OPERATION & MAINTENANCE
TRAINING MANUAL FOR AK3
Page 1
DG
EM DG CS&D SYS EM
COMM
INTRODUCTION TO SICAM AK3
•
AK3 automation component is an advance version of
SIEMENS SICAM RTU.
•
This is used to convert wide range of communication
protocols
•
The tool used for Engineering of RTU is TOOLBOX II
•
It is used in power plants, substations & industrial
plants.
•
It can be used as a controller, gateway or data
concentrator.
Page 2
EM DG
TOPOLOGY
Page 3
EM DG
AK3
KNOW THE
HARDWARES
Page 4
EM DG
RACK TYPE
9 SLOT
17 SLOT
Page 5
EM DG
DIFFERENT TYPES OF RACK
Page 6
EM DG
MASTER CARD REDUNDANCY
IN SAME RACK
Page 7
EM DG
AK3 WITH EXPANSION RACK
Page 8
EM DG
CP-2016 AND ITS LED DETAILS
Page 9
EM DG
CP-2019 & ITS LED DETAILS
Page 10
EM DG
MASTER & PROCESSOR CARD PRE DETAILS
Page 11
EM DG
CP-2017 & ITS LED DETAILS
Page 12
EM DG
CP-2017 PRE CONNECTION & PATCH PLUG CONNECTION
Page 13
EM DG
SSE ( SM-2558)
Page 14
EM DG
SSE ( SM-2551)
Page 15
EM DG
SSE ( SM-0551)
Page 16
EM DG
SSE ( SM-0551 OVER SM 2558)
Page 17
EM DG
SSE OVER BSE
Page 18
EM DG
I/O MODULES (DI) & ITS LED
Page 19
EM DG
I/O MODULES (DO) & ITS LED
Page 20
EM DG
I/O MODULES (DI) & ITS LED
AI ADD-ON
Page 21
EM DG
SETTING PBA & I/O MODULE’S CABLE PLUG
Page 22
EM DG
EJECTING BSE (CARDS) FROM RTU
Page 23
EM DG
POWER MODULES
Page 24
EM DG
RS485 TO RS232 CONVERTOR
Page 25
EM DG
CM-0842 BUS-INTERFACE
Page 26
EM DG
CM-0843 BUS-INTERFACE
Page 27
EM DG
MULTI-BUS-INTERFACE
Page 28
EM DG
FLASH/MEMORY CARD
Page 29
EM DG
6
Page 30
EM DG
KNOW THE SOFTWARE
OPTIONS
Page 31
EM DG
LOGIN TO TOOLBOX II
DEFAULT USER ID: SAT_ROOT
DEFAULT PASSWORD: SAT_ROOT
Page 32
EM DG
COMMUNICATION BETWEEN
RTU & TOOLBOX II
1)
USING TOOLBOX/OPM/RTU CABLE: ONLINE/DIRECT OPERATION
2) USING LAN CABLE: REMOTE OPERATION
Page 33
EM DG
1) USING TOOLBOX/OPM/RTU CABLE: ONLINE/DIRECT
OPERATION
Connect laptop/PC to mini USB port
available on Master Card (CP 2016)
using USB-Mini USB cable.
Note: Need to define Communication Port (Com Port)
It must be same as of LAPTOP/PC Com Port !
Page 34
EM DG
How To Define Com Port in Toolbox II
Open Toolbox > Toolbox II Presets > System >
Presets_TOOLBOX…> Interface to AU > Select from Drop Down.
Page 35
EM DG
COMMUNICATION BETWEEN
RTU & TOOLBOX II
Page 36
EM DG
2) USING LAN CABLE: REMOTE OPERATION
Open Toolbox II > Go to OPM > System > Remote operation…
Now select
‘Terminal Server’ as Transmission-medium &
‘TCP/IP’ in Transmission medium list (dropdown)
Page 37
NOTE:
HTTP: 80/2001
HTTPS: 443
Port ID (Without Security): Not Required
EM DG
COMMUNICATION BETWEEN
RTU & TOOLBOX II
Page 38
EM DG
COMMUNICATION BETWEEN
RTU & TOOLBOX II
CONDITION-1: AU IS ALREADY DEFINED.
