Waste Water Disposal Project Student Name: Paul Seiler Student ID: 030411347 ChallengerTAFE Waste Water Disposal Plant Project TABLE OF CONTENTS 1 Executive Summary............................................................................................ 1 2 Project Execution Plan ....................................................................................... 2 3 Scope ................................................................................................................. 4 3.1 Design Capacity ...................................................................................... 4 3.2 Mechanical .............................................................................................. 4 3.3 Electrical ................................................................................................. 4 3.4 Scada Control ......................................................................................... 4 3.5 What is not in scope ................................................................................ 4 4 Project Organisation ........................................................................................... 5 5 Engineering and Safety Codes/Standards .......................................................... 6 6 ISO 9002 Quality Systems Design and Design Safety ........................................ 7 7 Estimate ............................................................................................................. 9 8 Specifications and Procurement ....................................................................... 10 9 Fabrication, Manufacture Installation, Construction .......................................... 11 10 11 9.1 Fabrication Program.............................................................................. 11 9.2 Bolted Connections ............................................................................... 11 9.3 Tolerances and Workshop Assembly .................................................... 11 Testing and Commissioning .......................................................................... 13 10.1 Test Results .......................................................................................... 14 10.2 Fabrication Program.............................................................................. 14 Project Safety ............................................................................................... 15 Appendices ............................................................................................................. 16 © Challenger Institute of Technology Rev 1 – Submitted June 2015 ChallengerTAFE Waste Water Disposal Plant Project 1 Executive Summary The aim of the Waste Water Disposal Plant project are four-fold. 1. Establish and follow a competency development plan in an electro technology engineering discipline. This includes developing requirements to be incorporated into the writing of specifications for electrical engineering projects. It encompasses determining the safety requirements to be met, establishing client expectations, ensuring cost effective solutions are pursued and documenting design and technical requirements. 2. Estimate electrotechnology projects. This covers estimate material and labour costs for competitive quotation/tenders for work exceeding $20k. It encompasses reading and understanding job specifications, material take-offs, determining labour and site requirements, costing and documenting 3. Implement and monitor energy sector OHS policies and procedures. The mandatory requirements of a person in supervisory roles are to implement and monitor an organisation’s occupational health and safety policies, procedures and programs. It encompasses understanding an organisation’s OHS obligations, providing safety information to staff, implementing and monitoring participative arrangements, safety procedures and training and maintaining safety records. 