ABENGOA CONTRACT NO: N-18138B CONTRACT TITLE : Lot.2, Lot.3, Lot.4: OHL modification and Remote End works for establishing Mahawe-Wathba 220 kV OHL circuit 2 & Dismantling of 220 kV OHLS UNPS-MHWG-WATH-RAMG/KHZG/SHME and 400 kV SASN-MOSG REPLY TO COMMENTS ON DTS : 002 ATTACHMENT TO DTS : TITLE: Lot 2,3 and 4 Master Time schedule CSD No: N18138B CF 7600 X 991 A S/N Comments vide CS-002 040 Reply to comments 1 Program should highlight the pre-requisites as explained at the Contract Kick-Off Meeting The Pre-requisites like submission of performance bank guarantee and Insurance policies is included. 2 Remove the term “MOS”. It is either “Method Statement (MS)” OR “Statement of Method (S-o-M)” and, the former is recommended. Corrected as "Method statement". 3 Appropriate Primavera Original File should also be submitted. The Master time schedule is prepared in MS project and original file (soft) along with the document is included in the folder uploaded in TAQA collaboration portal. 4 Please follow the guidelines of Transco for Reporting Methodology of Time and Cost development program / schedule including reporting procedures. Noted. We have incorporated the baseline & actual planning of the Mastet Time schedule. 5 Brief description of the Scope of work, Legend for abbreviations, details of project calendar for review, Engineering, procurement, and construction etc., shall be included in the Master Time schedule. Legends for abbreviation is included in the bottom of the each sheet. The schedule includes the different stages like engineering and construction as applicable under the subject contract. 6 Please show the total float, free float, and critical path for the proposed Incorporated. master time schedule. 7 Work Breakdown Structure (WBS), dependencies are not logically / Noted and corrected in the new baseline plan. sequentially linked. For example, WBS ID: 1.3.4 – prep & submission of MS for dismantling of 400KV OHL is between 15th July – 20th July, whereas WBS ID: 1.5.1.4 dismantling of section commences between 04th July. Scaffolding Method statement submission is on 10th July and the works are shown as commencement on 04th July. Please check and correct all WBSs. Please check and correct in Lot 2, Lot3 & Lot 4. 8 Master project schedule shall be corrected as Project Baseline Programme/Schedule and WBS structure shall be limited to level 3. The detailed Level – 4 shall be submitted to project supervision team, prior to execution. Master project schedule is corrected as Project Baseline Schedule. WBS is limited to level 3 which spans the entire project and includes major milestones in document submissions, construction and importat stages applicable in the project. 9 WBS ID: 1.5.1.4.7 – Transportation of material to Transco stores, all dismantled conductors and accessories shall be shifted on daily basis and link shall be updated accordingly. This applicable for all lots. he WBS for transportation of materials is linked to the completion of destringing works & other OHL materials and may not happen daily in practical situation and the dates indicated in the schedule are planned dates only. Actual dates will be monitored and entered as actual start and actual finish during the progress of work. 10 WBS shall be prepared inline to contract BOQ and operative systems/sub-systems. Contract BOQ is only a Lot item. No breakdown of activities or items is provided in the BOQ from client/consultant and covers only dismantling of OHL and material handover as just lot items. 11 Master baseline schedule completion is earlier than the contract completion period Pease check and re-confirm. the observation is correct. The acual start and actual finish date may change according to the delays beyond Inabensa control (for example , receiving traffic detour permits, delay in providing shutdowns, delays in receiving NOCs etc) 12 WBS ID: 1.5.2 - LOT 3: - DISMANTLING MHWG-WATH- 220kV OHL The scope related to Lot 3 and its related activities are included in Ckt. 1 & 2 and MAHAWE 220kV S/S – Telecom modification works for the Baseline schedule. MHWG and WATH missed out. Please revise and include 13 WBS ID: 1.5.2.3 - REMOVAL OF SINGLE OPGW ASSOCIATED WITH MHWG-WATH D/C OHL & WBS ID: 1.5.2.7.3 & 1.5.2.8.3 OPGW DISMANTLING to be justified. Both are same activities. Noted and corrected. ABENGOA CONTRACT NO: N-18138B CONTRACT TITLE : Lot.2, Lot.3, Lot.4: OHL modification and Remote End works for establishing Mahawe-Wathba 220 kV OHL circuit 2 & Dismantling of 220 kV OHLS UNPS-MHWG-WATH-RAMG/KHZG/SHME and 400 kV SASN-MOSG REPLY TO COMMENTS ON DTS : 002 ATTACHMENT TO DTS : TITLE: Lot 2,3 and 4 Master Time schedule CSD No: N18138B CF 7600 X 991 A S/N 14 Comments vide CS-002 In Master Time Schedule (Project Baseline Programme/Schedule), Contract Title ”N-18138/B”, Project title, revision status etc., shall be updated. 15 Please be suggested to use the below Lot references (extract from SOW/LOA) in the milestone and all appropriate places as required. Noted and incorporated. 16 Please refer “DTS-003” for Additional comments. noted and complied as applicable. 17 Please update Rev status on DTS top sheets & CSD sheet. Updated rev status in the DTS top sheets and CSD sheet. Project Manager: Reply to comments Noted and incorporated. 040