B. FRAUD Legaspi Oil Co., Inc. v Court of Appeals, GR No. 96505, 01 July 1993 Facts: Petitioner Legaspi Oil Company had several transactions with Oseraos through the agents of the latter. The transactions involve the sale of copras (coconut husk) by private respondent to the petitioner. The selling price of Oseraos for every 100 kilos of copras depends on the prevailing market price at the time the contract was entered into. In one transaction, Oseraos committed to sell 100 tons of copra to Legaspi Oil for the price of P82 per 100 kilos with delivery terms of 20 days effective 8 March 1975. After the period to deliver had lapsed, Oseraos was only able to sell 46,334 kilos of copra thus leaving a balance of 53,666 kilos as per running account. Accordingly, demands were made upon Oseraos to deliver the balance with a final warning embodied in a letter dated 6 October 1976 that failure to deliver will mean cancellation of the contract, the balance to be purchased at open market and the price deferential to be charged against Oseraos. Since there was still no compliance, Legaspi Oil purchased the undelivered balance from the open market at the prevailing price of P168.00 per 100 kilos, or a price differential of P86.00 per 100 kilos, a net loss of P46,152.76 chargeable against private respondent. Issue: WoN Oseraos is liable for damages arising from fraud or bad faith in deliberately breaching the contract of sale entered into by the parties. Held: Despite repeated demands by petitioner, private respondent failed to fulfill his contractual obligation to deliver the remaining 53,666 kilograms of copra. Based on the foregoing facts, the actuality of private respondent’s fraud cannot be gainsaid. In general fraud may be defined as the voluntary execution of a wrongful act, or a willful omission, knowing and intending the effects which naturally and necessarily arise from such act or omission. The conduct of the private respondent clearly manifests his deliberate faudulent intent to evade his contractual obligation for the price of copra had in the meantime more than doubled from P82.00 to P168.00 per 100 kilograms. Under Art. 1170 of the Civil Code, those who in the performance of their obligation are guilty of fraud, negligence, or delay, and those who in any manner contravene the tenor thereof, are liable for damages. Pursuant to said article, private respondent is liable for damages. RCBC vs CA G.R. No 133107, March 25, 1999 Facts: Petitioner and private respondent stipulated a contract of sale, where payment of latter consisted of an initial lump sum and monthly installments, which he already made in post-dated checks. They also executed a contract of chattel mortgage (the car itself) stating that in the event of private respondent’s default, he is bound to pay the entire remaining balance, along with the interests of the balance. Unfortunately, one of the checks were left unsigned, thus money debited from private respondent was returned in his account. Later thereafter, petitioner declared him in default Remedies: Regional Trial Court (won by PRIVATE RESPONDENT) Court of Appeals (won by PRIVATE RESPONDENT) Issue: Given of the facts, the questions posed is whether or not the unsigned check causes respondent to be in default, and (underlying issue?) whether or not the chattel mortgage should be enforced. Rule: Art. 1159 of the Civil Code provides contractual obligations must be complied with good faith. Also, Art. 1370 provides that if the terms of a contract are clear and leave no doubt of intention of the contracting parties, the literal meaning shall control. Application: In this case, petitioner could have simply communicated such error to private respondent and asked for the signature. Instead, the former chose to inform him late that he “defaulted” from his payments, clearly an absence of good faith (Art. 1159). Also, it is clearly indicated that the chattel mortgage should only be enforced in the event that private respondent fails to pay for any of the installments (Art. 1370). He however did not fail to pay, given of the existence of sufficient funds, only the absence of required signature. Conclusion: From the foregoing, it is likely the Court may declare him not in default, and the mortgage will not be enforced. c. NEGLIGENCE Tort distinguished from breach of contract JUAN J. SYQUIA, CORAZON C. SYQUIA, CARLOTA C. SYQUIA, CARLOS C. SYQUIA and ANTHONY C. SYQUIA vs. THE HONORABLE COURT OF APPEALS, and THE MANILA MEMORIAL PARK CEMETERY, INC. G.R. No. 98695, January 27, 1993, J. Campos, Jr. FACTS: Juan Syquia, father of the deceased Vicente Syquia, entered in a contract of Deed of Sale and Interment Order with Manila Memorial Park Cemetery Inc (MMPCI). In the contract, there contained a provision which stated that the coffin would be placed in a sealed concrete vault to protect the remains of the deceased from the elements. During the preparation for the transfer of Vicente’s remains in the newly bought lot in Manila Memorial, it was discovered that there was a hole in the concrete vault which caused total flooding inside, damaged the coffin as well as the body of the deceased and covered the same with filth. Syquia filed a complaint for recovery of damages arising from breach of contract and/or quasi-delict against the MMPCI for failure to deliver a defect-free concrete vault to protect the remains of the deceased. In its defense, MMPCI claimed that the boring of the hole was necessary in order to prevent the vault from floating when water fills the grave. The trial court dismissed the complaint holding that there was no quasi-delict because the defendant is not guilty of any fault or negligence and because there was a pre-existing contract between the parties. The CA affirmed the decision of the trial court. Hence, the present petition. ISSUE: Whether or not the private respondent is guilty of tort HELD: Denied. Decision of the CA affirmed. We are more inclined to answer the foregoing questions in the negative. There is not enough ground, both in fact and in law, to justify a reversal of the decision of the respondent Court and to uphold the pleas of the petitioners. Although a pre-existing contractual relation between the parties does not preclude the existence of a culpa aquiliana, We find no reason to disregard the respondent’s Court finding that there was no negligence. “Article 2176. Whoever by act or omission causes damage to another, there being fault or negligence, is obliged to pay for the damage done. Such fault or negligence, if there is no preexisting contractual relation between the parties, is called a quasi-delict x x x.” In this case, it has been established that the Syquias and the Manila Memorial Park Cemetery, Inc., entered into a contract entitled “Deed of Sale and Certificate of Perpetual Care” on August 27, 1969. That agreement governed the relations of the parties and defined their respective rights and obligations. Hence, had there been actual negligence on the part of the Manila Memorial Park Cemetery, Inc., it would be held liable not for a quasi-delict or culpa aquiliana, but for culpa contractual as provided by Article 1170 of the Civil Code, to wit: “Those who in the performance of their obligations are guilty of fraud, negligence, or delay, and those who in any manner contravene the tenor thereof, are liable for damages.” METROPOLITAN BANK AND TRUST COMPANY v. COURT OF APPEALS GR. No. 112576, October 26, 1994 ROMERO, J.: (Bank’s Negligence as Source of Liability) FACTS: Isabel Katigbak, president and owner of 65% shares of Rural Bank of Padre Garcia, Inc., maintains a current account with Metropolitan Bank and Trust Company. MBTC received from Central Bank a credit memo that its demand deposit account was credited with P304k for the account of RBPG, representing loans granted by the CB. On the basis of the credit memo, Katigbak issued several checks against its account with MBTC, two of which were payable to Dr. and Mrs. Roque. The checks were deposited with Philippine Banking Corp. however the same bounced when they were forwarded to MBTC. It was twice dishonored. Dr. Roque went to RBPG for the bounced checks. RBPG paid Dr. Roque an amount of P50k representing the checks. Katigbak, who was on vacation in Hongkong with her family, received an overseas call from Mrs. Maris Katigbak-San Juan at her residence in Makati that Mr. Dungo, Asst. Cashier of MBTC, berating her about the bounced checks and saying “Nagissue kayo ng tseke, wala naming pondo”. Mrs. San Juan was instructed by Katigbak to check and verify regarding the credit memo of CB for P304K in favor of RBPG as she was certain that the checks were covered by the credit memo. Mrs. San Juan another insulting phone call from Mr. Dungo (“Bakit kayo nag-iisue ng tseke na wala namang pondo, P300K na”). He also brushed aside the request to check and verify the credit memo, telling her sarcastically that he was very sure that no such credit memo existed. Katigbak had to cut short her vacation and went back home. She then called MBTC and she was able to talk to Mr. Dungo who arrogantly said “Bakit kayo magagalit, wala naman kayog pondo?” This shocked Katigbak which caused her