Corrosion & Inspection Mari Daharki Field Asset Integrity Report – 2021 CONTENTS 1- Purpose 2- Executive Summary 3- MPCL Daharki Overview 4- Reservoir Composition 5- Mari Field Assets 5.1 – Wells 5.2 – Processing Facilities 5.3 – Junctions/Manifolds 5.4 – MPCL Gas Gathering Network 6- Damage Mechanisms (HRL, SML, PKL & Goru-B) 7- Corrosion & Inspection Control Framework 8- Work Plan 2021 9- Leak History 10- HSE Highlights 11- Asset Integrity Campaigns 11.1 - LRUT 11.1.1 – Survey Results 11.2 – Thickness Survey 11.2.1 – A scanning/ UFD Assessments 11.2.2 – A scanning Results 11.2.3 – Thickness Mapping Campaigns 11.3 – ECDA 11.4 – Cathodic Protection 11.4.1 – New Solar Based CP System Installation 11.4.2 – Third Party CP System Assessment 11.5 – Risk Based Inspection Study 11.6 – MDCPF ATA 11.7 – MDCPF Storage Tanks A & B 11.8 – Root Cause Failure Analysis 11.9 – Pipeline Pigging 11.10 – Inspection of Storage Tanks & Vessels Mari Petroleum Company Limited Page 2 Asset Integrity Report – 2021 11.11 – Kill Lines Survey 11.12 – Exposed Pipeline Survey 11.13 – Piping Supports Survey 11.14 – Pipeline Bell Holes Inspection Survey 11.15 – Underground Pipeline Accessibility Survey 11.16 – Pipeline Cellars Survey 11.17 – Well Casings Integrity Survey 11.18 – Isolation Gasket Survey 12- Circadian Activities 12.1 – Corrosion Inhibitor Injection 12.2 – C scan Survey 12.3 – Weight Loss Coupons 12.4 – Electrical Resistance Probes 12.5 – Pipe to Soil Potential Survey 12.6 – Holiday Detection 12.7 – Positive Material Identification 12.8 – Water Sampling 13- Asset Integrity Services To Satellite Fields 14- Challenges 15- Major Planned Activities FY: 2022~23 16- System Advancement Proposals List of Figures Figure-1: Well Formations Figure-2: Reservoirs Composition Figure-3: Daharki Field Assets Figure-4: Leak History Of Previous 4 Decades Figure-5: Leak History of 2021 Figure-6: HSE Tool Box Talk Figure-7: LRUT Activity Figure-8: Thickness Monitoring Activity Figure-9: A-scanning Activity Mari Petroleum Company Limited Page 3 Asset Integrity Report – 2021 Figure-10: ECDA Activity Figure-11: Anode Boring Activity Figure-12: RBI Matrix Figure-13: TEG Dehydration Unit Figure-14: MDCPF Condensate Storage Tank A & B Figure-15: Pipeline Pigging Figure-16: Vessels & Tanks Inspections Figure-17: Kill Lines Figure-18: Exposed Pipelines Figure-19: Piping Support Survey Figure-20: Pipeline Bell Hole Inspection Figure-21: Underground Pipeline Accessibility Survey Figure-22: Well Casing Integrity Figure-23: Isolation Gaskets Figure-24: Corrosion Inhibitor Injection Deep Figure-25: C-scan Survey Figure-26: Weight Loss Coupons Figure-27: ER Probe Data Recording Activity Figure-28: PSP Data Recording Activity Figure-29: Holiday Detection Figure-30: Positive Material Identification Figure-31: Produced Water Sample Collection & Analysis Figure-32: Zarghun Field Visit Activities Figure-33: Koonj Field Visit Activities List of Graphs Graph-1: Reservoirs Gas Composition Graph-2: Corrosion & Inspection Control Framework Graph-3: Leak History of Previous 4 Decades Graph-4: Leak History of 2021 Graph-5: LRUT Survey Results Graph-6: LRUT Phase I Thickness Graph-7: LRUT Phase I MAWP Graph-8: LRUT Phase II Thickness Mari Petroleum Company Limited Page 4 Asset Integrity Report – 2021 Graph-9: LRUT Phase II MAWP Graph-10: LRUT Phase III Thickness Graph-11: LRUT Phase III MAWP Graph-12: LRUT Phase IV Thickness Graph-13: LRUT Phase IV MAWP Graph-14: LRUT Phase V Thickness Graph-15: LRUT Phase V MAWP Graph-16: Thickness Survey Graph-17: A-scanning MAWP Goru-B Graph-18: A-scanning MAWP CMF-I Graph-19: A-scanning MAWP CMF-II Graph-20: A-scanning MAWP Phase I Wells Graph-21: A-scanning MAWP Phase I KODs Graph-22: A-scanning MAWP Phase II Wells Graph-23: A-scanning MAWP Phase II KODs Graph-24: Pipeline Pigging Graph-25: Kill Lines Thickness Survey Graph-26: Corrosion Inhibitor Injection Plan Graph-27: Weight loss Coupons HRL Graph-28: Weight loss Coupons SML Graph-29: Weight loss Coupons Goru-B Graph-30: Average Corrosion Rate Of Goru-B Graph-31: Average Corrosion Rate Of Shallow Graph-32: PSP Reading Of Well 3 To 50 Graph-33: PSP Reading Of Well 50 To 100 Graph-34: PSP Reading Of Wells & Other Assets Graph-35: PSP Reading Of Deep Wells Graph-36: PSP Reading Of Other Deep Assets Graph-37: Produced Water Analysis Trend List of Tables Table-1: Daharki Field Wells Table-2: Processing Facilities Table-3: Junctions / Manifolds Table-4: MPCL Gathering Network (Reservoirs) Mari Petroleum Company Limited Page 5 Asset Integrity Report – 2021 Table-5: MPCL Gathering Network (Pipeline Sizes) Table-6: Corrosion Severity Analysis Goru-B Table-7: Corrosion Severity Analysis HRL Table-8: Corrosion Severity Analysis SML Table-9: Corrosion Severity Analysis PKL Table-10: Work Plan 2021 Table-11: MARI Field Daharki Leaks in 2021 Table-12: LRUT Scope Table-13: A-scanning Scope Table-14: A-scan Result Summary Table-15: External Corrosion Direct Assessment Table-16: Assets Protected by CP Table-17: Other Assets Protected by CP Table-18: New Solar System Installation Table-19: RBI Locations Table-20: MDCPF ATA Recommendations Table-21: Repair Works on Storage Tanks A & B Table-22: Root Cause Failure Analysis Table-23: Exposed Pipeline Survey Table-24: Piping Support Sizes Table-25: Thickness Data Of Bell Hole Inspection Survey Table-26: Underground Pipeline Accessibility Survey Table-24: Pipeline Cellars Table-25: Isolation Gaskets Required Sizes Table-26: Isolation Gaskets Locations Table-27: C-scan Survey Loops Table-28: Holiday Detection loops Table-29: AIC Remote Fields Visits Table-30: Major Planned Activities FY: 22-23 Table-31: System Advancement Proposals Mari Petroleum Company Limited Page 6 Asset Integrity Report – 2021 Appendices Annexure 1: LRUT Annexure 2: A-scanning Annexure 3: Thickness Mapping Campaign Annexure 4: ECDA Annexure 5: Third Party CP Assessment Annexure 6: MDCPF ATA Report Annexure 7: MDCPF Storage Tanks A & B Reports Annexure 8: Portable Condensate Tanks Inspection Reports Annexure 9: Kill Lines Survey Annexure 10: Exposed Pipeline Survey Annexure 11: Piping Support Survey Annexure 12: Pipeline Bell Hole Inspection Annexure 13: Underground Pipeline Accessibility Annexure 14: Pipeline Cellars Survey Annexure 15: Well Casing Integrity Survey Annexure 16: Zarghun Field Visit Annexure 17: Koonj Field Visit Mari Petroleum Company Limited Page 7 Asset Integrity Report – 2021 Acronyms MPCL: MARI Petroleum Company Limited PSP: Pipe to Soil Potential TCF: Trillion Cubic Feet WLC: Weight Loss Coupons MMSCFD: Million Standard Cubic Feet per Day TEG: Tri-ethylene Glycol BTU: British Thermal Unit NDT: Non Destructive Technique MDCPF: MARI Deep Central Processing Facility SCC: Stress Corrosion Cracking SVPF: Swing Volume Processing Facility MPI: Magnetic Particle Inspection HRL: Habib Rahi Limestone Reservoir ECT: Eddy Current Testing SML: Sui Main Limestone PAUT: Phased Array Ultrasonic Testing PKL: Pirkoh Limestone Reservoir CRA liner: Corrosion Resistant Alloy Deep: Goru-B Reservoir VBT: Vacuum Box Testing CMF-I & II: Central Manifold I & II MFL: Magnetic Flux Leakage HRL DBN: Debottlenecking Project of HRL Loops KOD: Knock Out Drum CP: Cathodic Protection RCFA: Root Cause Failure Analysis LRUT: Long Range Ultrasonic Testing MFD: MARI Field Daharki UFD: Ultrasonic Flaw Detection TPI: Third Party Investigation RBI: Risk Based Inspection ROW: Right Of Way ECDA: External Corrosion Direct Assessment UTG: Ultrasonic Thickness Gauging CP: Cathodic Protection SPM: Side Pocket Mandrel ATA: Annual Turn around ICDA: Internal Corrosion Direct Assessment ER probe: Electrical Resistance Probe ICMS: Integrated Corrosion Management System C.I: Corrosion Inhibitor Mari Petroleum Company Limited Page 8 Asset Integrity Report – 2021 1 - Purpose: The report gives the insight of Mari Daharki Field Asset Integrity Activities during Year-2021. 