[NAME & LOGO OF IMPLEMENTING AGENCY] [PROJECT NAME (PPP)] Independent Engineer [NAME OF CONSULTING FIRM] Executive Summary MONTHLY PROGRESS REPORT NO. [XX] FOR THE MONTH OF: [MONTH], [YEAR] 1.1 Summary of Current Month’s Progress Expected Contents & Structure of Summary Please write a summary of construction progress in the current month, along with pending items, issues and actions recommended. Refer to quantitative data and facts from the subsequent sections as necessary, using the following format Summary of Progress [Please include inter alia, the following]: Physical progress & length completed – Actual vs. target Additional detail such as mobilization status, completion of structures, financial details, escrow withdrawal etc. as necessary Land Acquisition, clearances & utilities shifting – Total land in possession, current month progress, workfront available Additional detail such as encumbrances, encroachment etc. Current Issues & Recommended Actions by IE [Please include inter alia, the following]: Issues related to progress made by concessionaire Issues with pending land acquisition, clearances & utility shifting, encumbrances etc. Status of change of scope proposals – If applicable Action recommended by IE along with timelines Highlight potential risks due to the pending issues & pending issues from previous month Sample Summary – Illustrative, for reference Summary of Progress – [MONTH, YEAR]: Total length of project is Xx km from [Chainage] to [Chainage] with total cost Xx Cr. Appointed Date was [DD/MM/YYYY] and scheduled date of completion of construction was [DD/MM/YYYY] (with xxx days construction period). Cumulative physical progress is Xx%, against scheduled progress of Yy%. Financial progress is Zz%. Total expenditure till date is [TOTAL EXPENDITURE in Cr], including withdrawal from the escrow account. There is a gap of [GAP TO TARGET] which might delay the next milestone which is [DAYS TO NEXT MILESTONE] away unless this gap is covered up in the next few months. This delay is primarily due to poor mobilization by the concessionaire on site in the last few months. Total progress of DBM layer is Xx km, with Yy km pending across the entire stretch. Service road construction is yet to start. Good progress in land acquisition, with only [Pending Land] pending acquisition, all of which is in 3D stage. [COMPENSATION AMOUNT] Cr. Compensation was disbursed in the previous month. Many encroachments and buildings were demolished and land made available. Proposal for diversion of forest land (Xx Ha) submitted to Regional Office on [DD/ MM/ YYYY], MoEF, awaiting final clearance. Now, Xx km of project highway is encumbrance free and available for construction. Current Issues & Recommended Actions by IE: 1. Slow Progress of Structures: The progress of structures (especially, major bridges, flyovers and ROB’s) is very slow. Overall progress is only XX%. Out of the total YY underpasses not even single underpass structure and its approaches is completed so far. No bridge is open to traffic so far. a. Recommendation: Concessionaire should improve the progress of structures. Request for revised workplan from Concessionaire including specific activities on structures. 2. Status of Change of Scope Proposals: Concessionaire has submitted Xx No. Change of Scope proposals. Yy No. of them are still pending for decision. Concessionaire has not submitted necessary clarifications /details for the following Changes of Scope in spite of several reminders. a. Recommendation: Concessionaire to submit all pending clarifications to Authority. Authority and Concessionaire to expedite pending COS proposals. 