REVISED BASELINE PROGRAMME - BL - FINAL001 - UPDATE [D Activity ID Activity Name Week 01 05-Jan-22 12:09 Performance % Complete REVISED BASELINE BASELIN PROGRAMME - BL - FINAL001 - UPDATE [DD 26-12-21] -N 92.11% Procurement 98.59% Material Delivery 98.59% Electrical & ICA Material Materia Transmission Pipeline Sohar IWPP to Sohar IR - 1600mm CS Pipe - AL 01 (18.9Km) MADEI1710 Cathodic protection system 94.71% 90% 90% 90% Sohar IR to MPS 1 - 12 1200mm CS Pipe - AL 02 (14.325Km) MADEI2600 Cathodic protection system 90% 90% MPS 1 to MPS 2 - 120 1200mm CS Pipe - AL 03 (16.9Km) MADEI2610 Cathodic protection system 90% 90% MPS 2 to Dhahirah IR - 1200mm CS Pipe - AL 04 (24.0Km) MADEI2620 Cathodic protection system 90% 90% Dhahirah IR to Dhank Junction - 1200mm CS Pipe - AL 5A (86.8Km) MADEI2630 Cathodic protection system 90% 90% Dhank Junction to Ibri High Level 1 - AL 5B- CS Pipies MADEI2640 Cathodic protection system 90% 90% Structures Sohar IWPP MADEI1000 11KV Switchgear 99.65% 100% 100% MADEI1010 11KV Soft starter 100% MADEI1020 Step down Transformers 100% MADEI1030 LV Switchgear 100% MADEI1070 LV Sub-panels 100% MADEI1080 Power, control & earthing cables 100% MADEI1100 Earthing system 100% MADEI1130 Leak detection system 100% MADEI1150 lighting accessories 100% MADEI1160 HVAC system 100% MADEI1170 Cable accessories 100% Sohar IR MADEI1180 11KV Switchgear 100% 100% MADEI1190 11KV Soft starter 100% MADEI1200 Step down Transformers 100% MADEI1210 LV Switchgear 100% MADEI1250 LV Sub-panels 100% MADEI1260 Power, control & earthing cables 100% MADEI1280 Earthing system 100% MADEI1300 Leak detection system 100% MADEI1310 fire fighting equipment 100% MADEI1320 lighting accessories 100% MADEI1330 HVAC system 100% MADEI1340 Cable accessories 100% MPS 1 MADEI1350 11KV Switchgear 100% 100% MADEI1360 11KV Soft starter 100% MADEI1370 Step down Transformers 100% MADEI1380 LV Switchgear 100% MADEI1420 LV Sub-panels 100% MADEI1430 Power, control & earthing cables 100% MADEI1450 Earthing system 100% MADEI1470 Leak detection system 100% MADEI1480 fire fighting equipment 100% MADEI1490 lighting accessories 100% MADEI1500 HVAC system 100% MADEI1510 Cable accessories 100% MPS 2 MADEI1520 11KV Switchgear 99.31% 100% MADEI1530 11KV Soft starter 100% MADEI1540 Step down Transformers 100% MADEI1550 LV Switchgear 100% MADEI1590 LV Sub-panels 95% MADEI1600 Power, control & earthing cables MADEI1620 Earthing system 100% MADEI1640 Leak detection system 100% MADEI1650 fire fighting equipment 100% MADEI1660 lighting accessories 100% MADEI1670 HVAC system 100% MADEI1680 Cable accessories 95% 100% Dhahirah IR MADEI1690 11KV Switchgear 99.15% 100% MADEI1700 11KV Soft starter 100% MADEI1720 LV Switchgear 100% MADEI1760 LV Sub-panels 95% MADEI1770 Power, control & earthing cables 100% MADEI1790 Earthing system 100% MADEI1810 Leak detection system 100% Page 1 of 7 TASK filter: Weekly Update. © Oracle Corporation REVISED BASELINE PROGRAMME - BL - FINAL001 - UPDATE [D Activity ID Activity Name MADEI1820 fire fighting equipment MADEI1830 lighting accessories MADEI1840 HVAC system MADEI1850 Cable accessories Week 01 05-Jan-22 12:09 Performance % Complete 100% 95% 100% 100% Dhank MADEI1860 11KV Switchgear 98.84% 100% MADEI1870 11KV Soft starter 100% MADEI1890 LV Switchgear 100% MADEI1930 LV Sub-panels 95% MADEI1940 Power, control & earthing cables 95% MADEI1960 Earthing system MADEI1980 Leak