blood pressure to rise to a dangerous level and she had to undergo medical treatment at the Makati Medical Center for two days. MBTC did not only dishonored the check, it also issued four debit memos representing service and penalty charges for the returned checks. Katigbak filed the civil case in RTC Lipa against MBTC for damages. RTC rendered decision in favor of petitioner. The same was affirmed by CA with deletion as to temperate damages, and deduction as to amount of moral damages. ISSUE: Is there a basis as to negligent act of MBTC as the ground for the awarding of damages in the civil suit of Katigbak? HELD: YES. The presence of malice and the evidence of besmirched reputation or loss of credit and business standing, as well as a reappraisal of its probative value, involves factual matters which have been determined by the lower court. There is no merit in petitioner’s argument that it should not be considered negligent, much less be held liable for damages on account of inadvertence of its bank employee as Art. 1173 of the Civil Code only requires it to exercise the diligence of a good pater familias. The dishonoring of the respondent’s checks committed through negligence by the petitioner was rectified nine days after receipt of the credit memo. MBTC was remiss in its duty and obligation to treat private respondent account with the highest degree of care, considering the fiduciary nature of their relationship. The bank is under the obligation to treat the accounts of its depositors with meticulous care. Responsibility arising from negligence in the performance of every kind of obligation is demandable. While the bank’s negligence may not have been attended with malice and bad faith, nevertheless, it caused serious anxiety, embarrassment and humiliation to private respondents for which they are entitled to recover reasonable moral damages. Insult was added to injury by petitioner bank’s issuance of debit memoranda representing service and penalty charges for the returned checks, not to mention the insulting remarks from its Asst. Cashier. Moral and temperate damages which are not susceptible of pecuniary estimation are not awarded to penalize the petitioner but to compensate the respondents from injuries suffered as a result of the former’s fault and negligence. AFFIRMED. PHILIPPINE NATIONAL BANK, petitioner, vs. COURT OF APPEALS and LILY S. PUJOL, respondents. [G.R. No. 126152. September 28, 1999] FACTS: Sometime prior to 23 October 1990 private respondent Lily S. Pujol opened with petitioner PNB Mandaluyong an account denominated as "Combo Account," a combination of Savings Account and Current Account in private respondent's business name "Pujol Trading," under which checks drawn against private respondents checking account could be charged against her Savings Account should the funds in her Current Account be insufficient to cover the value of her checks. Hence, private respondent was issued by pthe etitioner a passbook on the front cover of which was typewritten the words "Combo Deposit Plan." On 23 and 24 October 1990, a private respondent issued a check in the amount of P30,000.00 each in favor of her daughter-in-law, Dr. Charisse M. Pujol and daughter Venus De Ocampo, respectively. When issued and presented for payment, private respondent had sufficient funds in her Savings Account. However, the petitioner dishonored her check allegedly for insufficiency of funds and debited her account with P500.00 as a penalty charge (P250 each per check transaction). On 4 November 1990, after realizing its mistake, the petitioner accepted and honored the second check for P30,000.00 and re-credited to private respondents account the P250.00 previously debited as penalty. Private respondent Lily S. Pujol filed with Pasig RTC a complaint about moral and exemplary damages against the petitioner for dishonoring her checks despite the sufficiency of her funds in the bank. Petitioner bank admitted in its answer that private respondent Pujol opened a "Combo Account," a combination of Savings Account and Current Account, with its Mandaluyong branch. It however justified the dishonor of the two (2) checks by claiming that at the time of their issuance private respondent Pujols account was not yet operational due to lack of documentary requirements. On 27 September 1994 the trial court (RTC) rendered a decision ordering petitioner to pay private respondent Pujol moral damages of P100,000.00 and attorneys fees of P20,000.00. CA affirmed RTC’s decision in toto. ISSUE: W/N the appellate court (C/A) erred in holding that petitioner was estopped from denying the existence of a "Combo Account" and the fact that it was operational at the time of the issuance of the checks in not holding that the award by the trial court of moral damages of P100,000.00 and attorneys fees of P20,000.00 was inordinately disproportionate and unconscionable. RULING: We cannot sustain the petitioner. Although the petitioner presented evidence before the trial court to prove that the arrangement was not yet operational at the time respondent issued the two checks, it failed to prove that she had actual knowledge that it was not yet operational at the time she issued the checks considering that the passbook in her Savings Account already indicated the words "Combo Deposit Plan." Hence, respondent Pujol had justifiable reason to believe that her accounts were effectively covered by the arrangement during the issuance of the checks. Either by its own deliberate act, or its negligence in causing the "Combo Deposit Plan" to be placed in the passbook, petitioner is considered estopped to deny the existence of and perfection of the combination deposit agreement with respondent Pujol. A bank is under obligation to treat the accounts of its depositors with meticulous care whether such account consists only of a few hundred pesos or of millions of pesos. Responsibility arising from negligence in the performance of every kind of obligation is demandable. While petitioners negligence in this case may not have been attended with malice and bad faith, nevertheless, it caused serious anxiety, embarrassment and humiliation to private respondent Lily S. Pujol for which she is entitled to recover reasonable moral damages. RTC and CA decision affirmed. PNB vs CA - SYPNOSIS Spouses Antonio M. Chua and Asuncion M. Chua were the owners of a parcel of land covered by Transfer Certificate of Title No. P-142. Upon Antonio's death, the probate court appointed his son, Allan M. Chua, as special administrator of his estate. It also authorized Allan to obtain a loan accommodation of five hundred fifty thousand pesos (P550,000) to be secured by a real estate mortgage over the above-mentioned parcel of land. Pursuant thereto, on June 29, 1989, Allan obtained a loan of P450,000.00 from the Philippine National Bank (PNB). However, for failure to pay the loan in full, the bank extrajudicially foreclosed the real estate mortgage. During the auction, PNB was the highest bidder with a bid price P372,825.63. Subsequently, to claim the deficiency, PNB instituted an action with the Regional Trial Court (RTC), Branch 10 of Balayan, Batangas, against both Mrs. Asuncion M. Chua and Allan M. Chua in his capacity as special administrator of his father's estate. Despite summons having been duly served, Asuncion Chua and Allan Chua did not answer the complaint. The trial court declared them in default and received evidence ex parte. Thereafter, the RTC rendered its decision, ordering the dismissal of PNB's complaint. The Court of Appeals affirmed the RTC decision. Hence, the PNB filed the instant petition. cHaADC The Court ruled that case law now holds that Section 7 of Rule 86 of the Rules of Court rule grants to the mortgagee three distinct, independent and mutually exclusive remedies that can be alternatively pursued by the mortgage creditor for the satisfaction of his credit in case the mortgagor dies, among them: (1) to waive the mortgage and claim the entire debt from the estate of the mortgagor Modes of Breach: Contravention of the Tenor No. L-73867 Telefast Communication/Philippine Wireless Inc. vs Castro, Sr. J. Herrera Petitioner is being charged by Sandiganbayan for failing to secure the truck seized from Ancla by the BIR for failure to pay taxes. IMPORTANT PEOPLE Telefast: petitioner/defendant-appellant Ignacio Castro, Sr.: respondents/plaintiffs-appellees FACTS 1. petition for review on certiorari on the decision of Intermediate Appellate Court 2. Sofia Crouch, daughter of Castro announced the death of her mother through telegram, which was accepted by defendant in its Dagupan Office but the telegram never reached hence the funeral of the mother was not attended by Castro and the other children who were all residing in the US 3. daughter only discovered that the telegram wasn't received so she and the plaintiffs brought action for damages; case was filed in CFI Pangasinan 4. defense of defendant: technical and atmospheric factors beyond its control; but it did not advise Sofia 5. CFI Pangasinan ordered defendant to pay plaintiffs damages 6. petitioner appealed and the Intermediate Appellate Court affirmed the decision but modified