4. Facilitate continuous improvement. The performance outcomes, skills and knowledge required to lead and manage continuous improvement systems and processes are detailed. Particular emphasis is on the development of systems and the analysis of information to monitor and adjust performance strategies, and to manage opportunities for further improvements. The project outcomes included successful implementation of tasks by all members which resulted in overall deadline accomplishments. Also, the variation of task integration between team member was deemed satisfactory by the project leaders and faculty staff. Key learnings by the author of this document, who was positioned initially within the engineering section of the group are detailed. He was chosen as one of two team leaders for the engineering section with deliverables that included maintaining a drawing register and fielding member queries. © Challenger Institute of Technology Rev 0 – Issued February 2015 Page 1 of 16 ChallengerTAFE Waste Water Disposal Plant Project 2 Project Execution Plan Each section needs to be summarized Project Brief 'Wastewater' flows in to the primary inflow distribution tank (First tank) At any given time one of the 2 primary treatment tanks is filling and the other is emptying. From the primary treatment tanks the water will flow into one of the batch reactor tanks, these tanks have 4 possible states and will proceed through them in sequence. Filling The tank is being filled from one of the primary treatment tanks Aerating The tank is being aerated by process air through the aeration system on the bottom of the tank Settling The tank is left alone and any particulates are allowed to settle out Emptying The tank is discharging into the outflow As there are 4 tanks at any given time 1 will be in each of the 4 states allowing for continuous operation of the plant. Inflow will be from an external reservoir (one of the existing fluids lab tanks has been reserved) and outflow will be into the same tank. © Challenger Institute of Technology Rev 0 – Issued February 2015 Page 2 of 16 ChallengerTAFE Waste Water Disposal Plant Project • Project Timeline • Project Budget $20,000 • Project Organisation PM Eng/Design Co-ordinator Estimation Scheduling Doc Control Procurement Construction Commissioning TM 1 TM3 TM1 TM3 TM1 TM3 TM1 TM3 TM2 TM4 TM2 TM4 TM2 TM4 TM2 TM4 TM5 TM6 TM5 TM6 TM5 TM6 TM5 TM6 • Project Safety © Challenger Institute of Technology Rev 0 – Issued February 2015 Page 3 of 16 ChallengerTAFE Waste Water Disposal Plant Project 3 Scope 3.1 Design Capacity 3.2 – – – – – – – – – – Key Documents Project Document Progress Status Update - Communications Project Schedule Estimate Spreadsheet Activity Hours Spreadsheet Deliverable List Status Lessons Learnt Spreadsheet Document Control Setup and management Document Standards and Revision Status – Quality Mechanical – – – – 3.3 Electrical – – – – – 3.4 Power Load Power Consumption Instrument Settings VSD/DOL Settings Design Safety Scada Control – 3.5 Flow, Pressure and Volume Pump Size Piping Size Design Safety Design Safety What is not in scope Warranty © Challenger Institute of Technology Rev 0 – Issued February 2015 Page 4 of 16 ChallengerTAFE Waste Water Disposal Plant Project 4 Project Organisation • • Student is to develop a project org chart explaining all the functions of project management, engineering, procurement, estimating and construction. The student need to highlight which roles they were involved with and what was the major activity they did in each role. © Challenger Institute of Technology Rev 0 – Issued February 2015 Page 5 of 16 ChallengerTAFE Waste Water Disposal Plant Project 5 Engineering and Safety Codes/Standards Codes and Standards referred to in this guideline are as follows: Australian Standards = AS Australian Standard of Structural AS/NZS 5131. AS 1163 Structural Steel Hollow Sections AS 1171 Methods for Magnetic Particle Testing of FerroMagnetic Products and Components AS 1250 Use of Steel in Structures AS 1252 High Strength Steel Bolts with Associated Nuts and Washers for Structural Engineering AS 1397 Steel Sheet and Strip - Hot Dipped Zinc Coated or Aluminium/Zinc-Coated AS 1538 Cold-Formed Steel Structures Code AS 1553 Covered Electrodes for Welding AS 3678 Structural Steel - Hot rolled plates, Floorplates and Slabs AS 3679 Structural Steel (Hot rolled bars and sections and welded sections) AS 3990 Mechanical Equipment - Steelwork AS 4100 Steel Structures © Challenger Institute of Technology Rev 0 – Issued February 2015 Page 6 of 16 ChallengerTAFE Waste Water Disposal Plant Project 6 ISO 9002 Quality Systems Design and Design Safety Design The student was technical lead in the coordination and implementation of the design drawing registry for this project in the Engineering stream. It consisted of a hard copy library of all drawings for reference by the team as well as electronic lists of all team member