Uploaded by vishal.dhamecha1985

EGAT-HEC-000-CMM-MST-00004 0 Method Statement for Lube Oil Flushing

advertisement
Doc No:
POLIMERY POLICE PROJECT
EGAT-HEC-000-CMM-MST00004
Date: 8-Feb-2022
METHOD STATEMENT FOR LUBE OIL FLUSHING
Page: 1 of 10
Rev: 0
METHOD STATEMENT FOR LUBE OIL FLUSHING
0
08-Feb-2022
Issued For Information
M.S. Park
K.K. Kim
S.Y. Jung
Rev
Date
Status
Prepared By
Checked By
Approved By
Doc No:
POLIMERY POLICE PROJECT
EGAT-HEC-000-CMM-MST00004
Date: 8-Feb-2022
METHOD STATEMENT FOR LUBE OIL FLUSHING
Page: 2 of 10
DOCUMENT REVISION HISTORY
Revision No
Date
0
08-Feb-2022
Description
Issued For Information
Rev: 0
Doc No:
POLIMERY POLICE PROJECT
EGAT-HEC-000-CMM-MST00004
Date: 8-Feb-2022
METHOD STATEMENT FOR LUBE OIL FLUSHING
Page: 3 of 10
Rev: 0
TABLE OF CONTENTS
1.0
INTRODUCTION .............................................................................................................4
2.0
DEFINITION ....................................................................................................................4
3.0
APPLICATION ................................................................................................................4
4.0
RESPONSIBILITIES .......................................................................................................4
5.0
TOOLS AND CONSUMABLES .......................................................................................5
6.0
PRE-REQUISITED LUBE OIL FLUSHNG.......................................................................6
7.0
LUBE OIL FLUSHING PROCEDURES ...........................................................................6
7.1
PLANNING ......................................................................................................................6
7.2
PREPARATION ...............................................................................................................7
7.3
EXECUTION ...................................................................................................................7
7.3.1 First oil flushing procedure...........................................................................................7
7.3.2 Final oil flushing ............................................................................................................8
8.0
ACCEPTANCE................................................................................................................9
9.0
POST WORKS ................................................................................................................9
10.0
SAFETY PLAN................................................................................................................9
Doc No:
POLIMERY POLICE PROJECT
EGAT-HEC-000-CMM-MST00004
Date: 8-Feb-2022
METHOD STATEMENT FOR LUBE OIL FLUSHING
Page: 4 of 10
Rev: 0
1.0 INTRODUCTION
The purpose of Lube oil flushing is to ensure cleanliness of lube oil system in rotating
equipment prior to Commissioning and Start-up. It is important and mandatory to
remove foreign materials (dust, debris, organic material, welding waste, etc.) which
might enter during fabrication and installation for reliable operation of rotating
equipment.
2.0
DEFINITION
OWNER: means Grupa Azoty Polyolefins
CONTRACTOR: means Hyundai Engineering Co., Ltd. (HEC)
PROJECT: means POLIMERY POLICE PROJECT
3.0
APPLICATION
4.0
RESPONSIBILITIES

Construction Site Manager
The Construction manager shall be responsible for the coordination and control of all th
e construction activities related to the Steam Blowing activities. He shall be responsible
for the welfare and facilities provided for all the workers under his control.

Piping Manager
The Piping manager shall report to and receive technical direction from the Constructio
n Site Manager. He shall be responsible for the over-all implementation and monitoring
of the entire piping job at shop and field. He shall control the activities as per the releas
ed.

Commissioning Manager
The Commissioning manager shall be responsible for the coordination and control of all
the activities related to the Steam Blowing. He shall be responsible for the welfare and f
acilities provided for all the workers under his control.

Pre-commissioning supervisor
Doc No:
POLIMERY POLICE PROJECT
EGAT-HEC-000-CMM-MST00004
Date: 8-Feb-2022
METHOD STATEMENT FOR LUBE OIL FLUSHING
Page: 5 of 10
Rev: 0
The Pre commissioning supervisor shall report to and receive project direction from the
Commissioning Manager. He shall be directly involved in the planning and execution of
the Steam Blowing activities. He shall likewise ensure the implementation of safety and
quality plans and thereby control the workers involved in the related activities.

Pre-commissioning Foreman
The Pre commissioning foreman shall be working under the instruction of the Pre com
missioning supervisor. He should coordinate with the supervisor for the execution of the
job at site.

Rigging supervisor
The Rigging supervisor shall report to and receive project direction from the Pre commi
ssioning supervisor. He shall be directly involved in the planning and execution of the a
ctivities involved in the rigging work related to blinding/de blinding, reinstatement, temp
orary spool and valve installation, etc.