the award of damages 7. compensatory damages to Sofia and exemplary damages were eliminated, and moral damages were reduced 8. petitioner appealed from the modified judgment of the appellate court contending that moral damages should be eliminated since its negligent act was not motivated by fraud, malice or recklessness; it can only be held liable for the fees paid by Sofia for the telegram ISSUE with HOLDING W/N petitioner is not liable for moral damages (NO) ● Art. 2176 Civil Code: whoever by act of omission causes damage to another, there being fault or negligence, is obliged to pay for the damage done ● petitioner and respondent entered into a contract whereby for a fee, petitioner undertook to send respondent's message ● petitioner did not do so despite respondent's performance of obligation (paying the fee) thus petitioner is guilty of contravening its obligation and is liable for damages ● liability is not limited to actual or qualified damages ● Article 2217 Civil Code: Moral damages include physical suffering, mental anguish, fright, serious anxiety, besmirched reputation, wounded feelings, moral shock, social humiliation, and similar injury. Though incapable of pecuniary computation, moral damages may be recovered if they are the proximate results of the defendant's wrongful act or omission. ● petitioner's act or omission was the cause of respondent's suffering ● trial court's award of compensatory damages is upheld, as well as exemplary damages DISPOSITIVE PORTION petition is denied and decision appealed from is modified NANCY GO & ALEX GO versus C.A. et al. GR No. 114791; May 29, 1997 FACTS: Private respondents contracted with the petitioner for the video coverage of their wedding. Three times thereafter, the newlyweds tried to claim the videotape, which they planned to show to their relatives in the US, and thrice they failed because the tape was apparently not yet processed. Upon their return, they found out that the tape had been erased by petitioners and therefore, could no longer be delivered. Private respondents filed a complaint about specific performance and damages against petitioners, which was granted by the RTC and affirmed by the CA. Hence, this petition. ISSUE Whether or not Nancy and Alex Go should be held liable for the damages sought RULING Yes. It is contrary to human nature for any newlywed couple to neglect to claim the video coverage of their wedding; the fact that private respondents filed a case against petitioners belies such assertion. Clearly, petitioners are guilty of actionable delay for having failed to process the video tape. Considering that private respondents were about to leave for the United States, they took care to inform petitioners that they would just claim the tape upon their return two months later. Thus, the erasure of the tape after the lapse of thirty days was unjustified. In this regard, Article 1170 of the Civil Code provides that “those who in the performance of their obligations are guilty of fraud, negligence or delay, and those who is any manner contravene the tenor thereof, are liable for damages.” In the instant case, petitioners and private respondents entered into a contract whereby, for a fee, the former undertook to cover the latter’s wedding and deliver to them a video copy of said event. For whatever reason, petitioners failed to provide private respondents with their tape. Clearly, petitioners are guilty of contravening their obligation to said private respondents and are thus liable for damages. Fortuitous Event ACTIONS FOR UNDOING OF POOR WORK Tanguilig vs CA 117190 Bellosillo, J Petitioner entered into a contract to construct a windmill for private respondents. subject windmill was destroyed by a “strong wind”. Court demands petitioner to reconstruct windmill. Important People Jacinto Tanguilig- owner JMT Eng’g and General Merchandise(pet) Vicente Herce Jr- availed services of JMT, (resp) FACTS 1. Parties entered into a contract to build a windmill. Tanguilig offered to construct in consideration of P60,000 from Herce Jr. Contract came with a 1-year guarantee; 2. Herce Jr tendered dp 30k, and another installment of 15k. Balance of 15k was not paid; 3. Tanguilig filed a complaint to collect the unpaid sum of 15k from Herce Jr; 4. In his answer, Herce Jr alleges he already paid said sum to certain Mr. Pili owner of SPGMI in consideration of a deep well constructed as a part of the windmill project. He claims therefore that he has fulfilled his obligation and that in any case his non-payment of the balance should be offset by the defects of the windmill which lead it to collapse after a strong wind struck their place Furthermore, the petitioner states that non-payment may also because of the destruction of the windmill, which he claims a cause of the fortuitous event 5. RTC ruled in favor of pet by finding no agreement between Tanguilig and Herce Jr to construct a well, that it was not part of their contract contrary to Mr Pili’s claim that he was commissioned by the pet. It also found no clear and convincing proof that the windmill fell down due to a defect in its construction; 6. CA reversed, finding the deep well was included in the contract to build the mill and that there can be no finding of force majeure that could free Tanguilig from his liability to reconstruct; 7. Tangulig finds error in the CA’s reversal Issue: Given these set of facts, the questions posed is whether or not such construction of the windmill included the installation of deep well (underlying issue: which may institute respondent to commission it to another – if it was allowed.) and whether petitioner is under obligation the reconstruction. Rule: Art. 1371 of the Civil Code provides that the parties’ contemporaneous and subsequent acts shall be the consideration to judge intention of contracting parties. Next, Art. 1240 provides that payment shall be made to the person whose favor the obligation has been constituted or any person authorized to receive it. Then, Art. 1174 provides that no person shall be responsible for events that could not be foreseen or inevitable. Finally, Nakpil v CA provides for the precepts to who may avail defense of a “fortuitous event.” Application: In this case, the words “suitable for” and “for” in the proposal were meant to convey the idea it appropriateness for a deep well. Also acts before and after the contract does not uphold the respondent’s defense (Art. 1371). Consequently, Art. 1240 cannot be raised for two reasons: (1) obligation did not include construction of the deep well, (2) no substantial proof that he was authorized to receive such payment in lieu of petitioner. Onto the second issue, Art. 1174 cannot be invoked because it was proven that it was not a typhoon that wrecked the windmill but a strong wind, which does not constitute a fortuitous event. Conclusion: From the foregoing, it is likely that the Court will award the petitioner of the balance. However, he is liable for the reconstruction of the windmill WHEREFORE, the appealed decision is MODIFIED. Respondent VICENTE HERCE JR. is directed to pay petitioner JACINTO M. TANGUILIG the balance of P15,000.00 with interest at the legal rate from the date of the filing of the complaint. In return, the petitioner is ordered to "reconstruct subject defective windmill system, in accordance with the one-year guaranty and to complete the same within three (3) months from the finality of this decision. RELEVANCE TO THE LESSON: Art 1167, supra Art. 1169. Those obliged to deliver or to do something incur in delay from the time the obligee judicially or extra-judicially demands from them the fulfillment of their obligation.- However, the demand by the creditor shall not be necessary in order that delay may exist: (1) When the obligation or the law expressly so declare; or (2) When from the nature and the circumstances of the obligation it appears that the designation of the time when the thing is to be delivered or the service is to be rendered was a controlling motive for the establishment of the contract; or (3) When demand would be useless, as when the obligor has rendered it beyond his power to perform. In reciprocal obligations, neither party incurs in delay if the other does not comply or is not ready to comply in a proper manner with what is incumbent upon him. From the moment one of the parties fulfills his obligation, delay by the other begins. (1100a LUZAN SIA, petitioner, vs. COURT OF APPEALS and SECURITY BANK and TRUST COMPANY, respondents. G.R. No. 102970 May 13, 1993 GOVERNING LAWS / PROVISIONS / DOCTRINES CIVIL CODE LEASE Art. 1643. In the lease of things, one of the parties binds himself to give to another the enjoyment or use of a thing for a price certain, and for a period which may be definite or indefinite DEPOSIT Art. 1962. A deposit is constituted from the moment a person receives a thing belonging to another, with the obligation of safely keeping it and of returning the same. If the safekeeping of the thing delivered is not the principal purpose of the contract, there is no deposit but some other contract. (1758a) Art. 2201. In contracts and quasi-contracts, the damages for which the obligor who acted in