producing drawings. Please refer to the Appendix for the final table of drawings. This also encompassed behaviour management of stakeholders as it was crucial to keep documents up to date and readily accessible under tight deadlines taking into account the loss of five classes due to various holidays. The key learning outcomes from the design registry maintenance included constraints from multiple tasks that stakeholders were responsible for and assisting them with their own time management. In the project we determined areas where some stakeholders would be better used elsewhere in the project and tasks were juggled according to timeline. This offered a substantial insight into project management and how efficiency and alternative pathways are essential to meeting goals. The student also took on the role for completing four designs to keep the target deadlines viable. This gave members the ability to put out fires in other areas of the project as they arose and kept the progress flow in a forward direction. • • • • PL-WTP-001 Plant Layout S-WTP-002 Process Layout E-WTP-004 SB PANEL - DB-001 Internal SC-WTP-001 Electrical Network Map . © Challenger Institute of Technology Rev 0 – Issued February 2015 Page 7 of 16 ChallengerTAFE Waste Water Disposal Plant Project . © Challenger Institute of Technology Rev 0 – Issued February 2015 Page 8 of 16 ChallengerTAFE Waste Water Disposal Plant Project 7 No Estimate WBS Level WBS Level 0 Directs 1 Structural 2 Mechanical 3 Electrical Indirects 4 Overheads (7%) 5 Contingency (10%) Total $ Materials Subtotals $ $ $ Labour Subtotals 4,358.80 $ 5,970.42 $ 4,619.00 $ Plant Subtotals 500.00 $ 800.00 $ 1,000.00 $ Subtotals Subtotals $ $ 200.00 $ 4,858.80 6,770.42 5,819.00 $ $ 4,073.30 407.33 Subtotals Subtotals Subtotals Total 21,928.85 $ 14,948.22 $ 2,300.00 $ 200.00 $ © Challenger Institute of Technology Rev 0 – Issued February 2015 21,928.85 . Page 9 of 16 ChallengerTAFE Waste Water Disposal Plant Project 8 Specifications and Procurement • The author was tasked with providing management of the design drawing register for this project. • Key learning was the lesson of organisation of a well-planned process is vital for outcomes to be assessed. © Challenger Institute of Technology Rev 0 – Issued February 2015 Page 10 of 16 ChallengerTAFE Waste Water Disposal Plant Project 9 Fabrication, Manufacture Installation, Construction 9.1 Fabrication Program A detailed fabrication program shall be submitted to the Owner's Representative before fabrication commences. This program shall be upgraded during fabrication and shall be made available to the Owner's Representative upon request. 9.2 Bolted Connections 9.2.1 Bolts Bolts for connections shall be grade 8.8 (high strength) or 4.6 (commercial grade). Torqued bearing type bolted joints complying with AS 4100 and denoted as 8.8/TB shall be used for all connections, unless noted otherwise on the drawings. Torqued friction joints complying with AS 4100 and denoted as 8.8/TF shall be used in joints as specified on the drawings where bolt slip is to be avoided. If the bolt size is not shown on the drawings, it shall be taken to be M20. Each bolted connection shall contain at least two bolts, unless shown otherwise on the drawings. Bolt holes shall be 2 mm larger in diameter than the nominal bolt diameter unless noted otherwise on the drawings. Holes for bolts shall be drilled or punched (for plates less than 10 mm thick). These holes shall not be flame cut. 9.3 Tolerances and Workshop Assembly 9.3.1 Tolerances The Contractor shall provide all necessary personnel, equipment and instruments necessary to fabricate the steelwork to the design dimensions and tolerances. All instruments used shall have the current valid calibration certificates. The tolerance limits for fabrication shall be those specified by AS 4100. © Challenger Institute of Technology Rev 0 – Issued February 2015 Page 11 of 16 ChallengerTAFE Waste Water Disposal Plant Project Monitoring of dimensions shall be carried out during fabrication of individual members, and before fit up of sections and sub-assemblies for conformance with the dimensions and tolerances. Out of tolerance fabricated steel items shall be rectified at the Contractor's cost. Where conflict between the drawings and the specifications occur, the most stringent requirements shall apply and the Contractor shall notify the Owner's Representative of the conflict. Where no appropriate tolerance is stated, then these tolerances shall be obtained from the Owner's Representative prior to fabrication continuing. 