detection system 100% MADEI1990 fire fighting equipment 100% MADEI2000 lighting accessories MADEI2010 HVAC system MADEI2020 Cable accessories 95% 95% 100% 100% Ibri Low Level MADEI2030 11KV Switchgear 98.16% 100% MADEI2040 11KV Soft starter 100% MADEI2060 LV Switchgear 100% MADEI2100 LV Sub-panels 95% MADEI2110 Power, control & earthing cables 95% MADEI2130 Earthing system MADEI2150 Leak detection system 100% MADEI2160 fire fighting equipment 100% MADEI2170 lighting accessories MADEI2180 HVAC system MADEI2190 Cable accessories Ibri High Level 1 MADEI2200 95% 95% 100% 100% 11KV Switchgear 97.92% 100% MADEI2210 11KV Soft starter 100% MADEI2230 LV Switchgear 100% MADEI2270 LV Sub-panels 95% MADEI2280 Power, control & earthing cables 95% MADEI2300 Earthing system MADEI2320 Leak detection system 100% MADEI2330 fire fighting equipment 100% MADEI2340 lighting accessories MADEI2350 HVAC system 100% MADEI2360 Cable accessories 100% Ibri Hihg Level 2 MADEI2370 95% 95% 11KV Switchgear 98.85% 100% MADEI2380 11KV Soft starter 100% MADEI2400 LV Switchgear 100% MADEI2440 LV Sub-panels 95% MADEI2450 Power, control & earthing cables 95% MADEI2470 Earthing system MADEI2490 Leak detection system 100% MADEI2500 fire fighting equipment 100% MADEI2510 lighting accessories MADEI2520 HVAC system 100% MADEI2530 Cable accessories 100% TRANSFORMERS 100% 100% MADPS1020 33KV& 11KV CABLES 100% MADPS1030 SUBSTAION MATERIAL 100% MADPS1040 POLES 100% MADPS1050 LV , CONTROL Cables 100% MADPS1060 33KV CB 100% MADPS1070 33KV METTERING PANELS 100% MADPS1080 DC SYSTEM 100% MADPS1090 CONTROL RELAIES AND PROTECTION PANELS 100% MADPS1100 RTU PANEL WITH INPUILT MARSHILING UNIT 100% MADPS1120 GANTERY AND BUS BARS 100% MADPS1130 33 KV DROPOUT FUSE 100% MADPS1140 CABLE TRAYS AND CABLES ACCESSORIER 100% MADPS1150 LIGHTINING ARISTOR 100% MADPS1160 INSULATOR SILICON TYPE 100% MADPS1170 FIBER GLASS ROAD STAY Power Supply Material MADPS1010 95% 95% 100% 86.92% Construction 86.92% Structures works Sohar IWPP Reservoir - Steel Tank 1 & 2 Zone A ( Steel Tank - 1 1) Substructure Works Cathodic Protection System CNSTIWPP1230 Implementation CP under bottom plate 85.78% 70% 70% 70% 70% 100% Page 2 of 7 TASK filter: Weekly Update. © Oracle Corporation REVISED BASELINE PROGRAMME - BL - FINAL001 - UPDATE [D Activity ID Activity Name Week 01 05-Jan-22 12:09 Performance % Complete CNSTIWPP1240 Implementation of the external CP System 25% CNSTIWPP1250 Implementation of the internal CP System 100% CNSTIWPP1260 Testing of CP System 50% Zone B ( Steel Tank - 2 ) Substructure Works Cathodic Protection System CNSTIWPP3450 Implementation CP under bottom plate 70% 70% 70% 100% CNSTIWPP3460 Implementation of the external CP System 25% CNSTIWPP3470 Implementation of the internal CP System 100% CNSTIWPP3480 Testing of CP System 50% Pump Station and Electrical Elec Room MEP Works Electrical works CNSTIWPP2300 Initial Electrical work for Pump House 93.6% 93.6% 93.6% 100% CNSTIWPP2310 Finishing Electrical work for Pump House 92% CNSTIWPP2320 Initial Electrical work for Control building 100% CNSTIWPP2330 Finishing Electrical work for Control building 92% Electrical Installation 95% 95% 95% Transformer Yard MEP work CNSTIWPP2485 Power Supply & Electrical Electri work CNSTIWPP2880 Installation of cable tray 88.73% 95% CNSTIWPP2885 Cable Laying & Termination (Medium- voltage cables and accessories_ 95% CNSTIWPP2890 Cable Laying & Termination (LV Cabling, grounding for buildings and site) 95% CNSTIWPP2900 Installation of Earthing and lightning protection system 90% CNSTIWPP2901 Cathodic protection for station 15% CNSTIWPP2905 Low- voltage switchboards and distribution panelboards 95% CNSTIWPP2910 Installation of MVSG,LVSG and DB 95% CNSTIWPP2920 Installation of UPS systems complete with Batteries CNSTIWPP2930 Installation of MV/LV Transformers CNSTIWPP2940 Installation of Soft Starter and Power Factor Correction 100% CNSTIWPP2950 Connection to Majan Substation/nearest Power source 87.43% CNSTIWPP3060 CCTV system 30% CNSTIWPP3180 Access control system 35% CNSTIWPP3190 Telephone system ( including Hotline system) 10% CNSTIWPP3200 Outdoor lighting 80% Site Work Site lighting CNSTIWPP2730 90% 100% Electrical cable laying and earthing 0% 0% 80% CNSTIWPP2740 Install Electrical pole 20% CNSTIWPP2750 Termination and lighting 0% Testing & Commissioning Commissioni CNSTIWPP3110 Testing & Commissioning for transformers 95% 95% CNSTIWPP3120 Testing & Commissioning for Fire alarm and firefighting system 0% CNSTIWPP3240 Testing & Commissioning for Cathodic protection for station 0% Sohar IR Reservoir - Steel Tank 3 & 4 Zone A ( Steel Tank - 3 3) Substructure Works Cathodic Protection System CNSTSHIR1230 Implementation CP under bottom plate 93.69% 73% 73% 73% 73% 100% CNSTSHIR1240 Implementation of the external CP System 40% CNSTSHIR1250 Implementation of the internal CP System 100% CNSTSHIR1260 Testing of CP System 50% Zone B ( Steel Tank - 4 4) Substructure Works Cathodic Protection System CNSTSHIR3640 Implementation CP under bottom plate 73% 73% 73% 100% CNSTSHIR3650 Implementation of the external CP System 40% CNSTSHIR3660 Implementation of the internal CP System 100% CNSTSHIR3670 Testing of CP System 50% Pump Station and Electrical Elec Room MEP Works Electrical works CNSTSHIR2310 Initial Electrical work for Pump House 98.4% 98.4% 98.4% 100% CNSTSHIR2320 Finishing Electrical work for Pump House 98% CNSTSHIR2330 Initial Electrical work for Control building 100% CNSTSHIR2340 Finishing Electrical work for Control building 98% Electrical Installation 98% 98% 98% Transformer Yard MEP work CNSTSHIR3190 Power Supply & Electrical Electri work CNSTSHIR2890 Installation of cable tray 97.96% 98% CNSTSHIR2900 Cable Laying & Termination (LV Cabling, grounding for buildings and site) 98% CNSTSHIR2910 Installation of Earthing and lightning protection system 95% CNSTSHIR2920 Installation of MVSG,LVSG and DB 98% CNSTSHIR2930 Installation of UPS systems complete with Batteries CNSTSHIR2950 Installation of MV/LV Transformers 100% CNSTSHIR2960 Installation of Soft Starter and Power Factor Correction 100% 90% Page 3 of 7 TASK filter: Weekly Update. © Oracle Corporation REVISED BASELINE PROGRAMME - BL - FINAL001 - UPDATE [D Activity ID Activity Name Week 01 05-Jan-22 12:09 Performance % Complete CNSTSHIR3320 Cable Laying & Termination (Medium- voltage cables and accessories_ 100% CNSTSHIR3330 Connection to Majan Substation/nearest Power source 100% CNSTSHIR3340 CCTV system 40% CNSTSHIR3350 Access control system 35% CNSTSHIR3360 Low- voltage switchboards and distribution panelboards 95% CNSTSHIR3370 Telephone system ( including Hotline system) 10% CNSTSHIR3380 Outdoor lighting 80% CNSTSHIR3390 Cathodic protection for station Chlorination Building MEP Works Electrical works CNSTSHIR4370 CNSTSHIR4380 Site Work