good faith is liable shall be those that are the natural and probable consequences of the breach of the obligation, and which the parties have foreseen or could have reasonably foreseen at the time the obligation was constituted. In case of fraud, bad faith, malice or wanton attitude, the obligor shall be responsible for all damages which may be reasonably attributed to the non-performance of the obligation. (1107a) GENERAL BANKING LAW Sec. 72. In addition to the operations specifically authorized elsewhere in this Act, banking institutions other than building and loan associations may perform the following services: (a) Receive in custody funds, documents, and valuable objects, and rent safety deposit boxes for the safeguarding of such effects; ********** FACTS: On March 22, 1985, plaintiff Luzan Sia, herewith referred to as “plaintiff” rented from Security Bank and Trust Co., herewith referred to as “respondent”, safety deposit box #54 to store rare collections of stamps. Such safety deposit box which was leased to the plaintiff by respondent at its Binondo branch was located at the bottom of the lowest level of safety deposit boxes. During the floods that took place in 1985 and 1986, floodwater entered into the defendant's premises, seeped into the safety deposit box leased by the plaintiff and caused, according to the plaintiff, damage to his stamps collection. The defendant rejected the plaintiff's claim for compensation for his damaged stamps collection and denied liability, on the basis of the "Rules and Regulations Governing the Lease of Safe Deposit Boxes". The defendant bank also contended that its contract with the plaintiff over safety deposit box No. 54 was one of lease and not of deposit and, therefore, governed by the lease agreement which should be the applicable law; that the destruction of the plaintiff's stamps collection was due to a calamity beyond obligation on its part to notify the plaintiff about the floodwaters that inundated its premises at Binondo branch which allegedly seeped into the safety deposit box leased to the plaintiff. The plaintiff thus instituted an action for damages against the defendant, which the trial court upheld and so ordered defendant to pay the sum of — a) Twenty Thousand Pesos (P20,000.00), Philippine Currency, as actual damages; b) One Hundred Thousand Pesos (P100,000.00), Philippine Currency, as moral damages; and c) Five Thousand Pesos (P5,000.00), Philippine Currency, as attorney's fees and legal expenses. The counterclaim set up by the defendant was hereby dismissed for lack of merit. No costs. The defendant appealed the trial court’s decision to the Court of Appeals and contended that the latter erred in (a) holding that the lease agreement is a contract of adhesion; (b) finding that the defendant had failed to exercise the required diligence of a bank in maintaining the safety deposit box; c) awarding to the plaintiff actual damages in the amount of P20,000.00, moral damages in the amount of P100,000.00 and attorney's fees and legal expenses in the amount of P5,000.00; and (d) dismissing the counterclaim. The Court of Appeals reversed the decision of the trial court and dismissed both the complaint of the plaintiff and the appeal of the respondent on the basis of the Lease Agreement contract. The plaintiff filed an instant petition where he insists that the trial court correctly ruled that SBTC had failed "to exercise the required diligence expected of a bank maintaining such safety deposit box . . . in the light of the environmental circumstance of said safety deposit box after the floods of 1985 and 1986." ISSUE: a. Was this a contract of lease or contract of deposit? b. Whether or not the bank is liable for negligence? RULING: a. A contract for the use of a safety deposit box is a contract of deposit governed by Book IV of the Civil Code. The relationship between a bank renting out safe deposit boxes and its customer with respect to the contents of the box is that of a bailor-bailee, the bailment being for hire and mutual benefit has been adopted in this jurisdiction. b. SBTC was aware of the floods of 1985 and 1986; it also knew that the floodwaters inundated the room where the safe deposit box was located. In view thereof, it should have lost no time in notifying the petitioner in order that the box could have been opened to retrieve the stamps, thus saving the same from further deterioration and loss. The bank’s negligence aggravated the injury or damage to the stamp collection. In this respect, it failed to exercise the reasonable care and prudence expected of a good father of a family, thereby becoming a party to the aggravation of the injury or loss. Hence, the petition was granted. V. Extinguishment of Liability in Case of Breach Due To Fortuitous Event B. Requisites Concurrent Fault G.R. No. L-47851 Nakpil & Sons v. CA Paras, J. An earthquake caused PBA’s building to partially collapse. PBA sought recovery for damages from UCI and Nakpil. The Court ruled that both UCI and Nakpil are liable for damages despite the fortuitous event due to their concurrent negligence resulting to defects in construction and in the plans and specifications. IMPORTANT PEOPLE Philippine Bar Association (PBA) – plaintiff, owner of building Juan F. Nakpil & Sons (Nakpil) – prepared the plans, specifications (architects) The United Construction Co., Inc. (UCI) – construction company FACTS 1. PBA decided to construct an office building and sought the services of UCI and Nakpil. 2. Aug. 2,1968 – an earthquake hit Manila and the building sustained major damage. 3. PBA filed for recovery of damages against UCI, alleging that the partial collapse was due to defects in construction. 4. UCI filed a complaint against architects Nakpil, alleging the collapse to be due to defects in the plans and specifications. 5. Technical issues were referred to Commissioner Hizon whose findings stated that while the damage sustained was caused directly by the August 2, 1968 earthquake, they were also caused by the defects in the plans prepared by Nakpil and deviations from said plans by UCI and even the owners to exercise the requisite degree of supervision in the construction of subject building. 6. Trial Court agreed with the findings (except regarding the owner) and ruled in favor of PBA. 7. Defendants claim that the damages were due to the earthquake, which was an act of God, and therefore they should not be liable. ISSUE with HOLDING 1. W/N the earthquake, an act of God which caused the collapse of the building, exempts from UCI and Nakpil from liability? NO. · The general rule is that no person shall be responsible for events which could not be foreseen or which though foreseen, were inevitable (Article 1174, New Civil Code). · An act of God has been defined as an accident, due directly and exclusively to natural causes without human intervention, which by no amount of foresight, pains or care, reasonably to have been expected, could have been prevented. (1 Corpus Juris 1174). The earthquake of August 2, 1968 is a fortuitous event. · To exempt the obligor from liability under Article 1174 of the Civil Code, the following must concur: (a) the cause of the breach of the obligation must be independent of the will of the debtor; (b) the event must be either unforseeable or unavoidable; (c) the event must be such as to render it impossible for the debtor to fulfill his obligation in a normal manner; and (d) the debtor must be free from any participation in, or aggravation of the injury to the creditor. · Thus, if upon the happening of a fortuitous event, there concurs a corresponding fraud, negligence, delay or violation or contravention in any manner of the tenor of the obligation which results in loss or damage, the obligor cannot escape liability. · The negligence of UCI and Nakpil was established beyond dispute both in the lower court and in the CA. UCI was found to have made substantial deviations from the plans and specifications and to have failed to observe the requisite workmanship in the construction as well as to exercise the requisite degree of supervision; while Nakpil were found to have inadequacies or defects in the plans and specifications prepared by them. The defects in the construction and in the plans and specifications were the proximate causes that rendered the PBA building unable to withstand the earthquake of August 2, 1968. (CA also affirmed the observation that buildings situated in the same area withstood the earthquake.) For this reason the defendants cannot claim exemption from liability. DISPOSITIVE PORTION Decision appealed from is hereby MODIFIED. Court imposes upon defendants indemnity in favor of PBA of P5,000,000.00 to cover all damages occasioned by the loss of the building and an additional P100,000.00 for attorney's fees. DOCTRINE When the negligence of a person concurs with an act of God in producing a loss, such person is not exempt from liability by showing that the immediate cause of the damage was the act of God. To be exempt from liability for loss because of an act of God, he must be free from any previous negligence or misconduct by which that loss or damage may have been occasioned. Extinguishment