REVISED BASELINE PROGRAMME - BL - FINAL001 - UPDATE [D
Activity ID
Activity Name
Week 01
05-Jan-22 12:09
Performance %
Complete
REVISED BASELINE
BASELIN PROGRAMME - BL - FINAL001 - UPDATE [DD 26-12-21] -N
92.11%
Procurement
98.59%
Material Delivery
98.59%
Electrical & ICA Material
Materia
Transmission Pipeline
Sohar IWPP to Sohar IR - 1600mm CS Pipe - AL 01 (18.9Km)
MADEI1710
Cathodic protection system
94.71%
90%
90%
90%
Sohar IR to MPS 1 - 12
1200mm CS Pipe - AL 02 (14.325Km)
MADEI2600
Cathodic protection system
90%
90%
MPS 1 to MPS 2 - 120
1200mm CS Pipe - AL 03 (16.9Km)
MADEI2610
Cathodic protection system
90%
90%
MPS 2 to Dhahirah IR - 1200mm CS Pipe - AL 04 (24.0Km)
MADEI2620
Cathodic protection system
90%
90%
Dhahirah IR to Dhank Junction - 1200mm CS Pipe - AL 5A (86.8Km)
MADEI2630
Cathodic protection system
90%
90%
Dhank Junction to Ibri High Level 1 - AL 5B- CS Pipies
MADEI2640
Cathodic protection system
90%
90%
Structures
Sohar IWPP
MADEI1000
11KV Switchgear
99.65%
100%
100%
MADEI1010
11KV Soft starter
100%
MADEI1020
Step down Transformers
100%
MADEI1030
LV Switchgear
100%
MADEI1070
LV Sub-panels
100%
MADEI1080
Power, control & earthing cables
100%
MADEI1100
Earthing system
100%
MADEI1130
Leak detection system
100%
MADEI1150
lighting accessories
100%
MADEI1160
HVAC system
100%
MADEI1170
Cable accessories
100%
Sohar IR
MADEI1180
11KV Switchgear
100%
100%
MADEI1190
11KV Soft starter
100%
MADEI1200
Step down Transformers
100%
MADEI1210
LV Switchgear
100%
MADEI1250
LV Sub-panels
100%
MADEI1260
Power, control & earthing cables
100%
MADEI1280
Earthing system
100%
MADEI1300
Leak detection system
100%
MADEI1310
fire fighting equipment
100%
MADEI1320
lighting accessories
100%
MADEI1330
HVAC system
100%
MADEI1340
Cable accessories
100%
MPS 1
MADEI1350
11KV Switchgear
100%
100%
MADEI1360
11KV Soft starter
100%
MADEI1370
Step down Transformers
100%
MADEI1380
LV Switchgear
100%
MADEI1420
LV Sub-panels
100%
MADEI1430
Power, control & earthing cables
100%
MADEI1450
Earthing system
100%
MADEI1470
Leak detection system
100%
MADEI1480
fire fighting equipment
100%
MADEI1490
lighting accessories
100%
MADEI1500
HVAC system
100%
MADEI1510
Cable accessories
100%
MPS 2
MADEI1520
11KV Switchgear
99.31%
100%
MADEI1530
11KV Soft starter
100%
MADEI1540
Step down Transformers
100%
MADEI1550
LV Switchgear
100%
MADEI1590
LV Sub-panels
95%
MADEI1600
Power, control & earthing cables
MADEI1620
Earthing system
100%
MADEI1640
Leak detection system
100%
MADEI1650
fire fighting equipment
100%
MADEI1660
lighting accessories
100%
MADEI1670
HVAC system
100%
MADEI1680
Cable accessories
95%
100%
Dhahirah IR
MADEI1690
11KV Switchgear
99.15%
100%
MADEI1700
11KV Soft starter
100%
MADEI1720
LV Switchgear
100%
MADEI1760
LV Sub-panels
95%
MADEI1770
Power, control & earthing cables
100%
MADEI1790
Earthing system
100%
MADEI1810
Leak detection system
100%
Page 1 of 7
TASK filter: Weekly Update.
