Dar Es Salaam Station DAR ES SALAAM & MOROGORO STATIONS TEST & COMMISSIONING SCHEDULE No System Equipment Duration ELECTRICAL SYSTEMS 1 Lighting System Lighting fixtures 2 Central Battery System Lighting fixtures, kits 2 Days 3 Panelboards Panelboards 6 Days 4 Earthing & Lightning Test Points 1 Day 5 UPS UPS Unit 1 Day 6 Fire Alarm FACP, Detectors, Modules 7 Transformer Transformer 1 Day 8 MV Switchgear MV Switchgear 1 Day 9 Generator Generator 1 Day 10 Fire Fighting System Fire Pumps 1 Day 11 Fire Fighting System Fire Hose Cabinets 1 Day 12 Fire Fighting System 13 Fire Fighting System 14 Clean Agent Suppression System Fire Hydrants Fire Fighting System components FM200 1 Day 1 Day 2 Days 15 Smoke Extract System Smoke Extract Fans 1 Day 16 Staircase Pressurization System Staircase Pressurization Fans 1 Day 17 Smoke Curtains Smoke Curtains 1 Day 18 Ventilation System MDF,FD 2 Days 19 Ventilation System Exhaust Fans 1 Day 20 Ventilation System Heat Recovery Units 1 Day 21 Ventilation System PACU 1 Day 22 Ventilation System AHU 1 Day 23 Ventilation System Air Curtains 1 Day 24 VRF and Split Units VRF, Split AC Units 7 Days 25 Domestic Water System Booster Pumps 1 Days 26 Water Treatment System 27 Waste Water System Water Treatment Unit Waste Water & Drainage Pumps 1 Day 1 Day Morogoro Station S: Tests to be done wi January 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 S S M T W T F S S M T F S S M W T F S S M T W T F S S M T W T 4 Days S 10 Days S S S S S S S MECHANICAL SYSTEMS S S S S S S S S S S