Riggers
Riggers should be trained and certified and they will follow the rigging supervisor’s instr
uctions for safe execution of the lifting job

HSE Manager
Contractor Safety Manager shall oversee and enforce the safety regulation and ensure
that all personnel involve in the work abide by the rules and regulations. He shall prepar
e to the start of the work safety plan that must be implemented and observed during the
work. He shall also conduct continuous safety inspection and should stop any work con
ducted unsafely and should take immediate action to rectify the unsafe conditions and r
eport to construction manager
5.0
TOOLS AND CONSUMABLES
1)
Temporary stainless wire mesh on lube oil return line and first bearing housing flange
(size 40-100 mesh can be changed by vendor recommendation and installed between
flanges shaped cone type).
2)
Rubber hammer.
3)
Heating source for circulation lube oil; Electrical Heater (Permanent on Lube oil system)
shall be used. Otherwise, dedicated temporary electrical heater for lube oil heating shall
be mobilized and to ensure all material to be check and ready to use upon the task.
Electrical inspection according to PTW system shall be completed.
4)
Cooling source for circulating lube oil.
2
Doc No:
POLIMERY POLICE PROJECT
EGAT-HEC-000-CMM-MST00004
Date: 8-Feb-2022
METHOD STATEMENT FOR LUBE OIL FLUSHING
Page: 6 of 10
5)
Sponge (not cotton and lug).
6)
Vinyl hose with clamps & install with whip check for rigid joint of element.
7)
Flushing oil (equivalent to permanent oil specified by vendor).
8)
Drums for used oil disposal with spillage oil kit
9)
Additional filter to change during Lube Oil Flushing
10)
Diagram pump, hose, connector or oil filtration unit (if required)
11)
Ensure all materials and tools are in good condition.
6.0
Rev: 0
PRE-REQUISITED LUBE OIL FLUSHNG
1) All oil serviced piping must be hydrotested and pre-cleaned by air blowing.
2) Oil reservoir, flanged pipes, manholes, removable headers, filters, coolers, temporary by
pass piping and so on shall be opened and inspected internally for cleanliness.
3) Accessible welds on pipes and fittings shall be inspected to remove slag.
4) Internal surfaces of component parts of field fabricated lube oil system shall be cleaned by
air prior to lube oil flushing.
5) Electricity for running Auxiliary lube oil pump and electrical heater (or temporary heater)
shall be available. In case temporary generator is used, the earthing system and any other
protection device (such as temporary MCC) shall be prepared and fully operational prior to
power up.
6) Make sure all flange joints are properly tightened to prevent any leakage during the activity.
7.0
LUBE OIL FLUSHING PROCEDURES
The following method is a general test method of Lube Oil Flushing. If Vendor’s
procedures are available, Vendor’s procedure shall be prevalent.
7.1
Planning
Planning the cleaning circuit;
1) Temporary hose connection and cross-over positions
2) Temporary mesh or strainer check point
3) Temporary blind locations
2
Doc No:
POLIMERY POLICE PROJECT
EGAT-HEC-000-CMM-MST00004
Date: 8-Feb-2022
METHOD STATEMENT FOR LUBE OIL FLUSHING
Page: 7 of 10
Rev: 0
4) In-line instrument to be removed
7.2
Preparation
1) Ensure to barricade & put signage in order to protect the equipment from an
unauthorized people enters the area.
2) Ensure cleanliness of the oil reservoir from dust by sponge and/or industrial vacuum
cleaner. Sponge and other tools must be clean to prevent any contamination.
3) All flanges to prepare drip pans at all times during the activity for any leakage.
4) Take out the permanent filter element and orifice (removing orifice is for higher
velocity).
5) Mount wire mesh at lube oil return line before oil reservoir in order to catch the foreign
matters. Wire mesh can be installed between flanges, otherwise in the wire box made
on purpose. Specific wire mesh installation location is based on the loops as per
vendor procedure/instruction.
6) Install temporary piping by passing the main equipment such as compressor, pump.
7) Insert blind between lube oil flange and equipment flange to protect equipment to
prevent the lube oil from entering the main equipment bearing housing during first oil
flushing.
8) Ensure installation of temporary piping and blind is properly tightened.
9) Fill the reservoir with lube oil. Required amount is 60~70 percent of reservoir capacity.
(Slightly higher than Low level).
10) Remove in-line instrument like PCV, TCV, Thermometers and etc.
11) Heat the flushing oil up to 50~70℃ by turning on electric heater. Temperature will be
measured by temperature gauge and potable temperature gun.
Field operator must check as below before turning on electrical heater:
7.3

Check Proper barrier & Signage ‘Caution Hot Surfaces’ and ‘Unauthorized Entry is
prohibited’.