© Oracle Corporation
REVISED BASELINE PROGRAMME - BL - FINAL001 - UPDATE [D
Activity ID
Activity Name
MADEI1820
fire fighting equipment
MADEI1830
lighting accessories
MADEI1840
HVAC system
MADEI1850
Cable accessories
Week 01
05-Jan-22 12:09
Performance %
Complete
100%
95%
100%
100%
Dhank
MADEI1860
11KV Switchgear
98.84%
100%
MADEI1870
11KV Soft starter
100%
MADEI1890
LV Switchgear
100%
MADEI1930
LV Sub-panels
95%
MADEI1940
Power, control & earthing cables
95%
MADEI1960
Earthing system
MADEI1980
Leak detection system
100%
MADEI1990
fire fighting equipment
100%
MADEI2000
lighting accessories
MADEI2010
HVAC system
MADEI2020
Cable accessories
95%
95%
100%
100%
Ibri Low Level
MADEI2030
11KV Switchgear
98.16%
100%
MADEI2040
11KV Soft starter
100%
MADEI2060
LV Switchgear
100%
MADEI2100
LV Sub-panels
95%
MADEI2110
Power, control & earthing cables
95%
MADEI2130
Earthing system
MADEI2150
Leak detection system
100%
MADEI2160
fire fighting equipment
100%
MADEI2170
lighting accessories
MADEI2180
HVAC system
MADEI2190
Cable accessories
Ibri High Level 1
MADEI2200
95%
95%
100%
100%
11KV Switchgear
97.92%
100%
MADEI2210
11KV Soft starter
100%
MADEI2230
LV Switchgear
100%
MADEI2270
LV Sub-panels
95%
MADEI2280
Power, control & earthing cables
95%
MADEI2300
Earthing system
MADEI2320
Leak detection system
100%
MADEI2330
fire fighting equipment
100%
MADEI2340
lighting accessories
MADEI2350
HVAC system
100%
MADEI2360
Cable accessories
100%
Ibri Hihg Level 2
MADEI2370
95%
95%
11KV Switchgear
98.85%
100%
MADEI2380
11KV Soft starter
100%
MADEI2400
LV Switchgear
100%
MADEI2440
LV Sub-panels
95%
MADEI2450
Power, control & earthing cables
95%
MADEI2470
Earthing system
MADEI2490
Leak detection system
100%
MADEI2500
fire fighting equipment
100%
MADEI2510
lighting accessories
MADEI2520
HVAC system
100%
MADEI2530
Cable accessories
100%
TRANSFORMERS
100%
100%
MADPS1020
33KV& 11KV CABLES
100%
MADPS1030
SUBSTAION MATERIAL
100%
MADPS1040
POLES
100%
MADPS1050
LV , CONTROL Cables
100%
MADPS1060
33KV CB
100%
MADPS1070
33KV METTERING PANELS
100%
MADPS1080
DC SYSTEM
100%
MADPS1090
CONTROL RELAIES AND PROTECTION PANELS
100%
MADPS1100
RTU PANEL WITH INPUILT MARSHILING UNIT
100%
MADPS1120
GANTERY AND BUS BARS
100%
MADPS1130
33 KV DROPOUT FUSE
100%
MADPS1140
CABLE TRAYS AND CABLES ACCESSORIER
100%
MADPS1150
LIGHTINING ARISTOR
100%
MADPS1160
INSULATOR SILICON TYPE
100%
MADPS1170
FIBER GLASS ROAD STAY
Power Supply Material
MADPS1010
95%
95%
100%
86.92%
Construction
86.92%
Structures works
Sohar IWPP
Reservoir - Steel Tank 1 & 2
Zone A ( Steel Tank - 1
1)
Substructure Works
Cathodic Protection System
CNSTIWPP1230
Implementation CP under bottom plate
85.78%
70%
70%
70%
70%
100%
Page 2 of 7
TASK filter: Weekly Update.