1.2 1.2.1 Critical Issues & Action Log Pending Issues & Action Log SNo Issue Description 1 Diversion of Xx ha of forest Land 2 21 Cr compensation disbursement pending Type Clearance Land Acquisition Slow progress Concessionaire 3 by Issue concessionaire Ongoing/ Chainage(s) Length New Concerned affected due affected Action(s) taken till now Issue/ Authority to the issue (km) Resolved Ongoing Issue MoEF [Chainage] 1. Proposal submitted to MoEF 4 kms 2. Letter sent by RO to MoEF nodal officer on [DD/MM/YYYY] Resolved [CALA Name] [Chainage] 1. Escalated to chief secretary level through 2.4 km DO from Chairman/ Secretary, dated [DD/MM/YYYY] New Issue [Concess. Name] [Chainage] 57 km None Action(s) suggested by the IE Expected date/ Actual Date for resolving issue Escalate to higher level officers at MoEF [DD/MM/YYYY] [DD/MM/YYYY] Project Director to call higher ups of concessionaire [DD/MM/YYYY] 1.2.2 Obligations as per Contract Expected Contents & Structure Please write a summary of non-compliances of contractual obligations highlighting reasons for delay, stating pending actions and their potential risk to the project’s progress and recommended actions by the IE. Critical obligations and constraints of concessionaire as per contract Critical obligations of authority as per contract Critical pending obligations of IE as per contract NOTE: Please include important issues requiring intervention of various parties, giving details and background wherever necessary ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS 1.3 1.3.1 Project Overview Salient Features of Project Project Name NH No. (New/ Old) Scheme/ Phase Mode of the Execution (BOT Toll/ BOT Annuity/ EPC/ HAM/ Item Rate/ Others) No. of Lanes/ Configuration Length of the Project (in Km) Total Project Cost (in Cr) No. of Bypasses (Name of Town, Length) No. of Major Bridges (Number and Location) No. of Toll Plazas (Number and Location) No. of Fly Overs (Number and Location) DPR Consultant Name Lead & Consortium Members of Banks Concessionaire Name (SPV & Parent Company) Date of Award (LOA Date) Appointed Date Concession Period Construction Period (in Days) O&M Period (in Days) Scheduled Date of Completion Independent Engineer IE Agreement Date IE Mobilization Date 6 ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS 1.3.2 Project Milestones Project Milestone Description (Days from Appointed Date) Planned Actual Physical Physical Scheduled Date Progress (%) Progress (%) Revised Date Delay Current (No. of Status months) Milestone I [Description] 25 [DD/MM/YYYY] 25 [DD/MM/YYYY] 5 Achieved Milestone II [Description] 65 [DD/MM/YYYY] [DD/MM/YYYY] 22 Started, not achieved Scheduled [Description] Completion 100 [DD/MM/YYYY] [DD/MM/YYYY] 21 Not started 7 ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS 1.3.3 Location Map 8 ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS 1.3.4 Key Plan [Above image is illustrative only. Please include chainage and name below the axis and list of features above the axis] 9 ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS 1.4 Physical Progress Physical Progress Physical Progress Component % Weightage Road Works 35.00% 5% (Cumulative, Upto Current Month) 15.0% Major Bridge works and ROB / RUB 40.00% 1.20% 26.2% Structures 21.00% 0.00% 0.8% 4.00% 0.00% 0.0% (During Current Month) Other Works Physical Progress 2% ILLUSTRATIVE LIST OF COMPONENTS. PLEASE USE STANDARD LIST OF COMPONENTS DEFINED IN SCHEDULE G OF CONTRACT AGREEMENT (LIST INCLUDED IN ANNEX 1) 10 42.0% ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS 1.4.1 Detailed Scope of Work & Physical Progress by Component Component 1 Cost Weightage in Project (%) 2 1. Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) 35.00% 2. Major Bridge works and ROB/RUB 40.00% 3. Structures (elevated sections, reinforced earth) 21.00% 4. Other Works 4.00% Item Description Cost Weightage in Component (%) Planned in Scope (As per Scope of Work) Progress till Date % Physical Progress 3 1. C&G 2. Embankment 3. Sub Grade 4. GSB 5. WMM 6. DBM 7. BC 1. Major Bridges 2. Minor Bridges 3. Flyovers 4. ROB 5. VUP 6. PUP 7. RUB 1. Foundation 2. Sub-structure 3. Super-structure 4. Reinforced Earth Wall 1. Toll Plaza 4 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 10.