined and progress will be measured against the target. The detailed schedule will be developed using a Master Project / Sub-Project format such that only one schedule exists. Honeywell will schedule, progress and analyze their sub-project schedule within the parameters spelled out by the CONTRACTOR master project scheduler. 8.5.2.5. Progress Updating Progress updates will be done on a monthly basis. The scheduler will gather internal progress data from both the Honeywell project engineers and any sub-contractors. The overall engineering progress by earned value analysis will be included in project status reports. In addition, the status of each deliverable will be indicated via the project deliverable control index. Both the updated schedule and deliverable control index will form part of the monthly progress report issued to the CONTRACTOR. While formal progress updating and reporting will be done on a monthly basis, any issues will be communicated to relevant parties as and when they are identified. Issues will not be “held” until formal reports are issued. 8.5.2.6. Internal Planning Meetings Internal Planning meetings will be held with the Honeywell engineering team(s) in weekly basis, schedule in every Tuesday 15:00 PM during project course. Participants will include the Project Manager, the MAC Lead engineer, the Project Engineer plus any other team member that is deemed necessary. 8.5.3. Reporting Internal Monthly reports will be generated as part of the overall project status reporting. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 40 of 72 The weekly and monthly progress report issued to the COMPANY and CONTRACTOR will include updated schedule and deliverable control index data. Driven from contractually milestone basis to develop Non engineering milestone progress (60%) and deliverable MH consumed as per MDR to develop Engineering progress Report (40%). Cumulative of both progress reports resulting 100% of Progress. 8.6. Project Change Control 8.6.1. Change Management Plan Honeywell recognizes that there will be changes – both additions and deletions- to the agreed project scope of supply. In anticipation of this, Honeywell GPM/GPC methodologies have developed a Change Management Plan (CMP), shall be in accordance with change management procedure that issued by CONTRACTOR. Change management ensures that project performance remains within the project's specified scope, schedule, and budget as documented in the contract and the project plan. If change is needed, it also facilitates adjustments to that contract and plan or their elements in a decisive, methodical way. The change management process is depicted in the next section. In supporting this Plan, Honeywell uses the following documents for project progress reporting: Project Schedule Deliverable Control Index Once the change has been approved, it provides the supporting record to ensure that project documentation(s) and contracts are updated to reflect the changes and that the budget or schedule is adjusted accordingly. Honeywell will raise formal clarification sheet to CONTRACTOR as valid reference channel addressing the impact due to its change 8.6.2. Change Management Flow Chart 8.6.3. Change Management Plan Implementation Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 41 of 72 Relevant articles of Purchase Order’s Terms and Conditions shall be the guidelines for Change Management Control Honeywell project team will work pro-actively to identify potential changes to the project scope. These changes will be submitted to the CONTRACTOR for review and approval to proceed with detail estimate and/or change-in-scope work. A Change Order database will be created as a depository for all the pertinent information. 8.6.4. Change Verification and Approval Identification of potential changes can either come from the CONTRACTOR or the Honeywell project team. Once changes are identified, Honeywell project team member will complete a Design Change (DC) form. The form will summarize the changes requested, identify the hardware and schedule impact. The Honeywell team will then evaluate the following: Schedule impact Resource impact Cost impact Sub-contract impact Shipping impact Contractual/business compliance 8.6.5. Approval of PO amendment Upon approval of the DC form and authorization to proceed with the detail estimate, the Core Team will implement the changes. A formal Purchase Order Amendment will be issued by the CONTRACTOR within an agreed timeframe from approval of Design Change form. 8.6.6. Change Implementation Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 42 of 72 Upon receiving the approved change order from the CONTRACTOR, the Honeywell Project Manager will work with the MAC Lead Engineer to update the Project Workbook and schedule. The Project Manager will then issue a “Notice to Proceed” to the Core Team. The below is Honeywell Standard GPM change management flow chart. Request for change Either project team submit notice or customer request change Enter change into CO log Status = "Active" Status Indicators Active Change entered into log Denied Change denied Estimate Detail estimate for Change Order Submit Change Order submit to customer Approved Change Order approved and notice to proceed PD/EM/CM/PLE review change Change in scope? NO Change Type (CT) Internal Change is in scope External Change is out of scope YES Submit DC to Customer for review/approval Personnel PD CM PLE EM NO CT = "Internal" PLE modify workbook/schedule PD issue "Notice to Proceed" YES Customer Approval to Proceed ? NO YES Honeywell formal acceptance Status = "Approved" PLE update workbook and schedule PD to issue project team "Notice to Proceed" Formal PO Amendment from Customer Project Execution Plan Enter Status = "Denied" Project Director Contracts Manager Project Lead Engineer Engineering Manager JIMBARAN TIUNG BIRU PROJECT 8.7. PROJECT EXECUTION PLAN Rev A Page 43 of 72 Customer Progress Reporting / Meetings 8.7.1. Progress Reports Progress reports will be issued on a weekly and monthly basis to COMPANY and CONTRACTOR. The progress report format will be agreed and finalised at the CONTRACTOR project kick off meeting. The progress report will contain, at a minimum, project schedule, milestone status, work completed, work planned, procurement status, project S-curve, critical issues, change order status, and action items list. 8.7.2. Customer Kick Off / Progress Meetings It is proposed that co-ordination / progress meetings will take place monthly, commencing with the Project Kick-Off Meeting. The monthly Progress Report, Action Items List and Project Schedule will be reviewed during this meeting. Requirements will be finalized in consultation with selected CONTRACTOR. It is anticipated that Company will attend the monthly progress meetings, and that these meetings will be an opportunity to identify and address concerns held by any party relating to the project execution. Additional meetings shall be required to discuss design reviews, changes, technical issues, third party interfaces etc and shall be identified and scheduled accordingly during the KOM. Wherever possible, these will be scheduled to coincide with monthly progress meetings. The venue and schedule of each planned meeting will be established during the kick-off meeting with the CONTRACTOR and Company and clearly identified in Honeywell’s Project Schedule. In case required, Honeywell will propose an unplanned meeting to addressing any technical issue raised during project course. Honeywell will prepare and issue meeting notes of each meeting. An Action Items List shall be prepared and updated after the meetings. The ‘RAIL’ shall contain the item number, reference documents, action by party, date on report, due date, remarks and current status. 8.8. Document Control Honeywell shall prepare and maintain a deliverable control index (DCI) and submittal schedule per CONTRACTOR of all drawings and documents to be supplied. The deliverable control index will track revision status, as well as issue and receipt dates. Honeywell developed system documents and drawings shall be formally transmitted to CONTRACTOR for review and approval so called MDR Honeywell developed hardware drawings shall be issued for Review (one revision), Issued for Construction and finally Issued as Built. All technical design documentation shall be issued to/from CONTRACTOR as soft copies. Customer inputs for design development will be listed in an Input document register and tracked separately based on mutually agreed dates. Any delays to inputs will be flagged to customer for impacts to schedule if any. 8.8.1. Document Handling Procedure Document approval plan will involve submission of documents officially by Honeywell to CONTRACTOR with necessary document transmittal. CONTRACTOR shall acknowledge receipt of the document immediately upon receipt by signing and returning the transmittal to Honeywell. Approval cycle shall be 10 calendar days for first review and 10 calendar days for subsequent reviews. Documents in general shall be submitted for a min of 3 revisions. First revision shall be issued for review, second for approval and if comments are minor second revision shall be issued for construction. Subsequent revisions to first revision shall not include comment over comments. Subsequent revisions shall be reviewed with respect to first round of comments only. Approval code shall be indicated on the cover sheet of the document and signed by customer before returning the same with proper transmittal. Comments shall be marked on the document itself or in a separate sheet attached to the document with Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 44 of 72 proper signature/stamp by customer. Revision numbers shall start with A, B, etc until IFC which shall be 0 (zero). All documents shall be approved for construction before FAT commencement. At the end of FAT as-built will be submitted based on marked up drawings maintained as part of FAT master. Customer input documents shall be accompanied by Transmittal with authorized signature and date. Customer inputs in the form of handouts and e-mails will not be recognized as official inputs. This is to avoid quality issues during implementation. Inputs received with AFC (Approved for construction) stamp only shall be used for design and implementation. All preliminary copies and IFD (Issued for design) inputs shall be considered only for information. As discussed during KOM, accuracy of inputs shall be maintained by CONTRACTOR contractors to minimize rework and changes. 8.8.2. Electronic Filing System Honeywell will implement a web based filing system (project workspace) to allow access by all Honeywell team members to project data. This is to ensure all the Honeywell team members have access to the common project documents and standards and that team members of project team have access to all of their project’s documentation. The project workspace is accessible globally via the Honeywell Intranet. Honeywell staff can access the Honeywell Intranet from anywhere with an Internet connection, giving ready access to all project data from any location. Access to the project workspaces will be controlled to allow only appropriate authorized users to have access to project specific or confidential data. All such project data is held on Honeywell corporate servers, and subject to regular backup and anti-virus measures. 8.8.3. Electronic Data Exchange Wherever possible, data will be exchanged with the CONTRACTOR and Company electronically. This will deliver productivity savings to all parties. The mechanism adopted will be agreed with the selected CONTRACTOR at the start of the project. Options range from email attachments (but this is often limited by email attachment size restrictions) to the use of FTP servers. All options will be reviewed – with CONTRACTOR and Company – and the most acceptable to all parties will be chosen at the time of project start. 