© Oracle Corporation
REVISED BASELINE PROGRAMME - BL - FINAL001 - UPDATE [D
Activity ID
Activity Name
Week 01
05-Jan-22 12:09
Performance %
Complete
CNSTIWPP1240
Implementation of the external CP System
25%
CNSTIWPP1250
Implementation of the internal CP System
100%
CNSTIWPP1260
Testing of CP System
50%
Zone B ( Steel Tank - 2 )
Substructure Works
Cathodic Protection System
CNSTIWPP3450
Implementation CP under bottom plate
70%
70%
70%
100%
CNSTIWPP3460
Implementation of the external CP System
25%
CNSTIWPP3470
Implementation of the internal CP System
100%
CNSTIWPP3480
Testing of CP System
50%
Pump Station and Electrical
Elec
Room
MEP Works
Electrical works
CNSTIWPP2300
Initial Electrical work for Pump House
93.6%
93.6%
93.6%
100%
CNSTIWPP2310
Finishing Electrical work for Pump House
92%
CNSTIWPP2320
Initial Electrical work for Control building
100%
CNSTIWPP2330
Finishing Electrical work for Control building
92%
Electrical Installation
95%
95%
95%
Transformer Yard
MEP work
CNSTIWPP2485
Power Supply & Electrical
Electri
work
CNSTIWPP2880
Installation of cable tray
88.73%
95%
CNSTIWPP2885
Cable Laying & Termination (Medium- voltage cables and accessories_
95%
CNSTIWPP2890
Cable Laying & Termination (LV Cabling, grounding for buildings and site)
95%
CNSTIWPP2900
Installation of Earthing and lightning protection system
90%
CNSTIWPP2901
Cathodic protection for station
15%
CNSTIWPP2905
Low- voltage switchboards and distribution panelboards
95%
CNSTIWPP2910
Installation of MVSG,LVSG and DB
95%
CNSTIWPP2920
Installation of UPS systems complete with Batteries
CNSTIWPP2930
Installation of MV/LV Transformers
CNSTIWPP2940
Installation of Soft Starter and Power Factor Correction
100%
CNSTIWPP2950
Connection to Majan Substation/nearest Power source
87.43%
CNSTIWPP3060
CCTV system
30%
CNSTIWPP3180
Access control system
35%
CNSTIWPP3190
Telephone system ( including Hotline system)
10%
CNSTIWPP3200
Outdoor lighting
80%
Site Work
Site lighting
CNSTIWPP2730
90%
100%
Electrical cable laying and earthing
0%
0%
80%
CNSTIWPP2740
Install Electrical pole
20%
CNSTIWPP2750
Termination and lighting
0%
Testing & Commissioning
Commissioni
CNSTIWPP3110
Testing & Commissioning for transformers
95%
95%
CNSTIWPP3120
Testing & Commissioning for Fire alarm and firefighting system
0%
CNSTIWPP3240
Testing & Commissioning for Cathodic protection for station
0%
Sohar IR
Reservoir - Steel Tank 3 & 4
Zone A ( Steel Tank - 3
3)
Substructure Works
Cathodic Protection System
CNSTSHIR1230
Implementation CP under bottom plate
93.69%
73%
73%
73%
73%
100%
CNSTSHIR1240
Implementation of the external CP System
40%
CNSTSHIR1250
Implementation of the internal CP System
100%
CNSTSHIR1260
Testing of CP System
50%
Zone B ( Steel Tank - 4
4)
Substructure Works
Cathodic Protection System
CNSTSHIR3640
Implementation CP under bottom plate
73%
73%
73%
100%
CNSTSHIR3650
Implementation of the external CP System
40%
CNSTSHIR3660
Implementation of the internal CP System
100%
CNSTSHIR3670
Testing of CP System
50%
Pump Station and Electrical
Elec
Room
MEP Works
Electrical works
CNSTSHIR2310
Initial Electrical work for Pump House
98.4%
98.4%
98.4%
100%
CNSTSHIR2320
Finishing Electrical work for Pump House
98%
CNSTSHIR2330
Initial Electrical work for Control building
100%
CNSTSHIR2340
Finishing Electrical work for Control building
98%
Electrical Installation
98%
98%
98%
Transformer Yard
MEP work
CNSTSHIR3190
Power Supply & Electrical
Electri
work
CNSTSHIR2890
Installation of cable tray
97.96%
98%
CNSTSHIR2900
Cable Laying & Termination (LV Cabling, grounding for buildings and site)
98%
CNSTSHIR2910
Installation of Earthing and lightning protection system
95%
CNSTSHIR2920
Installation of MVSG,LVSG and DB
98%
CNSTSHIR2930
Installation of UPS systems complete with Batteries
CNSTSHIR2950
Installation of MV/LV Transformers
100%
CNSTSHIR2960
Installation of Soft Starter and Power Factor Correction
100%
90%
Page 3 of 7
TASK filter: Weekly Update.