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 6.00% 4.00% 5 80 km 80 km 80 km 80 km 80 km 80 km 80 km 6 No 23 No 2 No 228 No 11 No 15 No 136 No 35 km 35 km 35 km 35 km 4 No 6 45 km 40 km 35 km 33 km 30 km 28 km 27 km 6 No 21 No 0 121 No 6 No 6 No 114 No 2.2 km 2.1 km 2.1 km 2.1 km 0 7 56% 50% 44% 41% 38% 35% 34% 100% 91% 0% 53% 55% 40% 84% 6% 6% 6% 6% 0% GRAND TOTAL 100% ILLUSTRATIVE LIST OF COMPONENTS. PLEASE USE STANDARD LIST OF COMPONENTS DEFINED IN SCHEDULE G OF CONTRACT AGREEMENT (LIST INCLUDED IN ANNEX 1) 11 Value of Physical Progress (7X4) 8 2.8% 2.5% 2.2% 2.1% 1.9% 1.8% 1.7% 10.0% 4.6% 0.0% 2.7% 2.7% 2.0% 4.2% 0.2% 0.2% 0.2% 0.2% 0.0% 42.0% ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS Strip Plan (Details) Not Started/ NA WI 1 WI 2 WI 3 Minor bridges Type of Structures NoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNo NoNoNoNoNoYesYesYes YesNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNo NoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNo COCOCOCOCOM COCOM COM COCOCOCOCOCOCOCOCOCOCOCOCOCOCOCOCOCOCOCOCOCOCOCOM COCOCOCOCOM COCOM COM COCOCOCOCOCOCOCOCOWI COCOCOCOCOCOCOCOCOCOCOCOCOCOM COCOCOCOCOM COCOM COM COCOCOCOCOCOCOCOCOM COCOCOCOCOCOCOCOCOCOCOCOCOCOM COCOCOCOCOM COCOM COM COCOCOCOCOCOCOCOCOM COCOCOCOCOCOCOCOCOCOCOCOCOCOM COCOCOCOCO COCO COCOCOWI COCOWI WI WI COCOCOCOCOCOCOCOCOCOCOCOCOCOM Major Bridge Workfront Available ‐ LA pending ‐ Clearance pending '‐ Other Hindrances C&G Sub‐Grade GSB WMM DBM BC RHS‐Service Road Workfront RHS‐Service Road Const. Bypass Status of Structures Number of Strucrures Completed COCOCOCOCOM CO CO CO COCOWI WI CO COCOCOCOCO COCOCOCOCOCOM COCOCOCOCOM CO CO COM COCOCOCOM COM COCOCOCOCOM COCOCOCOCOCOM COCOCOCOCOM CO CO COM COCOCOCOM COM COCOCOCOCOWI COCOCOCOCOCOM COCOCOCOCOM CO CO COM COCOCOCOM COWI WIP COCOCOCOCOCOCOCOCOCOCOCOM COCOCOCOCOM CO CO COM COCOCOCOM COCOCOM COCOCOCOCOCOCOCOCOCOCOCOM NoNoNoNoNoNoNo NoNoNoNoNoYesYesYes Yes No NoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNoNo Major Bridge Chainage Work In Progress 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62 64 66 68 70 72 74 76 78 80 82 84 LHS‐MCW Workfront LHS‐MCW Construction LHS‐Service Road Const. LHS‐Service Road Workfront BC DBM WMM GSB Sub‐Grade C&G ‐ Other Hindrances ‐ Clearance pending ‐ LA pending Workfront Available RHS‐MCW Wokfront 1.5.1 Strip Plan RHS‐MCW 1.5 12 Workfronnt Available Workfront Unavailable ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS 1.5.2 Strip Plan (Summary) 1. Workfront Unavailable & Reason for Unavailability % Total Prnding Length Length (km) Total Length 80 Total Workfront Unavailable Pending Land Acq. Pending Clearances Encumbrances 1.6 1.6.1 2. Length Completed by Layer (MCW) Length (km) Total Length Total Length Completed (Till DBM) 7 12% 0 0% BC 7 12% 0 0% 3. Length Completed by Layer (Service Road) % Total Length 80 27.5 33% 27 32% DBM 27.5 WMM GSB Sub-Grade C&G 29.5 32.5 35 47.9 Length (km) Total Length Total Length Completed (Till DBM) % Total Length 35 0 0% BC 0 0% 33% DBM 0 0% 35% 39% 42% 57% WMM GSB Sub-Grade C&G 0 0 0 0 0% 0% 0% 0% Land Acquisition and Clearances LA Summary Description Total Required (ha) Total in possession at start (ha) Total to be acquired (ha) Existing ROW 135.00 135.00 0.00 Pvt. Land To be Acquired 240.00 0.000 240.00 Public Land To be Transferred 52.00 50.35 1.65 Grand Total 185 242 427 13 ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS 1.6.2 LA Detail by CALA CALA [CALA 1] [CALA 2] [CALA 3] Grand Total 1.6.3 Total Land left to be Acquired (Ha) 150 67 23 240 3H Pend ing (ha) 3H Done (ha) 15 15 0 0 23 23 38 202 3G Pend ing (ha) Amount Amount Amount Disbursed Pending 3G 3D 3D 3A 3A Awarded Deposited by CALA Amount Done Pending Done Pending Done (Crore (Crore (ha) (ha) (ha) (Ha) (ha) (Crore (Crore Rs.) Rs.) Rs.) Rs.) 15 135 0 150 0 150 396 370 327 43 0 67 0 67 0 67 132 132 120 23 23 0 14 9 0 23 0 0 0 0 38 202 14 226 0 240 528 502 447 66 Clearances Summary Environment Proposal Description Approval of construction in coastal zone Status Obtained Length Impacted Current Stage Nil Issues/ Comments Completed Forest Land Proposal Description Status Diversion of Xx ha ([Chainage]) Pending Diversion of Xx Ha. ([Chainage]) Obtained Length Impacted Current Stage [Length in km] Completed Ongoing Nil 14 Issues/ Comments Stage 1 clearance pending ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS Wildlife