“Combining Solar Panels with Agriculture Makes Land More Productive” Proposal of Modern 100 MWp Solar Power Plant Complementary With Integrated Agro Activities Chief Aim Sdn Bhd August 2020 Location Lot 9098 PT4067 Lot size 322.11 Acres Mukim Beriah District Kerian Bukit Merah Perak DR BOT Turkey Contractor CMIE/CMEC, China E. P. C. + F. PROJECT OBJECTIVES 1. Renewable energy The Government of Malaysia (GoM) aims to raise the proportion of renewable energy in the national energy mix, from the current 2% to 20% by 2025. Enforced in 2011, the Renewable Energy Act is aimed at increasing the contribution of clean and renewable energy sources such as solar photovoltaic, biomass, biogas and hydro in Malaysia’s electricity generation mix. An important driver of the renewable energy industry is the feed-in-tariff mechanism, implemented and managed by the Sustainable Energy Development Authority of Malaysia. The mechanism supports the growth of the renewable energy industry by providing guaranteed long-term contracts for power generated by renewable energy sources. 2. Agriculture Agriculture is an important sector of the Malaysian economy. The GoM aims to turn Malaysia into a significant part of the global agriculture supply chain. The development of agriculture-based SMEs is an important focus area under the National Agricultural Policy. Therefore, initiatives that support the development of agro-entrepreneur (smallholder farmers) have the potential to increase the number of jobs, elevate rural incomes and create more value-added products in the market. Chapter 1 Project Overview 1.1 Project name Agro-photovoltaic (APV) Perak D.R. 1.2 Propose project address Plot 11, Lot 9098, PT 4067, Mukim Beriah. District Kerian. Perak D.R., Malaysia 1.3 Project construction scale The solar photovoltaic complementary modern photovoltaic agriculture project in Perak D.R., Malaysia belongs to a large-scale elevated power station project, covering a total area of 322 acres, and a total of 260 agro-ecological solar greenhouse photovoltaic greenhouses were built; a single roof shed on the roof was installed with 100MWp solar photovoltaic modules. 1.4 Source of project funds The total investment capital of this project is RM$ 300 million, and the source of funds is international investment institutions. 1.5 Project construction period The construction period of the project is from mid-2021 to mid-2022. 1.6 Project Introduction The project adopts the combination of photovoltaic and integrated agriculture, and adopts the form of elevated photovoltaic power generation support. The top of the elevated support is covered with photovoltaic components and the bottom is planted with high-valued return efficiency crops. The photovoltaic agriculture integrates grid-connected power generation, combining high-value integrated facility agriculture. On the one hand, the photovoltaic system can use agricultural land to generate electricity at low cost. The solar cells can be arranged at intervals or use certain photovoltaic modules with higher light transmittance where the main light sources required for the growth of animals and plants can be penetrated to. In addition, infrared light can also be stored with thermal energy, increase the temperature of the greenhouse, and is conducive to the growth of animals and plants in cooler temperatures to save energy. The project will be benefitted with the most advanced technology, experience and talents in the fields of solar energy, system integration, intelligent control technology, facility agriculture, agricultural planting, etc. With solar facility agriculture integrated grid-connected power stations as the core, the station will be utilized for various purpose such as solar power generation, agricultural optoelectronics engineering application, modern agricultural planting and breeding, processing and comprehensive utilization, agricultural planting and breeding technology exchange and promotion, talent training, sightseeing agriculture, Lohas agriculture, agricultural product logistics, contract farming and other functions as a high-tech agricultural industrial base. The photovoltaic agricultural house is a new type of photovoltaic system project that combines with agricultural production that has solar power generation on the roof and agricultural production in the shed. As a new model of modern agricultural development, it realizes clean energy power generation through the construction of rooftop photovoltaic power projects and eventually merges into the national grid. Photovoltaic agricultural houses focus on the combination of agriculture, ecology and tourism, using idyllic landscapes, agricultural production activities, agro-ecological environment and eco-agricultural business models, to attract tourists from surrounding cities to make short-term stays on weekends and holidays with characteristic tourism projects that are close to nature. With the maximization of resource usage, it gives advantages of agricultural and complementary tourism to promote the rapid development of the local tourism industry. This project is propose located Mukim Beriah, District Kerian, Perak D.R., Malaysia, with longitude of 1.4854° N and latitude of 103.7618° E, belonging to a tropical rainforest climate. The average altitude is 2 meters, and the conditions of light, water, humidity and heat are excellent. Annual average temperature of 30 ◦C, annual average sunshine 12.2 hours. The rainfall is abundant, and the annual rainfall is 2355.5 mm. The rainy season is mainly concentrated in the flood season during the October to January of the month, which is very beneficial to the development of tropical agricultural production conditions. The project is planned for 322 