2 - Executive Summary: To ensure the longevity of Mari field, being the back bone of fertilizer industry and key contributor to the food security of the country, full scale Asset Integrity inspection campaigns were launched for fixed assets during the year 2021. State of the art inspection tools and assessment methodologies prevalent in the industry were made part of these campaigns to assess the current health and fitness for service suitability. These assessments increased the confidence level regarding integrity health of our assets and delivered extensive baseline data of facilities which would be helpful in future trending and analysis. In addition, critical repairs and component replacements were advised in light of these inspections beforehand hence preventing hydrocarbon releases, unplanned downtimes and safety incidents. Major activities executed by Corrosion & Inspection section during the year 2021 included • Long Range Ultra Sonic Testing of Underground Pipelines and Well Casings • Annual Inspection of Processing Facilities in turn around • A-Scanning & Visual Inspection of Wellhead Surface & Gathering Facilities • External Corrosion Direct Assessment of 12 Production Critical loops • Third Party Assessments of Cathodic Protection Systems of Well Casings & Pipelines • Risk Based Inspection Pilot Project for 4 Wells, CMF I, II • In-house Storage Tanks Inspection, Kill Line Survey, Piping Supports Survey, Pipeline Pigging & Root Cause Failure Analysis • Internal & External Corrosion Monitoring and Mitigation of Well Casings, Pipelines, Vessels and Storage Tanks • Asset Integrity Support Services to Satellite Fields • Close liaison with Maintenance & Asset Integrity Team for System Upgradation and Improvement In light of above campaigns and in house surveys, significant interventions such as coating replacement of 10 pipeline loops (19.35 km), Repair of MDCPF TEG Contactor tower, Replacement of MDCPF Condensate Storage Tanks bottom and Replacement of piping fittings at MDCPF wellheads were recommended. In addition, multiple upgradation projects like Pipeline Cellars Uplifting, Piping Supports revamping, Industrial grade painting of piping and exposed well casings and upgradation of CP system have been conceived on the basis of inspection results. Moreover, green initiatives such as conversion of CP power sources from fuel gas to solar system were started to make our systems more sustainable, environment friendly and minimize carbon footprint. The team remained committed to promote and pursue excellence Mari Petroleum Company Limited Page 9 Asset Integrity Report – 2021 by maintaining highest standards of Health and Safety which resulted in achieving approximately 31,000 Safe Man Hours during asset integrity campaign execution phase this year. The upcoming year presents new challenges to the team as we embark upon a new journey with the vision to consolidate on the achievements of last year. Major projects include procurement and commissioning of Inspection Data Base Management Software, Upgradation of Downhole Corrosion Monitoring & Injection System, Static Equipment Integrity Surveys covering Pressure Vessels and Pipelines and implementation of Asset Integrity framework in true letter and spirit. 3 - MPCL Daharki Overview • MPCL Daharki is the largest Field in terms of remaining gas reserves, daily gas production (Avg.750 MMSCFD) and covers area of 969.27 sq. km. It is located 74 Km (NE) from Rahim Yar Khan and 94 Km (SW) from Sukkur City. The field consists of 149 wells, 398.90 km of gathering pipelines infrastructure and 2 gas processing facilities (MDCPF & SVPF). Mari Field Daharki is a major contributor in country’s urea production (90% Urea Production of Pakistan) thus ensuring National food security. • The field consists of the following types of assets: Wells of 4 different reservoirs(HRL , SUL & SML , PKL & Goru-B) Pipelines Gathering Manifolds (CMF-I & CMPF-II) Gas processing facilities(SVPF & MDCPF) Well Formations: SUL / SML Formation HRL PKL Goru-B 2.813" TRSCSSSV 20" Conductor pipe 13-3/8" Casing Shoe Tubing: 3-1/2", 9.3 ppf, L-80, BTS-8 B x P 7" Liner Top 9-5/8" Casing Shoe 7" Hydraulic Packer Sui Upper Limestone (Top @ 1040 m) 7" Permanent Packer Sui Main Limestone (Top @ 1120 m) 7" Liner Shoe s Total No of Wells Drilled = 7 Formation top PKL = ±500 m Avg. Production = 7 MMDCFD Avg. BTU = 731 BTU/SCF Total No of Wells Drilled = 116 Formation top HRL = ± 700 m Avg. Production = 650 MMSCFD Avg. BTU = 736 BTU/SCF Mari Petroleum Company Limited PBTD Total No of Wells Drilled = 10 Formation top SUL / SML= ± 1100 m Avg. Production = 45 MMSCFD Avg. BTU = 860 BTU/SCF Total No of Wells Drilled = 16 Formation top = ± 2600 m Avg. Production = 57 MMSCFD Avg. BTU = 530 BTU/SCF Page 10 Asset Integrity Report – 2021 4 - Reservoir Compositions: Avg. Heating Value: 736 Btu/scf Avg. Heating Value: 860 Btu/scf Methane, 82.4% Methane, 72.0% Ethane, 0.2% Carbon Dioxide 10.0% Ethane 1.0% Nitrogen, 17.8% Nitrogen, 13.6% SML Gas Composition HRL Gas Composition Avg. Heating Value: 545 Btu/scf Avg. Heating Value: 731 Btu/scf Nitrogen 11% Methane, 71.2% Ethane, 0.0% Nitrogen, 25.9% Carbon Dioxide 10.0% Carbon Dioxide 10.0% Other 1% Methane 45% Corbon Dioxide 41% Eathane 2% PKL Gas Composition Goru-B Gas Composition Graph: Reservoirs Composition Mari Petroleum Company Limited Page 11 Asset Integrity Report – 2021 5 - Daharki Field Assets MPCL Daharki Field Wells Processing Facilities Pipeline Gathering Network Junctions/Sub Manifolds 5.1 - Wells Reservoir Name No of Wells HRL 116 SML 10 PKL 07 Goru-B 16 Total Wells 149 5.2 - Processing Facilities MARI Daharki Field Processing Facilities 1 Mari Deep Processing Facility 2 Swing Volume Processing Facility Mari Petroleum Company Limited Page 12 Asset Integrity Report – 2021 5.3 - Junctions & Manifolds MARI Daharki Field Junctions & Manifolds HRL 20 PKL 2 Deep 5 Sub Manifolds 4 Manifolds 3 5.4 - MPCL Pipeline Gathering Network Sr. Pipeline 1 HRL 264.75 2 SML 38.50 3 PKL 16.87 4 Goru-B 35.66 5 HRL DBN 43.13 Total 398.90 km Sr. Pipe Diameter 1 2 3 4 5 6 7 6" 8" 10" 12" 14" 16" 20" Total Mari Petroleum Company Limited Network Length (KMs) Network Length (KMs) 167.80 106.6 56.9 11.8 11.9 17.0 26.9 398.90 km Page 13 Asset Integrity Report – 2021 6 - Damage Mechanisms (HRL, SML, PKL & Goru-B) 6.1 - Goru-B The CO2 and H2S enriched gas (37-41 mole % CO2, 10-11ppm H2S) is passing through Mari Deep flow lines which is can potentially cause both Sweet (CO2) Corrosion & Sour (H2S) Corrosion.CO2 corrosion results when CO2 dissolves in water to form carbonic acid (H2CO3). The acid lowers the system pH which promotes general corrosion and/or pitting corrosion. Wet H2S corrosion can occur, if system has even 1ppm of H2S gas which can cause steel blisters and cracking. Corrosion Severity Analysis – Under API-571 & API-581 CO2 Corrosion Susceptible Conditions Mari Deep Conditions Partial pressure of C02 above 30 psig. Existing C02 partial pressure is 311 psig. System pressure above 250 psig. Temperature below 284F increases the corrosion process. pH value 4.5~6 can accelerate corrosion. Carbon steel and Alloy steel are most affected materials. System running pressure is 760psig i.e. 510 psig above the limit. System temperature is 77F which is 207F below the limit. Existing pH is 4 -5.5 Valve Bodies and piping material is Carbon Steel. Wet H2S Corrosion Susceptible Conditions Carbon steel and Alloy steel are affected materials. Presence of as little as 1 ppm of H2S is sufficient to cause Sulfide Stress Corrosion Cracking. Presence of only 1 ppm of H2S is sufficient to cause hydrogen charging of steel. Sulfide Stress Corrosion (SSC) generally occurs below 180F. Wet H2S attack is more susceptible, if there is free water pH<4 with some dissolved H2S present. Mari Deep Conditions Piping material is Carbon Steel. 10~13 ppm H2S is present in gas stream. System temperature is 77F i.e. 103 F less than the limit. In Close piping loops pH<4 can be anticipated with dissolved H2S. Table-6: Corrosion Severity Analysis Goru-B Mari Petroleum Company Limited Page 14 Asset Integrity Report – 2021 6.2 - HRL It is the largest reservoir of the field with the production of 650MMSCFD Gas composition of this reservoir has nominal CO2 (mol % 10 CO2).This CO2 dissolves in water to form carbonic acid (H2CO3). The acid lowers the system pH which promote general corrosion and/or pitting corrosion and is transferred to customers through flow lines at CMF-I & CMF-II. Corrosion Severity Analysis – Under API-571 & API-581 CO2 Corrosion Susceptible Conditions HRL Conditions Partial pressure of C02 above 30 psig. Existing C02 partial pressure is 20 psig. System running pressure is 200 psig i.e. 40 psig lower than the limit. Temperature below 284F increases the corrosion System temperature is 80 F which is 204 F below the process. limit. pH value 4.5~6 can accelerate corrosion. Existing pH is 6.5-7.5 Carbon steel and Alloy steel are most affected Valve Bodies and piping material is Carbon Steel. materials. System pressure above 250 psig. Wet H2S Corrosion Susceptible Conditions Carbon steel and Alloy steel are affected materials. Presence of as little as 1 ppm of H2S is sufficient to cause Sulfide Stress Corrosion Cracking. Presence of only 1 ppm of H2S is sufficient to cause hydrogen charging of steel. Sulfide Stress Corrosion (SSC) generally occurs below 180F. Wet H2S attack is more susceptible, if there is free water pH<4 with some dissolved H2S present. HRL Conditions Piping material is Carbon Steel. 0 ppm H2S is present in gas stream. System temperature is 80 F Existing pH is 6.5-7.5 Table-7: Corrosion Severity Analysis HRL Mari Petroleum Company Limited Page 15 Asset Integrity Report – 2021 6.3 - SML This reservoir contains both CO2 and H2S (3.7 mol% C & 0-3 ppm H2S) which require greater precautions. 