Proposal Description Diversion of Xx Ha. of forest land Status Length Impacted Pending [Length in km] Current Stage Ongoing Issues/ Comments Queries sent to MoEF by RO, compliance pending Tree Cutting Proposal Description Status N.A. N.A. Length Impacted Current Stage N.A. N.A. Issues/ Comments N.A. Railways (ROBs/ RUBs) GAD Number Status Location/ Chainage Current Stage [GAD Number] Proposal Submitted, Approval pending [Chainage] Uploaded on portal on [DD/MM/YYYY] 15 Issues/ Comments ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS 1.6.4 Status of utilities shifting Utility Name Category Status Length affected Department Date of Date when Date of Date of Date of request Progress Certification Issue/C Estimate was Approval by Deposit of Estimate by Authority for of Physical from Agency ommen Received from Authority super-vision Amount estimate Shifting for ts concerned dept. RO/ HQ charge Completion Water [DD/MM/YYY [DD/MM/YY Estimate [Length [DEPARTMENT] [DD/MM/YYYY] [DD/MM/YYYY] Not started TBD Y] YY] Approved in km] Electricity [DD/MM/YYY [DD/MM/YY Estimate [Length [DEPARTMENT] [DD/MM/YYYY] [DD/MM/YYYY] Not started TBD Y] YY] Approved in km] Others [DD/MM/YYY [DD/MM/YY Estimate [Length [DEPARTMENT] [DD/MM/YYYY] [DD/MM/YYYY] Y] YY] Approved in km] 1.7 TBD Change of Scope Date of first submission to IE S No. Proposal Details 1 Construction of [Flyover Name] at [Chainage] 2 Nallah diversion through culvert at [Chainage] box Current Status COS Amount Expected/ Actual Date of Approval [DD/MM/YYYY] Approved in principle by Authority. Detailed quantities in proper order yet to be submitted [+/ Amount] [DD/MM/YYYY] [DD/MM/YYYY] Clarifications to be submitted by Concessionaire , expected date [DD/MM/YYYY] [+/ Amount] [DD/MM/YYYY] 16 ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS 1.8 No. Mobilization of Resources Equipment Name Make Model Age of Equipment Planned/ Required Quantity Actual Quantity Excavator/Poclain 5 Paver 2 Transit Meter 0 Plate Compactors 0 [ADD OTHERS] 17 Deployed During the Month Reason(s) for Under/Over Mobilization Expected Delay due to UnderMobilization (Months) Remarks ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS 1.9 1.9.1 Financial Progress Details Pen Picture - Escrow TPC (Cr) Cumulative inflow to Escrow till previous month (Cr) Cumulative outflow from Escrow till previous month Inflow to Escrow during the month (Cr) (Cr) (Cr) 1,206 1,033 900 Outflow from Escrow during the month 30 35 Are the Escrow withdrawals in accordance with the order of withdrawal as specified in the Concession Agreement? Tick as applicable Yes If not, details to be provided below: 18 No ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS 1.9.2 Escrow details TPC (Cr) 1,206 Cumulative exp. till date (Cr) 1,033 (Cr) Escrow Plan till date- Equity (BOT) (Cr) Escrow Plan till date- VGF (BOT) (Cr) Escrow Actual till date- Debt (BOT) (Cr) Escrow Actual till date- Equity (BOT) (Cr) Escrow Actual till date- VGF (BOT) (Cr) 900 306 - 769 264 - Escrow Plan till date- Debt (BOT) PLEASE EXCLUDE OUTSTANDING MOBILIZATION FEE/ ADVANCE IN S-CURVE 19 ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS 1.10 Monitoring of Operations & Maintenance Obligations 1.10.1 Maintenance Status during Construction Phase Expected Contents & Structure Please write a summary of maintenance status in the current month, along with pending items, issues and actions recommended using the following format. 1.10.2 Status of traffic worthiness and safety of project highway Status of necessary repair and maintenance works Compliance of other maintenance obligations as per contract Key issues and recommended action by IE Maintenance Status during Operations & Maintenance Phase (If Applicable) Expected Contents & Structure Please write a summary of maintenance status in the current month, along with pending items, issues and actions recommended using the following format. Status of maintenance of main carriageway, service road and paved shoulders. Status of major maintenance O&M of all communication, control & administrative systems Compliance of maintenance obligations