8.8.4. Document Transmittals Documents formally exchanged as design inputs or as part of the formal review cycle between Honeywell and CONTRACTOR / Company in whatever format (hard / soft) or by whatever mechanism (email, file transfer, mail) shall always be accompanied by a uniquely numbered transmittal. As a minimum, the transmittal should list all transmitted document numbers, their revision status, and the purpose for transmittal. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 45 of 72 8. ENGINEERING PLAN 8.9. General In compliance with Honeywell’s Global Project Engineering Methodology, the scope is sub-divided into Engineering Work Packages for each area, as summarized below in section 6.5. In order to ensure that the project will be executed smoothly, Honeywell requires detailed information, in the form of documents, databases, drawings, etc., from the CONTRACTOR in the time frame indicated in the schedule. 8.10. Detailed design phase Detailed design would be carried out at CONTRACTOR office at Jakarta. Two Key members of the project team will be located at CONTRACTOR office at Jakarta during this phase and will be led by MAC Project manager. The detailed design phase will comprise of clearly defined objectives, Kick-off meeting with CONTRACTOR/COMPANY representative, review meetings as required in CONTRACTOR office and a wrap-up meeting with CONTRACTOR/COMPANY representative/Honeywell MAC key team, where conclusions are documented and signed-off in line with meeting objectives set. During this Phase the MAC vendor will work with CONTRACTOR and COMPANY to achieve the following: FEED Verification: During this phase MAC vendor will verify the FEED documents already developed by the COMPANY as part of a separate FEED contract. Detailed design: Establish design basis and project fundamentals and agreed upon as possible. If any changes are required to the FEED documents the same will be discussed and agreed to ensure it is in line with the final ICSS system selected. Review and agree on the Project Execution Plan shall also be carried out during the FEED verification phase. 8.10.1. FEED verification During this phase MAC vendor will verify the FEED documents already developed by the COMPANY as part of a separate FEED contract. The following documents, specification and layouts are to be provided by the selected CONTRACTOR for the execution phase for Honeywell to check and verify compliance. Facilities design basis Process and Instrument Diagrams Instrumentation Controls and Safety System Philosophy Instrumentation Controls and Safety System Specifications Safeguarding philosophy Loss prevention Philosophy. Specification for Instrument cabinets System architecture diagram Specification for Process Control System (PCS) Specification for Process Shutdown System (PSD) Specification for Emergency Shutdown System (ESD) Specification for Fire and Gas System (FGS) Specification for Asset Management System (AMS) Specification for Alarm Management System (AS) Specification for Integrated Operator Consoles Specification for MOMS Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 46 of 72 If any changes are required to the FEED documents the same will be discussed and agreed to ensure it is in line with the final ICSS system selected. Review and agree on the Project Execution Plan shall also be carried out during the FEED verification phase. At the end of FEED verification, MAC will come out with a list of system specific changes needed on the specifications to make it match with the proposed ICSS and IECS system. Any additional scope would be discussed based on change control management process and agreed mutually. Based on mutual agreement MAC will proceed to next phase which is Implementation. 8.10.2. Detailed design During this phase the MAC vendor shall also work with the CONTRACTOR to establish design basis and project fundamentals and agreed upon as possible. Those include compliance to scope, conformance/options/exceptions, Minimize customization/use of vendor standards, Document Deliverable List, Graphic sketches basis, standard report format, data base format finalization (In Tools), System Architecture review with L4/L5 interface requirements/security, project timeline, design freeze and project milestones, customer input design data, prototyping as applicable, package vendor schedule, project specifications etc. Some of the below work would be carried out in Honeywell Jakarta office by project team and later reviewed with CONTRACTOR through the key member stationed at CONTRACTOR office. Similarly design inputs collected by key member stationed at CONTRACTOR office would be fed back to the project team in Honeywell office. During detailed design the following documents, specification and layouts are to be provided by the selected CONTRACTOR for the implementation phase for Honeywell to check and verify compliance. o o o o o o o o o o o o o o o o o o o o o o o Finalize and update PEP Review and finalize responsibility matrix Finalize Document Deliverable List. Update sizing basis and schedule for ICSS, OTS & IECS Finalize room layouts for CCR, LER etc. Develop and finalize Functional Design Specifications for ICSS, OTS & IECS Develop and finalize typical cabinet layouts and design. Minimize customization/use of vendor standards Coordinate ICSS, OTS & IECS design approach amongst various EPC contractors so that overall design and integration is consistent and standardized. Interface design finalization for instrumentation and control systems supplied or engineered by others Manage & resolve all interface issues between the MAC-supplied systems and other instrumentation and control systems Graphic sketches basis and typical Standard report format Define Shared User Database Structure (SUDS) data exchange matrix Data base format finalization (IN Tools) with SUDS process. System Architecture review with L4/L5 interface requirements/security, Project timeline, design freeze and project milestones, Customer input design data and schedule Prototyping as applicable Package vendor schedule Participate in Loss prevention study with CONTRACTOR Participate in HAZOP and SIL study with CONTRACTOR Hardware and Software freeze for procurement. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 47 of 72 At the end of detailed design, any additional scope would be discussed based on change control philosophy and agreed mutually. Based on mutual agreement MAC will proceed to next phase which is detailed design and manufacturing. 8.11. Implementation Phase The basis for detailed engineering drawings will be the specifications and typical developed during detailed design phase of the project, and the design inputs received from the CONTRACTOR as indicated in the schedule. Deviations from standards agreed in the specifications will only be permitted if reviewed and approved by the CONTRACTOR/Company. The magnitude of the deviation will determine the manner by which approval is obtained from CONTRACTOR/Company. This will be agreed at the Kick off Meeting with CONTRACTOR/Company. The “key team” of project will be involved in all reviews of detailed engineering documents, and a key part of the review process will be a check for compliance with project specifications. On completion of detail design drawings same will be submitted to CONTRACTOR/Company for review and comments. Honeywell will incorporate the comments into the specifications and then issue for final approval. On receipt of final approval Honeywell will then proceed with implementation and manufacturing. 8.11.1. Engineering Work Packages During preparation of detailed engineering drawings the deliverables will be broken down to the following various packages: PCS Hardware Design PCS Applications Design ESD/FGS Hardware Design ESD/FGS Applications Design HMI Design Network / High Level System Design Third Party Sub-systems Design Third Party Interface Design MOMS application All deliverables will be detailed in the Deliverable Control Index to be developed at the start of the project. 8.11.2. Use of Standard Builds (Toolkit) Engineering will be based on Honeywell’s design standards, guidelines and best practices in order to provide a proven design, optimized engineering time and long term benefits to customer. Honeywell seeks to maximize their application of Standard Builds, also known as “Toolkit”, during this project. These are automation best practices that define standards for design, implementation and test. Standard Builds consists of: • Templates • Guidelines • Solution Libraries • Checklists • Tools • Methodology Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 48 of 72 This collection of standard builds allows work to be performed consistently every time to improve productivity and global consistency. Additional benefits include reduction in project risk, improved commercial scope management, and efficient flawless start-ups. Customizations of design, if any shall be considered on mandatory situations as per mutual agreement with customer and as allowed by design guidelines/standards/best practices for process control. The same will be applicable for sub-systems design included in Honeywell’s scope. 8.11.3. PCS Hardware The PCS hardware engineer will use the CONTRACTOR supplied design inputs as defined in the PCS FDS to produce a package of hardware design documents. Typically these will include, but not be limited to: Cabinet / console GA drawings Cabinet / console layout drawings Cabinet / console wiring drawings Marshalling cabinet wiring schedules Power and Heat calculations 8.11.4. PCS Applications The PCS applications engineer will use the CONTRACTOR supplied design inputs and functional design specifications and loop typical prepared during detailed design phase to develop PCS applications. Database update and bulk generation tools will be used greatly to improve the efficiency during this phase. 8.11.5. ESD/FGS Hardware The ESD/FGS hardware engineer will use the CONTRACTOR supplied design inputs as defined in the ESD/FGS FDS to produce a package of hardware design documents. Typically these will include, but not be limited to: Cabinet / console GA drawings Cabinet / console layout drawings Cabinet / console wiring drawings Marshalling cabinet wiring schedules Power and Heat calculations 8.11.6. ESD/FGS Applications The ESD/FGS applications engineer will use the CONTRACTOR supplied design inputs and functional design specifications and loop typical prepared during detailed design phase to develop ESD/FGSapplications. Database update and bulk generation tools will be used greatly to improve the efficiency during this phase. 8.11.7. HMI The HMI Engineer will work with CONTRACTOR and Company to assist in defining a list of process graphics. Typical displays and HMI developed and demonstrated as well as functional design specifications developed during the detailed design phase will form the basis for this package. After an initial review of the overall philosophy and standards defined in the FDS and the HMI object library, Honeywell, with the CONTRACTOR/Company, will identify approximately 10% of the graphics to be developed first. The graphics will be developed in accordance with the standards defined in the HMI Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 49 of 72 FDS. Once developed, Honeywell will issue these 10% graphics to Customer for review and approval. A meeting will be held to review the comments. Honeywell will then incorporate the comments and continue the development for the rest of the graphics. Another batch of graphics will be issued to Customer for final approval following completion of all graphics. 8.11.8. Third Party Interfaces The PCS applications engineer will use the final CONTRACTOR supplied design inputs and functional design specifications prepared during detailed design phase to develop the 3rd party interface database and graphic applications. Database update and bulk generation tools will be used greatly to improve the efficiency during this phase. 