Chapter 1 Construction Contracts Background The Classification of Contracts The Standard Forms The JCT 2005/2011 Suite of Contracts Family of Contracts JCT Named Specialist Contractor’s Design Responsibilities Contractual Structures Contractual Procedure Terms of the Contract The Express Terms of Contract Housing Grants, Construction and Regeneration Act 1996 Implied Terms of Contract Payment under Lump Sum Contracts Delay, Prolongation and Disruption Quantification of Loss and/or Expense The Private Finance Initiative Partnering Privity of Construction Contracts International Contracts Quantum Meruit Chapter 1 Precedents Precedent—Letter of Intent from Employer to Contractor Precedent—Third Party Rights Exclusion Clause Precedent—Entire Remedies Clause Precedent—Entire Agreement Clause Precedent—Form of Definalisation Declaration Precedent—Sticker A Precedent—Sticker B Precedent—Discount Undertaking Precedent—Equivalent Rights Clause in Warranty Precedent—Choice of Law Clause Precedent—Re-enactment Clause Precedent—Notice Clause Precedent—Attestation Clause for a Deed: Individual Precedent—Attestation Clause for a Deed: Limited Company Chapter 2 Notices and Preliminary Considerations Introduction Claims by Employer/Building Owner Claim by Contractor for Time and/or Money Claim by Sub-contractor Claims by Architects for Payment Retrospective Delay Analysis Chapter 2 Precedents Precedent - Notice to Contractor to Inspect Defects Precedent - Letter Demanding Explanation for Fraud Precedent - Notice by Employer’s Solicitor or Agent to Contractor of Acceptance of Repudiation Precedent - Contractor’s Letter to Architect Demanding Proper Certification of Time Chapter 3 Self-Help Background Set-off Ejecting a Contractor or Protester from Site Working Alongside the Contractor Repudiation Frustration Leaving Site and Suspending Work Removing Materials Seizing Materials Preservation of Handover Documents Chapter 4 Alternative Dispute Resolution General Principles Consequences of Failing to Attempt ADR When Will the Courts Apply Sanctions? ADR Processes Providing for ADR Choosing a Neutral The ADR Agreement Conduct of the ADR Process The TeCSA ADR Protocol Conciliation under the CCG Procedure? Chapter 4 Precedents Precedent—TeCSA Model Mediation Agreement Precedent—TeCSA Mediation Rules Precedent—Draft ADR Order Precedent—CEDR Model ADR Clauses Precedent—CEDR Model Mediation Procedure and Agreement—2018 Edition Precedent—Hybrid ADR Agreement Precedent—Construction Conciliation Group Precedent—Invitation to Refer a Dispute to CCG Conciliation Precedent—Construction Conciliation Group Enquiry as to the Availability of a Conciliator Precedent—CCG—Charging and Fixed Period Bands Precedent—Construction Conciliation Group Appointment of a Conciliator by the Parties Precedent—CCG Conciliator’s Agreement Precedent—Construction Conciliation Group Code of Conduct Precedent—Construction Conciliation Group Conciliation Procedure Precedent—TCC Draft Settlement Order Chapter 5 Adjudication Introduction Judicial Control of Adjudication The Categorisation of Third Party Decision-Making Processes The Right to Adjudication The Role of the Adjudicator The Scope of an Adjudicator’s Jurisdiction The Identity of the Adjudicator The Appointment of the Adjudicator The Format of Proceedings Enforcement of Adjudicator’s Decisions Routes for Enforcement Grounds for Resisting Enforcement Adjudication Applications in the TCC Adjudication under the Scheme for Construction Contracts Adjudication under JCT Contracts Adjudication under CIC Model Adjudication Procedure Adjudication under ICE Contracts Adjudication under the Engineering and Construction Contract (Formerly Known as the New Engineering Contract) Adjudication under the TeCSA Adjudication Rules Expert Determination Chapter 5 Precedents Precedent—Notice of Intention to Refer Dispute as to Payment Precedent—Notice of Intention to Refer Dispute as to Set-Off Precedent-RICS Request for the Appointment of a Construction Adjudicator Precedent—CIC Form of Adjudicator’s Agreement Precedent—ICE Form of Notice of Intention to Refer a Dispute to Adjudication Precedent—Application