Site lighting CNSTSHIR2730 70% 96.5% 96.5% 96.5% 100% Initial Electrical work for Chlorination building Finishing Electrical work for Chlorination building 95% Electrical cable laying and earthing 0% 0% 95% CNSTSHIR2740 Install Electrical pole 25% CNSTSHIR2750 Termination and lighting 25% Testing & Commissioning Commissioni CNSTSHIR3130 Testing & Commissioning for transformers CNSTSHIR3140 Testing & Commissioning for Fire alarm and firefighting system CNSTSHIR3430 Testing & Commissioning for Cathodic protection for station 100% 100% 20% 0% MPS 1 Reservoir - Steel Tank ((5 & 6) Steel Tank 5 Substructure Works CNSTMPSI1260 Implementation CP under bottom plate CNSTMPSI1270A Implementation of the external and internal CP System CNSTMPSI1280A Testing of CP System Steel Tank 6 Substructure Works CNSTMPSI3490 91.55% 71.67% 71.67% 71.67% 100% 65% 50% 71.67% 71.67% 100% Implementation CP under bottom plate CNSTMPSI3491A Implementation of the external and internal CP System CNSTMPSI3492A Testing of CP System 65% 50% Pump Station and Electrical Elec Room MEP Works Electrical works CNSTMPSI2310 Initial Electrical work for Pump House 93.6% 93.6% 93.6% 100% CNSTMPSI2320 Finishing Electrical work for Pump House 92% CNSTMPSI2330 Initial Electrical work for Control building 100% CNSTMPSI2340 Finishing Electrical work for Control building 92% Electrical Installation 0% 0% 92% Transformer Yard MEP work CNSTMPSI3190 Power Supply & Electrical Electri work CNSTMPSI2890 Installation of cable tray 91.32% 92% CNSTMPSI2900 Cable Laying & Termination (LV Cabling, grounding for buildings and site) 92% CNSTMPSI2910 Installation of Earthing and lightning protection system 90% CNSTMPSI2920 Installation of MVSG,LVSG and DB 92% CNSTMPSI2930 Installation of UPS systems complete with Batteries 90% CNSTMPSI2950 Installation of MV/LV Transformers 100% CNSTMPSI2960 Installation of Soft Starter and Power Factor Correction 100% CNSTMPSI3320 Cable Laying & Termination (Medium- voltage cables and accessories_ CNSTMPSI3330 Connection to Majan Substation/nearest Power source CNSTMPSI3340 CCTV system 20% CNSTMPSI3350 Access control system 20% CNSTMPSI3360 Low- voltage switchboards and distribution panelboards 72% CNSTMPSI3370 Telephone system ( including Hotline system) 10% CNSTMPSI3380 Outdoor lighting 75% CNSTMPSI3390 Cathodic protection for station Site Work Site lighting CNSTMPSI2730 90% 91.68% 0% Electrical cable laying and earthing 0% 0% 80% CNSTMPSI2740 Install Electrical pole 15% CNSTMPSI2750 Termination and lighting 40% Testing & Commissioning Commissioni CNSTMPSI3130 Testing & Commissioning for transformers CNSTMPSI3140 Testing & Commissioning for Fire alarm and firefighting system CNSTMPSI3430 Testing & Commissioning for Cathodic protection for station 95% 95% 0% 0% MPS 2 Reservoir - Steel Tank 7 & 8 Steel Tank 7 Substructure Works CNSTMPSII1080 Implementation CP under bottom plate CNSTMPSII1120A 92.35% 50% 50% 50% 100% Implementation of the external and internal CP System 50% CNSTMPSII1120A10 Testing of CP System Steel Tank 8 Substructure Works CNSTMPSII3280 0% 50% 50% 100% Implementation CP under bottom plate Page 4 of 7 TASK filter: Weekly Update. © Oracle Corporation REVISED BASELINE PROGRAMME - BL - FINAL001 - UPDATE [D Activity ID Activity Name CNSTMPSII3290A Implementation of the external and internal CP System CNSTMPSII3291A Testing of CP System Week 01 05-Jan-22 12:09 