8.11.9. Network & High Level System Design The high-level system design will be based on the definitions in the FDS. Additional design inputs from CONTRACTOR and Company will be used to develop a detailed design package. MAC will work with Company on the L4 and L5 system integration for Company to access data from ICSS to the corporate LAN. Scope of work and level of responsibility shall be as defined in Honeywell proposal. 8.12. Testing 8.12.1. Design Validation Tests All testing philosophies, procedures templates, prototyping, 3rd party testing, LERs etc as applicable shall be reviewed during FEED for determining detailed scope of work against contractual requirements. 8.12.1.1. Software Prototype (Typical) test As a proactive measure of project implementation, the entire I/O loop typical that require compliance to project specification, shall be developed as part of the basic engineering activity, tested for design validation and signed-off by the customer ahead of mass production. This approach shall ensure a smoother implementation of HMI and process graphics at a later stage for each portion of plant. This typical testing shall include: Graphics sub-picture library Graphics testing for given typical Typical testing for all PCS, Safety system and FGS systems Upon completion of typical testing a sample PCS graphics shall be built using a combination of typical I/Os, with the HMI concept of overview and a few navigational displays. This test will be carried out based on the graphic specification document, witnessed by the customer and signed-off. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 50 of 72 8.12.1.2. Hardware Prototype (Typical) Test A typical cabinet of each type shall be fabricated as per approved design specification and witnessed for concurrence before being mass produced. The objective is to identify gaps between actual fabrication and the design drawings, and correct them before the impact is huge. The schedule for the above activity shall be mutually agreed upon but completed before mass production of design starts. 8.12.2. Communication Interface / Handshaking Test The intent of the test is to verify communication between the PCS and each of the sub-systems interfaced with the PCS. The IFAT shall also cover the interface testing of the UCPs package systems, that are free issued to the testing location in HON. UCPs for package systems that cannot be delivered to HON shall be tested for interface functionality using either of the following method. For interface via OPC, where it is possible, to establish a VPN link, the test can be conducted remotely by setting up a VPN between PCS vendor and UCP package supplier where the UCP system cannot be delivered to a central place of testing with the target PCS. A Video-IP camera can be setup at the PCS vendor site to capture EPKS screen for communication verification. In case if the VPN is not feasible or possible, a Mini PCS that shall be dispatched by Honeywell to the UCP sub-system manufacturer’s location for interface test. For interface via Modbus Ethernet (ModbusTCP), similar method may be applied For interface via Modbus Serial, a serial to Ethernet converter (terminal server) can be dispatched to supplier location. Once serial and Ethernet setting is setup by the supplier, PCS vendor will be able to interface with the remote equipment. Use of Modbus simulator to establish link and complete other parts of the tests. The schedule for the above activities shall be mutually agreed upon but completed before IFAT starts.. 8.12.3. Internal Testing Internal Factory Acceptance Test (FAT) shall be conducted at Honeywell, Jakarta. The following items shall be tested by Honeywell prior to FAT start with CONTRACTOR / Company representatives Cabinet internal layouts per the approved drawings I/O loop test Hardware verification Graphics Application configuration, logic and software verification against the approved application engineering documents Third Party Interfaces Subsystem Integration Internal FAT shall be conducting using the same procedure that will be used for Factory Acceptance Test (FAT) and a log of all the hardware/software corrections shall be maintained. 8.12.4. System Readiness Review This is a key milestone before the Factory acceptance test can start. During this CONTRACTOR and COMPANY will jointly review the test records of MAC carried out during internal tests, input design document revisions used to ensure latest inputs have been used for implementation, FAT procedure and check sheets, actual staging readiness of hardware, facilities for testing, test organization from MAC, test equipment calibration reports etc.. Upon completion of the review CONTRACTOR/COMPANY will decide to proceed with FAT and IFAT. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 51 of 72 8.12.5. Factory Acceptance Test There will be separate Factory Acceptance Tests (FATs), conducted for the PCS and ESD/FGS systems as well as other sub-systems to carry out independent 100% I/O and functionality tests, as per approved design documentation and mutually agreed upon FAT procedures. The FAT’s for PCS, ESD/FGS, AMS and AS systems are carried out independently first in order to test full functionality in full and to resolve issues if any, before connecting to form the PCS for integrated FAT. All tests shall be based on mutually agreed and approved test procedures and check sheets. All test results shall be recorded on check sheets. Any punch list items or wish list items shall be recorded in separate punch/wish list forms. Proper numbering and tracking of punch/wish list will be maintained during entire testing and post testing and will be part of documentation submitted to customer. Outstanding punch items will be tracked and mutually agreed to be carried forward to site or to be corrected before shipment. All corrections shall be retested and approved by customer and signed off. 8.12.6. Third party interface testing All the third party devices shall be tested prior to start of the integrated FAT. This testing shall involve the third party device (or a simulation of it with CONTRACTOR / Company approval) being physically connected to the Experion system network at Honeywell staging area to prove that they successfully communicate without any communication errors. For 3rd part systems that cannot be made available at Honeywell staging location, Honeywell shall arrange the necessary equipment and resources to carry out the interface test at the vendor’s shop in line with project specification requirement. 8.12.7. Integrated Factory Acceptance Test An overall Integrated ICSS & IECS system IFAT will be organized as per a separate test procedure prepared by Honeywell and approved by CONTRACTOR / Company to test some critical interfaces of the whole ICSS & IECS. This test is expected to be performed to meet the intent of the full ICSS & IECS IFAT and shall take place before the final shipment of the ICSS & IECS system. Honeywell will provide supervision, specialist personnel, test equipment, test technicians and all necessary materials to support customer witnessed testing. Honeywell will assign a test coordinator whom will be the point of contact for all communications during the test. CONTRACTOR / Company will provide personnel to witness the factory tests and to assist in the overall execution of the tests. Honeywell will maintain a system log to report all deficiencies found during testing. The deficiency log will be in punch list format; each deficiency will be uniquely numbers, signed off and will indicate the action taken to clear the item. Any change during FAT/IFAT shall be done following the approved change control procedure. All documents and drawings shall be red lined as and when there will be any correction and the redlined documents will be used for installation and commissioning. 8.12.8. Certificate of Acceptance Upon completion of FAT and IFAT, Honeywell will prepare “Certificate of Acceptance”. Any noted deficiencies / errors / action items identified during the FAT/IFAT which have not been cleared (and as agreed by CONTRACTOR / Company) will be attached to the FAT dossier. Signing of Certificate of FAT acceptance denotes the completion of FAT/IFAT. The system will then be turned over to Honeywell’s logistics group for packing and shipping documentation preparation. All packing shipment shall be as per project specifications. The CONTRACTOR will be notified when the equipment is ready for shipment to CONTRACTOR freight forwarder. Once the equipment is turned over to the CONTRACTOR freight forwarder, it is then the responsibility of the CONTRACTOR to ensure that the equipment arrives at the stated destination safely and without any damage. Honeywell will update any deliverable documentation to reflect accurately the as-built System. Final asbuilt documentation will be submitted after the shipment of the equipment. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 52 of 72 Honeywell will work out packing /shipment document requirements separately with CONTRACTOR during detailed design phase. 8.12.9. Site Acceptance Test Site Acceptance Test (SAT) shall be conducted at site by Honeywell and shall be witnessed by CONTRACTOR and Company representatives. The SAT will be carried out in line with the approved SAT procedure prepared by Honeywell. The SAT shall prove the following 8.12.10. All parts of the system are connected and interfaces working properly Repeat full testing of the application software as a part of commissioning. Operation of Asset Management and Alarm Management systems Pre-Commissioning / Commissioning The plant commissioning and start up support will be provided by Honeywell as per the purchase order. Resource pool for this in general shall be drawn from Honeywell local affiliate (HON, Indonesia) as it will enable them to provide long term support for the plant. 8.13. Documentation All engineering documentation and databases will be developed in the English language and will be prepared using proprietary packages such as Microsoft Office, IN tools, AutoCAD and Adobe Acrobat. 8.13.1. INtools Instrument Database The PCS I/O databases will be generated from the CONTRACTOR instrument databases, which will be built using Intergraph’s “INtools” package. CONTRACTOR IN tools project database will be the master database for all associated instrument-related information. Honeywell and CONTRACTOR will be responsible for maintaining their data fields, as identified during basic engineering phase. Honeywell will be responsible for maintaining the databases for all PCS control systems. PCS database development will be handled in accordance with Honeywell Quality Procedures, with particular emphasis on management of change A remote data entry system will be required to be set up so that Honeywell engineers can populate the database from Honeywell, Jakarta in a secure and reliable manner. Please refer Appendix L for INtools work flow process. A critical component on any MAC project has to do with the exchange of project data. Therefore, Honeywell utilizes a proven method of an electronic data transfer mechanism between all major project participates using our Shared User Database Structure (SUDS) process by maximizing the single point of entry concept. This process seeks to establish the following objectives: Minimize rework Eliminate duplicate work Identify areas of expertise Create standard roles and responsibilities structure Create tools around standard Support virtual project team concepts This concept allows the EPC to create the Project Instrument (INTools seed) database with an early understanding of data requirements for MAC Projects. Honeywell will accept data directly from the EPC via INTools export, therefore remove addition work associated with re-keying or converting data. The Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 53 of 72 work package concept was also applied to the SUDS database work flow. This allows for work to be executed in a sequential manner and tracked on the project schedule by activity. Database work packages are timed as such to reduce the burden associate with Management of Change (MOC) for data received out of sequence or too early. 