1ppm of H2S gas is adequate for steel Hydrogen charging causing blisters and cracking. And CO2 can convert to Carbonic acid on contact with water to produce acidic environment. Transportation of this gas is done through CMF-I to customers. Corrosion Severity Analysis – Under API-571 & API-581 CO2 Corrosion Susceptible Conditions SML Conditions Partial pressure of C02 above 30 psig. Existing C02 partial pressure is 11.84 psig. System pressure above 250 psig. Temperature below 284F increases the corrosion process. pH value 4.5~6 can accelerate corrosion. Carbon steel and Alloy steel are most affected materials. System running pressure is 320 psig i.e. 70 psig lower than the limit. System temperature is 74 F which is 210 F below the limit. Existing pH is 6.5-7.5 Valve Bodies and piping material is Carbon Steel. Wet H2S Corrosion Susceptible Conditions Carbon steel and Alloy steel are affected materials. Presence of as little as 1 ppm of H2S is sufficient to cause Sulfide Stress Corrosion Cracking. Presence of only 1 ppm of H2S is sufficient to cause hydrogen charging of steel. Sulfide Stress Corrosion (SSC) generally occurs below 180F. Wet H2S attack is more susceptible, if there is free water pH<4 with some dissolved H2S present. SML Conditions Piping material is Carbon Steel. (0.0 -3.0) ppm H2S is present in gas stream. System temperature is 74F Existing pH is 6.5-7.5 Table-8: Corrosion Severity Analysis SML Mari Petroleum Company Limited Page 16 Asset Integrity Report – 2021 6.4 - PKL Like all other shallow wells this reservoir’s gas is also transported to customers through CMF-II facility and its gas contains 0 ppm H2S and 5.4 mol % CO2. Corrosion Severity Analysis – Under API-571 & API-581 CO2 Corrosion Susceptible Conditions Partial pressure of C02 above 30 psig. System pressure above 250 psig. PKL Conditions Existing C02 partial pressure is 9.18 psig. System running pressure is 170 psig i.e. 70 psig lower than the limit. System temperature is 70 F which is 214F below the limit. Existing pH is 7-7.5 Temperature below 284F increases the corrosion process. pH value 4.5~6 can accelerate corrosion. Carbon steel and Alloy steel are most affected Valve Bodies and piping material is Carbon Steel. materials. Wet H2S Corrosion Susceptible Conditions PKL Conditions Carbon steel and Alloy steel are affected materials. Piping material is Carbon Steel. Presence of as little as 1 ppm of H2S is sufficient to cause Sulfide Stress Corrosion Cracking. 0 ppm H2S is present in gas stream. Presence of only 1 ppm of H2S is sufficient to cause hydrogen charging of steel. Sulfide Stress Corrosion (SSC) generally occurs System temperature is 70F below 180F. Wet H2S attack is more susceptible, if there is free pH is 7-7.5 water pH<4 with some dissolved H2S present. Table-9: Corrosion Severity Analysis PKL * Apart from CO2 and H2S Microbiologically influenced corrosion (MIC) is a threat that is prone to cause damage in the gathering network of all reservoirs. The same aspect has also been highlighted by the third party during RBI study. 7 - Corrosion and Inspection Control Framework: Owing to the aging assets, corrosion monitoring and mitigation is utmost need of hour to extend the useful life of existing assets. Modern researches have resulted in development of availability various corrosion control tools and methodologies which are extremely beneficial for the successful operation of gas pipelines even under high corrosive environment. Although, Mari Daharki field’s process fluid composition and conditions are favorable to produce CO2 and Wet H2S corrosion, relevant API & NACE guidelines have successfully been implemented to counter the corrosion menace with cautious monitoring. Pipeline corrosion assessment history also unfolds that corrosion phenomenon has successfully been arrested by executing the following corrosion control framework Mari Petroleum Company Limited Page 17 Asset Integrity Report – 2021 Corrosion and Inspection Control Framework Corrosion Management System AICs to remote fields Inspection/AICs Internal Corrosion Control In-house Inspection Well Casing Integrity Third Party Inspection LRUT Tanks & Vessels Inspection RBI Pipeline Cellars Survey A-scan Isolation Gasket Survey ECDA Pipe Support Survey CP Assessment Exposed Pipeline Survey MDCPF ATA Root Cause Failure Analysis MDCPF Storage tank A&B Kill lines Survey External Corrosion Control Monitoring Plan Control Plan Monitoring Plan Control Plan Weight Loss Coupons (WLCs) Analysis Pipeline Pigging Coating C-scan Survey PSP data Analysis Electrical Resistance (ER) Probes Corrosion Inhibitor (CI) Injection Pipe to Soil Potential Survey (PSP) Water Sampling Soil Resistivity Survey Iron Counts RCI Monitoring Thickness Mapping Campaigns Holiday Detection Thickness Data Analysis CP system & Solar System Revamping TEG maintenance Solar System Installation Gaskets maintenance Pipeline Bell-hole inspection Survey Corrosion Logging report Analysis Underground Pipeline Accessibility Survey Mari Petroleum Company Limited Page 18 Asset Integrity Report – 2021 8 - Work Plan 2021 Corrosion & Inspection Section Frequency Locations Thickness Surveys*: Annually Annually Annually 1 Thickness Monitoring of Deep Pipelines 2 Thickness Monitoring of Shallow Pipelines 3 Thickness Monitoring of Tanks 08 X Wells 40 wells per year 19 X Tanks Hardness Surveys: 1 Hardness survey of Deep Pipelines & Shallow Pipeline ER Probes Data Recording: 1 ER Probes data recording of Mari Deep 2 ER Probes data recording of Shallow Weight Loss Coupons Analysis: 1 Weight Loss Coupons analysis of Mari Deep 2 Weight Loss Coupons analysis of Shallow Pipe - To - Soil Potential Surveys: 1 All Wells Casings & Pipelines On Requirement Monthly Monthly 09 X Locations 136 X Locations Bi Annually Bi Annually 09 X Locations 70 X Locations Quarterly 01-149 X Wells 02-CMF-I & CMF-II 03-MDCPF Plant 04-Turbine 05-Nara Canal Quarterly 01-149 X Wells 02-CMF-I & CMF-II 03-MDCPF Plant 04-Turbine TEG Maintenance & Repair: 1 All installed TEGs Corrosion Inhibitor Injection: All Wells Casings & Pipelines After 22-24 Days Pipeline Pigging: 1 Pipelines pigging is performed as per plan & the availability of pipelines. 1 149 X Wells Soil Resistivity Survey: 1 Soil resistivity survey is performed as per requirement. Assets Integrity Campaigns: 1 A-Scanning/UFD Services for 100 x HRL, 08 x Deep Wells 16 x Junctions / Manifolds & above ground piping at CMF-I & II 30-Jun-22 2 LRUT Survey 01-233 Underground Pipelines Loops 02-54 X Canal Crossings 03-150 X Risers 04- 67 Well Surface Casings 30-Jun-22 10-April to 31st -December-2021 5 ECDA Survey of 12 Production Critical Pipeline Loops Cathodic Protection System Performance Assessment Survey at Mari Field Daharki 25 Solar Powered System Installations 6 96 Isolation Gaskets Installation 5-Apr-22 7 CP Post Installation at 66 X Locations 10-Jan-21 8 RBI of CMF-I, CMF-II, Well-12, SMl-01, PKl-01 & MD-02 15-Feb-22 9 Asset Integrity Campains of Remote Fields Jan, Feb & August 3 4 11-June to 20-August-2021 28-Apr-21 *Thickness Survey frequency shall be revised according to RBI outcomes. Mari Petroleum Company Limited Page 19 Asset Integrity Report – 2021 9 - Leakage History Mari Daharki Field -Historical Leak Trend 1982 to 2020 - Data is Based on Departmental Information - No Formal Leak Report is available 6 5 5 NO OF LEAKS 4 4 4 3 3 3 3 No Leakage Records Available 3 3 3 2 2 2 2 2 1 1 1 1 1 1 1 0 0 0 YEAR 1983 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2019 2017 2015 2013 2011 2009 2007 2005 2003 2001 1999 1997 1995 1993 1991 1989 1987 1985 YEAR Leaks in 2021 Leaks History - Year 2021 6 5 5 No. of Leaks 4 4 3 2 2 2 2 1 1 1 1 0 0 January February March April May July August November December Months Mari Petroleum Company Limited Page 20 Asset Integrity Report – 2021 Mari Field Daharki Leak Events - 2021 Sr. # 1 Descriptions Locations 1/2 inch line CMF-I Leakage of 1/2 inch line 2 TEG Reboiler 3 Instrument gas package regulator Nozzle CMF-I MDCPF Plant MD-06 to MD-14 Date Month 5-Jan-21 Nos. of Leak 1 January 30-Jan-21 1 2-Feb-21 1 February 4 2" Flare-weld Access Fitting Assembly on 20” pipeline 2" Fitting W-17 6-Feb-21 1 5 Well head piping 6" CS/SS Portion MD-09 6-Mar-21 1 6 Condensate Storage Tank-A Tank MDCPF Plant 7-Mar-21 1 7 8” Bypass meter run of M/s Engro Fertilizers Limited CMF-I 10-Mar-21 1 8 Well No.04 pipeline leakage Well # 04 24-Mar-21 1 9 Upstream elbow of KOD W-95 9-Apr-21 8" Pipeline 6" Elbow March 1 April 10 KOD Water drain line leakage Well # 65 25-Apr-21 11 Gas pipeline leakage Colony 31-May-21 May 1 12 Condensate Storage Tank-B Tank MDCPF Plant 28-Jul-21 July 1 13 Bhittai-3 to Well-04 (Tie-In JCT-221 Pipeline), Approx. 