Purchasing Requirement of High temperature industrial chamber furnace Ⅰ. (End-user's Use and Feature) - Sintering of ceramic materials at high temperature(>1750℃) Ⅱ. (Configurations of Goods) 1. Furnace (main unit) 1) Heating chamber 2) Control system 3) Frame/parts 1 set 1 set 1 set Ⅲ. (Specification) Equal to or greater than the following specification: 1. Heating chamber (1) Type: 1800℃ high temperature industrial chamber furnace. - Max. operating temperature: 1800℃ (2) Dimension: Usable chamber size: 400(H)x400(W)x400(D) mm, 64 Liter volume. (3) Furnace design & product quality control by the following certificate. - ISO9001 - Machinery Directive(2006/42/EG) - The EMC Directive 2014/30/EU - The Low Voltage Directive 2014/30/EU (4) Temperature uniformity dimensions: - 315(H)x340(W)x340(D) mm - Distance from hearth: 38mm - Distance from door: 80mm - Central loading - Temperature uniformity @ 1600℃in air ±7.5℃ (5) Electrical operated Up & Down door system. (6) Advanced refractory interior, used in combination with energy efficient loss thermal mass fiber board insulation. (7) Roof insulation boards to prevent crack - The roof is cut into pieces to help avoid cracks. - In addition to that the roof has some internal SiC rods which the roof and give it more stability. (8) Heating elements: Kanthal Super 1900℃ High quality molybdenum tungsten disilicide: 8EA - “U” heating elements suspended vertically from roof. - Left = 3EA, Right = 3EA, Back = 2EA the chamber radiating heat. (9) Chimney be the top. 2. Control system (1) Temperature control: Eurotherm EPC3016P1 Programmer. - 1 Program 24 segments (12 ramps and 12 dwell times) - Digital dual display, Ramp rate -℃/sec.min.hour - Dwell/min. hours, Run, Hold, Reset, Navigating (2) Digital over-temperature protection controller. (3) Thermocouple from the back side into the chamber at top of hight: ( + ) =Pt70%Rh30%// ( - ) =Pt94%Rh6%, 1820℃, 2EA (1EA - main controller, 1EA – OTC). (4) Thyristor unit: Eurotherm microprocessor controlled phase angle fired 3 phase thyristor unit. (5) 3phase isolating transformer: using high grade OFHC. - Oxygen-Free High-Conductivity Copper a pure grade of copper wires. - for full protection against over-voltage and current. (6) Main contractor, EMC Filter, Fuse. (7) Power supply: 380V, 3Phase, Neutral, Earth, 60Hz, 26Kw. 3. Frame/Parts (1) Steel work: Double skin case zinc coated steel sheet with a tough epoxy powder paint, cool outer cabinet. (2) Dimensions (External size=>HxWxD mm: 2,000(H)x1,000(W)x1,200(D). (3) One body compact design. IⅤ. (Remarks) 1. It should be delivered within 8 months after receipt of the order. 2. The installation and operation should be carried out by the bidder/supplier’s responsibility at end user’s site. 3. Warranty Period - When defective parts are founded during the installation of the order, it should be preplaced immediately with new one. 4. 2 copies of operation & maintenance manuals should be supplied. 5. Include certificate of furnace design & product quality control. - ISO9001 - Machinery Directive 2006/42/EG - The EMC Directive 2014/30/EU - The Low Voltage Directive 2014/35/EU