8.13.2. Loop Schematics Honeywell expects that the instrument loop schematics will be produced by CONTRACTOR as an output from INtools. 8.13.3. Bill Of Materials Honeywell shall submit a complete bill of materials (BOM) consisting of original quantity, revised quantity, material description and model numbers. The bill of materials shall be maintained in electronic format. The bill of materials shall be provided with as-built documentation. Honeywell will issue the BOM two weeks after the completion of the procurement phase as “Issue for Design”. Honeywell will re-issue the BOM at the start of the FAT activities as “Issue for Construction”. 8.13.4. System Self Documentation The PCS uses the EPKS Control Builder software package to configure and monitor the applications which reside in the PCS Controllers. Once the configuration is complete the package will be used as a self-documentation tool to print out the Control Builder function block configuration charts. The PSD, ESD and FGS use the Safety Manager Safety Builder software package for application development and on-line maintenance. Once the configuration is complete the package will be used as a self-documentation tool to print out the Functional Logic Diagrams. 8.13.5. Technical Query Forms During the implementation of the project, Honeywell will inevitably require clarification and/or further information from the CONTRACTOR on a number of technical issues. For each such case Honeywell will complete a Technical Query form and submit this to CONTRACTOR. Each form includes a log number, the name of the requestor, the requested information (including details of any reference documentation), and the date by which the information is required. CONTRACTOR completes the response box, and signs and dates before returning to Honeywell. Honeywell will track the Technical Queries in a Register, which will record the Query date of issue, the date of response, and the status (open/closed). 8.13.6. Standard System Manuals Honeywell shall provide standard system manuals (operation and service manuals) as part of the deliverables. The CONTRACTOR shall be supplied with all revisions to system manuals, as they are released, until the standard manual update warranty period expires. 8.14. Packing and Shipping The Honeywell, Integration centre shall perform all the packing and shipping in compliance with the project requirements. Honeywell will update any deliverable documentation to reflect accurately the as-built System. Final asbuilt documentation will be submitted after the shipment of the equipment. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 54 of 72 8.14.1. Packing and Preparation for Shipment The System shall be cleaned and inspected prior to packing for shipment. The system shall be packed as appropriate to avoid damage due to rough handling. Consoles shall be shipped individually. Consumable equipment such as batteries, fuses, lamps, breakers, etc. shall be packed in separate boxes and clearly labelled. Start-up spares, if applicable, shall also be packed in separate boxes. Keys, disks, cartridges, tools, manuals and other small items shall be packaged in separate boxes and clearly identified on the outside of the package. A set of keys shall be taped to the outside of each cabinet door. All lifting points shall be clearly marked. Lifting details shall be supplied to the engineering contractor for review. Any special handling instructions shall be provided. Slings shall be colour coded to indicate proper placement. The outermost covering shall be clearly marked with complete identification. The CONTRACTOR supplied equipment numbers shall be identified on the container. Packing lists itemizing contents of each box shall be placed inside each shipping unit. A second copy, together with any special shipping instructions, shall sealed in a water proof envelop and securely fastened to the outside of each shipping unit. Packing lists shall state the purchase order, list of items and full description of contents. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT Project Execution Plan PROJECT EXECUTION PLAN Rev A Page 55 of 72 JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 56 of 72 9. INTERFACE MANAGEMENT METHODOLOGY After project kick off and during basis design phase MAC will prepare an interface management procedure for COMPANY/CONTRACTOR approval. 9.2. Interface Management Plan A typical process for management of Interfaces is outlined below. This procedure provides guidelines and instructions in supporting project interfaces among the MAC Team, CONTRACTOR, vendors and COMPANY. It provides a means to communicate across interfaces in the most effective and coordinated manner without providing negative effects on the project cost or schedule. This methodology will be applied to the project with the expectation that it will be followedwith all interfaces which are required for the Project. It is expected that MAC, COMPANY and CONTRACTOR involved with the project will bring their effective methodologies for discussion and possible incorporation into an overall project integrated interface procedure. 9.3. Project Responsibilities for Interfaces MAC will nominate a dedicated Lead Interface Engineer with the COMPANY and CONTRACTOR. This is to ensure the correct and timely flow of information between CONTRACTOR, COMPANY, MAC supplier and other involved parties. The Lead Interface Engineer will report directly to the ICSS Lead engineer. Interfaces between MAC team and External Entities shall be further identified by the COMPANY, CONTRACTOR and ICSS Lead Engineer during basic design activities. For the purposes of this document, “External Entities” are those persons, companies and organizations that are not contractually obligated to the MAC project team, so MAC does not have contractual authority to direct the entity as needed to ensure the deliverable or task requiring the interface is achieved. Examples of external entities are: CONTRACTOR Team Members CONTRACTOR vendors and sub-contractors COMPANY Team Members 9.4. Client Responsibilities The COMPANY or CONTRACTOR will be responsible to: Ensure that all parties approve the overall interface plan and activity (task) descriptions so proper tie-ins can be made to the individual schedules. Issue an initial Interface List with narrative description of the interfaces. Assign the management of each interface to a single entity (COMPANY, CONTRACTOR, or MAC/ICSS supplier). 9.5. MAC Responsibilities MAC will support and manage the Interfaces related to the ICSS scope of delivery by performing the following: Actively support the interface definition phase(s) Once defined, manage all direct MAC interfaces related to the ICSS scope Tracking of the interface and providing status and scheduled data Project Execution Plan JIMBARAN TIUNG BIRU PROJECT 9.6. PROJECT EXECUTION PLAN Rev A Page 57 of 72 Arrange formal communications and meetings as appropriate Provide ICSS test kit. CONTRACTOR or Third Party Responsibilities The CONTRACTOR or third party vendors will be responsible to: Support the interface definition phase Cooperate with and assist with Interface Lead engineer Provide status and scheduled data to the Interface Lead engineer Supply the required data and facilities to the appropriate party in the format and within the time frame requested by the Interface Lead engineer. This includes all interface data related to CONTRACTOR’s vendors and CONTRACTOR’s 3rd party subcontractors. When necessary, Interface Lead engineer shall be allowed direct communications with vendor’s lead engineer to ensure specific data requirements are understood by the vendor. All such communications however will be managed by the CONTRACTOR Should formal meetings be necessary to discuss an interface and obtain the required data, all parties to participate and respond to reasonable requests. 9.7. Potential Interfaces Issues Examples of interface problems include: Not receiving required information in a timely manner to start or complete work on schedule Not communicating to the ICSS team any changes within their scope that impacts ICSS implementation Ambiguity in the delineation or interpretation of responsibilities Incompatible technical interfaces that may require changes to project scope, cost or schedule Lack of corrective action by any party Schedule not updated or communicated Performance or technical issues within one party’s deliverables that impact the interface not being communicated in a timely manner Work links incorrectly applied to the interfaces After project kick off, the following shall be identified: Project deliverables that require an interface to an external entity Project activities that require an interface to an external entity Schedule for interface activities including milestones and critical dates As soon as practical, all interface activities shall be scheduled and resourced. When problems affecting the project occur that cannot be resolved by either party, the COMPANY/CONTRACTOR shall provide the necessary assistance, resources and authority to facilitate resolution. Since interface issues could impact the cost and schedule dearly, all project team members are encouraged to correct the situation once identified. MAC, CONTRACTOR and COMPANY Project Managers shall be responsible for ensuring that this procedure is implemented, and for determining their proper design interface requirements with others. All interface issues related to ICSS shall be worked through the ICSS Lead engineer, Interface Lead engineer, ICSS Project Manager and CONTRCTOR as the case may be. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT 9.8. PROJECT EXECUTION PLAN Rev A Page 58 of 72 Interface Procedures 9.8.1. Defining ICSS Interfaces All organizations affecting the successful completion of the Project will define the interfaces required from other organizations to deliver their own scope. Interface tasks shall define all pertinent data, include but are not limited to: deliverables, work activities, procured items and database packages. As a minimum, the Interface List shall provide the task description, date required, ID, project package, phase of the project (engineering, procurement or construction) and shall be sent to the CONTRACTOR/COMPANY Project Manager or designee. The CONTRACTOR/COMPANY will review each interface and reach an agreement with the originator as to its validity. Once the interface is agreed to be valid, the interface will be sent to the receiving organization by the CONTRACTOR/COMPANY for review. The receiving organization shall review the interface and provide comments to the CONTRACTOR/COMPANY. If the receiving organization agrees with the interface, it is then added to both the receiving and requesting organization’s schedules. This response shall be no longer than five business days. In case of a disagreement to validate an interface between CONTRACTOR/COMPANY and requesting organization or between CONTRACTOR/COMPANY and receiving organization, the disagreement shall be recorded formally by the CONTRACTOR/COMPANY and all parties notified. For ICSS scope related interfaces, and once the Interface has been validated, the management of the interface will be assigned by the CONTRACTOR/COMPANY, to MAC team and the other party advised of this appointment. Defined interfaces in the Interface List will not be deleted unless it is coordinated and agreed to by CONTRACTOR/COMPANY and all affected parties. 