1740 Meter, 6-Inches (WT: 5.02 mm) 6" Pipeline Near W88 26-Aug-21 August 1 14 Drain Line 8" pipeline MDCPF Plant 3-Nov-21 15 Glycol Absorber PSV Nozzle 1" Nozzles CMF-II 8-Nov-21 16 Water Disposal Well 2" Pipeline CMF-II 11-Nov-21 1 17 Bhittai-3 Tank Leakage Tank Bhittai-3 19-Nov-21 1 18 Bhittai-1 Tank leakage Pipeline Bhittai-1 22-Nov-21 1 Total Nos. of Leaks 1 1 November 1 18 10 - HSE Highlights Extensive Asset Integrity Campaigns were launched in the past year for evaluation of Aging Physical Assets with the aim to maintain continuity of operations, increased assets availability, Reduction in Safety and Environmental Hazards from leaks and compliance with statutory and corporate HSE requirements. All activities were carried out with utmost regard of prevailing MPCL safety policies and resulted in approximately 31,000 safe man hours. Mari Petroleum Company Limited Page 21 Asset Integrity Report – 2021 Safety Talk Session 11 - Asset Integrity Campaigns 11.1 - LRUT A ring of transducers is fitted around the pipeline and the transducers generate and receive low frequency ultrasonic guided waves along the pipe. The returning echoes indicate defects such as corrosion and other abnormalities. This method therefore saves time and money that would otherwise be spent on excavation at extended span of pipelines, coating inspection and recoating. LRUT Activity LRUT Shallow Well Casing Coating brittleness / cracks observed LRUT Scope Phase I to X underground Pipelines (233 loops) 67 Well Surface Casings 54 Canal Crossings 150 risers Mari Petroleum Company Limited Page 22 Asset Integrity Report – 2021 • • • • • Sample based LRUT is under way @ 2 to 3 shots per KMs, 114/233 pipeline segments have been completed. Phase-1 ~ 5 & well casing reports have been submitted by M/s SGS. Phase-6 Pipelines & Risers Scanning is underway. Phase-7 and onwards is to be completed by June 2022 11.1.1 - Survey Results Phase 1-3 •MAWP > Operating pressure. Pipelines are safe to operate at current parameters. •Pipeline coating condition were found satisfactory at all bell holes locations. •Coating damaged and disbondment issues were observed at exposed pipeline sections e.g. inside water courses/ cellars and near canal banks. •MAWP > Operating pressure. Pipelines are safe to operate at current parameters. •Coating replacement suggested for 04 X pipelines loops cumulative length ~ 13 KMs. •Pitting observed in 9 feet span of 6” Pipeline from CMF-I to CMF-II. Replacement of defective portion mandated in light of LRUT results. •Results on the basis of C-scan survey Partial Coating Repair shall be planned for multiple pipelines of around 1400 m. Phase-4 •MAWP > Operating pressure. Pipelines are safe to operate at current parameters. •Coating replacement suggested for 02 X pipeline loops cumulative length ~ 4.95 KMs. Phase-5 •No significant metal loss recorded. •Paint Flaking/Deterioration, Corrosion / rusting & short bolting were observed. •Interseal 670HS Black (OEM :Akzonobel) is selected as protective coating for Wellhead surface Well Casings casings. Phase I Results (1965) Thickness 10 8 6 7.11 6.95 4 7.11 6.83 8.18 8.18 8.18 8.18 8.18 4.48 4.98 4.94 4.91 4.88 3 4 5 6 7 2 0 1 2 Original Thickness [mm] Mari Petroleum Company Limited Actual Thickness [mm] Page 23 Asset Integrity Report – 2021 MAWP 1500 1000 1011 990 435 500 345 345 335 503 325 498 325 494 320 490 235 1 2 3 4 5 6 7 0 Operating Pressure [ Psig] MAWP [Psig] After Deducting Corrosion Allowance = 1 mm Phase II Results (1977) Thickness 10 7.11 8 7.11 6 7.11 6.18 4 6.11 6.95 2 3 9.27 9.27 8.28 8.37 4 5 2 0 1 Original Thickness [mm] Actual Thickness [mm] MAWP Operating Pressure [ Psig] MAWP [Psig] After Deducting Corrosion Allowance = 1 mm 1500 1000 500 871 859 360 330 1 2 1009 758 768 335 325 325 3 4 5 0 Mari Petroleum Company Limited Page 24 Asset Integrity Report – 2021 Phase III Results (1981) Thickness 10 7.11 7.11 8 6 6.11 4 7.11 6.03 7.11 6.05 3 4 8.18 6.78 8.18 6.81 5 6 9.27 8.16 9.27 8.44 9.27 8.47 7 8 9 6.08 2 0 1 2 Original Thickness [mm] Actual Thickness [mm] MAWP 1000 857 800 852 843 846 360 320 320 744 748 744 775 315 315 310 778 600 400 335 390 200 390 0 1 2 3 Operating Pressure [ psig] 4 5 6 7 8 MAWP [Psig] After Deducting Corrosion Allowance = 1 mm 9 Phase IV Results (1985) Thickness Results 10 8 6 4 2 0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 Origional Thickness [mm] Mari Petroleum Company Limited Actual Thickness [mm] Page 25 Asset Integrity Report – 2021 MAWP 1200 1000 Cellar Location 800 600 400 200 0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 Operating Pressure [ Psig] MAWP [Psig] After Deducting Corrosion Allowance = 1mm Phase V Results (1993) Thickness Results 10 8 6 4 2 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 Origional Thickness [mm] Actual Thickness [mm] MAWP 1200 1000 800 600 400 200 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 Operating Pressure [ Psig] MAWP [Psig] After Deducting Corrosion Allowance = 1mm Outcomes Of LRUT: [Refer Annexure 1, for further details] • Phase: 1-5 pipelines are safe to operate at current parameters. • 19.35 KMs coating replacement recommendation for 10 pipeline loops Mari Petroleum Company Limited Page 26 Asset Integrity Report – 2021 11.2 - Thickness Surveys Thickness monitoring is an effective mean to identify the “As Is” condition of assets by trending the average metal loss over period of time. Thickness monitoring of Mari Daharki Deep is being carried out on “Yearly Basis” using in house resources. Thickness Trend of Deep Wells For 2021 4 3.6 3.6 3.4 3.5 2.88 3 2.6 2.5 2.3 2.15 2 1.7 1.5 1 0.5 0 Maximum Thickness Loss (mm) 1 MD-02 2 MD-03 3 MD-04 4 MD-06 5 MD-09 6 MD-12 7 MD-14 8 MD-15 Thickness Monitoring Activity 11.2.1 - A scanning/UFD Assessment M/s Velosi performed the fitness for service assessment as per API 570 of Well Head piping at MPCL Daharki Gas Field to carry out a detailed condition evaluation and remaining life assessment of Well Head piping. Detailed inspection of piping system included Mari Petroleum Company Limited Page 27 Asset Integrity Report – 2021 Scope of Work for A-scanning Above ground piping at CMF-I & CMF-II HRL X 100 Wells Deep X 08 Wells Junctions / Manifolds X 16 Sr. Description Scanned Percentage % 01 02 03 04 05 06 Well Piping (HAZ area of Weld Joints 4” to 6”) KODs Shell: KODs Nozzles: Fittings [ Elbows , Tees, Bends ] Dead legs: By pass Lines: 07 Drain Valves: Locations Results Summary • CMF-1 & 2 100% 20%(at suspected locations) 100% 100% 100% 100% A-Scanning /UFD to possible extent, at suspected corrosion prone areas MAWP (Maximum Allowable Working Pressure) greater than MOP (Maximum Operating Pressure) at all scanned locations MAWP (Maximum Allowable Working Pressure) greater than MOP (Maximum • Operating Pressure) at all scanned locations Deep Phase I & II • Localized Metal loss observed at multiple fittings on Mari Deep-02, 04, 09,14 • Replacement of 22 fittings recommended based upon A-Scan results • Safe to operate at current parameters based on acquired thickness data • Proper paint cleaning repair, bolting, degraded supports replacing/repairing and gauges calibration to be done Phase III & onwards • Scanning of wells is under progress (93% completed) • Reports are under review and will be shared soon 11.2.2 - A scanning Results [Refer Annexure 2, for further details] MAWP Analysis Goru-B MAWP 1205 Pressure (Psi) 1500 1000 904 782 750 Operating Pressure 1134 750 1068 907 979 750 750 750 MD-12 MD-14 MD-15 767 750 750 MD-04 MD-06 750 500 0 MD-02 MD-03 MD-09 Well Location Mari Petroleum Company Limited Page 28 Asset Integrity Report – 2021 MAWP Analysis CMF-I 1175 1139 1290 1348 1356 875 699 240 240 240 240 240 240 240 PIPING CIRCUTS (12"FFCIII BYPASS METER RUN ) HEADERS 1 HEADERS 2 HEADERS 3 KOD -1 KOD -4 KOD -5 Operating Pressure PSI MAWP [Psig] After Deducting Corrosion Allowance = 1 mm MAWP Analysis CMF-II 1272 1274 1275 965 956 240 240 240 240 240 240 PIPING (10" EFL-II 1BYPASS METER RUN) HEADERS 1 HEADERS 2 KOD-7 KOD-8 KOD-9 734 Operating Pressure [Psig] MAWP [Psig] After Deducting Corrosion Allowance = 1 mm Phase I Wells & KODs MAWP Analysis of Well Piping MAWP Analysis of KODs 2500 919 838 839 823 2061 2000 1500 1637 1635 729 656 2025 1307 1313 1000 295 253 260 240 281 270 500 295 253 260 240 281 270 0 WELL-03 WELL-04 WELL-05 WELL-06 WELL-08 WELL-09 Well-03 KOD Well-04 KOD Well-05 KOD Well-06 KOD Well-08 KOD Well-09 KOD Operating Pressure PSI MAWP [Psig] After Deducting Corrosion Allowance = 1 mm Mari Petroleum Company Limited Operating Pressure (Psig) Page 29 Asset Integrity Report – 2021 Phase II Wells & KODs MAWP Analysis of KODs MAWP Analysis of Well Piping 2000 1601 1617 1620 1618 1666 1608 978 895 944 876 949 975 805 786 1355 1500 1507 1000 285 264 262 266 254 269 246 246 500 285 264 262 266 254 269 246 246 0 WELL-10WELL-11WELL-12WELL-13WELL-14WELL-15WELL-16WELL-17 Well-10 KOD Well-12 KOD Well-14 KOD Well-16 KOD Operating Pressure PSI Operating Pressure (Psig) MAWP [Psig] After Deducting Corrosion Allowance = 1 mm MAWP [Psig] After Deducting Corrosion Allowance = 1 mm A-scanning Activity 11.2.3 – Thickness Mapping Campaigns [Refer Annexure 3 for further details] Thickness mapping campaign comprising of the following was conducted: • • • • 2 x condensate Storage Tanks & 3 x produced water tanks at CMF II Fire Water Network CMF-I & II Three Phase Separator Portable Oil & Water Tank Campaign Results: • • • • Baseline Thickness data were recorded. (Storage Tanks) Pin holes, Severe Pitting / metal chip off were observed. (Fire Water Network) Internal Protective coating was found disbonded. (Three Phase Separator) Incomplete welding, Rusting / pitting & no internal coating were observed. (Portable Oil & Water Tank) Mari Petroleum Company Limited Page 30 Asset Integrity Report – 2021 11.3 – External Corrosion Direct Assessment ECDA as per (NACE standard SP0502) was performed by SGS for 12 Production Critical Pipelines (Headers) of Daharki field transporting approximately 600 MMSCFD of natural gas. Sr. # Pipeline Description Pipeline Size (Inches) Length (KM) Gas Flow Rate (MMSCFD) Defects detected during DCVG 1 Junction-204- Junction-317- CMF-I 20 7 155 12 2 Junction-317 To CMF-II 20 3 80 6 3 Junction-204- Junction-317 16 3.6 30 5 4 CMF-I To CMF-II 16 0.7 5 CMF-I To CMF-II 16 0.7 6 Junction-515 To CMF-II 16 11 100 7 7 Well-14 To CMF-I 12 3.7 22 9 8 Junction-11 To Junction-317 10 2.6 75 8 9 Junction-107 To CMF-I 10 2 55 0 10 Well-14 To Junction-107 8 2 40 1 11 MD-14 To MDCPF 12 1.9 24 7 12 MD-9 To MDCPF 8 4 8 11 Total Number of Defects 50 0 0 66 * Site Activity (except for 1 location due to local issues) has been completed and the report is under review and will be shared in February 2022. General Observations: [Refer Annexure 4 for further details] • Uncoated patches were detected during inspection. • Pipeline coating damaged was observed. • Rusting / Pitting was observed at uncoated portion • Metal loss observed at 05 x locations. ECDA Activity Mari Petroleum Company Limited Page 31 Asset Integrity Report – 2021 11.4 - Cathodic Protection Cathodic protection is achieved by passing enough direct current electricity from an external source (a more powerful anode), which could be a galvanic anode or an impressed current anode. CP system deployed at MFD protects an extensive network comprising of the following: CP system Dharki Field Sr.