CADANGAN PELEBARAN JALAN DAN MENAIK TARAF PERSIMPANGAN JALAN LANGAT/JALAN DELIMA 4 DIATAS SEBHG LOT 67694 MUKIM KLANG, DAERAH KLANG UNTUK TETUAN GABUNGAN EFEKTIF SDN. BHD. PROGRESS REPORT 19 July To 31 August, 2018 AUGUST 15, 2018 CIRCUITRY ELECTRICAL ENGINEERING SDN BHD No.10 & 12, Jalan Bandar 13, Pusat Bandar Puchong, 47100 Puchong, Selangor Darul Ehsan, Malaysia. Introduction Client: Gabungan Efektif Sdn Bhd C & S Engineering: Jurutera TSSC Lim Sdn Bhd Consultant: Perunding ICLA Sdn Bhd Main Contractor: Benih Hadapan Sdn Bhd Infrastructure Contractor: Circuitry Electrical Engineering Sdn Bhd Contract Value: RM 530,000.00 Organization Chart Site Team Circuitry Electrical Engineering Sdn Bhd Mervyn Chan Project Director 012 202 0323 Prabhim Nair Project Manager 012 5222 986 Admin & Finance Team Key Milestones No. 1 a b c Milestone Klang bound Removal of existing poles Laying of Conduits Feeder Pillar Installation d Streetlight and pole installation e Laying of Cables 2 3 Current Status Completed – 100% Completed – 100% Pegging Done. Plinth Works Ongoing. Manufacturing Completed. Awaiting FAT confirmation from JKR. Completed – 100% Completed Laying – 100% Termination to Feeder Pillar Pending Temporary supply connections made HDD Works for Road Crossing Banting bound a Removal of existing poles 3 poles removed, balance 17 remaining – 15% complete b Laying of Conduits c Streetlight and pole installation d Laying of Cables 4 Out of Scope Works – Relocation of TM pole Completed – 100% Site Photographs Removal of poles on Klang bound route - 21 poles Removal of poles on Klang bound route - 21 poles Removal of poles on Klang heading route - 21 poles Storage of removed poles Relocation of TM pole Relocation of TM pole Relocation of TM pole Relocation of TM pole Material Submission & Approval Material on Site Laying of conduit Laying of conduit Feeder Pillar Location Pegging Laying of conduit Laying of conduit Laying of conduit arrival of the 12m octagonal poles arrival of 12m octagonal poles Laying the premix after the placement of pipes Laying of premix after the placement of pipes