of Liability in Case of Breach Due to Fortuitous Event G.R. No. L-47379 NPC vs. CA Gutierrez, Jr. ECI was tasked with a construction project for NAWASA. Due to a strong typhoon, NPC had open the spillway gates of Angat Dam which was near the project site. This damaged and destroyed the equipment and facilities of ECI. Court reduced the award of damages due to ECI but found NPC to be negligent and liable despite thepresence of an act of God. FACTS 1. Consolidated petitions seeking to set aside the decision of the CA, declaring NPC liable for damages against Engineering Construction Inc. (ECI) 2. August 4, 1964 — ECI executed a contract in Manila with National Waterworks and Sewerage Authority (NAWASA) where it would furnish all tools, labor, equipment and materials and construct the 2nd Ipo-Bicti Tunnel and the necessary structures within 800 calendar days 3. ECI finished the tunnel excavation phase by September 1967 but in November of that year, typhoon “Welming” struck causing the water levels of NPC’s Angat dam (which was near the project site) to rise up to dangerous levels. Because of this, they opened the spillway gates and caused ECI’s materials and supplies as well as camp facilities and some permanent structures to be destroyed 4. CA found NPC liable due to the negligent manner with which they let the spillway gates be opened, allowing an “extraordinary large volume of water” out when they should have opened them gradually before the climax (??) of the storm. Note that NPC knew the typhoon was coming 5. Damages awarded equalled P675,785.31 but this was reduced by the court (a) P213,200 was for the rentals of a crane for 1 year to temporarily replace the one that was destroyed but it appears that they were able to buy another crane which, if the contract of sale was adhered to, arrived in a month. So the temporary replacement was probably only rented for that time for a total cost of P19,200. (b) P120,000 was supposed to be given to ECI for finishing the project a month early (within the 800 days) but the court rejected the award of this because the incident occurred after 1170 days (c) Exemplary damages were also eliminated because there was no bad faith on the part of NPC ISSUE with HOLDING NPC’s petition: the destruction of ECI’s equipment and facilities were due to force majeure and the rapid rise of water in the reservoir of its damn could not have been foreseen ECI’s petition: the CA has no basis in concluding that they acquired a new crane and so the reduction of consequential damages from P333,200 to P19K is unwarranted and the award of P120k for lost bonus is justified 1. Whether or not the destruction of ECI’s equipment and facilities was due to force majeure • based on the trial court’s and appellate court’s findings, NPC was NEGLIGENT because it opened the spillway gates of the Angat Dam only at the height of the typhoon when they knew it would’ve been safer to open it gradually and earlier since they knew it was coming 4 days before it arrived • the typhoon may have been force majeure but the proximate cause of the loss and damage was their negligence so they cannot escape liability • Juan Nakpil & Sons vs. CA: “Thus if, upon the happening of a fortuitous event or an act of God, there concurs a corresponding fraud, negligence, delay, or violation or contravention in any manner of the tenor of the obligation as provided for in Article 1170 of the CC which results in loss or damage, the obligor cannot escape liability” • to escape liability, the damage done must be caused exclusively by the violence of nature • Also, whether or not there was negligence on the part of NPC is a question of fact which the court will not address 2. Whether or not the CA erred in reducing the consequential damages • considering the fact that there was a contract of sale with the promise by Asian Enterprises that they would deliver the new crane within 60 days (after the flooding) and this would have been cheaper than renting a crane for a year, there’s no reason that ECI would’ve opted to rent a crane instead. Also, it was found that they were able to repair their crane for P77k which was already included in the compensatory damages. No reason, then, to find anything erroneous about the award of damages • The P120k supposedly lost for failing to earn the one month bonus from NAWASA cannot be granted because the damage was incurred long after the deadline to finish construction. They wouldn’t have earned it anyway. • Additionally, the court was right in ruling that there was no bad faith on the part of NPC and the deletion of exemplary damages is justified DISPOSITIVE PORTION Wherefore, the petitions in G.R. No. 47379 and G.R. No. 47481 are both DISMISSED for LACK OF MERIT. The decision appealed from is AFFIRMED. DOCTRINE One cannot escape liability on the basis of force majeure (act of God) if the proximate cause of the damage caused is their fraudulence, negligence, delay, or violation or contravention in any manner of the tenor of the obligation. The damage caused must be exclusively due to the act of God Dioquino vs. Laureano | G.R. No. L-25906 | May 28, 1970 | Ponente: Fernando, J. Nature of Case: Liability on fortuitious events Plaintiff(s): Pedro D. Dioquino Defendant(s): Federico Laureano, Aida de Laureano, Juanito Laureano SUMMARY: While Federico Laureano was using the car owned by Atty. Dioquino, some ‘mischievous boys’ stoned the car which resulted to a broken windshield. Although the car was driven by the plaintiff’s driver, Laureano being only a passenger, Dioquino proceeded against Laureano to claim damages. Plaintiff also included Laureano’s wife and father in the suit filed. Lower court ruled for Dioquino, while dismissing the suit filed against the defendant’s wife and father. Supreme Court granted Laureano’s appeal because the case falls within the definition of a fortuitous event, making defendant not liable. FACTS • Atty. Dioquino, a practicing lawyer of Masbate, owns the car • Dioquino went to the office of the MVO, Masbate to have his car registered • Plaintiff met defendant Federico Laureano, a patrol officer of said MVO office, who was waiting for a jeepney to take him to the office of the Provincial Commander (P.C.), Masbate - Dioqunio requested defendant to introduce him to one of the clerks in the MVO offive who could facilitate the registration of his car • Laureano rode on the car of Dioquino on his way to P.C. Barracks - car, driven by Dioquino’s river and with Laureano as the sole passenger, was stoned by some ‘mischievous boys’ —> windshield was broken • Laureano was only able to catch one of the boys - boy admitted to having thrown the stone - the father of the boy was called but no satisfactory arrangements were made about the damage to the windshield • Laureano refused to file charges against the boy and his parents believing that the stone-throwing was merely accidental and that it was due to force majeure - defendant Laureano also refused to pay the windshield himself • Plaintiff now holds defendant Federico Laureano accountable for the loss sustained - also included in the action filed were the defendant’s wife, Aida Laureano, and his father, Juanito Laureano • Lower court granted plaintiff’s action for damages but absolved defendant’s wife and father of any responsibility • all 3 Laureanos’ appealed, raising the following: 1. lower court failed to dismiss such a suit as no liability could have been incurred as a result of fortuitous event 2. lower court failed to award damages against plaintiff for the unwarranted inclusion of the wife and the father in this litigation ISSUE(S) + RULING 1. WON the lower court erred in not dismissing the suit against Laureano — YES • Art. 1174, Civil Code: "Except in cases expressly specified by the law, or when it is otherwise declared by stipulation, or when the nature of the obligation requires the assumption of risk, no person shall be responsible for those events which could not be, foreseen, or which, though foreseen were inevitable.” • In obligations arising from contract that some extraordinary circumstance independent of the will of the obligor, or of his employees —> essential element in fortuitous events - if the above situation happens, there is no liability - the law does not require diligence beyond what human are and foresight can provide • Caso fortuito or force majeure are extraordinary events not forseeable or avoidable, events that could not be foreseen, or which, though foreseen, were inevitable (must be impossible to foresee or to avoid) • What happened to the car was clearly unforeseen — it was a fortuitous event resulting in a loss which must be borne by the owner of the car 2. WON damages could be awarded for the unwarranted inclusion of defendant’s wife and father in the litigation — NO • Plaintiif included the wife and the father because, according to him, the father was the administrator of the inheritance of an undivided property to which defendant could lay claim and the wife for the conjugal partnership would be made to respond for whatever liability would be adjudicated against the husband • Plaintiff was merely propmted by the desire to inflict needless and unjustified vexation on them (wife and father) • Since plaintiff already suffered a pecuniary loss which was the result of a fortuitous event (would have not occured if defendent Laureano had not borrowed his car), court feels that he is not to be penalized further by his mistaken view of the law in including them in his complaint Decision of lower court REVERSED. LESSON: Effect of concurrent fault No. L-21749 Republic vs. Luzon Stevedoring Corporation Reyes, JBL Appeal from a decision of the CFI of Manila adjudging the defendant-appellant, Luzon Stevedoring Corporation, liable in damages to the plaintiff-appellee Republic of the Philippines. IMPORTANT PEOPLE Republic of the Philippines Luzon Stevedoring Corporation (LSC) FACTS 8. A barge owned by the LSC rammed against one of the wooden piles of the Nagtahan bridge, smashing the posts and causing the bridge to list. 9. There was a heavy downpour the previous days, causing the river to swell and making the currents swift. 