CONTRACT VARIATION
Bryant Built Projects
47 East Street
Wollongong, NSW, 2500
Date: 10/11/2021
Owner: Mr. Brown
Job: Seabreeze Ave
Variation No: 1
Original contract date: 7/11/2021
Variation Details:
Change cladding product from James Hardie stria to James Hardie linea.
Tile entire bathroom walls instead of skirting tiles.
The original contract sum was: $660,00
Total amount of this variation: $10,000
The new contract amount including this variation will be: $670,000
The contract time will be changed by the following number of days: 5 days
The date of completion as of the date of this change order is: 15/8/22
Contractor:
Owner:
Bryant Built Projects
47 East St, Wollongong, NSW, 2500
10/11/2021
0450694175
SB
Greg Brown
12 Seabreeze Ave, Wollongong, NSW, 2500
10/11/2021
0414841978
GB