acres, which is mainly used for the construction of agricultural houses, roof photovoltaic power generation (solar energy), and plans to build 260 agricultural and solar complementary houses. Each photovoltaic agricultural house project covers an area of about 2400m2, agricultural houses 100% of solar photovoltaic modules are laid above the top, and the photovoltaic modules are at least 3.2 meters above the ground, which belongs to the demonstration project of facility agriculture. Photovoltaic highefficiency planting house is a combination of solar photovoltaic power generation and agricultural planting. The house is equipped with plant to fill light to achieve green, high yield, and high efficiency of agricultural planting. The building structure is a frame-shear structure, the structural design service life is expected to be 30 years, and the building seismic design category is category C. No Item’s name 1 PV modules 2 3 4 5 6 7 8 9 10 11 12 Unit set Quantity Specification 312498 Polycrystalline TSM320PD14 (320Wp, Di. 1956 × 992 × 40 mm, effi: 16.5%). Total area for installing PV module arrays is 101 ha (249,7acres) Optimum tiled angle degree 17o Pitch of PV module array m 6.51 (w=3.91m, D=6.51m, GCR=0.6) Inverters and AC set 45 Sunny Central 2200 Subsystems (power medium voltage station with transformer 0,4/33kV switchgear preinstalled) combiner boxes with set 45 string monitors integrated 33/230kV Switchyard ha 2 230kV overhead line km 4 Internal roads km 6.75 Surface width of 4m Management and m2 640 operation house Guard house m2 400 Material and equipment m2 400 store Fence km 4.67 Table 1.1 -Main parameters or equipment of the project No Main Items 1 Total area for installing PV module arrays, inverters with transformers 0,4/33kV and Internal roads 2 33/230kV Switchyard 3 PMU / Management and Operation area 4 Standby area Total = Project boundary Land –occupied area 103.9 ha 256.73 acres 2 ha 0.6 ha 4.94 acres 1.48 acres 4.8 ha 128 ha 11.86 acres 322 acres Table 1.2 – Land –occupied area of main items of the project. No Task name 1 Receiving Investment License/Certificates (MOA, PPA, BOT,) 2 Getting Letter of Commitment of Funding 3 EPC contractor selection, and site preparation 4 Construction period 5 Testing, commissioning, and COD 6 Expected commercial operation day Schedule March 2021 -July 2021 Notes 4 months July 2021 – Nov 2021 4 months Nov 2021 – Dec 2021 2 months Jan 2022 – Dec 2022 12 months Dec 2022 -Jan 2023 2 months First quarter of year 2023 Table 1.3 – Master schedule for project preparation and execution stages No. Descriptions A DIRECT CAPITAL COST 1 PV Module Inverters and AC Subsystem (power medium 2 voltage station with transformer 0,4/33kV switchgear preinstalled) 3 BOS Structural BOS for Mounting structure and Structural installation included ground leveling site preparation, 3.1 foundations of inverters, transformers, buildings, fence /security system, fire fighting system, etc. Electrical BOS (equipment of DC system, wiring, cables, combiner boxes with string monitor, 3.2 protection, switchgear, High Voltage transformer, SCADA,…) 3.3 230KV transmission line 4 Direct labor Costs 4.1 Labour for Installation, civil works and commissioning 4.2 Costs for cargo 4.3 Overhead & other for EPC 4.4 Contingency B INDIRECT CAPITAL COST 1 Permits and environmental studies 2 Monitoring and Inspection 3 Grid interconnection 4 Engineering design 5 Overhead and other for Developer Sub-total (A+B) 6 Land lease cost before O&M stage Total investment cost Cost (RM $) 270,000,000 30,000,000 300,000,000 No. 1. 2. 3. 4. 5. Indicators Value Power purchase price (UScent/kWh) 0.041 NPVf (Million Dollar) 38.19 FIRR (%) 14.83 % B/C 1.23 Payback Period (years) 11 Average Debt Service Coverage Ratio 6. (DSCR) 1.37 Table 1.5 – Financial indicators of Perak Solar Power Plant project (for base case) Power purchase price (UScent/kWh) 13.0 NPVe (Million Dollar) 9.71 B/Ce 1.04 Table 1.6 Economic indicators of Perak Solar Power Plant project No . 1 2 3 4 5 6 7 8 9 10 11 12 13 Main characteristics Values / Contents Intended rated capacity Investment form Project economic lifetime Location Land lease area Technological selection 100 MWp BOT 25 years Perak D.R. State 322 acres Total 312.498 Poly-crystalline silicon PV modules with 320Wp, efficiency 16.5% 45 Central inverter 2200kWac (power medium voltage station with transformer 0,4/33kV switchgear preinstalled) 17o with GCR 0.6 RM$ 300 Million 160,129 MWh/year Optimum tilted angle and GCR Total investment cost Annual Energy injected in grid (50% probability) Grid connection solution Single 230kV transmission line to Bukit Merah, Beriah Substation Financial indicators at base NPV = 38.19 million dollar case (with power purchase price IRR = 6.72 % of 13 cents/kWh) Modified B/C = 1.23 Payback period = 11 years Average of DSCR=1.37 Power purchase price negotiated at least 13.08 US suggested cents/kWh Expected commercial operation First quarter of year 2022 day Chapter 2 Agriculture Products and Services 2.1 Product category The products of the project are diversified, mainly vermicomposting, planted with fruits and corn, various organic vegetables, organic moringa, dendrobium officinale, golden squash, passion fruit, lemongrass etc. 1. Colored corn: Colored corn has higher nutrient content than ordinary corn, plus simple planting methods, is suitable for fresh food and processing and refining anthocyanin. The economic benefits from the cultivation of colored corn is multiple in compared to the ordinary corn cultivation. Therefore, the cultivation and processing of colored corn is one of the agricultural projects with broad development and utilization prospects in Malaysia and even Southeast Asia and Asian markets. Fruit corn can be sold directly after harvesting or can be processed by yourself. Processing methods range from simple to complex and can be selected according to specific requirements. After years of development, fruit corn has spread all over the world and has become a special fruit and vegetable corn for mass consumption. 