© Oracle Corporation
REVISED BASELINE PROGRAMME - BL - FINAL001 - UPDATE [D
Activity ID
Activity Name
Week 01
05-Jan-22 12:09
Performance %
Complete
CNSTSHIR3320
Cable Laying & Termination (Medium- voltage cables and accessories_
100%
CNSTSHIR3330
Connection to Majan Substation/nearest Power source
100%
CNSTSHIR3340
CCTV system
40%
CNSTSHIR3350
Access control system
35%
CNSTSHIR3360
Low- voltage switchboards and distribution panelboards
95%
CNSTSHIR3370
Telephone system ( including Hotline system)
10%
CNSTSHIR3380
Outdoor lighting
80%
CNSTSHIR3390
Cathodic protection for station
Chlorination Building
MEP Works
Electrical works
CNSTSHIR4370
CNSTSHIR4380
Site Work
Site lighting
CNSTSHIR2730
70%
96.5%
96.5%
96.5%
100%
Initial Electrical work for Chlorination building
Finishing Electrical work for Chlorination building
95%
Electrical cable laying and earthing
0%
0%
95%
CNSTSHIR2740
Install Electrical pole
25%
CNSTSHIR2750
Termination and lighting
25%
Testing & Commissioning
Commissioni
CNSTSHIR3130
Testing & Commissioning for transformers
CNSTSHIR3140
Testing & Commissioning for Fire alarm and firefighting system
CNSTSHIR3430
Testing & Commissioning for Cathodic protection for station
100%
100%
20%
0%
MPS 1
Reservoir - Steel Tank ((5 & 6)
Steel Tank 5
Substructure Works
CNSTMPSI1260
Implementation CP under bottom plate
CNSTMPSI1270A
Implementation of the external and internal CP System
CNSTMPSI1280A
Testing of CP System
Steel Tank 6
Substructure Works
CNSTMPSI3490
91.55%
71.67%
71.67%
71.67%
100%
65%
50%
71.67%
71.67%
100%
Implementation CP under bottom plate
CNSTMPSI3491A
Implementation of the external and internal CP System
CNSTMPSI3492A
Testing of CP System
65%
50%
Pump Station and Electrical
Elec
Room
MEP Works
Electrical works
CNSTMPSI2310
Initial Electrical work for Pump House
93.6%
93.6%
93.6%
100%
CNSTMPSI2320
Finishing Electrical work for Pump House
92%
CNSTMPSI2330
Initial Electrical work for Control building
100%
CNSTMPSI2340
Finishing Electrical work for Control building
92%
Electrical Installation
0%
0%
92%
Transformer Yard
MEP work
CNSTMPSI3190
Power Supply & Electrical
Electri
work
CNSTMPSI2890
Installation of cable tray
91.32%
92%
CNSTMPSI2900
Cable Laying & Termination (LV Cabling, grounding for buildings and site)
92%
CNSTMPSI2910
Installation of Earthing and lightning protection system
90%
CNSTMPSI2920
Installation of MVSG,LVSG and DB
92%
CNSTMPSI2930
Installation of UPS systems complete with Batteries
90%
CNSTMPSI2950
Installation of MV/LV Transformers
100%
CNSTMPSI2960
Installation of Soft Starter and Power Factor Correction
100%
CNSTMPSI3320
Cable Laying & Termination (Medium- voltage cables and accessories_
CNSTMPSI3330
Connection to Majan Substation/nearest Power source
CNSTMPSI3340
CCTV system
20%
CNSTMPSI3350
Access control system
20%
CNSTMPSI3360
Low- voltage switchboards and distribution panelboards
72%
CNSTMPSI3370
Telephone system ( including Hotline system)
10%
CNSTMPSI3380
Outdoor lighting
75%
CNSTMPSI3390
Cathodic protection for station
Site Work
Site lighting
CNSTMPSI2730
90%
91.68%
0%
Electrical cable laying and earthing
0%
0%
80%
CNSTMPSI2740
Install Electrical pole
15%
CNSTMPSI2750
Termination and lighting
40%
Testing & Commissioning
Commissioni
CNSTMPSI3130
Testing & Commissioning for transformers
CNSTMPSI3140
Testing & Commissioning for Fire alarm and firefighting system
CNSTMPSI3430
Testing & Commissioning for Cathodic protection for station
95%
95%
0%
0%
MPS 2
Reservoir - Steel Tank 7 & 8
Steel Tank 7
Substructure Works
CNSTMPSII1080
Implementation CP under bottom plate
CNSTMPSII1120A
92.35%
50%
50%
50%
100%
Implementation of the external and internal CP System
50%
CNSTMPSII1120A10 Testing of CP System
Steel Tank 8
Substructure Works
CNSTMPSII3280
0%
50%
50%
100%
Implementation CP under bottom plate
Page 4 of 7
TASK filter: Weekly Update.