9.8.2. MAC ICSS 3rd Party Interface MAC shall be responsible for implementing ICSS external interfaces to the process, utility and Third Party Packages. MAC will proactively interface with 3rd party package vendors for technical information regarding ICSS design. However such information received from vendors will be facilitated and validated by COMPANY/CONTRACTOR. CONTACTOR/3rd party vendor shall be responsible to: Arrange ICSS to Third Party Package interface and integration design meetings until Final version Approved by COMPANY. Supply the necessary interface design documentation (interface drawings, functional specifications, full tag database with addresses and descriptors) needed by the MAC to develop the ICSS side of the interface, and to properly identify the signal cabling and related devices between these systems. Facilitate MAC access to the suppliers' facilities as needed to perform ICSS interface test in their facility. Provide Third Party Package simulators in cases where the Third Party Package cannot be made physically available for testing. Assign a designated contact to be responsible for all communication and activities with MAC. Provide resources as required to assist the MAC in developing and scheduling of Third Party Packages into the overall project schedule. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 59 of 72 Provide resources and equipment to assist MAC with the FAT for ICSS interface testing to Third Party Packages. Provide resources to assist MAC with resolving any discrepancies discovered during Design data exchange, ICSS interface test and FAT that are or may be within the Third Party Equipment. 9.8.3. ICSS Interface Coordination The CONTRACTOR/COMPANY or MAC shall maintain the Master ICSS Interface List. However, MAC shall provide information to the CONTRACTOR/COMPANY, so that a master Interface list for the overall project can be maintained. Typically, the CONTRACTOR/COMPANY shall be responsible for submitting the Master Interface Coordination Report to all affected parties on a regular basis. MAC Interface Lead Engineer and Project Manager shall be responsible for ensuring all interfaces between MAC, CONTRACTOR, Third Party Vendors and other contractors are actively managed. In-general, the MAC Interface Lead engineer shall: Inform the MAC Project Manager who will notify the CONTRACTOR of all significant interface issues that may impact project cost, schedule or quality of work. Liaise with Discipline Leads of the CONTRACTOR and other suppliers to ensure a clear understanding of the tasks to be performed, to identify problem areas and obtain agreed solutions. Provide planning and scheduling coordination within the MAC's organization, MAC subcontractors (if any) and Contractor Third Party Packages and third party systems. Develop and comply with documented procedures establishing methods of communication. Identify, track, document and expedite required data exchanges between MAC and other parties. Develop required data formats for ICSS design to be followed by the 3rd party system vendors. Ensure interface design philosophy as per CONTRACTOR/COMPANY standards are adhered to and report deviations if any for CONTRACTOR/COMPANY approval. Provide separate focus for DCS interfaces If ICSS equipment includes equipment from MAC Third Party Vendors (e.g., SIS hardware) MAC shall be responsible for integrating this equipment into ICSS. Resolution of technical issues such as intersystem compatibility or communications shall be the responsibility of MAC who shall work directly with MAC Third Party Vendors to resolve such issues. 9.8.4. Interface Coordination Meetings The CONTRACTOR/COMPANY or designee, Interface Lead Engineer/ICSS Lead Engineer/ MAC Project Manager shall attend regularly scheduled coordination meetings to review and report progress on each of the interfaces. The required interface meetings shall be identified upfront and included in the project schedule and held at a suitable location and hosted by the CONTRACTOR/COMPANY. 9.8.5. Interface Work Packages MAC’s internal interfaces are based on work packages that are issued to various internal organizations or locations. Honeywell Global Project Management (GPM), contains detailed procedures, flowcharts, checklist, tools, etc. to support this methodology. Details of GPM procedures are considered sensitive IP information, however an over view of this process can be presented to CONTRACTOR/COMPANY under the existing global confidentiality agreement if required. All Internal Interfaces, regardless of geographical location or activity type are covered by and will be managed in accordance with the above proven Honeywell procedures. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 60 of 72 9.8.6. Interface miles tones within Project Schedule ICSS project schedule shall indicate the documentation, materials or information required from the COMPANY, CONTRACTOR or other external entities. Design data associated with these interfaces will require a design “Freeze” date for ICSS team to effectively complete the deliverables. Such design Freeze dates will be represented as milestones on the Project Schedule. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 61 of 72 10. QUALITY PLAN 10.2. Quality Plan Honeywell Project Operations policy is to deliver defect-free products and services consistent with the Contract, Customer Specifications, and Honeywell internal standards. Honeywell Global Quality certification initiative ensures consistency of engineering across the Honeywell regions. The plan will be in accordance with Exhibit C Coordination Procedure. Honeywell shall submit a project specific Quality Plan for review at the start of the project. The Quality Plan shall detail the following: Details of all freeze dates for data required from CONTRACTOR Details of all planned hold points Details of all planned design reviews with CONTRACTOR Details of planned design reviews with third party vendors Details of all testing activities (including third party interface tests) A complete list of the Honeywell procedures, working practices and work instructions required completing the Work. An audit schedule for assessing compliance to the Quality procedures and processes. Honeywell Project Operations quality management process is based on several Quality measures listed below: Quality Plan Policies: The Project will utilize Honeywell Quality Plan Policies as overall quality directives. Engineering Centre Local Work Instructions and Procedures: At each Execution Centre, standard work Instructions and procedures are utilized during the execution of work packages. The Honeywell Project Manager will ensure that standard work instructions are followed while implementing the work packages on a day-to-day basis. These work instructions include internal review of Honeywell deliverables for consistency, maintaining integrity of databases through revision control and access control, and developing deliverables such as graphics embedded objects and extensively testing them prior to usage on a large scale in the displays. The Project Manager shall ensure that the standard work instructions are followed at each work location by means of audits. Milestone Work Audit Procedures (Gating Process) Honeywell management will conduct internal audit of work packages implemented by the project team at major project milestones. The deliverables will be audited for completeness, accuracy and functional intent. The work package implementation will also be reviewed for proper work process utilization. If any deficiencies are observed, the project team will utilize additional preventive and corrective measures. Such corrective actions will be re-audited to ensure that the additional quality measures have been effective. Audits and any compliance measures will be fully documented. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN The top level Gate Control Process map is indicated below. Project Execution Plan Rev A Page 62 of 72 JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 63 of 72 Inspections of Factory and Integration Facilities: Honeywell factories and Integration Centres are regularly audited to verify compliance of manufacturing operations with design documents and overall quality of work. Inspections and any compliance measures are fully documented. Internal Honeywell Factory Test (prior to Customer FAT): Honeywell will conduct an internal Factory Test prior to Customer FAT to verify the functionality of the system. Any deficiencies observed during these tests will be rectified by corrective measures. Internal Honeywell test documentation will be maintained and made available to Customer upon request. Personnel Training: Honeywell implements extensive training programs - both classroom-type as well distant learning type for its employees. The training sessions pertain to the Employees work activities. Local management maintains training records. Use of Experts from Engineering Centres of Excellence: Honeywell utilizes Subject matter Experts from the Centres of Excellence from its worldwide organization. These personnel will participate in design reviews to ensure best practices are followed. The following Centres of Excellence are identified: Honeywell SMS Netherlands: ESD consultancy Honeywell Belgium: Experion / networking consultancy Project Audits A project specific audit plan will be included as part of the Quality Plan. A Honeywell, Quality engineer will carry out audits in accordance with the audit plan. An audit report will be issued and it will list any observations and any non-conformances. The QA engineer in conjunction with the project team will implement corrective actions, which will be reviewed and accepted by the QA engineer. A record of all the audits will be maintained Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 64 of 72 11. PROCUREMENT PLAN Although Honeywell is not providing any significant 3rd Party scope in the proposed system, it is possible that 3rd Party scope will be added in the CONTRACTOR-contract. The Supply Management Plan to cover this eventuality is detailed here. 11.2. General The overall procurement strategy for this project will meet the following objectives: Timely delivery of purchased equipment. Quality in all Procurement Project functions Leverage purchases Standardize purchasing best practices and processes The Honeywell project team will utilize the expertise of Honeywell Global Supply Management personnel. Honeywell Supply Management will work with the CONTRACTOR to identify and utilize suppliers who are committed to the delivery of Quality products on schedule. Honeywell will perform all required procurement functions, purchasing, material control, expediting, inspection, logistics, and subcontracts. All work, regardless of location, will be executed in a uniform manner and in accordance with this instruction and the CONTRACTOR requirements. Honeywell will issue to the CONTRACTOR, a list of equipment to be purchased for approval. 11.3. Breakdown of Work activities 11.3.1. Engineering Phase During the engineering phase Supply Management personnel will: Work closely with Honeywell engineering personnel to produce a consolidated bill of material that Honeywell is responsible for. Identify preferred suppliers to obtain favourable commercial/logistic terms. Use Honeywell-Supplier agreements wherever possible Prepare and execute purchase orders Track and expedite deliveries 11.3.2. System Integration Phase Supply Management shall: Support assembly activities with purchase of bulk material. Honeywell will issue list of bulk material to be purchased to Customer. Track and expedite deliveries Support shipping requirements 11.3.3. Installation Phase During the installation phase, Supply Management shall: Support project team members with procurement or warranty replacement. Track and expedite deliveries. For the case of the system installation, Supply Management shall support the project utilizing local expertise to achieve the above. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 65 of 72 11.3.4. Organisation and Staffing The Supply Chain Manager will be responsible for the Coordination effort and reporting for all procurement, expediting, and traffic for the Project. Efforts shall be coordinated between all Honeywell locations to provide the CONTRACTOR with a consistent methodology and tools for procurement. The Supply Management personnel will report administratively to the Project Manager. Dedicated, experienced personnel covering purchasing, material control, expediting, inspection and logistics will support the Supply Manager. The Supply Chain Manager will be responsible for the following functions: 11.3.5. Procurement Management The Supply Chain Manager will be responsible for purchasing materials to be used during the engineering, integration and installation phases of the project. The supply manager is responsible for optimizing content through analysis of suppliers’ capability, capacity and shop load status with special emphasis on critical materials. For materials that are to be competitively bid, the manager is responsible for obtaining quotations and analyzing direct and indirect costs associated with transporting the materials to site. The below flow chart shows the project procurement cycle. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 66 of 72 Project Procurement Cycle - SM1300Process Flow Honeywell Process Solutions- GPSM EMEA Process Details Executing Responsibility (O)=Owner / (S) = Support Project Kick-Off Determine final 3rd party scope of the project . Determine final Honeywell scope of the project . 3rd party > € 100k ? Ø (O) Project Manager or (S) authorized project team member. Honeywell Products If 3rd party content for the total project > € 100k, an IPP is required latest 2 weeks after project kick-off including all requested and relevant information . This overview will allow the procurement team to start working on opportunities well before the requisitions are issued , allowing to maximize the benefits to the project. Yes Create Internal Procurement Plan (IPP) Request IPP approval IPP Approved? [Template: Internal Procurement Plan] Review & complete IPP No The IPP need to be approved by procurement. Opportunities, concerns,... etc. need to be identified and discussed with the Project Manager or responsible team member. Ø (O) EMEA Procurement Leader or (S) RPC. An approval will be issued after the analysis. Ø (O) EMEA Procurement Leader or (S) RPC. Review will be required in case vital information is missing. Ø (O) Project Manager or (S) authorized project team member. Yes Execute agreed IPP actions on identified opportunities. Add quotation overviews (Bid-Tab's) and justify supplier selection on objective criteria. Update the IPP as supplier selection is taking place. Use it as a communication tool between buyer and requisitioner. Execute IPP Issue Requisition Requisitions need to be made and sent to the buyer for execution. They must be in line with the in the IPP and approval conditions if applicable. Request approval [SM1330] Requisition approved? Ø (O) Project Manager or (S) authorized project team member. Revise Requisition Ø (O) RPC (S) LPC (S) Project Manager or (S) authorized project team member (S) Contract Management member if necessary ( i.e. substantial subcontracts) Ø (O) Project Manager or (S) authorized project team member. {ORACLE :UGOPA004 (TB) section-2 & 3 } Request and expedite Approval according the the SEA [SM1500] No {ORACLE :UGOPA004 (TB) section-7.8 } Ø (O) Project Manager or (S) authorized project team member. Yes Select Honeywell Factory / Select Suppliers [SM1310] 1 AG - Rev02 : 5 April 2005 Project Execution Plan Select Honeywell factory(ies). Select the Suppliers taking the competitive bidding procedure into account . [Template: Bid-Tab ] Ø (O) Project Manager or authorized project team member. (S) LPC (S) RPC Note : in case the 3rd party scope changed substantially, the IPP need to be reviewed and re-approved. Page 5 JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 67 of 72 Project Procurement Cycle - SM1300Process Flow Honeywell Process Solutions- GPSM EMEA Process Details Executing Responsibility (O)=Owner / (S) = Support 1 supplier on ASL ? No Qualify supplier or select a alternative ASL supplier [SM1320] If the supplier is not qualified then initiate Ø (O) RPC/LPC the qualification process or select (S) Project Manager or equivalent supplier from the Approved (S) authorized project team supplier List (ASL). Qualification is member. mandatory when anticipated yearly spend is > 100k Eur Create and check PO respecting a unique sequential numbering.The PO must be in line with the supplier selection data in the IPP and/or approval conditions. Make sure the bid-tab is added as supporting documentation in case of competitive bids Issue PO Ø (O) LPC { ORACLE :UGOPA004 (TB) section 2 } Request approval [SM1330] Revise PO Approval required according the the SEA (Schedule of Executive Approval) In order to facilitate approval, the Approval Check List need to be completed and added in case total project 3rd party scope exceeds € 125k. [Template : Approval Check list] Ø (O) LPC { ORACLE :UGOPA004 (TB) section 3 } { ORACLE :UGOPA003b (IP) section 3 } PO approved? No Send the PO to the supplier. Expedite on acknowledgements and advise requisitioner. { ORACLE :UGOPA004 (TB) section 5 } Send PO's / expedite on acknowledgments Receive good/ services [SM1340] Process invoice [SM1350] Verify that all necessary approvals (according to the SEA) have been provided before sending out the PO. Make sure PO promise dates are updated in the system with acknowledged or anticipated delivery. Receive the material / services and verify compliance with PO. { ORACLE :UGOPA003b (IP) section 4 } Process the invoice including approvals required from Project Manager or Authorized team member. Ø (O) LPC Ø (O) Requisitioner or (S) Authorized project team member. Ø (O) GBS / Finance { ORACLE : AP User Guide section 1 + 2 } Process Payment Process the payment as per Payment terms in the contract. Ø (O) GBS / Finance { ORACLE : AP User Guide section 5 } Close PO End AG - Rev02 : 5 April 2005 Project Execution Plan After full payment is done and all open actions on receiving report are closed, the PO must be closed Ø (O)LPC/RPC (S) Project Manager or authorized project team member. Important note: All 3rd party contract labor and sub-contracts requires a PO or legally enforcable LOI ( faxed & signed by both parties , checked by contract management and explecitely stating that generated costs will be reimbursed by the client in case the project is not going ahead) before any work can start . The PO cannot be issued unless performance bound/ insurance and other related contractual documents are retained by the buyer within the agreed time. Page 6 JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 68 of 72 Honeywell Process Solutions- GPSM EMEA Approval Process -SM1330Process Flow Process Details Executing Responsibility (O)=Owner / (S) = Support IPP approval request ? Yes Analyse IPP content. Discuss & clarify with project team No Agree on action plan / provide Approval or Rejection End Requisition approval request? Identify the sourcing requirements Forward for further approvals as per to SEA No Approve or Reject the requisition End No Analyse the IPP content on completeness, competitive bidding opportunities, use of eauctions, supplier qualification, T&C's...etc Ø (O) RPC (S) LPC (S) EMEA Procurement Leader Clarify incompleteness or other issues with project manager or appropriate project team members. Ø (O) RPC (S) LPC (S) Project Manager or (S) authorized project team member. Identify the saving opportunities and agree on an action plan. In case the IPP is not allowing to get to this stage by not providing the required level of data, it will be rejected. Approval is required by the EMEA Procurement Leader. Ø (O) RPC (S) LPC (S) Project Manager or (S) authorized project team member. The operational management need to validate the timing, scope, conditions , supporting documentation, ..etc for requested goods or services. Ø (O) Project Manager or (S) authorized project team member. Depending on the amount, other mandatory approvals may be required as per SEA. Approvals should be expedited by the forwarder in case they did not return within 2 working days. Ø (O) Project Manager or (S) authorized project team member. Requisitions need to be corrected and completed in case of rejections or comments before they can be approved Ø (O) Project Manager or (S) authorized project team member. { ORACLE :UGOPA003b (IP) section 3 } Contract /PO approval request? Yes Approved Requisition ? In addition to project specific supplier contracts, other contracts or agreements for regular / strategic Honeywell suppliers are subject to SEA approval Ø (O) LPC/ RPC (S) EMEA Procurement Leader Purchase orders can only be issues based on approved requisitions in line with the SEA Ø (O) LPC (S) RPC (S) EMEA Procurement Leader In case the total 3rd party project spend exceeds 125k Eur, the Check-List to include details on the contract for PO exceeding € 50k . In case the PO is the execution of an already approved contract, only a confirmation of compliance with this contract need to be included. [Template: Approval Check List] Ø (O) Project Manager or (S) authorized project team member. Depending on the amount, other mandatory approvals may be required as per SEA. Approvals should be expedited by the forwarder in case they did not return within 2 working days. Ø (O) Project Manager or (S) authorized project team member. Yes Complete the SM approval CheckList No Forward for further approvals as per to SEA End Approve or Reject the requisition PO's need to be corrected and completed in case of rejections or comments before they can be approved. Ø (O) Project Manager or (S) authorized project team member. { ORACLE :UGOPA003b (IP) section 3 } AG - Rev02 : 5 April 2005 Project Execution Plan Page 11 JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 69 of 72 Receiving Process -SM1340 Process Flow Honeywell Process Solutions- GPSM EMEA Process Details The goods need to be received in a dedicated area sufficiently segregated from other area's, especially from outgoing goods. Only authorized persons can have access to this area. Send the shipping and packing documents to the buyer (LPC). Delivery of goods or services Executing Responsibility (O)=Owner / (S) = Support Ø (O) responsible manager for the receiving area. Ø (O) authorized persons receiving the goods Ø (O) LPC In case of a known PO, inform the requisitioner of received goods/services . Ø (O) authorized persons receiving the goods Verify goods/ services on completeness and compliance with the PO. A quality check / testing could be part of this. Ø (O) Requisitioner Ø (O) Requisitioner Ø (O) LPC Agree on the corrective actions and expedite progress. In case the goods need to be returned, the suppliers Return Authorization procedure should be used. Ø (O) LPC (S) requisitioner In case ORACLE is not available, the registry needs to be updated with matching information between receipt and PO. Update the supplier Quality & performance metrics. Ø (O) LPC File the receipt report and the shipping & packing documents. Ø (O) LPC { ORACLE :UGOPA003b (IP) Section 4 } Match with open PO#? No Acceptance approval required Delivery accepted? Yes If there is no match with an existing PO number, the project manager-- in case he is not the requisitioner-- or the department manager requires to approve for acceptance. In case no ORACLE or equivalent system is available, a central Registry need to be consulted. [Template : Registry template] { ORACLE :UGOPA004 (TB) Section 6.3} No Return goods/ services and advise supplier { ORACLE :UGOPA003b (IP) Section 6 } Notify requisitioner Verify delivery Document deviations in receipt report and forward it with shipping and packing documents to the buyer . In case an ORACLE or equivalent system is available, feedback on receiving can directly be entered in iProcurement. Defective or damanged goods can not be received in the ORACLE system (payment). [Template :Receiving Report.] Provide receipt reporting Delivery comply with PO? No Yes If the delivery is not accepted then the receiver need to advise the buyer who will contact the supplier to return the goods or refuse the services in no later than 5 working days. Advise supplier of non compliance and request corrective actions. Delivery comply with PO? In case the delivery does not comply with the PO or goods were received damaged or defect, then the supplier needs to be immediately contacted for corrective actions. For wrong deliveries, a complaint needs to be sent by fax as well (confirmed by fax receipt report ). In case an invoice is sent, it should be returned by fax referring to the complaint and advising partial or full payment stop until the issues are resolved. This is important if legal actions turn out to be required at a later stage. No Expedite corrective actions Document PO<> receipt match & update Q-metrics File the shipping/ packing documents End AG - Rev02 : 5 April 2005 Project Execution Plan Page 12 JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 70 of 72 Invoice Processing - SM1350Process Flow Honeywell Process Solutions- GPSM EMEA Process Details Executing Responsibility (O)=Owner / (S) = Support Invoice Receipt Invoice matches open PO ? No Clarify situation Invoices should be sent to the GBS or the local accounting / Finance department Ø (O) Supplier Match the invoice against receipt and open PO. In case of no match, the buyer (LPC) will need to clarify the deviations with the possible requisitioner . Ø (O) GBS/AP administrator (S) LPC { ORACLE: AP User Guide section 1.1 + 1.2 } Invoice w/o PO ? No Yes Refuse & return the invoice Yes Invoice matches Receipt ? Approve Invoice No Clarify situation and agree corrective actions Corrective actions completed? Invoices are refused within 5 working days after receipt when no PO is connected to it. Refusal should be advised via fax indicating the refusal reason with a copy of the invoice. The original is returned by postal mail. Corrective actions need to be organised with the supplier in case not all conditions are met to issue payment. 3 way matching is required (PO, receipt and invoice). If no ORACLE system is available, a central registry must be consulted for matching details. Ø (O) LPC (S) GBS/AP administrator Ø (O) GBS/AP administrator Ø (O) LPC (S) Project manager (S) GBS/AP administrator Approve the invoice and notify GBS/AP in case all conditions for payment are correct. Inform the LPC of the approval as well. Ø (O) Project Manager Instruct GBS/AP to hold the invoice fully or partially and advise the supplier in writing (send a fax indicating the reasons why the invoice is on hold as well as conditions to release it ). Ø (O) Project Manager (S) LPC Yes No HOLD approval & full or partial payment. { ORACLE: AP User Guide section 2 + 7 } Process Invoice in AP system Process the invoice for payment taking the PO payment terms into account Ø (O) GBS/AP administrator { ORACLE: AP User Guide section 5 } End AG - Rev02 : 5 April 2005 Project Execution Plan Page 13 JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 71 of 72 8.14.2. Subcontract Management Supply Manager will oversee the subcontract requirements. The subcontracts personnel will support the Project Team’s Subcontract strategy development, sourcing, bidding, selection, award, and change management activities. The Subcontract Personnel will interface with the Supply Manager, Project Manager, Project Engineer, Project Controls, Project Administrators, and other staff functions to assure materials, services and subcontracts meet the project cost and schedule objectives. The Subcontract Personnel will also provide subcontract site administrative support, on an as needed basis, and will be driven by the project needs as agreed to with the Project Manager. The Subcontract Personnel is responsible for procurement and administration support of all project subcontract requirements, unless otherwise agreed to with the Project Manager. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 72 of 72 E-auction Process - SM1311- Collect the supplier details which are required to organise the e-auction Ø (O) LPC (S) Project Manager or (S) authorized project team member. Issue the RFQ to suppliers Issue the RFQ to the suppliers and ask to provide the quote by a certain dead-line. This could be done via classic channels (email ; postal mail) Ø (O) LPC (S) Project Manager or (S) authorized project team member. Evaluate and clarify received quotes/ agree the T&C's Returned quotes need to be clarified, reviewed and finally summarised in a bid overview (Bid -Tab). It is important that the terms and conditions to be agreed before the e-auction starts so that no price reviews are necessary because of this after the e-auction. Ø (O) LPC (S) Project Manager or (S) authorized project team member. In case the quotes are not in line with the RFQ, the supplier will have to review and update his quote. Ø (O) LPC (S) Project Manager or (S) authorized project team member. Send out an invitation to the suppliers listed on the Supplier Info template including details on training, actual e-auction . Ø (O) LPC/ RPC (S) EMEA Procurement Leader CLASSIC PROCESS SECTION Collect suppliers details scope in line with RFQ? No Ask supplier to align quotation with RFQ CLASSIC PROCESS SECTION E-AUCTION PROCESS SECTION Invite suppliers for e-auction [Template: e-auction Supplier Info form] Suppliers already trained ? No Organise a training for the suppliers In some cases suppliers have already been participating to an e-auction event. In that case no training is required anymore. Ø (O) LPC/ RPC (S) EMEA Procurement Leader Set-up the e-auction ( actual and training session) and create the supplier in the system . Run the sessions at the scheduled time. Ø (O) LPC/ RPC (S) EMEA Procurement Leader Update the bid overview with the outcome of the e-auction so that all criteria could be considered for supplier selection (technical, compliance with T&C, previous experiences, customer preference,..etc). Ø (O) LPC/ RPC (S) EMEA Procurement Leader Select the supplier and document criteria Based on an updated bid-tab, the supplier will be selected by the Project Manager taking strong advise from Procurement & Contract Management into account. Ø (O) Project Manager or (S) authorized project team member. (S) RPC (S) LPC Advise suppliers accordingly The supplier selection needs to be documented and justified by the Project Manager. After that the e-auction will be settled on the system and suppliers will be advised. Ø (O) LPC (S) Project Manager or (S) authorized project team member. Run the e-auction Update the BidTab prices End Important Note : Managing and setting up an e-auction can only be done by trained procurement people. At the moment the RPC or EMEA procurement leader are considered to be these persons in the GPO organisation. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 73 of 72 11.3.6. Materials Coordination Supply Management is responsible for the management and control of the material flow from the point of identification of requirements, through engineering, supplier manufacturing, transportation, and delivery to the installation site. Supply Management is responsible for the timely delivery of the assembled equipment to the various fabrication yards. Supply Management will develop plans for timely and complete acquisition of material for execution. Supply Management will analyze, report progress, set priorities, and help assure the project is construction driven. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 74 of 72 12. HEALTH SAFETY ENVIRONMENT (HSE) PLAN Honeywell Process Solutions is committed to maintaining the highest standards of Health & Safety achievable. It is Honeywell policy that the promotion of Health & Safety measures is the mutual responsibility of management and all employees. Honeywell’s Executive Management uses a safety checklist when visiting all Honeywell locations to reinforce the safety culture. The plan will be consistent with Exhibit.C Coordination Procedure. Honeywell will work to our documented Global Health and Safety Policy and Procedures which cover all areas of design, development, construction and delivery. Honeywell HSE Policy and Procedures are published in the ‘Policies and Procedures Manual’ located on the Honeywell Intranet. Local Policies and Procedures will be complied with as appropriate. These are also published on Honeywell’s Intranet. Health & Safety Bulletins, newsletter and other information are also published and available on the Honeywell Intranet. Access to the Intranet is available at all Honeywell offices. Honeywell will also comply with Health Safety and Environmental requirements of COMPANY/CONTRACTOR. Honeywell employees and our sub-contractors, suppliers or representatives will also attend any required Site Safety induction and training prior to commencing work on Site. A Project Health & Safety Plan will be produced by Honeywell to cover all aspects of Honeywell’s work. Risk assessments will be performed for all site work to be completed by Honeywell and Method Statements developed for each site activity. Training will be provided for each activity as necessary. Please refer to Project HSE Plan that will be issued during project execution for Health & Safety policy/procedures details. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 75 of 72 13. SITE EXECUTION PLAN 13.2. Site Scope All Site services offered by Honeywell for Jambaran Tiung Biru project are based on time and materials. The Honeywell MAC Team scope includes Supervision of construction works at site and does not include any construction or installation responsibility for the project. Installation of physical deliverables from the Honeywell MAC Team is the responsibility of the Site Construction Contractor employed by the COMPANY/CONTRACTOR. The Honeywell MAC Site Team will provide supervision and inspection of the MAC supplied equipment during the construction stage. The MAC team will perform physical verification, power-on and Site Acceptance Test on the supplied systems/equipments. 13.3. Site Organization and Responsibilities The Honeywell MAC will deploy a team to the Site for the supervision of construction, pre-commissioning and commissioning activities defined in this PEP. The Honeywell MAC Team will provide engineering support to the Site Construction Contractor to respond to RFIs about the Construction Work Packages issued by the Honeywell MAC Team. The execution strategy for the staffing the Honeywell MAC Site Team is to assign some key members of the MAC home office to the site to assure resource continuity and transfer of knowledge from the Detailed Design and Implementation Stage to the Construction and Pre-Commissioning Stage. Similarly for long term perspective, local affiliate engineers who were engaged during project testing phase would be assigned to the site team to carry on the commissioning and long term support later. Mobilization: The Honeywell MAC Site Teams will be deployed to the Project site on a schedule based on the delivery of the Automation equipment from the staging area. The Honeywell MAC Site Team infrastructure will be supplied by the Site Construction Contractor and should include a temporary office complex. The temporary office shall be supplied by CONTRACTOR to accommodate the Honeywell MAC Site Team members, with meeting rooms, a coffee/lunch break room, and standard office equipment (printers, plotters, copiers, fax machines, etc.). Members of Site team shall be provided with meals and accommodation of decent quality by CONTRACTOR/COMPANY at their expenses. Communication and Commutation facilities between accommodation and site shall also be provided by CONTRACTOR/COMPANY. Support vehicles will be provided by others for Honeywell MAC Team transportation on the project site. A materials and equipment warehouse and lay down yard will be required and should be supplied by CONTRACTOR for the interim storage of cabinets, consoles, and other equipment delivered by the Honeywell MAC. The storage area should be as close as practical to the Project site to facilitate expeditious retrieval of equipment and materials. The storage area must be secured against unauthorized entry. 