as per contract Key issues and recommended action by IE 20 ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS 1.11 Pen Picture on safety features Details to be provided after assessment of the site requirement vis-à-vis provisions in the Concession Agreement: Location of Black Spots Suggested Remedial Measures within provisions of Concession Agreement Additional Remedial Measures (if any) Financial implications of additional Remedial Measures for Authority (Cr.) 21 ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS 1.12 Annex 1: Detailed List of Physical Components as per Schedule G Component Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) Physical Item A- Widening and strengthening of existing road (1) Earthwork up to top of the sub-grade (2) Granular work (sub- base, base, shoulders) (a) GSB (b) WMM (3) Shoulders (4) Bituminous work (a) DBM (b) BC (5) Rigid Pavement Concrete work (6) Widening and repair of culverts (7) Widening and repair of minor bridges B- New realignment/bypass (1) Earthwork up to top of the sub-grade (2) Granular work (sub- base, base, shoulders) (a) GSB (b) WMM (3) Shoulders (4) Bituminous work (a) DBM (b) BC (5) Rigid Pavement Concrete work C- New culverts, minor bridges, underpasses, overpasses on existing road, realignments, bypasses: (1) Culverts 22 ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS Component Physical Item (2) Minor bridges (a) Foundation (b) Sub-structure (c) Super-structure (including crash barriers etc. complete) (3) Cattle/Pedestrian underpasses (a) Foundation (b) Sub-structure (c) Super-structure (including crash barriers etc. complete) (4) Pedestrian overpasses (a) Foundation (b) Sub-structure (c) Super-structure (including crash barriers etc. complete) (5) Grade separated structures (a) Underpasses (i) Foundation (ii) Sub-structure complete) (iii) Super-structure (including crash barriers etc. (b) Overpass (i) Foundation (ii) Sub-structure complete) (iii) Super-structure (including crash barriers etc. (c) Flyover (i) Foundation (ii) Sub-structure complete) (iii) Super-structure (including crash (d) Foot over Bridge Major Bridge A- Widening and repairs of Major Bridges 23 barriers etc. ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS Component works and ROB/RUB Physical Item (1) Foundation (a) Open Foundation (b) Pile Foundation/Well Foundation (2) Sub-structure (3) Super-structure (including crash barriers etc. complete) B- Widening and repair of (a) ROB (1) Foundation (2) Sub-structure (3) Super-structure (including crash barriers etc. complete) (b) RUB (1) Foundation (2) Sub-structure (3) Super-structure (including crash barriers etc. complete) C- New Major Bridges (1) Foundation (a) Open Foundation (b) Pile Foundation/Well Foundation (2) Sub-structure (3) Super-structure (including crash barriers etc. complete) D- New rail-road bridges (a) ROB (1) Foundation (2) Sub-structure (3) Super-structure (including crash barriers etc. complete) (b) RUB (1) Foundation (2) Sub-structure (3) Super-structure (including crash barriers etc. complete) 24 ALL FIGURES & GRAPHS IN TEMPLATES ARE ILLUSTRATIVE. PLEASE ADD ACTUAL DETAILS Component Structures (elevated sections, reinforced earth) Physical Item (1) Foundation (2) Sub-structure (3) Super-structure (including crash barriers etc. complete) (4) Reinforced Earth Wall (includes Approaches of ROB, Underpasses, Overpasses, Flyover etc. Other Works (i) Service roads/ Slip Roads (ii) Toll Plaza (iii) Road side drains (iv) Road signs, markings, km stones, safety devices, …. (a)Road signs, markings, km stones, …. (b) Concrete Crash Barrier/ W-Beam Crash Barrier in Road work (v) Project facilities (a) Bus bays (b) Truck lay-byes (c) Rest areas (vi) Repairs to bridges/structures (vii) Road side plantation (viii) Protection works (a) Boulder Pitching on slopes (b) Toe/Retaining wall (ix) Tunnel (a) Excavation (b) Construction of support system including rock lining etc. bolting, (c) On complete completion of tunnel (x) Miscellaneous * The above list is illustrative and may require modification as per the actual scope of the work 25