© Oracle Corporation
REVISED BASELINE PROGRAMME - BL - FINAL001 - UPDATE [D
Activity ID
Activity Name
CNSTMPSII3290A
Implementation of the external and internal CP System
CNSTMPSII3291A
Testing of CP System
Week 01
05-Jan-22 12:09
Performance %
Complete
50%
0%
Pump Station and Electrical
Elec
Room
MEP Works
Electrical works
CNSTMPSII1800
Initial Electrical work for Pump House
93.6%
93.6%
93.6%
100%
CNSTMPSII1810
Finishing Electrical work for Pump House
92%
CNSTMPSII1820
Initial Electrical work for Control building
100%
CNSTMPSII1830
Finishing Electrical work for Control building
92%
Electrical Installation
85%
85%
85%
Transformer Yard
MEP work
CNSTMPSII2680
Power Supply & Electrical
Electri
work
CNSTMPSII2380
Installation of cable tray
93.15%
95%
CNSTMPSII2390
Cable Laying & Termination (LV Cabling, grounding for buildings and site)
92%
CNSTMPSII2400
Installation of Earthing and lightning protection system
85%
CNSTMPSII2410
Installation of MVSG,LVSG and DB
92%
CNSTMPSII2420
Installation of UPS systems complete with Batteries
CNSTMPSII2440
Installation of MV/LV Transformers
100%
CNSTMPSII2450
Installation of Soft Starter and Power Factor Correction
100%
CNSTMPSII2810
Cable Laying & Termination (Medium- voltage cables and accessories_
CNSTMPSII2820
Connection to Majan Substation/nearest Power source
CNSTMPSII2830
CCTV system
20%
CNSTMPSII2840
Access control system
20%
CNSTMPSII2850
Low- voltage switchboards and distribution panelboards
85%
CNSTMPSII2860
Telephone system ( including Hotline system)
10%
CNSTMPSII2870
Outdoor lighting
60%
CNSTMPSII2880
Cathodic protection for station
35%
Guard House
MEP Works
Electrical works
CNSTMPSII3190
CNSTMPSII3200
Site Work
Site lighting
CNSTMPSII2220
90%
88%
94.48%
Initial Electrical work for Guard house
0%
0%
0%
100%
Finishing Electrical work for Guard house
100%
Electrical cable laying and earthing
0%
0%
80%
CNSTMPSII2230
Install Electrical pole
15%
CNSTMPSII2240
Termination and lighting
25%
Testing & Commissioning
Commissioni
CNSTMPSII2620
Testing & Commissioning for transformers
CNSTMPSII2630
Testing & Commissioning for Fire alarm and firefighting system
CNSTMPSII2920
Testing & Commissioning for Cathodic protection for station
95%
95%
0%
0%
Dhahirah IR
Reservoir - Steel Tank 9 & 10
Steel Tank 9
Substructure Works
Cathodic Protection System (Steel Tank 9)
CNSTDHIR1230
Implementation CP under bottom plate
53.89%
63%
63%
63%
63%
100%
CNSTDHIR1240
Implementation of the external CP System
0%
CNSTDHIR1250
Implementation of the internal CP System
100%
CNSTDHIR1260
Testing of CP System
52%
Steel Tank 10
Substructure Works
Cathodic Protection System (Steel Tank 10)
CNSTDHIR3450
Implementation CP under bottom plate
63%
63%
63%
100%
CNSTDHIR3460
Implementation of the external CP System
0%
CNSTDHIR3470
Implementation of the internal CP System
100%
CNSTDHIR3480
Testing of CP System
52%
Power Supply & Electrical
Electri
work
CNSTDHIR2880
Installation of cable tray
19.89%
0%
CNSTDHIR2885
Cable Laying & Termination (Medium- voltage cables and accessories_
0%
CNSTDHIR2890
Cable Laying & Termination (LV Cabling, grounding for buildings and site)
0%
CNSTDHIR2900
Installation of Earthing and lightning protection system
0%
CNSTDHIR2901
Cathodic protection for station
CNSTDHIR2905
Low- voltage switchboards and distribution panelboards
0%
CNSTDHIR2915
Installation of AC System /HAVC for Gaurd House
0%
CNSTDHIR2920
Installation of UPS systems complete with Batteries
0%
CNSTDHIR2940
Installation of Soft Starter and Power Factor Correction
0%
CNSTDHIR2950
Connection to Majan Substation/nearest Power source
90%
CNSTDHIR3060
CCTV system
0%
CNSTDHIR3180
Access control system
0%
CNSTDHIR3190
Telephone system ( including Hotline system)
CNSTDHIR3200
Outdoor lighting
Guard House
MEP Works
Electrical works
CNSTDHIRI3190
CNSTDHIRI3200
10%
0%
10%
84.6%
84.6%
84.6%
100%
Initial Electrical work for Guard house
Finishing Electrical work for Guard house
78%
Site Work
0%
Page 5 of 7
TASK filter: Weekly Update.