CONDITION-2: AU IS NOT DEFINED.
Page 39
EM DG
CONDITION-1: AU IS ALREADY DEFINED.
Select AU> Go to remote-station in menu bar> Call
OR
Select AU and Double Click on its serial number
OR
Select AU and click on ‘call’ icon in icon bar.
Page 40
EM DG
COMMUNICATION BETWEEN
RTU & TOOLBOX II
Page 41
EM DG
COMMUNICATION BETWEEN
RTU & TOOLBOX II
Page 42
EM DG
CONDITION-1 AU IS NOT DEFINED.
Open Toolbox II > Go to OPM > System >
Remote operation…
Now select
‘Terminal Server’ as Transmission-medium &
‘TCP/IP’ in Transmission medium list (dropdown)
Now, right click on 1st Row > Append Lines…> No. of lines > Define 1)
Rem. Station & 2) RTU’S PRE IP
Page 43
EM DG
COMMUNICATION BETWEEN
RTU & TOOLBOX II
Page 44
EM DG
COMMUNICATION BETWEEN
RTU & TOOLBOX II
Rest will be similar to condition 1
Page 45
EM DG
STRONG RECOMMENDATION !
Compare Backup before troubleshooting in Toolbox II Software
How to compare ?
Page 46
EM DG
COMPARE
Toolbox II > OPM > Target System > SICAM 1703 >
Parameterloader > Select all rows & columns >
Parameter > Comparison AU <-> TOOLBOX.
Result:
1) up-to-date: Same backup is running in RTU.
2) not-up-to-date: Backup is other than running in RTU !
Page 47
EM DG
COMPARE
STEP-1
STEP-3
STEP-2
STEP-4
Page 48
EM DG
UPDATING FIRMWARE IN TOOLBOX II
Toolbox II > Service Programs > Special Programs >
Master Data Update > Select Firmware Folder > Ok >
Page 49
EM DG
UPDATING FIRMWARE IN TOOLBOX II
Page 50
EM DG
FIRMWARE LOADING IN RTU
OPM > Target Systems > SICAM 1703 > Firmwareloader > Double click on project
> Select all rows > Load > Selected system elements> Load intelligent Ok.
The picture can't be display ed.
Page 51
The picture can't be display ed.
EM DG
FIRMWARE LOADING IN RTU
The picture can't be display ed.
Page 52
The picture can't be display ed.
EM DG
FIRMWARE LOADING IN RTU
The picture can't be display ed.
Page 53
EM DG
DIAGNOSTIC
OPM > Target Systems > SICAM 230 > Diagnostic >
Select the project by double clicking > Select all rows >
Acknowledgement > Acknowledge AU > Ok >
Diagnostic >
1) AU overview diagnostic
2) AU Individual diagnostic
3) AU History diagnosis
4) CPU diagnostic
Page 54
EM DG
DIAGNOSTIC
Page 55
EM DG
DIAGNOSTIC
Page 56
EM DG
DIAGNOSTIC
Page 57
EM DG
DIAGNOSIS REPORT
Page 58
EM DG
DATA FLOW TEST
Toolbox II > OPM > Target Systems > SICAM 230 > Data flow test > Double click on Project > Select BSE
(Data in/out) > Simultaneous-log > Display Process Informations…
Display
Page 59
EM DG
DATA FLOW TEST
Page 60
EM DG
DATA FLOW TEST
Page 61
EM DG
DATA FLOW TEST
Page 62
EM DG
DATA FLOW TEST RESULT
Page 63
EM DG
TRANSFORMING/COMPILING DATABASE
Toolbox II > OPM > Target System > SICAM
1703 > Transform… > Move AU to Selected
Entries > Ok.
NOTE: Transform Parameters must be checked
in below ‘Functions’ !