10. LSC disclaimed liability on the grounds that: It had exercised due diligence in the selection and supervision of its employees Damages to the bridge were caused by force majeure Plaintiff has no capacity to sue Nagtahan bridge is an obstruction to navigation 11. CFI held the defendant liable for the damage caused by its employees and ordering it to pay to plaintiff the actual cost of the repair of the Nagtahan bridge. ISSUE with HOLDING 2. Whether or not the collision of appellant’s barge with the supports or piers of the Nagtahan bridge was in law caused by fortuitous event or force majeure. No The appellant strongly stresses the precautions taken by it on the day in question and concludes that it had done all it was called to do, and that the accident, therefore, should be held due to force majeure or fortuitous event. These very precautions, however, completely destroy the appellant's defense. Caso fortuito or force majeure are extraordinary events not foreseeable or avoidable, "events that could not be foreseen, or which, though foreseen, were inevitable" (Art. 1174, Civil Code) It is not enough that the event should not have been foreseen or anticipated, but it must be one impossible to foresee or to avoid. The mere difficulty to foresee the happening is not impossibility to foresee the same. The very measures adopted by appellant prove that the possibility of danger was not only foreseeable, but actually foreseen, and was not caso fortuito. 3. Whether or not it was error for the Court to have permitted the plaintiff-appellee to introduce additional evidence of damage after said party had rested its case. No Whether or not further evidence will be allowed after a party offering the evidence has rested his case, lies within the sound discretion of the trial Judge, and this discretion will not be reviewed except in clear case of abuse. In the present case, no abuse of that discretion is shown. DISPOSITIVE PORTION WHEREFORE, finding no error in the decision of the lower Court appealed from, the same is hereby affirmed. Costs against the defendant-appellant. DOCTRINE Caso fortuito or force majeure are extraordinary events not foreseeable or avoidable, "events that could not be foreseen, or which, though foreseen, were inevitable." (Art. 1174, Civil Code) RELEVANCE TO THE LESSON For an event to be considered a fortuitous event, it is not enough that the event should not have been foreseen or anticipated, but it must be one impossible to foresee or to avoid. VICTORIAS PLANTERS ASS., INC., ET AL. VS. VICTORIAS MILLING CO., INC. G.R. No. L-6648 July 25, 1955 FACTS: The petitioners Victorias Planters Association, Inc. and North Negros Planters Association, Inc. and the respondent Victorias Milling Co., Inc entered into a milling contract whereby they stipulated a 30-year period within which the sugar cane produced by the petitioner would be milled by the respondent central. The parties also stipulated that in the event of force majuere, the contract shall be deemed suspended during this period. The petitioner failed to deliver the sugar cane during the four years of the Japanese occupation and the two years after liberation when the mill was being rebuilt or a total of six years. ISSUE: Can the petitioners be compelled to deliver sugar cane for six more years after the expiration of the 30-year period to make up for what they failed to deliver to the respondent? RULING: No. Fortuitous event relieves the obligor from fulfilling the contractual obligation under Article 1174 of the Civil Code. The stipulation in the contract that in the event of force majeure the contract shall be deemed suspended during the said period does not mean that the happening of any of those events stops the running of the period agreed upon. It only relieves the parties from the fulfillment of their respective obligations during that timethe petitioner from delivering the sugar cane and the respondent central from milling. In order that the respondent central may be entitled to demand from the petitioner the fulfillment of their part in the contracts, the latter must have been able to perform it but failed or refused to do so and not when they were prevented by force majeure such as war. To require the petitioners to deliver the sugar cane which they failed to deliver during the six years is to demand from them the fulfillment of an obligation, which was impossible of performance during the time it became due. Nemo tenetur ed impossibilia. The respondent central not being entitled to demand from the petitioners the performance of the latter’s part of the contracts under those circumstances cannot later on demand its fulfillment. The performance of what the law has written off cannot be demanded and required. The prayer that the petitioners be compelled to deliver sugar cannot for six years more to make up for what they failed to deliver, the fulfillment of which was impossible, of granted, would in effect be an extension of the terms of the contracts entered into by and between the parties. ARRIETA VS. NATIONAL RICE AND CORN CORPORATIONGR L-15645 January 31, 1964 Regala, J. FACTS: On May 19, 1952, plaintiff-appellee Mrs. Paz Arrieta participated in a public biddingcalled by NARIC for the supply of 20,000 metric tons of Burmese rice. As her bid of$203.00 per metric ton was the lowest, she was awarded she contract for the same. OnJuly 1, 1952,Arrieta and NARIC entered into Contract of Sale of Rice under the termof which the former obligated herself to deliver to the latter 20,000 metric tons ofBurmese rice at $203.00 per metric ton. In turn, NARIC committed itself to pay forthe imported rice“by means of an irrevocable,confirmed and assignable letter ofcredit in US currency in favor of Arrieta and/or supplier in Burma, immediately.” However, it was only on July 30, 1952 that NARIC took the first step to open a letterof credit by forwarding to the PNB its application for Commercial Letter of Credit. On the same day, Arrieta, thru counsel, advised NARIC ofthe extreme necessity for theopening of the letter of credit since she had by then made a tender to her supplier in Rangoon, Burma equivalent to 5% of the F.O.B. price of 20, 000 tons at $180.70 andin compliance with the regulations in Rangoon, this 5% will be confiscated if therequired letter of credit is not received by them before August 4, 1952.On August 4,PNB informed NARIC that its application for a letter of credit has been approved bythe Board of Directors with the condition that 50% marginal cash deposit be paid andthat drafts to be paid upon presentment. It turned out that NARIC was not in financial position to meet the condition. As a result of the delay, the allocation of Arrieta’s supplier in Rangoon was cancelled and the 5% deposit amounting to 524 kyats orapproximately P200,000 was forfeited. ISSUE: Was NARIC liable for damages? RULING: Yes. One who assumes a contractual obligation and fails to perform the same on account of his inability to meet certain bank which inability he knew and was aware of when he entered into contract, should be held liable in damages for breach of contract. Under Article 1170 of the Civil Code, not only debtors guilty of fraud, negligence or default but also debtor of every, in general, who fails in the performance of his obligations is bound to indemnify for the losses and damages caused thereby. [G.R. No. 126152. September 28, 1999] PHILIPPINE NATIONAL BANK, petitioner, vs. COURT OF APPEALS and LILY S. PUJOL, respondents. FACTS: Sometime prior to 23 October 1990 private respondent Lily S. Pujol opened with petitioner PNB Mandaluyong an account denominated as "Combo Account," a combination of Savings Account and Current Account in private respondent's business name "Pujol Trading," under which checks drawn against private respondents checking account could be charged against her Savings Account should the funds in her Current Account be insufficient to cover the value of her checks. Hence, private respondent was issued by petitioner a passbook on the front cover of which was typewritten the words "Combo Deposit Plan." On 23 and 24 October 1990, private respondent issued a check in the amount of P30,000.00 each in favor