for the Nomination/Appointment of an Adjudicator by ICE Nomination/Appointment of an Adjudicator by ICE ICE Form of Adjudicator’s Agreement Precedent—Other Party’s Statement of Case—Denial of Contract Precedent—Claimant’s Reference to Alleged Settlement Precedent—Adjudicator’s Rejection of Demand for Resignation Precedent—Adjudicator’s Decision Precedent—The Disputes Clause in Thames Valley Power v Total Gas and Power Chapter 6 Statements of Case Principles Causes of Action Interest Value Added Tax The Claim Form Particulars of Claim Defences Counterclaims Reply and other Subsequent Pleadings Scott Schedules Limitation Quantum of Damages Further Information Amendment Proceedings Against Third Parties Chapter 6 Precedents Precedent—Concise statement of nature of claim—Certified Sum Precedent—Concise statement of nature of claim—Balance of Contract Sum Precedent—Concise statement of nature of claim—Quantum Meruit Precedent—Concise statement of nature of claim—Loss and Expense Claim Precedent—Concise statement of nature of claim—Defects Claim Precedent—Concise statement of nature of claim—Adjudicator’s Decision Precedent—Concise statement of nature of claim—Multi Defendant Defects Claim Precedent—Scott Schedule in Action for Defective Work Precedent—Scott Schedule in Action for Defective Work where Parties use Word Processors Precedent—Scott Schedule in Action Claiming Extras and Omissions to Fixed Price Contract Precedent—Specimen Column Headings for Scott Schedule for Work Done and Materials Supplied Precedent—Specimen Column Headings for Scott Schedule for Work Done and Materials Supplied: Alternative Form Precedent—Specimen Column Headings for Scott Schedule for Work Done and Materials Supplied: Alternative Form Precedent—Specimen Column Headings for Scott Schedule for Goods Sold and Delivered Precedent—Specimen Column Headings for Scott Schedule Agent’s Commission Precedent—Denial of Construction Contract Precedent—Statement of Truth of Defence Precedent—Request for Further Information—Letter Form Precedent—Request for Further Information—Separate Document Precedent—Objection to Request for Further Information Precedent—Letter Objecting to time for response in Request for Further Information Precedent—Identification of Means by Which Amendment Pre Service is Made Precedent—Identification of Means by Which Amendment With Consent is Made Precedent—Identification of Means by Which Amendment With Leave of Court is Made Chapter 7 Pre-action Protocols Introduction The Construction and Engineering Pre-action Protocol Pre-action Protocol for Construction and Engineering Disputes, 2nd Edition The Letters The Pre-action Meeting Protocol Referee Procedure The Construction and Engineering Pre-action Protocol—Protocol Referee Procedure Pre-action Protocol for Construction and Engineering Disputes, 2nd Edition Issuing Claims Just Before the Limitation Period Expires Application of the Protocol to Other Processes Chapter 8 The Management of Proceedings and Legal Representation Principles of Management Solicitors Barristers Professional client access Public access Licensed access Chapter 9 Litigation Coronavirus update Guidance from the Technology and Construction Court COVID-19: Overview of HMCTS response: July 2020 The Civil Procedure Rules (“CPR”) Forms The Electronic Working Scheme Issue Service Acknowledgment of Service Statements of Case Amendment Further Information Addition and Substitution of Parties Part 20—Counterclaims and Other Additional Claims Applications for Orders Summary Judgment, Interim Payment and Striking Out of Defences Injunctive Relief Case Management Disclosure and Inspection of Documents Evidence Offers to Settle Discontinuance Trials Court Fees Costs against Non-parties Appeals from the TCC to the Court of Appeal Enforcement Chapter 9 Precedents Precedent—Claim form N1 Precedent—TCC Claim Form Precedent—Response Pack/Acknowledgment of Service Precedent—Title of Proceedings—Two Parties Precedent—Title of Proceedings—Multiple Claimants/Defendants Precedent—Title of Proceedings—Part 20 Parties Precedent—Statement of Truth—Statement of Case, a Response, Application