# 1 Assets Underground pipeline network 2 3 4 HRL Well casings SML Well casing PKL Well casings 5 Goru-B Well casings Status Protected Length/Number 398.9 km Protected Protected Protected Protected Not Protected 116 10 8 5 3 Other Assets Protected by CP 1 2 3 4 5 6 7 8 9 10 11 CMF-II piping NCWGL Nara Canal Colony 2" Gas Line Colony 3" Gas Line Colony 6" Gas Line Colony 8" Gas Line MDCPF Plant Piping MDCPF Condensate TANK-A & B Fire Water Network Fire Water Tank Anode Boring Activity 11.4.1 - New Solar Based CP System Installation Due to favorable conditions of environment and green initiative of the company solar system are being used and Third Party assessment is underway on the field. A total of 25 wells were shifted to solar energy in the year 2021. Wells Powered By Solar Energy In 2021 Sr.# Reservoir name Well names 1 HRL Well-102 to Well-120 & Watayo-01 (19 wells) 2 SML Shaheen-01,02, Bhitai-02, 05 & Shahbaz-01 (6 wells) Total Number of Wells Mari Petroleum Company Limited 25 Page 32 Asset Integrity Report – 2021 11.4.2 – Third Party CP system Assessment A third party assessment was conducted for determining condition of existing CP systems. Initial findings of the assessment confirm that in-placed CP System is fully effective as per NACE guidelines. However, assessment report is under review and will be shared by mid of February 2022.In light of recommendations and gap analysis findings, following activities are planned to be performed in 2022[Refer Annexure 5 for further details] E log I survey of well casings to determine current requirement as per NACE RP0186 Increase/replacement of anodes as per current requirements of well casings Upgradation of Current Control/ Anode junction boxes Drafting of CP system As-built drawings Installation of Isolation gaskets Tagging of Cable connection and Junction boxes * Cathodic Protection system of GTH is being planned by P&E department. 11.5 – Risk Based Inspection Study RBI is an integrated methodology that reviews prevailing inspection techniques and frequencies consequently leading to optimized inspection strategies based upon risk analysis. M/s SGS has carried out RBI study at the following locations in the year 2021.The report of this study is yet to be shared by the third party. RBI Study Locations Sr. # 1 2 3 4 5 Reservoir Well CMF-I & II HRL SML PKL Goru-B Well-12 SML-01 PKL-01 MD-02 RBI Matrix Mari Petroleum Company Limited Page 33 Asset Integrity Report – 2021 11.6 - MDCPF ATA Inspections Inspection of Glycol Dehydration Unit including TEG contactor Tower, TEG Reboiler, Stripping Column, Reflux Coil, TEG Flash Tank, Three Phase Test Separator A & B, TEG Reboiler Surge Tank and TEG Lean Rich Heat Exchanger was carried out from 1st to 4th April 2021. Scope of Work: Following Inspections and NDT techniques were used for assessment and evaluation • Internal visual inspection of TEG Contactor Tower, TEG Flash Tank, TEG Reboiler, TEG Surge Tank and Three Phase Test Separators • External visual inspection of all equipment for assessment of any imperfections and defects in relating to service like cuts, cracks, gouges, pits, corrosion, SCC and deterioration of insulation and susceptibility of any CUI (corrosion under insulation) due to ingress of moisture. • UTG of TEG Contactor Tower, TEG Flash Tank, TEG Reboiler, TEG Surge Tank and Three Phase Test Separator A & B for determination of any thickness loss. • DPT of Nozzle connections and selected Tee sections on TEG Contactor, TEG Flash Tank and TEG Surge Tank for determination of any surface discontinuity like (Pin holes, cracks, under cuts etc.). • MPI was performed on selected Tee sections of TEG Reboiler and associated nozzle openings for assessment of any surface and near surface defects. • Hardness testing of welds was performed on TEG Surge Tank and TEG Reboiler for assessment of metallurgical changes due to long term exposure with Process stream temperature. • ECT of Lean Rich Heat Exchanger tubes for evaluation of thickness loss. • Acoustic Emission testing of Lean Rich Heat Exchanger tubes for evaluation of thickness loss Recommendations: [Refer Annexure 6 Report Page # 203 ~ 207 for further details] Lean Rich Heat Exchanger: • • Considering this inspection as baseline, TEG-Exchanger shall be re-inspected during next TA, to estimate exact rate of deterioration. Tubes with 30% wall loss are acceptable as per acceptance criteria. TEG Gas Contactor: • • • Damaged CRA liner and Temporary repaired N6A nozzle will be permanently rectified under the guidelines of API-510 and ASME PCC2. All 04 nozzles indication shall be evaluated during next turnaround for defects propagation. Tower will be inspected after “One Year” for assessment of all reported anomalies. Due date for next inspection will be April-2021. TEG Surge Tank, TEG Reboiler: • • TEG Surge Tank and TEG Reboiler are made of low corrosion resistance material i.e. A36 [Carbon Steel]. By replacing the A36 with SS (300 series) material can permanently mitigate consistently occurring damages. Both equipments will be inspected after “One Year” for assessment of all reported anomalies. Due date for next inspection will be April-2021. Flash Tank, Three Phase Separators: • All above equipment’s are declared Fit-For-Service as no significant abnormality observed during inspection. Mari Petroleum Company Limited Page 34 Asset Integrity Report – 2021 • Calculated due date for next internal inspection is April-2031 however, inspection will be planned in line with forthcoming ATAs. General view of vessel MDCPF Glycol Dehydration Unit 11.7 - MDCPF Storage Tank A & B Inspection and subsequent repair works of 3000 barrel Condensate Storage tank A and B were carried out at MDCPF under third party inspection plan in the following dates: • • Tank-A: 14th March to 14th April, 2021 Tank-B: 21st August to 30th October, 2021 Internal coating of both tanks was absent which caused degradation of bottom plates in both these tanks. Subsequent repair works were initiated for restoration of tanks. Repair Works Conducted On Each Tank: [Refer Annexure 7 for further details] Storage Tank-A Tank Foundation Repair Complete Bottom Replacement Addition of Water Draw off Sump and Sump Nozzle Internal Coating of Bottom and Shell & Roof Installation of sacrificial anodes for Internal CP protection Storage Tank-B Mari Petroleum Company Limited Tank concrete ring wall repair Replacement of sand cushion underneath tank bottom Complete bottom replacement Addition of water draw off sump and nozzle Installation of sacrificial anodes for Internal CP protection Replacement of inlet nozzle Internal Coating of Bottom and Shell & Roof Welding of liquid level gauge upper nozzle and 4 inch foam line nozzle Page 35 Asset Integrity Report – 2021 MDCPF Condensate Storage Tank A & B 11.8 - Root Cause Failure Analysis Root Cause Failure Analysis (RCFA) is a systematic way of reviewing all the evidence from a failure in order to determine a root cause that is manageable and prevent recurrence. Following RCFA were conducted during the year 2021 RCFA Sr. IIR No. Date of IIR Description 01 104 26th Aug 2021 2mm pinhole at 6 o clock in 6 ‘’ Bhitai-03 to Well-04( Jct-221 Tie-in pipeline) 02 114 17th Nov 2021 Drain line leakage at MDCPF 03 117 10th Nov 2021 Leakage from Glycol Absorber PSV Nozzle 04 119 11th Nov 2021 Pinhole leakage from injection line of WDW at CMF-II 05 123 19th Nov 2021 Pinhole leakage at Condensate Storage Tank of Bhitai-03 06 124 19th Nov 2021 Minor leakage at 4” header of Liquid storage tank of Bhitai-01 *All leakages were corrected through proper procedures and preventive measures for long term safe functionality of all such assets were also recommended to management. 