Dubai South Mall Main Contract Works Expo 2020, Dubai, United Arab Emirates Risk Assessment Project Name: Dubai South Mall Project @ EXPO 2020 DUBAI Ref. No.: QC MS 25 rev 3 Operation / Tasks: Site Re-Mobilization Works Date : SN Task/ Activity and Location Potential Hazards Potential Harms/ Damages Risk Rating (P) (S) Rating (P X S) Control Measures (Refer to Hierarchy of Control) 22.12.18 Residual Risk Responsibility Action Date (P) (S) Rating (P X S) Risk Acceptable (Yes/No) 1 4 4 Yes Site Engineer / Supervisor Daily basis 1 3 3 Yes Site Engineer, Supervisor, crane operator Daily basis Levelling and compaction work 1 Levelling and compaction work 02 Shifting materials by mobile crane Page 1 of 8 Hit with other vehicle and Workers Un-even surface Road traffic incident and injury 3 4 12 Injury to operator / Crane damages 2 4 8 1.Shovel and Bob cat Should have the valid third party annual examination certificate from DAC accredited agencies 2. Valid RTA License holder with valid thirdparty training certificate from DAC accredited agencies are engaged as operator 3. Shovel and Bob cat are inspected on daily by driver and monthly by HSE & plant division. 4. Vehicle should be inspected by the operators on daily basis by using Daily prestart briefing check-list and it will be verified by HSE Department 5. Automatic Reverse horn are placed in wheel loader and Bobcat 6. Flagman are engaged with wheel loader to guide the operator 7. Pedestrian access to be made and workers are not allowed to work Levelling operated area. This will be supervised by Site Engineers and HSE officers. 1. Shifting permit will be issued by HSE Department 2.Area are compacted and crane to be placed on compacted area only. Form # HSEQ – HSERA(Rev 3 – Feb 17) Dubai South Mall Main Contract Works Expo 2020, Dubai, United Arab Emirates Risk Assessment Cranes are not in acceptable level/ in competent operator Page 2 of 8 Injury to worker and damage to crane and cabin Damaged lifting tools and Tackles Fall of material from crane and Injury to worker and damage to cabin Over loading the crane / lifting tool Fall of material from crane and Injury to worker and damage to cabin 2 3 2 4 4 4 8 12 8 3. Ensure that out triggers are extended fully 3.Outriggers pads are placed in the underneath of the crane out triggers 1. Crane and operator should have valid registration and driving license as per RTA Regulations. 2. Crane should have valid third party annual examination certificate from DAC accredited agencies 3. Crane operator should have valid thirdparty training certificate from DAC accredited agencies. 4. Crane are inspected on daily by operator and monthly by plant division. 5. Crane more than 25 years are not allowed to use in the site 6. Vehicle should be inspected by the operators on daily basis by using Daily prestart briefing check-list and it will be verified by HSE Department 1.Lifting tools should have valid thirdparty Bi-annual examination certificate from DAC accredited agencies. 2.Lifting tools are inspected on monthly basis and color coding system will be followed 3.Lifting tools and tackles should be inspected on daily basis by rigger 1. Trained appointed persons and lifting supervisor are engaged. 2.Appointed persons do the lifting permit by considering the operating radius and boom length 3. SWL Monitor is installed in the crane. 4. Lifting tools and tackles will be selected as per weight of the load. 1 4 4 Yes Site Engineer / Plant Engineer Daily basis 1 4 4 Yes Site Engineer / Plant Engineer Daily basis Yes Site Engineer / Appointed person / Lifting Supervisor Daily basis 1 4 4 Form # HSEQ – HSERA(Rev 3 – Feb 17) Dubai South Mall Main Contract Works Expo 2020, Dubai, United Arab Emirates Risk Assessment 03 shifting by trailers Adverse weather conditions Crane collapse. Injury to operator and damages in crane 2 4 8 Hit with other vehicle and Workers Road traffic incidents and injury 3 4 12 Over speeding / Lack of access 04 Shifting the materials by boom loader Page 3 of 8 Toppling of boom loader Collision with other vehicles/workers, Road traffic incident and injury 3 4 12 Serious accidents 3 5 15 5. All lifting activities are carried out after taking Lifting permit from the appointed person only 1. Crane works will be stopped if the wind speeds exceed 38KPH. 2.Wind speed indicator are available in the Tower crane -02 and 04 to monitor the same 3. Crane works will be stopped during rain and dusty weather conditions. 1. All vehicles are having the valid registration as per RTA Regulations 2. Vehicle inspection are done on daily basis by the driver 3. Monthly vehicle inspection are done by HSE Department along with co-ordination of plant department and approved vehicles are allowed to deploy in the site with identification sticker. 1. Follow speed limit of 20km/hr as per EXPO requirement 2. Valid driving license holders are engaged as driver per RTA Regulations. 3. Driver are trained on defensive driving by HSE Department 4. Survey are done for trailer movement area by HSE officer and Site Engineer 1.Only block work pallet are allowed to lift by using Boom loader fork and it should be tied 2. Any shutters and other materials should be lifted by using the slings. 2. Materials in the boom loader will be tied to avoid any fall of materials. 3. Trained Riggers will be used to tie slings incase required. 