Notice or a Notice of Objections Precedent—Statement of Truth—Witness Statement Precedent—Statement of Truth—Separate Document Precedent—Authority for Solicitor to Sign Statement of Truth Precedent—Part 36 Offer by a Claimant Precedent—Application Notice—TCC Cases Precedent—First case management questionnaire (the prescribed form) Precedent—First case management questionnaire—Simple example Precedent—Case management Conference Directions Form Ungley Order Precedent—Wording Snippet for Defendant’s Skeleton for Case Conference Draft Directions In Adjudication Enforcement Proceedings Precedent—Application Notice—Practice Form N244 Precedent—Application Notice in TCC Case where No Hearing is Sought Precedent—Pre-trial Review Questionnaire (the prescribed form) Precedent—Pre-trial Review Directions Form (the prescribed form) Precedent—Costs Form 1—Statement of Costs (summary assessment) Precedent—List of Documents: Standard Disclosure— Prescribed Form N265 Precedent—Appellant’s Notice Respondent’s Notice Precedent—Application Notice in Court of Appeal Precedent—Application Notice for Permission to Appeal Precedent—Request for Dismissal of an Appeal Precedent—General Form of Request for Dismissal of an Application Precedent—Request for a Dismissal of an Application which has not been Served on Any Other Party Precedent—General Form of Judgment or Order Precedent—Witness Statement Precedent—Claim Form (CPR Part 8) Precedent—Application Notice Precedent—Electronic documents questionnaire Chapter 10 Expert Evidence The Purpose of Expert Evidence The Independence of Expert Witnesses The Expertise and Case Knowledge of Expert Witnesses Expert Disciplines Expert Evidence upon Payment for the Works Expert Evidence as to Delay Expert Evidence as to Defects Expert Evidence—Other Cases Choosing an Expert Witness Expert Evidence under the CPR—Getting Permission The Civil Justice Council Experts Protocol—Guidance for the Instruction of Experts in Civil Claims 2014 Witnesses of Fact as Experts The Payment of Party-appointed Experts The Liability of Experts Assessors Chapter 10 Precedents The Instruction Letters Precedent - Pre-advice enquiry Precedent - Instructions to advice Precedent - Pre-report evidence enquiry Precedent - Instructions to prepare and give expert evidence Application for a Direction as to Expert Evidence Application in a County Court for a Direction as to Expert Evidence Order for Expert Evidence Order for Appointment of a Court Expert Application to a County Court for Reference for Enquiry and Report by District Judge Precedent—Expert Report Skeleton Chapter 11 Arbitration Introduction The Making of an Effective Arbitration Agreement Arbitration Agreement or Expert Determination? The Jurisdiction of the Arbitrator The Legal Principles to be Applied Stay of Court Proceedings Anti-suit Injunctions The Arbitration Notice (Notice to Concur) Choosing an Arbitrator Appointment of the Arbitrator Entitlement of the Arbitrator to Fees Interlocutory Matters Provisional Orders and Interim Awards Costs in Arbitrations The Arbitration of Multi-partite Disputes Trial Appeals and other Challenges The Position of the Arbitrator: Revocation, Resignation, Death and Immunity Enforcement CIMAR The ICE Arbitration Procedure The ICC Court of Arbitration The Role of the Courts in ICC Arbitrations Enforcement of ICC Awards The Text of the Arbitration Act 1996 Chapter 11 Precedents Precedent—Clause for Pendulum Arbitration Agreement Precedent—ICC Arbitration Clause Precedent—Proviso to Arbitration Clause for Adjudication Precedent—The Joinder Clause in City & General v AYH Precedent—Headings Precedent—Dispute Generation Letter Precedent—Notice to Concur: Short Form Precedent—Default Arbitration Notice Number 1 (named or designated arbitrator) Precedent—Joint Letter Proposing Alternative Commitment Fee (Pre-Acceptance) Precedent—Joint Letter Refusing Commitment Fee (Post-Acceptance) Precedent—Claimant’s Proposals for Procedure Precedent—Respondent’s Refusal to Pay Share of ICC Advance of Costs Precedent—The Turner Arbitration Chambers Typical Form of Agreement for Appointment of a Costs