Performance % Complete 50% 0% Pump Station and Electrical Elec Room MEP Works Electrical works CNSTMPSII1800 Initial Electrical work for Pump House 93.6% 93.6% 93.6% 100% CNSTMPSII1810 Finishing Electrical work for Pump House 92% CNSTMPSII1820 Initial Electrical work for Control building 100% CNSTMPSII1830 Finishing Electrical work for Control building 92% Electrical Installation 85% 85% 85% Transformer Yard MEP work CNSTMPSII2680 Power Supply & Electrical Electri work CNSTMPSII2380 Installation of cable tray 93.15% 95% CNSTMPSII2390 Cable Laying & Termination (LV Cabling, grounding for buildings and site) 92% CNSTMPSII2400 Installation of Earthing and lightning protection system 85% CNSTMPSII2410 Installation of MVSG,LVSG and DB 92% CNSTMPSII2420 Installation of UPS systems complete with Batteries CNSTMPSII2440 Installation of MV/LV Transformers 100% CNSTMPSII2450 Installation of Soft Starter and Power Factor Correction 100% CNSTMPSII2810 Cable Laying & Termination (Medium- voltage cables and accessories_ CNSTMPSII2820 Connection to Majan Substation/nearest Power source CNSTMPSII2830 CCTV system 20% CNSTMPSII2840 Access control system 20% CNSTMPSII2850 Low- voltage switchboards and distribution panelboards 85% CNSTMPSII2860 Telephone system ( including Hotline system) 10% CNSTMPSII2870 Outdoor lighting 60% CNSTMPSII2880 Cathodic protection for station 35% Guard House MEP Works Electrical works CNSTMPSII3190 CNSTMPSII3200 Site Work Site lighting CNSTMPSII2220 90% 88% 94.48% Initial Electrical work for Guard house 0% 0% 0% 100% Finishing Electrical work for Guard house 100% Electrical cable laying and earthing 0% 0% 80% CNSTMPSII2230 Install Electrical pole 15% CNSTMPSII2240 Termination and lighting 25% Testing & Commissioning Commissioni CNSTMPSII2620 Testing & Commissioning for transformers CNSTMPSII2630 Testing & Commissioning for Fire alarm and firefighting system CNSTMPSII2920 Testing & Commissioning for Cathodic protection for station 95% 95% 0% 0% Dhahirah IR Reservoir - Steel Tank 9 & 10 Steel Tank 9 Substructure Works Cathodic Protection System (Steel Tank 9) CNSTDHIR1230 Implementation CP under bottom plate 53.89% 63% 63% 63% 63% 100% CNSTDHIR1240 Implementation of the external CP System 0% CNSTDHIR1250 Implementation of the internal CP System 100% CNSTDHIR1260 Testing of CP System 52% Steel Tank 10 Substructure Works Cathodic Protection System (Steel Tank 10) CNSTDHIR3450 Implementation CP under bottom plate 63% 63% 63% 100% CNSTDHIR3460 Implementation of the external CP System 0% CNSTDHIR3470 Implementation of the internal CP System 100% CNSTDHIR3480 Testing of CP System 52% Power Supply & Electrical Electri work CNSTDHIR2880 Installation of cable tray 19.89% 0% CNSTDHIR2885 Cable Laying & Termination (Medium- voltage cables and accessories_ 0% CNSTDHIR2890 Cable Laying & Termination (LV Cabling, grounding for buildings and site) 0% CNSTDHIR2900 Installation of Earthing and lightning protection system 0% CNSTDHIR2901 Cathodic protection for station CNSTDHIR2905 Low- voltage switchboards and distribution panelboards 0% CNSTDHIR2915 Installation of AC System /HAVC for Gaurd House 0% CNSTDHIR2920 Installation of UPS systems complete with Batteries 0% CNSTDHIR2940 Installation of Soft Starter and Power Factor Correction 0% CNSTDHIR2950 Connection to Majan Substation/nearest Power source 90% CNSTDHIR3060 CCTV system 0% CNSTDHIR3180 Access control