11.9 - Pipeline Pigging Mari flow lines pigging activity is carried out on “Yearly Basis” to displace the accumulated water and sludge etc. which consequently reduces the corrosion activity inside pipelines. Moreover, corrosion inhibitor batch treatment is also performed while pigging for effective internal corrosion prevention. Iron counts of samples gathered during pigging are also measured for gauging the corrosion activity. Mari Petroleum Company Limited Page 36 Asset Integrity Report – 2021 Pipeline Pigging Program HRL Loops Mari Deep Lines (17) (11) MD Lines MD Lines (Completed Loops = 08) (Remaining Loops = 03) HRL Shallow Wells Loops HRL DBN Loops (Remaining Loops = 15) (Completed Loops = 02) Pigging Activity Challenges • Pig Launcher and Pig Receivers are missing at a few locations. • Pressure and Temperature Gauges installation and calibration are required at a few locations. • Pig Doors / Valves functionality verification is required at certain locations. • Pig Signals installation and functionality verification is required at a few areas. • Drain Pits formulation is required at a few locations. 11.10 - Inspection of Storage Tanks & Vessels On the basis of leakage in 50 BBLs condensate storage tank bottom at Bhittai-03 step by step inspections were in of all condensate storage tanks placed at below mentioned locations along with 4 KODs placed at CMF. • • • Shaheen-1, Shaheen-2, Shahbaz-1, • • • Mari Petroleum Company Limited SML-1, Bhittai-1, Bhittai-2, • • • Bhittai-3, Bhittai-5, CMF, • • • Hilal-1, Iqbal-1, KOD 7, 8, 9 & 10 Page 37 Asset Integrity Report – 2021 Tanks Inspections Vessels Inspections * Shaheen-01, Shaheen-02 and Shahbaz-01 are yet to be inspected under this plan. The inspection reports comprised of the following: 1. Introduction 2. Background 3. Inspection Techniques 4. Inspection Findings 5. Thickness Results 6. Recommendations Results: • Although foreign Debris was found in KOD vessels, the overall condition was satisfactory • Condensate Storage Tanks had major issues regarding their design and functionality General Recommendations: [Refer Annexure 8 for further details] • • • • • • External and internal protective coating after surface preparation to be ensured for storage tanks Repair /replacement of damaged plates Proper welding at nozzles and shell to bottom joints Proper bolting Sacrificial Anode installation recommended for Internal Cathodic protection of storage tanks Third Party Investigation shall be done of all condensate storage tanks 11.11 – Kill Lines Survey In house Kill Line Inspection Campaign was carried out at 81 well locations. Following aspects were covered and became the basis of recommendations: 1-1- Thickness Thickness Profile Profile 2-2- Gaskets conditions Gasket Conditions 3- Line supports condition Mari Petroleum Company Limited 4- Coating condition for buried lengths 5- Paint condition for surface lengths 6- Housekeeping related matters Page 38 Asset Integrity Report – 2021 [Refer Annexure 9 for further details] Kill Lines Survey *Planning and Execution Department is working on the revamping mentioned in this survey. 11.12 – Exposed Pipelines Survey: Exposed Pipelines survey was conducted in Jan-Feb 2021, to identify the locations where pipelines are exposed and prone to damage at HRL, SML, Goru-B ROWs. [Refer Annexure 10 for further details] Total pipeline length accumulated to 12 km and the activity comprised of the following • • • Protection of all exposed pipeline sections by proper excavation, lowering and backfilling operation. Acquisition of pipeline integrity data of “Thickness Profile” and “Coating Condition”. Exposed pipeline sections inspection and rectification. Mari Petroleum Company Limited Page 39 Asset Integrity Report – 2021 Exposed Pipeline Survey Sr. # 1 2 3 4 5 6 7 Pipeline size (inches) 6 8 10 12 14 16 20 Number of lines exposed 26 17 5 2 1 1 1 Well # 99 - Tie-in Main line 10" at Well # 79 to Jct.515) (6'' Exposed Pipeline Section) Well # 98- Tie-in Main line 10"at Well # 79 to Jct.515 (6'' Exposed Pipeline Section) *80 % of the highlighted pipelines through this survey have been revamped till now. 11.13 - Piping Supports Survey: In the backdrop of Well-4 gas leak which occurred on September 15th, 2019 at 8” pipeline coming from Junction-133 to Junction- 204, a comprehensive pipeline supports inspection survey was carried out to avoid the reoccurrence of similar leakages. Production Shallow Pipeline Junction Pipe Supports and Production Shallow & Deep Pipeline Support assessment survey was conducted. Summary: [Refer Annexure 11, for further details] Piping Supports Found Damaged = 218. Piping Supports Foundation Damaged = 166. Mari Petroleum Company Limited Page 40 Asset Integrity Report – 2021 Location Well-17 JCT 117 Location Well-23 * Planning and Execution Department is working on the revamping mentioned in this survey. 11.14 - Pipeline Bell Holes Inspection Survey Utilizing the in-house resources thickness and coating wrapping condition of flow lines was inspected before the commencement of LRUT of the whole field [Refer Annexure 12 for further details] Thickness monitoring Pipe Surface after Coating Removal Bell Holes Inspection Thickness Results Phase I (6-inch Pipeline) Well-05 to JCT-105 Well-03 to Well-08 Thickness Loss ( mm) Bell hole-1 Bell hole-2 Bell hole-1 Bell hole-2 Bell hole-3 Bell hole-4 (8-inch Pipeline) Well-09 to Well-16 Mari Petroleum Company Limited 0.35 0.36 -0.35 -0.17 -0.20 -0.22 Thickness Loss ( mm) Bell hole-1 Bell hole-2 Bell hole-3 Bell hole-4 3.35 3.34 3.27 3.34 Page 41 Asset Integrity Report – 2021 Well-08 to Well-15 to CMF-1 Bell hole-5 Bare Pipe L-1 (W-55) Bare Pipe L-2 (W-55) Bell hole-6 Bell hole-7 Bare Pipe (W-97) Bell hole-8 Bell hole-9 Bell hole-10 Bell hole-1 Bell hole-2 Bell hole-3 Bell hole-4 Bell hole-5 Bell hole-6 Bell hole-7 Bell hole-8 Bell hole-9 3.34 3.34 3.33 3.37 3.40 3.35 3.31 3.32 3.29 3.40 3.37 3.31 3.38 3.35 3.38 3.38 3.34 3.36 Phase II (6-inch Pipeline) Well-23 to Well-14 Thickness Loss ( mm) Bell hole-1 Bell hole-2 Bell hole-3 Bell hole-4 Bell hole-5 0.67 0.97 0.90 0.95 1.06 Phase III (6-inch Pipeline) Well-20 to Well-53 Thickness Loss ( mm) Bell hole-1 Bell hole-2 0.86 0.78 11.15 - Underground Pipeline Accessibility Survey Pipeline Accessibility survey was conducted earlier in Feb 2021, to identify the locations where pipelines are inaccessible owing to encroachment issues, sand dunes, cultivated lands and unavailability of ROW etc. which could result in possible hindrance to perform Inspection & Maintenance activities. Objectives of the activity are listed below: • • • • All encroachments can be removed Lines can be made accessible in sand dunes and cultivated land New ROWs can be prepared at inaccessible locations Line rerouting can be planned / executed where needed Mari Petroleum Company Limited Page 42 Asset Integrity Report – 2021 [Refer Annexure 13 for further details] Sr.# Summary Of Findings Locations 1 Total No. of "Land Encroachment Locations" 163 2 Total No. of Locations Where "Pipelines Passing Through Cultivated Lands" 210 3 Total No. of Locations Where "Pipelines Passing Through Sand dunes" 86 4 Total No. of Locations Where "No ROW Availability" 11 5 Total No. of Locations Which are "Not Approachable" 4 *29 % progress has been made till now by the land department. 11.16 - Pipeline Cellars Survey A complete survey of cellars at Daharki field wells was performed to assess the condition of pipeline in cellars, and take rectifying measures to prevent any incident that could disrupt the pipeline operations. A comprehensive plan comprising of both Production shallow wells and Production Deep wells was derived. [Refer Annexure 14 for further details] Sr. # Types of Cellars 1 Cellars containing Pipelines 2 Cellars at MDCPF. 3 Cellars with ER Probe. Quantity Action Plan and Responsibilities 15 13 Renovation 2 Backfill 4 4 Renovation 0 Backfill 21 4 Cellars with Valves. 5 Cellars with Valves and ER probe. 18 Renovation 52 Renovation 3 Backfill 52 0 Backfill 6 6 Renovation 0 Backfill House Keeping of Cellars. (Corrosion team) Coating/Painting of Pipeline in the Cellar. (Corrosion Team) Backfill of Cellar. (Field Maintenance) Housekeeping of Cellars. (Production Deep). Coating/Painting of Pipeline. (Corrosion Team) House Keeping of Cellars. (Corrosion team) Coating/Painting of Pipeline in the Cellar. (Corrosion Team) Backfill of Cellar. (Field Maintenance) Housekeeping of Cellar. (Production Shallow) Coating/Painting of Pipeline.