of her daughter-inlaw, Dr. Charisse M. Pujol and daughter Venus De Ocampo, respectively. When issued and presented for payment, private respondent had sufficient funds in her Savings Account. However, petitioner dishonored her check allegedly for insufficiency of funds and debited her account with P500.00 as penalty charge (P250 each per check transaction). On 4 November 1990, after realizing its mistake, petitioner accepted and honored the second check for P30,000.00 and recredited to private respondents account the P250.00 previously debited as penalty. Private respondent Lily S. Pujol filed with Pasig RTC a complaint for moral and exemplary damages against petitioner for dishonoring her checks despite sufficiency of her funds in the bank. Petitioner bank admitted in its answer that private respondent Pujol opened a "Combo Account," a combination of Savings Account and Current Account, with its Mandaluyong branch. It however justified the dishonor of the two (2) checks by claiming that at the time of their issuance private respondent Pujols account was not yet operational due to lack of documentary requirements. On 27 September 1994 the trial court (RTC) rendered a decision ordering petitioner to pay private respondent Pujol moral damages of P100,000.00 and attorneys fees of P20,000.00. CA affirmed RTC decision in toto. ISSUE: W/N the appellate court (C/A) erred in holding that petitioner was estopped from denying the existence of a "Combo Account" and the fact that it was operational at the time of the issuance of the checks in not holding that the award by the trial court of moral damages of P100,000.00 and attorneys fees of P20,000.00 was inordinately disproportionate and unconscionable. RULING: We cannot sustain petitioner. Although petitioner presented evidence before the trial court to prove that the arrangement was not yet operational at the time respondent issued the two checks, it failed to prove that she had actual knowledge that it was not yet operational at the time she issued the checks considering that the passbook in her Savings Account already indicated the words "Combo Deposit Plan." Hence, respondent Pujol had justifiable reason to believe that her accounts were effectively covered by the arrangement during the issuance of the checks. Either by its own deliberate act, or its negligence in causing the "Combo Deposit Plan" to be placed in the passbook, petitioner is considered estopped to deny the existence of and perfection of the combination deposit agreement with respondent Pujol. A bank is under obligation to treat the accounts of its depositors with meticulous care whether such account consists only of a few hundred pesos or of millions of pesos. Responsibility arising from negligence in the performance of every kind of obligation is demandable. While petitioners negligence in this case may not have been attended with malice and bad faith, nevertheless, it caused serious anxiety, embarrassment and humiliation to private respondent Lily S. Pujol for which she is entitled to recover reasonable moral damages. RTC and CA decision affirmed. PNB vs CA - SYPNOSIS Spouses Antonio M. Chua and Asuncion M. Chua were the owners of a parcel of land covered by Transfer Certificate of Title No. P142. Upon Antonio's death, the probate court appointed his son, Allan M. Chua, as special administrator of his estate. It also authorized Allan to obtain a loan accommodation of five hundred fifty thousand pesos (P550,000) to be secured by a real estate mortgage over the above-mentioned parcel of land. Pursuant thereto, on June 29, 1989, Allan obtained a loan of P450,000.00 from the Philippine National Bank (PNB). However, for failure to pay the loan in full, the bank extrajudicially foreclosed the real estate mortgage. During the auction, PNB was the highest bidder with a bid price P372,825.63. Subsequently, to claim the deficiency, PNB instituted an action with the Regional Trial Court (RTC), Branch 10 of Balayan, Batangas, against both Mrs. Asuncion M. Chua and Allan M. Chua in his capacity as special administrator of his father's estate. Despite summons having been duly served, Asuncion Chua and Allan Chua did not answer the complaint. The trial court declared them in default and received evidence ex parte. Thereafter, the RTC rendered its decision, ordering the dismissal of PNB's complaint. The Court of Appeals affirmed the RTC decision. Hence, the PNB filed the instant petition. cHaADC The Court ruled that case law now holds that Section 7 of Rule 86 of the Rules of Court rule grants to the mortgagee three distinct, independent and mutually exclusive remedies that can be alternatively pursued by the mortgage creditor for the satisfaction of his credit in case the mortgagor dies, among them: (1) to waive the mortgage and claim the entire debt from the estate of the mortgagor as an ordinary claim; (2) to foreclose the mortgage judicially and prove any deficiency as an ordinary claim; and (3) to rely on the mortgage exclusively, foreclosing the same at any time before it is barred by prescription without right to file a claim for any deficiency. The plain result of adopting the last mode of foreclosure is that the creditor waives his right to recover any deficiency from the estate. Clearly, petitioner herein has chosen the mortgagecreditor's Woodhouse v Halili, GR No L-4811 31 July 1953 Facts: The Plaintiff entered into an agreement with the defendant for the establishment of a partnership for bottling and distribution of Mission soft drinks. Before the partnership was actually established the defendant required the plaintiff to secure an exclusive franchise for the said venture. In behalf of the said partnership and upon obtaining the said exclusive franchise the defendant stipulated to pay the plaintiff 30% of the profits. The plaintiff sought to obtain the said exclusive franchise but was only given a temporary one, subject only to 30 days. The parties then proceeded with the signing of the agreement. The partnership was still not initiated, only the agreement to work with each other, with the plaintiff as manager and the defendant as financer, was established. Together the two parties went to the US to formally sign the contract of franchise with Mission Dry Corporation. The defendant then found out about the temporary franchise right given to the plaintiff, different from the exclusive franchise rights they stipulated in their contract. When the operations of the business began he was paid P 2,000 and was allowed the use of a car. But in the next month, the pay was decreased to P 1,000 and the car was withdrawn from him. The plaintiff demanded the execution of the partnership, but the defendant excused himself, saying that there was no hurry to do so. The Court of First Instance ordered the defendant to render an accounting of the profits and to pay the plaintiff 15% of such amount. It also held that execution of the contract of partnership cannot be enforced upon the defendant and that fraud as alleged by the defendant was also not proved. Hence the present action. Issues: (1) WoN plaintiff falsely represented that he had an exclusive franchise to bottle Mission beverages (2) WoN the representation of the plaintiff in saying that he had exclusive franchise rights rather than the actual temporary right he possessed invalidated the contract Held: (1) Yes. Plaintiff did make false representations and this can be seen through his letters to Mission Dry Corporation asking for the latter to grant him temporary franchise so that he could settle the agreement with defendant. The trial court reasoned, and the plaintiff on this appeal argues, that plaintiff only undertook in the agreement “to secure the Mission Dry franchise for and in behalf of the proposed partnership.” The existence of this provision in the final agreement does not militate against plaintiff having represented that he had the exclusive franchise; it rather strengthens belief that he did actually make the representation. The defendant believed, or was made to believe, that plaintiff was the grantee of an exclusive franchise. Thus it is that it was also agreed upon that the franchise was to be transferred to the name of the partnership, and that, upon its dissolution or termination, the same shall be reassigned to the plaintiff. Again, the immediate reaction of defendant, when in California he learned that plaintiff did not have the exclusive franchise, was to reduce, as he himself testified, plaintiff’s participation in the net profits to one half of that agreed upon. He could not have had such a feeling had not plaintiff actually made him believe that he(plaintiff) was the exclusive grantee of the franchise. (2) No. In consequence, article 1270 of the Spanish Civil Code distinguishes two kinds of (civil) fraud, the causal fraud, which may be ground for the annulment of a contract, and the incidental deceit, which only renders the party who employs it liable for damages only. The Supreme Court has held that in order that fraud may vitiate consent, it must be the causal (dolo causante), not merely the incidental (dolo incidente) inducement to the making of the contract. The record abounds