system 0% CNSTDHIR3190 Telephone system ( including Hotline system) CNSTDHIR3200 Outdoor lighting Guard House MEP Works Electrical works CNSTDHIRI3190 CNSTDHIRI3200 10% 0% 10% 84.6% 84.6% 84.6% 100% Initial Electrical work for Guard house Finishing Electrical work for Guard house 78% Site Work 0% Page 5 of 7 TASK filter: Weekly Update. © Oracle Corporation REVISED BASELINE PROGRAMME - BL - FINAL001 - UPDATE [D Activity ID Activity Name Site lighting CNSTDHIR2730 Week 01 05-Jan-22 12:09 Performance % Complete Electrical cable laying and earthing 0% 0% CNSTDHIR2740 Install Electrical pole 0% CNSTDHIR2750 Termination and lighting 0% Testing & Commissioning Commissioni CNSTDHIR3120 Testing & Commissioning for Fire alarm and firefighting system CNSTDHIR3240 0% 0% Testing & Commissioning for Cathodic protection for station 0% Dhank Reservoir - Steel Tank 1 11 Substructure Works Cathodic Protection S System CNSTDHAN1230 Implementation CP under bottom plate 52.23% 65% 65% 65% 100% CNSTDHAN1240 Implementation of the external CP System 0% CNSTDHAN1250 Implementation of the internal CP System 100% CNSTDHAN1260 Testing of CP System 50% Power Supply & Electrical Electri work CNSTDHAN2880 Installation of cable tray 23.16% 65% CNSTDHAN2885 Cable Laying & Termination (Medium- voltage cables and accessories_ 15% CNSTDHAN2890 Cable Laying & Termination (LV Cabling, grounding for buildings and site) 50% CNSTDHAN2900 Installation of Earthing and lightning protection system 10% CNSTDHAN2901 Cathodic protection for station CNSTDHAN2905 Low- voltage switchboards and distribution panelboards 50% CNSTDHAN2915 Installation of AC System /HAVC for Gaurd House 10% CNSTDHAN2920 Installation of UPS systems complete with Batteries 60% CNSTDHAN2940 Installation of Soft Starter and Power Factor Correction 0% CNSTDHAN2950 Connection to Majan Substation/nearest Power source 90% CNSTDHAN3060 CCTV system 5% CNSTDHAN3180 Access control system 5% CNSTDHAN3190 Telephone system ( including Hotline system) 5% CNSTDHAN3200 Outdoor lighting 0% Chlorination Building MEP Works Electrical works CNSTDHAN4370 CNSTDHAN4380 Site Work Site lighting CNSTDHAN2730 0% 75.5% 75.5% 75.5% 100% Initial Electrical work for Control building Finishing Electrical work for Control building 65% Electrical cable laying and earthing 0% 0% 0% CNSTDHAN2740 Install Electrical pole 0% CNSTDHAN2750 Termination and lighting 0% Testing & Commissioning Commissioni CNSTDHAN3120 Testing & Commissioning for Fire alarm and firefighting system CNSTDHAN3240 0% 0% Testing & Commissioning for Cathodic protection for station 0% Ibri Low Level Reservoir - Steel Tank 1 12 Substructure Works Cathodic Protection S System CNSTILL1230 Implementation CP under bottom plate 58.11% 62.5% 62.5% 62.5% 100% CNSTILL1240 Implementation of the external CP System 0% CNSTILL1250 Implementation of the internal CP System 100% CNSTILL1260 Testing of CP System Chlorination Building MEP Works Electrical works CNSTILL4370 CNSTILL4380 50% 0% 0% 0% 0% Initial Electrical work for Control building Finishing Electrical work for Control building 0% Ibri High Level 1 Reservoir - Steel Tank 1 13 , 14 & 15 Steel Tank 13 Substructure Works Cathodic Protection System (Steel Tank 13) CNSTIHLI1230 Implementation CP under bottom plate 48.67% 62.5% 62.5% 62.5% 62.5% 100% CNSTIHLI1240 Implementation of the external CP System 0% CNSTIHLI1250 Implementation of the internal CP