(Corrosion Team) Housekeeping of Cellar. (Corrosion Team) Coating/Painting of Pipeline. (Corrosion Team) *The comprehensive rectification and uplifting plan has been developed in the light of “Cellars Survey”, “Kill lines Survey”, and “Piping Support Survey”. Maintenance Static, Corrosion and Inspection along with Head Office Planning and Engineering department are jointly working on these projects. These restoration projects are under way. Mari Petroleum Company Limited Page 43 Asset Integrity Report – 2021 11.17 - Well Casing Integrity Survey Integrity was ascertained of 66 wells by visual inspection of Casing pipe and conductor pipe (where accessible) and measuring thickness of conductor pipe at multiple locations. Recommendations: [Refer Annexure 15 for further details] • Assets external surface to be painted periodically with industrial grade paints after proper surface preparation. • Wellhead pits / cellars will be made waterproof. • Regular removing of water from pits to be ensured. • Conductor pipe and surface casing documents shall be shared for effective analysis. Before After Before After Before After Mari Petroleum Company Limited Page 44 Asset Integrity Report – 2021 11.18 - Isolation Gaskets Survey Flange Isolation Gaskets provide an effective seal and electrical isolation of flanges. Gaskets are an integral component of CP system and are beneficial in following ways • • • • CP system efficiency improvement, Ground bed life enhancement, Facilitation during UG pipeline surveys [C-scan, PCM, DCVG etc.], Protection of Assets from stray currents etc. Isolation Gasket Required Sizes 4-Inch 6-Inch 8-Inch 10-Inch 12-Inch 14-Inch 16-Inch 20-Inch 0 32 33 10 5 0 6 10 Total Required Gaskets 96 Already installed Gaskets 69 Remaining 27 Gaskets Locations Planned for without Shutdown JCT-154 JCT-186 JCT-118 JCT-515 JCT-138 JCT-159 JCT-111 JCT-133 JCT-197 JCT-134 JCT-131,11 JCT-136 Planned with Shutdown CMF-I JCT-221 CMF-II JCT-114 JCT-317 JCT-116 JCT-204 Gasket Conditions Mari Petroleum Company Limited Page 45 Asset Integrity Report – 2021 12 - Circadian Activities 12.1 - Corrosion Inhibitor Injection Program: CI Injection Plan Non Packer Wells Packer Wells In Tubing via Bottles In Tubing via Pump (Total Locations: 05) (Total Location: 01) In Tubing via Master Valve (Total Location: 41) Through Casing via Bottles Through Casing via Injection Pump (Total Location: 76) (Total Location: 05) In Tubing through Swab Valve Top In Tubing through Wing Valve (Total Location: 17) (Total Location: 24) Deep M/s Nalco has carried out the comprehensive Chemical Treatment study of Mari Deep gas gathering network. After performing detailed lab performance analysis, they have recommended to perform continuous injection of Oil Soluble Inhibitor (EC 1391 A). These pipelines are being constantly treated by the rate “1 Pint / MMCFD” with 1:4 (Inhibitor: Condensate). Overall protection performance of said methodology is above “98%”. Corrosion Inhibitor Injection Skid – Preventive Maintenance Shallow Shallow wells of HRL, SML and PKL receive Corrosion Inhibitor in the form of Batch injection.16 gallons for flow lines and 20 gallons for casings are injected respectively. Frequency of Batch injection in shallow wells is 24 days. Mari Petroleum Company Limited Page 46 Asset Integrity Report – 2021 12.2 - C-scan C-scan of underground pipeline is done under the guidelines of MSP-FMT-03. The equipment has the ability to record the data from different locations and to display the graphs between different properties such as depth cover over pipelines, coating resistance, coating conductance, pipeline diameter and attenuation revealing the exact locations of holidays to be rectified. Pipeline Loops C-scanned in 2021 Sr. no 1 2 3 4 5 Loops Well-06 to Well-16 Well-17 to CMF-II Well-17 to CMF-II Shahbaz-1 to Well-04 to Jct-221 Well-15 to Well-06 C-scan Activity size 10'' 20'' 20'' 6'' 8'' Total Length (Km) length(m) 1478.0 3250.2 3090.7 576.1 2511.2 11.0 C-scan Analysis Graph 12.3 - Weight Loss Coupon Analysis: Under the guidelines of NACE SP 0775-18, Weight Loss Coupons are being used to analyze the relative corrosion behavior with “Bi-annual frequency”. Online weight Loss Coupon Retreival Mari Petroleum Company Limited Page 47 Asset Integrity Report – 2021 * 50 % difference between blank Corrosion rates and CI dosage corrosion rates at SML wells during the 2 mentioned months. Mari Petroleum Company Limited Page 48 Asset Integrity Report – 2021 12.4 - Electrical Resistance (ER) Probes Results: ER Probes data of Daharki field pipelines is being gathered on “Monthly Frequency”. The acquired data is analyzed to scrutinize the relative corrosion trends for the optimization of corrosion inhibitor injection program. ER Probe Data Recording Average Corrosion Rate (mpy) Of Deep 12" Pipeline from Deep-2,14&15 at MDCPF 10" Pipeline from Deep-3,4&12 at MDCPF 0.105 0.023 8" Pipeline from Deep-01 & 09 at MDCPF 0.373 6" Pipeline from Deep-06 at MDCPF 0.082 8" Pipeline from Deep-15 at Deep-02 10" Pipeline from Deep-2 & 15 at Deep-14 0.117 0.039 8" Pipeline from Deep-3 & 12 at Junction at Deep-13 6" Pipeline from Deep-4 to Junction Deep 13 6" Pipeline from Deep-12 at Deep-03 0.000 0.191 0.057 0.044 0.050 0.100 0.150 0.200 0.250 0.300 0.350 0.400 Avg ER Probe Data Trend Analysis-2021 0.9 0.8 0.7 0.6 0.5 0.4 0.3 0.2 0.1 -0.1 3 5 10 12 14 16 19 26 29 32 35 37 40 42 44 47 50 52 55 57 60 64 67 71 73 75 77 79 81 83 85 87 90 93 95 98 100 102 104 107 109 116 118 120 0 Mari Petroleum Company Limited Page 49 Asset Integrity Report – 2021 12.5 - PSP Data Recording Pipe to soil potentials are being measured to gauge the protection level of an underground metallic structure under cathodic protection. The Protection criteria of a “structure to electrolyte potential” of -850 mV to -1250 mV as measured with respect to a saturated copper/copper sulphate reference electrode is sufficient to protect the structure from corrosion. PSP data recording activity P S P ( VO LT S ) O F H R L W E L L S 3 TO 5 0 1.6 Fullfills NACE criteria of -850 mV for Cathodic Protection 1.4 1.2 1 0.8 0.6 0.4 0.2 0 3 1.8 1.6 5 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 P S P ( VO LT S ) O F W E L L S 5 0 TO 1 0 0 Fullfills NACE criteria of -850 mV for Cathodic Protection 1.4 1.2 1 0.8 0.6 0.4 0.2 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 67 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 92 93 94 95 97 98 99 100 0 Mari Petroleum Company Limited Page 50 Asset Integrity Report – 2021 P S P ( VO LT S ) O F W E L L S & OT H E R A S S E T S Fullfills NACE criteria of -850 mV for Cathodic Protection 1.6 1.4 1.2 1 0.8 0.6 0.4 0.2 0 PSP (Volts) - Piping Deep 1.4 Fullfills NACE criteria of -850 mV for Cathodic Protection 1.2 1 0.8 0.6 0.4 0.2 0 Deep-1 Deep-2 feb Deep-3 march Deep-4 april Deep-6 may june Deep-9 July Deep-12 August Sept Deep-13 Deep-14 Oct-Nov Dec Deep-15 Other Deep Assets PSP Reading Fullfills NACE criteria of -850 mV for Cathodic Protection 1.4 1.2 1 0.8 0.6 0.4 0.2 0 MDCPF Tipu-I march Mari Petroleum Company Limited Tipu-II april may Azadi-1 june July MDCPF Condensate TANK-A August MDCPF Condensate TANK-B Sept Oct-Nov Fire Water Tank Fire Water Network Dec Page 51 Asset Integrity Report – 2021 12.6 – Holiday Detection Inspection of coating wrapping of pipelines by holiday detection was done at following locations Holiday Detection Locations Sr.# Locations Size (inch) 1 2 3 4 5 6 7 8 Well # 50 - 09 Well # 30 -Jct.11 (PKL Loops) Well # 97 to 8 (16-22-50) Well # 09-Jct-157 Jct-157 - Well 55 Tie-in Well # 09-Jct-157 Well # 26 -Jct.204 Well # 36 - Jct.134 6 6 6 8 8 8 8 10 Holiday Detection 12.7 – Positive Material Identification (PMI) Newly acquired tool for Positive Material Identification has been acquired for material verification and traceability. The tool has been used for following purpose since its procurements • • • • MD-02 SS pipeline grade verification MD-13 to MDCPF pipeline grade verification Reboiler coil material verification Verification of MTCs before during inspection of incoming stock at the warehouse PMI Mari Petroleum Company Limited Page 52 Asset Integrity Report – 2021 12.8 - Produced Water Analysis Samples are collected from 146 wells on monthly basis from both deep and shallow for iron count and RCI analysis which is used in CI injection rates optimization. Water sample collection Lab analysis of collected samples ER probe / WLCs / Iron Counts Graphical Trend Year 2021 5.00 ER Probe WLC 4.00 2.00 Corrosion rates (mpy) 3.00 Iron Count 1.00 0.00 Well No. On the basis of such data collected trends are made for analysis and review of corrosion inhibitor dosage requirement for these wells. Mari Petroleum Company Limited Page 53 Asset Integrity Report – 2021 13 - Asset Integrity Campaigns of Remote Fields Corrosion & Inspection team of MPCL Daharki field made a total of 3 visits to other satellite fields: AIC Remote Field Visits In 2021 Sr.