Page 64
EM DG
TRANSFORMING/COMPILING DATABASE
Page 65
EM DG
TRANSFORMING/COMPILING DATABASE
Errors can be found here !
Page 66
EM DG
LOADING FILE IN RTU
1) Using Flash/Memory Card
2) Using USB-Mini USB cable/LAN Cable
1) Using Flash/Memory Card
Insert the SD Memory card in Laptop SD Memory
card slot > OPM > Tools > System Technique >
Explore and Right Click on project name(Reg,Comp)
> Flashcard > Create files… > Select Floppy > Ok >
Delete existing content > Yes > Ok.
Page 67
EM DG
LOADING FILE IN RTU
Page 68
EM DG
LOADING FILE IN RTU
Page 69
EM DG
LOADING FILE IN RTU
Page 70
EM DG
2) Using USB-Mini USB cable/LAN Cable
Connect laptop with master card using OPM/Toolbox
(USB-MINI USB) Cable > Toolbox II > OPM > Target
Systems > SICAM 1703 > Parameterloader > Select
the project by double clicking > Select all rows > Load
> Selected System elements > Load Intelligent > Now
see the state: Loaded and up-to-date/ up-to-date
Page 71
EM DG
LOADING FILE IN RTU
Page 72
EM DG
LOADING FILE IN RTU
Page 73
EM DG
EXPORTING DATA FROM TOOLBOX II
(CREATING BACKUP)
Toolbox II > Data distribution center > Export > All >
Ok > Start Export > Browse the location > Ok > Ok
Page 74
EM DG
EXPORTING DATA FROM TOOLBOX II
(CREATING BACKUP)
Page 75
EM DG
EXPORTING DATA FROM TOOLBOX II
(CREATING BACKUP)
Page 76
EM DG
EXPORTING DATA FROM TOOLBOX II
(CREATING BACKUP)
Page 77
EM DG
IMPORTING BACKUP IN TOOLBOX
(RESTORING BACKUP IN TOOLBOX)
Toolbox II > Data distribution center > Import > Browse the
backup > Click on ‘All’ > Ok > Ok All > Start Import > Ok.
Page 78
EM DG
IMPORTING BACKUP IN TOOLBOX
(RESTORING BACKUP IN TOOLBOX)
Page 79
EM DG
IMPORTING BACKUP IN TOOLBOX
(RESTORING BACKUP IN TOOLBOX)
Page 80
EM DG
CONVERTING DATABASE FROM COPY TO
ORIGINAL & VICE-VERSA
Toolbox II > Data distribution center > Preset
customer/plant > Right click on System Tech. (Project
Name) > Convert to Original / Read only parameters.
Again, Right click on Process Technique (Project Name) >
Convert to Original / Convert to copy.
Page 81
EM DG
CONVERTING DATABASE FROM COPY TO
ORIGINAL & VICE-VERSA
Page 82
EM DG
DOWNLOAD ENABLED BACKUP
1) UPLOADING IN RTU
2) DOWNLOADING FROM RTU
1) UPLOADING IN RTU
TOOLBOX > TOOLBOX II Presets > System >
Presets_TOOLBOX… > Select ‘COM’ > Check ‘Generate
and upload AU file after parameter loading’ > Ok.
Now load the file using OPM/TOOLBOX Cable or Using
LAN Cable as explained earlier.
(Refer ‘LOADING FILE IN RTU’)
Page 83
EM DG
DOWNLOAD ENABLED BACKUP
Page 84
EM DG
DOWNLOAD ENABLED BACKUP
Page 85
EM DG
2) DOWNLOADING FROM RTU
Toolbox II > Data Distribution Center > Action >
Download SICAM 1703 TOOLBOX II >Ok
(Using OPM/TOOLBOX Cable or LAN Cable).
Page 86
EM DG
2) DOWNLOADING FROM RTU
Page 87
EM DG
AT LAST BUT NOT LEAST
Page 88
EM DG
HELP ??
Page 89
EM DG
HELP & SUPPORT
Page 90
EM DG
HELP & SUPPORT
Page 91
EM DG
Thank You All !