CONTRACT VARIATION Bryant Built Projects 47 East Street Wollongong, NSW, 2500 Date: 10/11/2021 Owner: Mr. Brown Job: Seabreeze Ave Variation No: 1 Original contract date: 7/11/2021 Variation Details: Change cladding product from James Hardie stria to James Hardie linea. Tile entire bathroom walls instead of skirting tiles. The original contract sum was: $660,00 Total amount of this variation: $10,000 The new contract amount including this variation will be: $670,000 The contract time will be changed by the following number of days: 5 days The date of completion as of the date of this change order is: 15/8/22 Contractor: Owner: Bryant Built Projects 47 East St, Wollongong, NSW, 2500 10/11/2021 0450694175 SB Greg Brown 12 Seabreeze Ave, Wollongong, NSW, 2500 10/11/2021 0414841978 GB