9.3.2 Workshop Assembly Fabrication shall be carried out on a flat and level surface. During workshop assembly the drifting of misaligned bolt holes shall not be permitted. Critical field splices and joints shall be mated in the shop on completion of fabrication to ensure satisfactory fit when installed. 9.3.3 Surface Treatment and Paint Finish • All structural steelwork shall be surface treated and painted in accordance with SE11 and the type of surface protection shall comply with as shown on the design drawings.. © Challenger Institute of Technology Rev 0 – Issued February 2015 Page 12 of 16 ChallengerTAFE Waste Water Disposal Plant Project 10 Testing and Commissioning All inspection and testing required by this specification and the relevant Australian Standards shall be performed. An Inspection and Test Plan (ITP) shall be submitted for approval at least two weeks before the start of fabrication. The ITP shall describe the inspections, tests and verifications for the works required, identify the mandatory hold and witness points and describe the sequence of work activities. Inspection and testing shall comply with ISO 9002. The minimum acceptance requirements in the ITP shall be: • 100% visual check on materials and copies of certificates (if applicable). • 100% check on dimensions. • 100% visual check on all welds. • 100% visual check on surface treatment. • Signed off inspection check for each item by Contractor's inspector. (This shall be made available to the Owner's Representative). • NDT as required by this specification. • Completion report within two weeks of completion of work. Any subsequent amendments to the ITP shall be submitted for review and approval prior to being implemented. The ITP shall include all of the non-destructive weld testing required, as shown on the drawings or in the detailed specification. The ITP shall be adhered to. All ITP inspection activities shall be performed by appropriately qualified personnel acceptable to the Owner's Representative. The name of the person who has the responsibility of upholding the ITP shall be submitted to the Owner's Representative. © Challenger Institute of Technology Rev 0 – Issued February 2015 Page 13 of 16 ChallengerTAFE Waste Water Disposal Plant Project 10.1 Test Results A copy of the test results shall be provided to the Owner's Representative as specified in Section 17, . Copies of these test results, plus any relevant documentation shall be retained by the Contractor until the defects liability period has expired. The Contractor shall permit examination of such results by the Owner's Representative. 10.2 Fabrication Program The fabrication program shall include allowance for inspection and testing, including that by the Owner's Representative. © Challenger Institute of Technology Rev 0 – Issued February 2015 Page 14 of 16 ChallengerTAFE Waste Water Disposal Plant Project 11 Project Safety • Safety was documented through a JSA (Job Safety Audit) procedure. A register was kept on file.. © Challenger Institute of Technology Rev 0 – Issued February 2015 Page 15 of 16 ChallengerTAFE Waste Water Disposal Plant Project Appendices Drawing Register Process Engineering Drawing Number: Drawing Title: Drawn By: Revision EL-WTP-001 PFD-WTP-001 PL-WTP-001 PID-WTP-001 PID-WTP-002 Symbol List Process Flow Diagram Plant Layout P&ID P&ID E.WATSON David Paul Milan Milan A A A S-WTP-001 S-WTP-002 Structural Layout Process Layout Jason Webb Paul S A A Piping Iso - SHT 1 Piping Iso - SHT 2 AIR SUPPLY DRAWING Instrument Air E.WATSON E.WATSON FRED David A A A A Electrical Layout SLD SB PANEL - DB-001 External SB PANEL - DB-001 Internal SB PANEL - DB-002 External SB PANEL - DB-001 Internal JB-001 (Typical) Electrical Network Map JB1 Schematic JB2 Schematic JB3 Schematic DB-001 Schematic SHT1 DB-002 Schematic SHT1 DB-002 Schematic SHT2 CONTROL CIRCUIT Paul Ellise Jack Paul A A A A A A A A A A A Structural Engineering Mechanical Engineering PI-WTP-001 PI-WTP-002 PI-WTP-003 PI-WTP-004 Electrical Engineering E-WTP-001 E-WTP-002 E-WTP-003 E-WTP-004 E-WTP-005 E-WTP-006 E-WTP-007 SC-WTP-001 SC-WTP-002 SC-WTP-003 SC-WTP-004 SC-WTP-005 SC-WTP-006 SC-WTP-007 CC-WTP-001 © Challenger Institute of Technology Rev 0 – Issued February 2015 Quon Tan Paul Fabiana Fabiana Fabiana Fabiana Jack A Page 16 of 16