2. Organic vegetables: Organic vegetables are currently an international reference to non-polluting, naturally grown vegetables. It restricts the use of pesticides, fertilizers, growth regulators, and other chemicals during the planting process, nor can they use genetically modified technology, without the being certified by an independent agency. There is an increasing demand for safe food, and the cultivation of organic vegetables focuses on safe and natural production methods, which can promote and maintain an ecological balance. Organic vegetables have no chemical residues and have been proven to be more nutritious than ordinary vegetables. Organic food is hailed as a "sunrise industry" and has a broad market. An analysis of a report published by the Food and Agriculture Organization of the United Nations shows that in the past 10 years, in the markets of some countries, the annual growth rate of sales of organic agricultural products has exceeded 20%. This is in stark contrast to the stagnation of some conventional food markets. In Europe and America, organic vegetables are the fastest growing industry. In the past six years, sales have increased at a rate of 20% per year. According to the climate conditions and natural environment of Perak D.R. State, there are many cultivable vegetable varieties. We will focus on selecting new, high-yielding, and good-efficient vegetable varieties for cultivation according to local conditions. 3. Vermicomposting earthworm Vermicomposting has gained popularity in both industrial and domestic settings because, as compared with conventional composting, it provides a way to treat organic wastes more quickly. In manure composting, it also generates products that have lower salinity levels. Chapter 3 Benefit Analysis 3.1 Economic benefits The installed capacity of the project is 100MW, with an average annual power generation capacity of 325 million kWh in 21 years. The minimum electricity price in Malaysia is 4 cents/kWh, and total revenue of RM$ 560.910 million in 21 years of electricity sales is estimated. A total of about RM$ 57.3077 million in tax revenue was created for Perak D.R. State. 3.2 Social benefits (1) The construction of this project can develop low-carbon economy, promote energy conservation and emission reduction, alleviate energy and environmental crises, realize industrial structure adjustment and industrial upgrading opportunities, implement the scientific development concept, and realize the social benefits of sustainable development in Perak State. (2) The project construction can obtain social benefits of coping with climate change and participating in international cooperation and competition. (3) This project can expand the domestic demand for photovoltaic products, promote the healthy development of the photovoltaic industry and related industrial chains, and ease the social benefits of the negative impact of the international economic crisis on my country's photovoltaic industry. (4) This project will accelerate the sustainable development of the economy of Perak D.R. State and improve the people's living standards, which thereby obtain the social benefits of strengthening the unity of the people, ensuring social stability and building a harmonious environment. (5) The completion of the house in this project will improve the agricultural productivity level of the project location, transforming the planting mode of one year to all year round’s uninterrupted planting. The crops will be transformed from single planting to diversify planting. In addition, animal husbandry may be appropriately introduced to accelerate the development of the agricultural economy in Perak D.R. State. (6) After the completion of the construction of some agricultural houses in this project, the agricultural companies can hire locals for planting and breeding. The agricultural companies hiring increases the local employment rate (the project can increase more than 300 local jobs); transform individual agriculture into collective agriculture and improve agriculture production efficiency, while increasing state and local government revenue. Attached: Opinions No Description Unit Value Project analyse 1 Capacity MW 100 2 Operation period Year 25 3 Investment RM$ 300,000,000,000 4 Unit/Price $/W 2.7 5 Yearly average production KW.h 144976000 6 Average tariff yearly $/KW.h 0.1722 7 Income RM$ M 24,964 8 Operation cost (plus land) RM$ M ? 9 Operation profit RM$ 13,662 10 ROI Year 10 11 Yearly internal return(FIRR) % 7.08 1. The model only considers photovoltaic power plants, without taking into account the income and costs of agriculture; Calculation table of energy saving and emission reduction of solar photovoltaic system Item Unit Value Generate capacity Annual average power generation of the system Annual saving of raw coal Annual savings of standard coal Reduce CO2 emissions every year Annual reduction of S02 emissions Reduce nitrogen oxide emissions annually Reduce carbon emissions every year KW 100000 Ten thousand KWh 13029.28 Kg Kg 72962.53 52117.13 Kg 129901.95 Kg 3908.78 Kg 1954.39 Kg 35439.65 2. According to the current electricity purchase price in Malaysia and our calculation model, the internal rate of return (IRR) of this project is 7.08%. 3. According to the investment amount of RM$ 2.318/W, the data is a bit conservative. It is necessary to consider the related cost before obtaining the PPA.