Check cable connection to equipment which should be connected with molded lug
and soldered lug.

The laying of cable should performed after taking the measures to protect damage of
insulation and to avoid contact with water, oil, steel cables and hot pipelines.

The connection of cable should be conducted by qualified electrician.

Fully supervise and monitor oil temperature through temperature gauge during
heating up of oil until completion of work.
Execution
7.3.1 First oil flushing procedure
Doc No:
POLIMERY POLICE PROJECT
EGAT-HEC-000-CMM-MST00004
Date: 8-Feb-2022
METHOD STATEMENT FOR LUBE OIL FLUSHING
Page: 8 of 10
Rev: 0
1) Install a bypass line of bearing housing of main equipment.
2) Blinds should be installed at main equipment’s flanges to avoid rust entering the main
equipment. To make sure block valves (Close position) are available upstream of the
main equipment with blind install.
3) Check that the permanent oil filter element and temporary wire mesh are installed as
per the plan.
4) Circulate the lube oil through bypass line and keep the proper lube oil temperature
during the lube oil circulation in accordance with vendor recommendation.
5) Careful hammering is to be done on a regular basis in order to remove the slag.
(Hammering must be concentrated on the welding part and wrapping bend part of the
pipe)
6) Check the bellows during the lube oil flushing.

Lube oil temperature

Check the operation of oil flushing

Abnormal of the oil and overheating of the heating equipment

Check the any leakage of oil
7) Check the temporary wire mesh periodically and write down state of the accumulated
foreign matters. If foreign material found at the strainer and it is out of acceptance
criteria, the lube oil flushing activity should be repeated.
7.3.2 Final oil flushing
1) Remove temporary piping
2) Blinds should be installed at main equipment’s flanges to avoid rust entering the main
equipment. To make sure block valves (Close position) are available upstream of the
main equipment with blind install.
3) Clean pump suction strainer, install permanent filter element (new), clean wire mesh
on the lube oil return line and wire mesh between lube oil inlet flange and bearing
housing flange.
4) After removing the temporary piping, it is necessary to mount permanent piping and
check them for possible oil leaks.
5) New lube oil refilling (only if the lube oil is contaminated or recommendation by
vendor). If analysis of oil sample is within acceptance criteria, flushing oil will be used
for operation. Flushing oil shall be proved as clean by oil analysis report including
physical inspection.
6) Establish lube oil circulation and check the lube oil temperature.
7) Confirm normal operation pressure and Check oil leakage.
Note: Lube oil used for lube oil flushing is same as normal operating lube oil or
specified/approved oil by vendor.
Doc No:
POLIMERY POLICE PROJECT
EGAT-HEC-000-CMM-MST00004
Date: 8-Feb-2022
METHOD STATEMENT FOR LUBE OIL FLUSHING
8.0
Page: 9 of 10
Rev: 0
ACCEPTANCE
No foreign matters on meshes in accordance with vendor’s criteria indicate the completion
of lube oil flushing.
9.0
POST WORKS
1) After flushing is completed, drain the flushing oil from the oil reservoir, overhead tank,
filters, coolers and piping. Lube oil to be disposed as scheduled waste.
2) Remove all remaining bypass lines and wire meshes and install new filter elements.
3) Fill the oil system with the permanent oil required for operation.
4) Establish normal lube oil system for equipment start-up.
5) System leak test will be carried out after final reinstatement
10.0
SAFETY PLAN
1) Risks




Lubrication oil leak
Electrocution
Fire
Confined space
2) Relevant Safety Document



Mark-up P&ID. Check the diagram and ensure installation of spool is correctly done
prior to lube oil flushing.
Brief the team on activity.
Other safety precaution as required according to HSE plan.
3) Machines / Equipment



Lube oil pumps
Electric heaters.
Lube oil systems.
4) Safety measures

Identification of oil circuits and concerned areas
Doc No:
POLIMERY POLICE PROJECT
EGAT-HEC-000-CMM-MST00004
Date: 8-Feb-2022
METHOD STATEMENT FOR LUBE OIL FLUSHING


Page: 10 of 10
Rev: 0
Carefully follow the technical procedure recommendations to operate the electrical
devices.
Verify the operability of the firefighting system or place in the area, temporary fire
extinguishers.
5) Communications

Personnel must be provided with adequate communication devices (ie. Walkie
Talkie)
Download
Study collections