© Oracle Corporation
REVISED BASELINE PROGRAMME - BL - FINAL001 - UPDATE [D
Activity ID
Activity Name
Site lighting
CNSTDHIR2730
Week 01
05-Jan-22 12:09
Performance %
Complete
Electrical cable laying and earthing
0%
0%
CNSTDHIR2740
Install Electrical pole
0%
CNSTDHIR2750
Termination and lighting
0%
Testing & Commissioning
Commissioni
CNSTDHIR3120
Testing & Commissioning for Fire alarm and firefighting system
CNSTDHIR3240
0%
0%
Testing & Commissioning for Cathodic protection for station
0%
Dhank
Reservoir - Steel Tank 1
11
Substructure Works
Cathodic Protection S
System
CNSTDHAN1230
Implementation CP under bottom plate
52.23%
65%
65%
65%
100%
CNSTDHAN1240
Implementation of the external CP System
0%
CNSTDHAN1250
Implementation of the internal CP System
100%
CNSTDHAN1260
Testing of CP System
50%
Power Supply & Electrical
Electri
work
CNSTDHAN2880
Installation of cable tray
23.16%
65%
CNSTDHAN2885
Cable Laying & Termination (Medium- voltage cables and accessories_
15%
CNSTDHAN2890
Cable Laying & Termination (LV Cabling, grounding for buildings and site)
50%
CNSTDHAN2900
Installation of Earthing and lightning protection system
10%
CNSTDHAN2901
Cathodic protection for station
CNSTDHAN2905
Low- voltage switchboards and distribution panelboards
50%
CNSTDHAN2915
Installation of AC System /HAVC for Gaurd House
10%
CNSTDHAN2920
Installation of UPS systems complete with Batteries
60%
CNSTDHAN2940
Installation of Soft Starter and Power Factor Correction
0%
CNSTDHAN2950
Connection to Majan Substation/nearest Power source
90%
CNSTDHAN3060
CCTV system
5%
CNSTDHAN3180
Access control system
5%
CNSTDHAN3190
Telephone system ( including Hotline system)
5%
CNSTDHAN3200
Outdoor lighting
0%
Chlorination Building
MEP Works
Electrical works
CNSTDHAN4370
CNSTDHAN4380
Site Work
Site lighting
CNSTDHAN2730
0%
75.5%
75.5%
75.5%
100%
Initial Electrical work for Control building
Finishing Electrical work for Control building
65%
Electrical cable laying and earthing
0%
0%
0%
CNSTDHAN2740
Install Electrical pole
0%
CNSTDHAN2750
Termination and lighting
0%
Testing & Commissioning
Commissioni
CNSTDHAN3120
Testing & Commissioning for Fire alarm and firefighting system
CNSTDHAN3240
0%
0%
Testing & Commissioning for Cathodic protection for station
0%
Ibri Low Level
Reservoir - Steel Tank 1
12
Substructure Works
Cathodic Protection S
System
CNSTILL1230
Implementation CP under bottom plate
58.11%
62.5%
62.5%
62.5%
100%
CNSTILL1240
Implementation of the external CP System
0%
CNSTILL1250
Implementation of the internal CP System
100%
CNSTILL1260
Testing of CP System
Chlorination Building
MEP Works
Electrical works
CNSTILL4370
CNSTILL4380
50%
0%
0%
0%
0%
Initial Electrical work for Control building
Finishing Electrical work for Control building
0%
Ibri High Level 1
Reservoir - Steel Tank 1
13 , 14 & 15
Steel Tank 13
Substructure Works
Cathodic Protection System (Steel Tank 13)
CNSTIHLI1230
Implementation CP under bottom plate
48.67%
62.5%
62.5%
62.5%
62.5%
100%
CNSTIHLI1240
Implementation of the external CP System
0%
CNSTIHLI1250
Implementation of the internal CP System
100%
CNSTIHLI1260
Testing of CP System
50%
Steel Tank 14
Substructure Works
Cathodic Protection System
CNSTIHLI3450
Implementation CP under bottom plate
62.5%
62.5%
62.5%
100%
CNSTIHLI3460
Implementation of the external CP System
0%
CNSTIHLI3470
Implementation of the internal CP System
100%
CNSTIHLI3480
Testing of CP System
50%
Steel Tank 15
Substructure Works
Cathodic Protection System
CNSTIHLI3990
Implementation CP under bottom plate
62.5%
62.5%
62.5%
100%
CNSTIHLI4000
Implementation of the external CP System
0%
CNSTIHLI4010
Implementation of the internal CP System
100%
CNSTIHLI4020
Testing of CP System
50%
Power Supply & Electrical
Electri
work
8.09%
Page 6 of 7
TASK filter: Weekly Update.