Security Arbitrator Precedent—The Turner Arbitration Chambers Costs Security Arbitration Scheme Rules Precedent—Heading for a Calderbank Letter in Arbitration Precedent—Invitation to Arbitrator to make a Peremptory Order Chapter 12 Disclosure, E-disclosure and Technology Types of Information Disclosure and Inspection of Documents Key Changes Introduced by the CPR Standard Disclosure Documents in a Party’s Control Dispensing With and Limiting Disclosure Search for Documents E-disclosure Form of List of Documents Pre-action Disclosure Non-party Disclosure Specific Disclosure Continuing Duty of Disclosure Inspection and Copying Inadvertent Disclosure and Inspection Is Adjudication “Litigation” for the Purposes of Claiming Litigation Privilege? Use of Disclosed Documents Sanctions for Non-disclosure Privilege—Reports upon Defects and Third-party Correspondence Practice Direction 51U—Disclosure Pilot for the Business and Property Courts Definition of Document When do Disclosure Obligations Start? The Duty on Legal Representatives: Preservation of Documents Initial Disclosure Extended Disclosure The Extended Disclosure Models Identifying the Issues for Disclosure Other Provisions concerning Disclosure Models The Disclosure Review Document Disclosure Guidance Hearings Complying with an Order for Extended Disclosure Production of Documents The Right to Withhold Production of Documents Confidentiality Redaction Sanctions and the Failure Adequately to Comply with an Order for Extended Disclosure Specific Disclosure Documents Referred to in Evidence Chapter 12 Precedents The TeCSA Protocol eDisclosure Protocol Pack The Electronic Working Scheme Chapter 13 Guarantees, Bonds, Warranties and Assignments Principles of the Law of Surety Interpretation of Bonds Conditional (Traditional) Bonds Demand Bonds Mareva Injunction Retention of Title and Charges Retention Money Promissory Notes, Letters of Credit and Post-dated Cheques Collateral Warranties Specific Performance: Collateral Warranties and Bonds Assignments Chapter 13 Precedents Witness Statement in Support of Application for Setting Aside Retention Money Draft Minute of Order for Setting Aside Retention Money Wording to be Added to JCT 2011, Clause 4 if Deleting the Obligation to Separate Retention Money Chapter 14 Settlement Introduction Achieving the Climate for Settlement The Ingredients of a Binding Settlement Settlements Obtained by Economic Duress Terms of Settlement—Interim Settlements Terms of Settlement—Final Settlements Procedure Complications in Multipartite Disputes Confidentiality of Settlement Agreements Chapter 14 Precedents Precedent—Without Prejudice Funding Agreement Precedent—Acceleration Agreement Precedent—Order Staying Proceedings for Adjudication Precedent—Final Settlement: “All In” Deal Precedent—Final Settlement, Alternative Form: Agreement as to Certification Entitlement Precedent—Tomlin Order Precedent—Terms of Settlement between Claimant and Defendant where no Third Party Settlement Precedent—Notice of Discontinuance Precedent—Letter Sending Cheque in Full and Final Satisfaction Precedent—Letter by Recipient of Settlement Cheque Denying Accord and Satisfaction Precedent—Wording to Catch Extra-Contractual Claims Precedent—Wording to Resolve Doubt about Past Costs Orders Precedent—Wording to Resolve Doubt about Inter Firm Photocopying Charges Precedent—Tomlin Order Wording Chapter 15 Construction Insurance Relevance of Insurance Insurance Protects Both Parties to a Construction Contract Cost of Insurance Types of Insurance on Construction Projects Scope of Cover Liability and Loss Insurance Distinguished Joint Names Insurance Preferable Versus Noting an Interest on the Policy Insurer Recovering in the Name of the Insured (Subrogation) “Events Occurring” and “Claims Made” Cover Distinguished Aggregate and “Each and Every Event” Insurance Affects the Amount Recoverable under a Policy Deductibles and Excesses are Borne by the Insured Party Dealing with Insurers Negotiating Insurance Provisions in Construction Documents Directory Directory Part I Organisations Part II—Legally Qualified Adjudicators Part II—Adjudicators