# 1 2 3 Visit date 26-30th January 2021 15-18th February 2021 26-30th August 2021 Field name Zarghun Field Koonj Field Zarghun Field 13.1 - Zarghun Field: Zarghun field was visited by Daharki team twice in the last year. Once in January to perform inspection activities so that detailed diagnostics could be performed on the increasing frequency of replacement of inlet Coalescing Filter at ASU. Second visit was made during August-2021 planned shutdown of Zarghun field. Activities Performed By Daharki Team in January-2021: 1. Thickness Monitoring Of Pipelines & Equipment 2. Weight Loss Coupons Online Retrieval and Installation 3. Functionality check of ER Probes 4. Visual Inspection of facilities Recommendations after the Visit: [Refer Annexure 16 for further details] Locations of ER probes and WLCs were suggested for Corrosion Monitoring of assets Critical fitting for thickness monitoring was identified and its monitoring frequency was set Pigging activity and its necessary requirements i.e. Pig launcher and receiver were to be set up Activities Performed By Daharki Team in August-2021: 1. Pipeline Pigging Activities Pipeline From ZS2 To Plant Pipeline From ZS4 To Plant 2. Weight Loss Coupons Replacement Activities 3. ER Probe Data Acquisition and Installation Activities 4. Thickness Monitoring at Selected Locations Recommendations after the Visit: [Refer Annexure 16 for further details] Corrosion Inhibitor Injection System to be installed at ZS-03 on priority basis ZS-03 piping to be re-evaluated with P & E by considering the design and operating philosophy. ER probe and WLCs locations identified Inspection Management System to be upgraded to A-Scanning from conventional Ultrasonic Thickness Gauging (UTG). Mari Petroleum Company Limited Page 54 Asset Integrity Report – 2021 Pigging activity facilities that need upgradation were proposed General Observations of the facility were conveyed Zarghun Visits Activities 13.2 - Koonj Field: Daharki team visited Koonj Field in February for integrity assessment of Koonj Field Underground Gas Transportation Pipeline [6’’ Sch.40; 13 KMs]. The line serves the purpose for gas transmission from facility to Tie-In assembly. Inspection Activities Performed: The buried pipeline was examined by formulation of bell holes at various locations. The following activities were performed at selected locations: 1234- Pipeline Cover, Pipeline Coating Condition, Pipeline Base Metal Inspection, Pipeline Thickness Monitoring, Observations of the Visit: [Refer Annexure 17 for further details] All above integrity assessment activities reveal that pipeline coating and base metal are in good condition. Regular monitoring and assessment of all facility assets shall be carried out for establishment of healthy reliability data. Koonj Field Visit Activities Mari Petroleum Company Limited Page 55 Asset Integrity Report – 2021 14 - Challenges: 1. Although Downhole Assets Corrosion Rates are under control through effective batch treatment via conventional technique however, advanced tool of SPM (Side-pocket mandrel) need to be incorporated in future wells for safe chemical injection for well casing and tubing protection. Suggested Way Forward SPM technology should be introduced in forthcoming wells by Petroleum Engineering Team. 2. Higher Blank Corrosion Rates recorded at SML wells. Batch Treatment was conducted after 07months that reduced the CRs by 50 %. The downhole injection is indispensable at these critical locations and deferment of same due to well unavailability can cause serious menace to Well Integrity. Suggested Way Forward Production Team to ensure the Well availability i.e. 2hr/month for effective downhole treatment. 3. Downhole corrosion monitoring along with WLCs and standardized corrosion inhibitor injection at all well locations is required to check the Batch treatment effectiveness and corrosion rates calculation. Suggested Way Forward MOC for “Corrosion Monitoring System Upgradation” to be expedited on priority basis for timely completion of project. Presently MOC is under review of P & E Department. 4. Unavailability of As-built drawings. Suggested Way Forward Formation of As-built drawings. 5. No design documents available. Suggested Way Forward All essential design documents should be developed and accessible to all end users. 6. 1 technician is burdened with handling of injection and maintenance of injection pumps at 131 wells Suggested Way Forward Pump maintenance to be transferred to rotary section as per new organogram. 7. Retired manpower resources have not been replaced by new hiring for more than a year now. Suggested Way Forward Hiring of skilled resources against retired personnel. Mari Petroleum Company Limited Page 56 Asset Integrity Report – 2021 8. Timely resolution of Land and Security Issues pertaining to third party and in-house inspection activities Suggested Way Forward Land and security department should swiftly resolve the land and security issues so that on-sites activities can be concluded timely. 9. Water Logged Areas are an issue for C & I department while working with sensitive equipment to obtain on ground readings. Suggested Way Forward Although, we are executing the tasks after fulfilling the all pre-requisites. However, above issue is hampering the AI activities progress and pace. 10. Lack of certification and training plan for the Asset Integrity Team Suggested Way Forward Local training budget has also incorporated in OPEX Year-2022~23 budget. Whereas, advance level trainings have also been incorporated in TNA. Mari Petroleum Company Limited Page 57 Asset Integrity Report – 2021 15 - Major Planned Activities FY: 2022~23 Activity Scope LRUT Survey ECDA Survey (Phase-II) A Scanning CP System Upgradation Asset Integrity Inspections Based upon the results of first phase of survey, 100 LRUT shoots are planned for critical loops and bends FY 2022-2023 ECDA survey would be extended to 15 more production critical loops in year 2022-2023 A-scanning of critical equipment would be conducted for corrosion mapping New CP System Installation at 05 Locations Elog I Assessments of 35 X Well casings Sacrificial Anode installation for Cathodic Protection for 04 storage tanks CP System rehabilitation in line with Third Party CP System Assessment Report Baseline inspection of Swing Volume Compression Facility Annual inspection of Mari Deep Central Processing Facility Baseline inspection of 2xCondensate Storage Tanks, 1xFirewater Tank and 1xProduced Water Storage Tank Corrosion Monitoring System Upgradation Upgradation of downhole corrosion monitoring system for 30 wells is planned for the year FY 2022-2023. Project will include installation of corrosion coupons, produced water sampling points and upgradation of inhibitor injection assemblies. QA/QC Activities Management Asset Integrity Support To Satellite Fields RBI Study – Mari Daharki Field Asset Integrity Software Implementation Assurance of QA/QC during TEG contacting tower Liner replacement job. NDT Testing (DPT, MPI, RT ..) provision for repair and maintenance activities as per requirement Inspection of Coating repair activities of underground pipelines Asset Integrity Support Services like Static Equipment Inspection, Corrosion Monitoring and Control, Pipeline Pigging and Cathodic Protection System Assessment etc. on requirement basis. Risk Based Inspection Study of entire Mari Daharki Field with close coordination of M & AI Mari Petroleum Company Limited Inspection Data Base Management Software selection and implementation with close coordination of M & AI Page 58 Asset Integrity Report – 2021 16 - System Advancement Proposals Sr. # 01 Proposals Internal Corrosion Direct Assessment – ICDA (Pilot Project : NACE –SP0206) 02 Integrated Corrosion Management System – ICMS (Feasibility Study and Installation Project) 03 Online Leak Detection System (Feasibility Study and Installation Project) Downhole Corrosion Coupons Assemblies (Feasibility Study and Installation Project) Intelligent Pigging ( For Production Critical Line) 04 05 06 AIMS Implementation - Brown Fields (Mari Daharki Field) Mari Petroleum Company Limited Brief Introduction Internal Corrosion Direct Assessment (ICDA) is a structured process that improves safety by assessing and reducing the impact of internal corrosion on pipeline integrity and is implemented under the guide lines of NACE - SP0206. The primary goal of the approach is to determine if internal corrosion is likely or unlikely to exist in a chosen length of pipe. ICDA standards provide guidelines to calculate the remaining life of the pipe based on the data collected in the Direct Examination Step and based on these results it recommends half of the remaining life as the re-assessment interval. The Integrated Corrosion Management System ICMS is the most comprehensive and powerful online corrosion monitoring system available. The ICMS corrosion management server is the hub of the corrosion or erosion monitoring system, integrating several forms of corrosion monitoring and process data into one complete online system, shared over a variety of communication links. Online Leak Detection System shall enable the real time monitoring of Production Critical and Aged Pipelines. That accelerates the rectification response time and minimize the HSE risk. The Downhole Coupon Holder Assembly (DCHA) is developed to test the effects of different types of corrosion on downhole tube materials, including general corrosion, crevice corrosion, stress corrosion, and pitting in downhole conditions. Intelligent Pigging is an inspection technique whereby an inspection probe, often referred to as a "smart" pig, is propelled through a pipeline while gathering important data, such as the presence and location of corrosion or other irregularities on the inner walls of the pipe. Intelligent pigs use nondestructive examination techniques such as ultrasonic testing and magnetic flux leakage testing to inspect for erosion corrosion, metal loss, pitting, weld anomalies, and hydrogen induced cracking, among others. They are also able to gather data on the pipeline's diameter, curvature, bends, and temperature. Like GTH AIMs Implementation Project, Third Party should be engaged for proper implementation of AIMs at Brown Field (Particularly Mari Daharki Field) so that RAM, RCM, RBI etc. can be implemented in true letter and spirit. Page 59