13.4. Pre-Commissioning Plan The Pre-Commissioning Plan defines the pre-commissioning scope to be performed by the Honeywell MAC Team and the execution plan for implementing the pre-commissioning work. 13.5. Pre-Commissioning Strategy The Honeywell MAC Team strategy for pre-commissioning is to perform the following major activities: Verify that the site infrastructure is in place and meets Process Automation System requirements. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 76 of 72 Verify that the shipped equipment is in good working order and functions same as the equipment shipped from Staging. Perform system activation and check-out validating that the system is ready for commissioning check-out by Ready for Operations (RFO). The following testing steps are performed: o SAT – Validates that the Automation equipment shipped from staging is functioning properly in site environment and validates that equipment shipped from staging works. o Loop Checking – Lead by CONTRACTOR; validates that each control loop performs as designed. This is the final stage of pre-commissioning. 13.6. Pre-Commissioning Scope The Honeywell MAC Team scope for pre-commissioning is to test the performance and integration of the installed Honeywell MAC supplied Automation equipment. The Automation equipment will be shipped to the Site Construction Contractor, who is responsible for the installation. The site infrastructure (e.g. interconnecting FO Cables) to support the communication of the Automation equipment is supplied and constructed by the Site Construction Contractor. The site infrastructure integrates the Automation system equipment installed throughout the site including Control Centre equipment and various kinds of equipment. The Table below outlines the Honeywell MAC Pre-Commissioning Team roles and responsibilities. Honeywell MAC Pre-Commissioning Team Roles and Responsibilities: HONEYWELL MAC TEAM ROLE Site Manager Site Safety/Quality Leader Lead Area Engineers Engineers GENERAL RESPONSIBILITY Manages the overall site activities for the Honeywell MAC Team Responsible for safety and quality performance Responsible for delivery and acceptance of the Automation system in assigned Area Provides technical support to the Lead Area Engineer The pre-commissioning scope of work is technical in nature and requires integration of multiple engineered systems. The work is performed by qualified engineers, designers, and technicians. The Honeywell MAC Team will contract to specialized vendors for skilled support for technology not supplied by the Honeywell MAC Team. The Honeywell MAC Pre-Commissioning Team will be supported by Jakarta office for overall project management, cost control, administration, and procurement. 13.7. Permit to Work (PTW) The Honeywell MAC Site Teams or suppliers working on Honeywell’s behalf will work under a Safe Work permitting process (Permit to Work System of COMPANY/CONTRACTOR) for work activities performed at the Project site facilities. Before any work is performed, the appropriate permit must be obtained from the Site Construction Contractor responsible for the site where the work is to be performed. Each day will start with work teams performing a Field Level Risk Assessment of the day’s activities prior to the issue of the work permit. Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 77 of 72 13.8. Pre-Commissioning Responsibilities The Honeywell MAC Pre-Commissioning team is responsible to perform the SAT. Preceding the SAT, the Honeywell MAC Pre-Commissioning Team will execute an engineering validation procedure to prepare the system for the SAT. The SAT will be witnessed by CONTRACTOR and Owner representatives. The Site Construction Contractor is responsible for the loop checking activity and is responsible for supplying all Loop Check Team resources. The Honeywell MAC Pre-Commissioning Team will provide technical support for troubleshooting and corrective actions. The Site Construction Contractor will lead the loop check activity and supply resources. The loop check deficiencies will be “punch listed” for Honeywell MAC Team action. The Honeywell MAC Team will resolve Honeywell MAC scope deliverable issues only (not construction). Loop checking is not considered to be part of SAT. 13.9. Pre-Commissioning Activities Table below provides a list of typical activities to be performed in the Site Pre-Commissioning Stage. This list is not intended to be a complete list. The complete list of Site Pre-Commissioning activities is included in the Automation Level 3 schedule. Site Pre-Commissioning Activities: TYPICAL SITE PRE-COMMISSIONING ACTIVITIES Obtain “Notice of Readiness” notification from CONTRACTOR for power and fibre infrastructure Inspect installation to confirm completeness Verify power supply terminations for the Automation equipment Verify the communication cabling is properly connected Load all licensed and configured software onto the appropriate platform Complete any FAT deficiencies Execute the Engineering Verification procedure • Power-up procedures and verification for cabinets, servers, workstations and network components. • Verify all software and firmware includes version number. • Confirm Windows Domain settings and network security policies for PAS network • Verify the Control System’s networking setup • Confirm EPKS system settings • Verify all EPKS applications and associated configurations (e.g. Alarm grouping) necessary to support I/O to HMI Display checks • Confirm Third Party Server’s system settings Execute the SAT • Complete power-up procedures and power-up verifications for cabinets, servers, workstations and network components. • Complete a 100% verification checking of licensed software application installation and versioning. • Complete a 10% check of firmware versions • Verify that all relevant Project developed software (e.g. logic and graphics) is loaded • Validate Windows Domain settings and network security policies for PAS network • Complete a 10% check of EPKS system settings • Complete a 10% check of EPKS applications and associated configurations (e.g. Alarm grouping) necessary to support I/O to HMI Display checks • Complete a 10% check of Third Party Server’s system settings • Complete a 100% Dynamic failover and diagnostics check • Complete a 10% hardwired and communication check of EPKS to TPDs • Complete controller logic testing for C300 and SIS from simulated field I/O to HMI Displays and HMI Faceplates • Complete a 100% network test with the number of required devices on the network to be documented in the SAT Test Procedure • Complete a 100% soft-tag data transfer between the DCS and third party controllers that were not physically at Honeywell Staging Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 78 of 72 • Provide Pre-commissioning (loop check) support to the Contractor 13.10. HSE and QA The Honeywell HSE Plan defines the HSE requirements for the site activities. The Honeywell MAC Site Safety/Quality Leader is responsible to assure compliance with the requirements defined in the HSE Management Plan. QA for the Honeywell MAC Pre-Commissioning Team will be measured on the basis of compliance with the documented SAT procedures and the documented results of the testing activities. The Honeywell MAC Site Team Safety/Quality Leader will audit the site SAT activities and documentation for compliance. Deficiencies identified by the Honeywell MAC Safety/Quality Leader will be documented and issued to the Honeywell MAC SM as NCRs. The Honeywell MAC Team Site Safety/Quality Leader will log and track the status of the NCRs. 13.11. Deficiency List Completion The procedure and method for completion and tracking of the deficiency list will be developed during the Detailed Engineering stage. 13.11.1. Site Changes and Control Strict change control shall be adopted and adhered to by all parties at site. All changes at site shall be evaluated for impact on system loading, power availability, spare capacity etc. Change control forms including Impact analysis forms used shall be signed off by CONTRACTOR and MAC before it can be implemented. Once agreed the change shall be implemented. One set of SAT master documents shall be maintained at site with red stamped as “SAT Master”. This document shall be red marked for all changed agreed and implemented at site. Mark up shall be signed on the page to confirm it is a legal mark up. At the end of commissioning the red markup master shall be copied and transferred to MAC for updating the FAT as-built deliverable to Final As-built deliverable. 13.12. COMMISSIONING AND START-UP PLAN The Commissioning and Start-up Plan defines the support role to be performed by the Honeywell MAC Team during the Project Commissioning and Start-Up Stage. Commissioning and Start-up is the period of the Project after Mechanical Completion. 13.12.1. Commissioning and Start-up Scope Based on the requirements, the Honeywell MAC Team scope includes commissioning and start-up support for the project. Commissioning and start-up is the responsibility of CONTRACTOR. The Honeywell MAC Team will supply professional and technical resources to support the Project Commissioning and Start-Up Stage. Planning for the Commissioning and Start-up stage will be conducted during the Detailed Engineering stage and may include the following. Commissioning and Start-Up Organization Mobilization Commissioning and Start-Up Responsibilities Health, Safety, and Environment Plan Quality Assurance Project Execution Plan JIMBARAN TIUNG BIRU PROJECT PROJECT EXECUTION PLAN Rev A Page 79 of 72 14. PROJECT COMPLETION PLAN 14.2. General Honeywell will prepare the as-built documentation developed by the project design team. Final drawings will be prepared in AutoCAD format and will be submitted after FAT is completed. Drawings will be delivered in printed format as well as on CD-ROM. 14.3. Knowledge Transfer to Customer The goal of the project is to transfer the knowledge of the project to the customer for enhancing operations and maintenance. This can be achieved through training of customers as per individual project scopes. Transfer of knowledge and project information shall be achieved through systematic documentation and as-built procedures and final documentation to customer. Involvement of local affiliate personnel during detailed engineering FAT and IFAT to ensure that they understand the design and configuration of the system as well as hardware features to enable them take over the responsibility at site. 14.4. Project Closeout Package The Project Closeout package will also consist of the following documentation: Honeywell generated drawings Softcopy of the PCS configuration Softcopy of the HMI graphics Softcopy of the PSD/ESD configuration Documentation pertaining to the Network equipment Factory Acceptance Completion forms Integrated Acceptance Tests forms Request For Service Cost/Invoice/Payment Completed Certificate As-Built BOM, including spares Software Listing and licenses Licenses transferred to Customer Letter of Transfer Care and Custody Warranty and Technical Assistance Centre (TAC) support will be provided in accordance with the contract. Project Execution Plan