© Oracle Corporation
REVISED BASELINE PROGRAMME - BL - FINAL001 - UPDATE [D
Activity ID
Activity Name
Week 01
05-Jan-22 12:09
Performance %
Complete
CNSTIHLI2880
Installation of cable tray
0%
CNSTIHLI2885
Cable Laying & Termination (Medium- voltage cables and accessories_
0%
CNSTIHLI2890
Cable Laying & Termination (LV Cabling, grounding for buildings and site)
0%
CNSTIHLI2900
Installation of Earthing and lightning protection system
0%
CNSTIHLI2901
Cathodic protection for station
0%
CNSTIHLI2905
Low- voltage switchboards and distribution panelboards
0%
CNSTIHLI2915
Installation of AC System /HAVC for Gaurd House
0%
CNSTIHLI2920
Installation of UPS systems complete with Batteries
0%
CNSTIHLI2940
Installation of Soft Starter and Power Factor Correction
0%
CNSTIHLI2950
Connection to Majan Substation/nearest Power source
40%
CNSTIHLI3060
CCTV system
0%
CNSTIHLI3180
Access control system
0%
CNSTIHLI3190
Telephone system ( including Hotline system)
0%
CNSTIHLI3200
Outdoor lighting
0%
Site Work
Site lighting
CNSTIHLI2730
Electrical cable laying and earthing
0%
0%
0%
CNSTIHLI2740
Install Electrical pole
0%
CNSTIHLI2750
Termination and lighting
0%
Testing & Commissioning
Commissioni
CNSTIHLI3120
Testing & Commissioning for Fire alarm and firefighting system
CNSTIHLI3240
0%
0%
Testing & Commissioning for Cathodic protection for station
0%
Ibri Hihg Level 2
Power Supply & Electrical
Electri
work
CNSTIHLII2880
Installation of cable tray
15.39%
15.44%
20%
CNSTIHLII2885
Cable Laying & Termination (Medium- voltage cables and accessories_
0%
CNSTIHLII2890
Cable Laying & Termination (LV Cabling, grounding for buildings and site)
0%
CNSTIHLII2900
Installation of Earthing and lightning protection system
0%
CNSTIHLII2901
Cathodic protection for station
0%
CNSTIHLII2905
Low- voltage switchboards and distribution panelboards
5%
CNSTIHLII2915
Installation of AC System /HAVC for Gaurd House
0%
CNSTIHLII2920
Installation of UPS systems complete with Batteries
0%
CNSTIHLII2940
Installation of Soft Starter and Power Factor Correction
0%
CNSTIHLII2950
Connection to Majan Substation/nearest Power source
75%
CNSTIHLII3060
CCTV system
0%
CNSTIHLII3180
Access control system
0%
CNSTIHLII3190
Telephone system ( including Hotline system)
0%
CNSTIHLII3200
Outdoor lighting
0%
Site Work
Site lighting
CNSTIHLII2730
Electrical cable laying and earthing
0%
0%
5%
CNSTIHLII2740
Install Electrical pole
5%
CNSTIHLII2750
Termination and lighting
0%
Testing & Commissioning
Commissioni
CNSTIHLII3120
Testing & Commissioning for Fire alarm and firefighting system
CNSTIHLII3240
0%
0%
Testing & Commissioning for Cathodic protection for station
0%
Page 7 of 7
TASK filter: Weekly Update.