System 100% CNSTIHLI1260 Testing of CP System 50% Steel Tank 14 Substructure Works Cathodic Protection System CNSTIHLI3450 Implementation CP under bottom plate 62.5% 62.5% 62.5% 100% CNSTIHLI3460 Implementation of the external CP System 0% CNSTIHLI3470 Implementation of the internal CP System 100% CNSTIHLI3480 Testing of CP System 50% Steel Tank 15 Substructure Works Cathodic Protection System CNSTIHLI3990 Implementation CP under bottom plate 62.5% 62.5% 62.5% 100% CNSTIHLI4000 Implementation of the external CP System 0% CNSTIHLI4010 Implementation of the internal CP System 100% CNSTIHLI4020 Testing of CP System 50% Power Supply & Electrical Electri work 8.09% Page 6 of 7 TASK filter: Weekly Update. © Oracle Corporation REVISED BASELINE PROGRAMME - BL - FINAL001 - UPDATE [D Activity ID Activity Name Week 01 05-Jan-22 12:09 Performance % Complete CNSTIHLI2880 Installation of cable tray 0% CNSTIHLI2885 Cable Laying & Termination (Medium- voltage cables and accessories_ 0% CNSTIHLI2890 Cable Laying & Termination (LV Cabling, grounding for buildings and site) 0% CNSTIHLI2900 Installation of Earthing and lightning protection system 0% CNSTIHLI2901 Cathodic protection for station 0% CNSTIHLI2905 Low- voltage switchboards and distribution panelboards 0% CNSTIHLI2915 Installation of AC System /HAVC for Gaurd House 0% CNSTIHLI2920 Installation of UPS systems complete with Batteries 0% CNSTIHLI2940 Installation of Soft Starter and Power Factor Correction 0% CNSTIHLI2950 Connection to Majan Substation/nearest Power source 40% CNSTIHLI3060 CCTV system 0% CNSTIHLI3180 Access control system 0% CNSTIHLI3190 Telephone system ( including Hotline system) 0% CNSTIHLI3200 Outdoor lighting 0% Site Work Site lighting CNSTIHLI2730 Electrical cable laying and earthing 0% 0% 0% CNSTIHLI2740 Install Electrical pole 0% CNSTIHLI2750 Termination and lighting 0% Testing & Commissioning Commissioni CNSTIHLI3120 Testing & Commissioning for Fire alarm and firefighting system CNSTIHLI3240 0% 0% Testing & Commissioning for Cathodic protection for station 0% Ibri Hihg Level 2 Power Supply & Electrical Electri work CNSTIHLII2880 Installation of cable tray 15.39% 15.44% 20% CNSTIHLII2885 Cable Laying & Termination (Medium- voltage cables and accessories_ 0% CNSTIHLII2890 Cable Laying & Termination (LV Cabling, grounding for buildings and site) 0% CNSTIHLII2900 Installation of Earthing and lightning protection system 0% CNSTIHLII2901 Cathodic protection for station 0% CNSTIHLII2905 Low- voltage switchboards and distribution panelboards 5% CNSTIHLII2915 Installation of AC System /HAVC for Gaurd House 0% CNSTIHLII2920 Installation of UPS systems complete with Batteries 0% CNSTIHLII2940 Installation of Soft Starter and Power Factor Correction 0% CNSTIHLII2950 Connection to Majan Substation/nearest Power source 75% CNSTIHLII3060 CCTV system 0% CNSTIHLII3180 Access control system 0% CNSTIHLII3190 Telephone system ( including Hotline system) 0% CNSTIHLII3200 Outdoor lighting 0% Site Work Site lighting CNSTIHLII2730 Electrical cable laying and earthing 0% 0% 5% CNSTIHLII2740 Install Electrical pole 5% CNSTIHLII2750 Termination and lighting 0% Testing & Commissioning Commissioni CNSTIHLII3120 Testing & Commissioning for Fire alarm and firefighting system CNSTIHLII3240 0% 0% Testing & Commissioning for Cathodic protection for station 0% Page 7 of 7 TASK filter: Weekly Update. © Oracle Corporation