CADANGAN PELEBARAN JALAN DAN MENAIK TARAF
PERSIMPANGAN JALAN LANGAT/JALAN DELIMA 4 DIATAS
SEBHG LOT 67694 MUKIM KLANG, DAERAH KLANG UNTUK
TETUAN GABUNGAN EFEKTIF SDN. BHD.
PROGRESS REPORT
19 July To 31 August, 2018
AUGUST 15, 2018
CIRCUITRY ELECTRICAL ENGINEERING SDN BHD
No.10 & 12, Jalan Bandar 13, Pusat Bandar Puchong, 47100 Puchong, Selangor Darul Ehsan,
Malaysia.
Introduction
Client:
Gabungan Efektif Sdn Bhd
C & S Engineering:
Jurutera TSSC Lim Sdn Bhd
Consultant:
Perunding ICLA Sdn Bhd
Main Contractor:
Benih Hadapan Sdn Bhd
Infrastructure Contractor:
Circuitry Electrical Engineering Sdn Bhd
Contract Value:
RM 530,000.00
Organization Chart
Site Team
Circuitry Electrical
Engineering Sdn Bhd
Mervyn Chan
Project Director
012 202 0323
Prabhim Nair
Project Manager
012 5222 986
Admin & Finance
Team
Key Milestones
No.
1
a
b
c
Milestone
Klang bound
Removal of existing poles
Laying of Conduits
Feeder Pillar Installation
d Streetlight and pole installation
e Laying of Cables
2
3
Current Status
Completed – 100%
Completed – 100%
Pegging Done. Plinth Works Ongoing.
Manufacturing Completed. Awaiting FAT
confirmation from JKR.
Completed – 100%
Completed Laying – 100%
Termination to Feeder Pillar Pending
Temporary supply connections made
HDD Works for Road Crossing
Banting bound
a Removal of existing poles
3 poles removed, balance 17 remaining –
15% complete
b Laying of Conduits
c Streetlight and pole installation
d Laying of Cables
4
Out of Scope Works – Relocation of TM pole
Completed – 100%
Site Photographs
Removal of poles on Klang bound route - 21 poles
Removal of poles on Klang bound route - 21 poles
Removal of poles on Klang heading route - 21 poles
Storage of removed poles
Relocation of TM pole
Relocation of TM pole
Relocation of TM pole
Relocation of TM pole
Material Submission & Approval
Material on Site
Laying of conduit
Laying of conduit
Feeder Pillar Location Pegging
Laying of conduit
Laying of conduit
Laying of conduit
arrival of the 12m octagonal poles
arrival of 12m octagonal poles
Laying the premix after the placement of pipes
Laying of premix after the placement of pipes