with circumstances indicative of the fact that the principal consideration, the main cause that induced defendant to enter into the partnership agreement with plaintiff, was the ability of plaintiff to get the exclusive franchise to bottle and distribute for the defendant or for the partnership. The original draft prepared by defendant’s counsel was to the effect that plaintiff obligated himself to secure a franchise for the defendant. But if plaintiff was guilty of a false representation, this was not the causal consideration, or the principal inducement, that led plaintiff to enter into the partnership agreement. On the other hand, this supposed ownership of an exclusive franchise was actually the consideration or price plaintiff gave in exchange for the share of 30 per cent granted him in the net profits of the partnership business. Defendant agreed to give plaintiff 30 per cent share in the net profits because he was transferring his exclusive franchise to the partnership. Having arrived at the conclusion that the contract cannot be declared null and void, may the agreement be carried out or executed? The SC finds no merit in the claim of plaintiff that the partnership was already a fait accompli from the time of the operation of the plant, as it is evident from the very language of the agreement that the parties intended that the execution of the agreement to form a partnership was to be carried out at a later date. , The defendant may not be compelled against his will to carry out the agreement nor execute the partnership papers. The law recognizes the individual’s freedom or liberty to do an act he has promised to do, or not to do it, as he pleases. Geraldez v CA 230 108253, 23 February 1994 Facts: Petitioner booked the Volare 3 tour with private respondent, Kenstar. The tour covered a 22day tour of Europe for $2,990.00 which she paid the total equivalent amount of P190, 000.00 charged by private respondent for her and her sister, Dolores. At the tour, petitioner claimed that what was alleged in the brochure was not what they experienced. There was no European tour manager as stated in the brochure, the hotels where they stayed in which were advertised as first class were not (the hotels lacked basic amenities and were of considerable distance from the city center), the UGC leather factory which was specifically included as a highlight of the tour was not visited and The Filipino tour guide provided by Kenstar was a first timer thus inexperienced. The Quezon City RTC rendered a decision ordering respondent Kenstar to pay moral, nominal, and exemplary damages totaling P1, 000,000 and P50, 000 attorney’s fees. On appeal, respondent Court of Appeals deleted the award for moral and exemplary damages and reduced the nominal damages and attorney’s fees to P30,000 and P10,000 respectively. Issue: WoN Kenstar acted with fraud or in bad faith or with gross negligence in discharging its obligations in the contract Held: The fraud or dolo, which is present or employed at the time of birth or perfection of a contract, may either be dolo causante or dolo incidente. The first, or causal fraud referred to in Article 1338, are those deceptions or misrepresentations of a serious character employed by one party and without which the other party would not have entered into the contract. Dolo incidente, or incidental fraud which is referred to in Article 1344, are those, which are not serious in character and without which the other party would still have entered into the contract. Dolo causante determines or is the essential cause of the consent, while dolo incidente refers only to some particular or accident of the obligations. The effects of dolo causante are the nullity of the contract and the indemnification of damages, and dolo incidente also obliges the person employing it to pay damages. Kenstar’s choice of the tour guide is a manifest disregard of its specific assurances to the tour group, and which deliberate omission is contrary to the rules of good faith and fair play. Providing the Volare 3 group with an inexperienced first timer as a tour guide, Kenstar manifested indifference to the satisfaction, convenience and peace of mind to its clients. The election of the tour guide was a deliberate and conscious choice on the part of Kenstar in order to afford her on-the job-training making the tour group her unknowing guinea pigs, furthermore the inability to visit the UGC leather factory is reflective of the ineptness and neglect of the tour guide. The failure of Kenstar to provide a European Tour Manager although it specifically advertised and promised to do so is also a contractual breach. Kenstar expressly stated in its advertisement that a European Tour Manager would be present. Kenstar’s contention that the European Tour Manager does not refer to a natural person but a juridical personality does not hold because a corporate entity could not possibly accompany the tour group. Lastly Kenstar committed grave misrepresentation when it assured in its tour package that the hotels provided would provide complete amenities and would be conveniently located along the way for the daily itineraries. The testimonies by petitioner and private respondent show that the hotels were unsanitary and sometimes did not even provide towels and soap. Further testimonies claim that the hotels were also located in locations far from the city making it difficult to go to. The fact that Kenstar could only book them in such hotels because of budget constraints is not the fault of the tour group. Kenstar should not have promised such accommodations if they couldn’t afford it. Kenstar should have increased the price to ensure accommodations. Petitioners therefore should be awarded moral damages because of breach of contract because the obligor acted fraudulently or in bad faith. International Corporate Bank v Gueco, GR No 141968, 12 February 2001 Facts: Respondent Gueco spouses obtained a loan from petitioner International Corporate Bank (now Union Bank of Philippines) to purchase a car – Nissan Sentra 1989 model. In consideration, spouses executed promissory note which were payable in monthly installment & chattel mortgage over the car. The spouses defaulted payment. In the ensuing events Dr. Gueco had a meeting with petitioner to negotiate for the payment of the unpaid installment of P184,000 (balance of the loan). The load was eventually reduced to P150,000. However, the car was detained by the bank pending its payment. When Dr. Gueco delivered the manager’s check amounting to P150,000, the car was not released because of his refusal to sign the Joint Motion to Dismiss.The bank insisted that the Joint Motion to Dismiss is a standard operating procedure to effect a compromise & to preclude future filing of claims or suits for damages. The Gueco spouses, on the other hand, maintain that no such requirement was agreed upon during the negotiation for the payment of the loan. As a result, Gueco filed an action against the bank for fraud, failing to inform them regarding Joint Motion to Dismiss requiment during the meeting & for failing to release the car despite payment of the P150,000 obligation. Issues: WoN the bank was guilty of fraud? Held: No. Fraud has been defined as the deliberate intention to cause damage or prejudice. It is the voluntary execution of a wrongful act, or a willful omission, knowing and intending the effects which naturally and necessarily arise from such act or omission. the fraud referred to in Article 1170 of the Civil Code is the deliberate and intentional evasion of the normal fulfillment of obligation. Petitioner’s act of requiring respondents to sign the Joint Motion to Dismiss can not be said to be a deliberate attempt on the part of petitioner to renege on the compromise agreement of the parties. The motion to dismiss was in fact also for the benefit of Dr. Gueco, as the case filed by petitioner against it before the lower court would be dismissed with prejudice. The whole point of the parties entering into the compromise agreement was in order that Dr. Gueco would pay his outstanding account and in return petitioner would return the car and drop the case for money and replevin before the Metropolitan Trial Court. The joint motion to dismiss was but a natural consequence of the compromise agreement and simply stated that Dr. Gueco had fully settled his obligation, hence, the dismissal of the case. Petitioner’s act of requiring Dr. Gueco to sign the joint motion to dismiss cannot be said to be a deliberate attempt on the part of petitioner to renege on the compromise agreement of the parties. The law presumes good faith. Dr. Gueco failed to present an iota of evidence to overcome this presumption. In fact, the act of petitioner bank in lowering the debt of Dr. Gueco from P184,000.00 to P150,000.00 is indicative of its good faith and sincere desire to settle the case. If respondent did suffer any damage, as a result of the withholding of his car by petitioner, he has only himself to blame. Necessarily, the claim for exemplary damages must fail. In no way, may the conduct of petitioner be characterized as “wanton, fraudulent, reckless, oppressive or malevolent.”