4. Wall shutters, column shutters will be shifted by boom loader by using the slings 1 4 4 Yes Site Engineer / Appointed person / Lifting Supervisor Site Engineers, Supervisors 1 4 4 Yes 2 3 6 Yes Site Engineer, Supervisor, 2 3 6 Yes Site Engineer, Supervisor, Form # HSEQ – HSERA(Rev 3 – Feb 17) Daily basis On daily basis On daily basis On daily basis Dubai South Mall Main Contract Works Expo 2020, Dubai, United Arab Emirates Risk Assessment Over speeding Incompetent operators 05 Dismantling and Erection of Prayer room Page 4 of 8 Working in Height locations. Serious accidents Serious accidents Fall of persons 3 3 3 5 5 5 15 15 15 and shutter materials more than 3 mtr will not lifted by boom loader 5. Boom loaders are allowed to run only in the levelled and compacted surface. 6.Emergency preparedness plan will be implemented in the site. 7.Operator must wear the seat belt while operating it. 8. Operator cabin must be protected with cage. 9. Operator cabin must be kept close in all the times. 1. Follow speed limit of 20km/hr as per EXPO requirement 2. Valid driving license holders are engaged as driver per RTA Regulations. 3. Boom loader are trained on defensive driving 4. Survey are done for boom loader movement area by HSE officer. 5. Third party test certificate will be verified for that vehicle. 1.Valid driving license holders are engaged as driver per RTA Regulations 2.Third party test certificate will be verified for that vehicle and driver. 3. Drivers will be interviewed and screened by their competency by plant division and HSE Department and further evaluation will be done by Site Engineer 1.Trained scaffolders will be used to dismantle the scaffold. 2. Mobile scaffold will be used to dismantle the prayer room with support of outtriggers. 3. Safety harness will be used by scaffolders while working in the height 2 3 6 Yes Site Engineer, Supervisor, 2 3 6 Yes Site Engineer, Supervisor, 2 3 6 Yes Site Engineer, Supervisor, Form # HSEQ – HSERA(Rev 3 – Feb 17) On daily basis On daily basis On daily basis Dubai South Mall Main Contract Works Expo 2020, Dubai, United Arab Emirates Risk Assessment locations. 4. Casting will be carried-out on the ground floor. 06 07 Barriers Erection Laying of MEP Services and commissionin g Testing of Electrical and Firefighting line Page 5 of 8 Loose materials Flying of materials 2 5 10 Manual handling Manual handling hazards 2 3 6 Sharp edges, Hand tools Physical Injury 3 2 6 Underground cable / Utilities Electrical Shock / Property damage 3 4 12 Accidental start-up Electric shock / Release of water in pressure 3 4 12 1.All loose sheets will be tied to avoid flying in the materials 1.Shovel or bobcat will be used to shift the barriers 1. Only inspected and approved hand tools are allowed to use. (Homemade hand tools are not allowed to use). 2. Hand tools are to be inspected on monthly basis. 3. Always use the Hand gloves while handling pipes. 1. Excavation work-permit is followed. Excavation permit is used after crosschecking the As-built drawing. 2. Trail pit to be done in the suspicious areas by using the un-sharp tools with rubber hand-gloves. 3. No excavator will be placed if the underground utilities and cable is found. 4. Excavation works will only be carried out under a ‘Permit to Excavate’ system and it should be available with excavator operator. 1. LOTO procedure to be followed while testing the Electrical and firefighting line. 2. Only Electrical and Mechanical engineers are authorized to test the system. 3. Work-permit and LOTO to be followed to work any commissioned electrical and fire-fighting line 2 3 6 Yes Site Engineer, Supervisor, 2 3 6 Yes Site Engineer, Supervisor, 2 2 4 Yes Site Engineer, Supervisor, 1 4 4 Yes Engineer, Supervisor On daily basis 1 4 4 Yes Electrical / Mechanical Engineer daily basis Form # HSEQ – HSERA(Rev 3 – Feb 17) On daily basis On daily basis Dubai South Mall Main Contract Works Expo 2020, Dubai, United Arab Emirates Risk Assessment Usage of power tools Usage of Electrical equipment Electrical shock & Fire 3 4 12 1.110 volt portable power tools are only allowed to use. 2. All Electrical appliance will be routed through residual current and overload protection device like RCCB and MCB. 3. IP protection (Fire resistant and water ingress) DBS are used to tape electrical power. 4. Earthing are ensured for all Electrical appliances like DG and DB, 5. Monthly inspection are carried-out for all power tools and identification stickers will be given with different colors on monthly basis. Damaged power tools will not be given with stickers. 6. Power sockets are not allowed to over load. 7. Industrial type plugs and sockets are used 8. PAT test are done for all Power driven tools. 2 3 6 Yes Site Engineer, Electrical Engineer Notes: (Legal Compliance) The following legislation must be complied with at all times 1. U.A.E Ministry of Labour and Social Affairs, Federal Law No 8, Year 1980 Ministerial Order No 32 – 1982 2. Federal Law No. 24 of 1999 for the Protection and Development of the Environment, UAE Official Gazette, Issue No. 340, Yr. 8, October 1999. 3. DM Construction code of safety Practice 4. Expo 2020 standards. Assessed by: Name : J.Jayakarthic Designation: HSE Manager Sign & Date : Page 6 of 8 Reviewed by: Name : Mohammed Kilani Designation: .Construction Manager Sign & Date : Approved by: Name : Hayman Ahmed Designation: Project Director Sign & Date : Date of next review: Form # HSEQ – HSERA(Rev 3 – Feb 17) On daily basis Dubai South Mall Main Contract Works Expo 2020, Dubai, United Arab Emirates Risk Assessment Probability (P) Page 7 of 8 Severity (S) Form # HSEQ – HSERA(Rev 3 – Feb 17) Dubai South Mall Main Contract Works Expo 2020, Dubai, United Arab Emirates Risk Assessment Risk Rating Hierarchy of Control Page 8 of 8 Form # HSEQ – HSERA(Rev 3 – Feb 17)